“ Improvement of the Central Pond and

strengthening of the adjacent part of the


Tagging bundh by sheet piling etc. at
country side and Construction of Storm
water Pump House with its allied
components at Gazoldoba in P.S.-
Bhaktinagar,Dist-Jalpaiguri.”
(Electro-mechanical part)
Estimated Cost
 Estimated cost : Rs. 16.76 Cr
 Tendered Amount :Rs. 13.98 Cr (4.44% Less)

 Cost for Electric power service connection &

security deposit: Rs. 1.75 Cr (WBSEDCL)

 Executing Agency: Wilo Mather & Platt Pumps


Pvt. Ltd. , Pune, Maharastra

 Work order issued on: 28.06.2019


Status of Fund

Cumulative Fund received till date:


Rs. 10.10 Cr

Fund Utilized:Rs 9.60 Cr


Necessity of SWD Pump House
Entire Mega Tourism Park is located in a low level basin.
Very high rainfall occurs during monsoon.
Estimated storm discharge is around 10 Cumec.
Capacity of existing cross drainage (CD) structure is only
1 Cumec.
Construction of Additional CD structure is not a feasible
solution.
Construction of storm water drainage pump house is
inevitable for quick disposal of accumulated water.
Major Mechanical Components
Vertical Turbine Pump (50 Cusec, 7.5 m head).
CIDF delivery pipes.
Screen & Accessories (Trash Rack, Bar Screen).
Valves (Flap Valve, Air Release, etc).
EOT Crane (15 T), Monorail Crane,Chain pulley block.
Deep Tube Well with Submersible Pump.
Cooling water Recirculating(CWR) Pump.
Rader type water level sensor.
Location of the SWD Pump House

Location of SWD PUMP HOUSE


Vertical Turbine (VT) Pump
Pump- 8 Nos. (7 working + 1 standby)
 Discharge : 1.42 cum/sec (50 cusec) (+10%)
Total Dynamic Head: 7.5 m (+5%)
Efficiency : Not less than (88%)
Speed: <600 RPM
Type :Vertical Axial Flow
Lubrication: Fresh water lubricated
Type of impeller: Open type(propeller)
Duty: Continuous
EOT Crane
Capacity: 15 M.T.
Lift: 8 M
Span: 7 M
Double girder
Trash Rack and Bar screen
Flap Valve

 Flap Valve – 8 nos.


  size: 900 dia
 Single swing Disc
 non return type
CWR Pump
Horizontal Centrifugal Pump
Fresh water lubrication
Drive Motor rating :1.1 KW
Head: 25 m
Discharge: 25cum/hr
3 nos.( 2 nos.working and 1 no.spare)
For fresh water lubrication and bearing cooling water of
SWD Pump
Submersible Pump
Submersible Pump (for fresh
water supply)
Drive motor rating: 3.7 KW
Head: 50 m
Discharge: 25m3/hr
Delivery pipe: 100mm dia
Nos: 2 nos ( 1 working and 1 no kept
as spare)
Radar Type Water level indicator
Major Electrical Components
HT Panel at Sub-station.
LT Panel ( 2 at Sub Station, 1 at Pump House)
Transformer –Dry type, indoor ,resin cast(2 nos,1250 kVA)
Capacitor Bank( 100 KVAR)
SPDP Induction Motor (180 kW)
500 kVA DG set
H.T Panel
 
Ratings : 11 KV, 1250 A
Breaking capacity :
500 MVA for 11 KV
Type: Cubical draw
out type extensible on
either side
L.T Panels
 Type of L.T Panel:  Rating of Incoming •Rating of Outgoings
Cubical – vertical free  Board 1(at S/S): 2000A, •Board 1
standing extensible TPN ACB - 1 No. •2000 A TPN ACB – 1 No.
on either side  Board 2(at S/S): (ACB)
 Nominal Voltage (V): 2000A,TPN ACB - 1 No •32A, TPN MCCB –1 No.
415 V, TPN •100A, TPN MCCB– 2 Nos.
 Board 3(Pump House):
 Fault level (MVA): 35 •63A TPN MCCB-5 Nos.
2000A,TPN ACB – 2 No.
MVA
Transformer Number of Transformers: 2
Rating : 2Nos 1250 KVA,
11KV, 433 V, 3 ph 
Type of Transformer:
INDOOR air cooled cast
resin Dry type 
Capacitor Bank
• 8 nos
• 100KVAR
• Power Factor near to 1
• Delta connected
• 425/440 VAC, 3 ph,
50Hz
SPDP Induction Motor
•Motor – 8 Nos.
•Rating: 180 KW
•Type: Vertical Sq. cage induction
•Voltage: 415 V+-10%
•Frequency: 50 Hz + -5%
•Phases: 3
•Speed: 600 RPM
•Class of insulation: B
•Mounting: Vertical flange
mounted
•Duty cycle: Continuous
•Cooling: Fan cooled
DG SET
•Rating (kVA):500
•Rated kW:400
•Rated Current (Amps):695
•Total Dry Weight (Kgs):6200
•BHP: 595
•No. of Cylinders: 12
•RPM: 1500
Present Status of M&E Works
Supply of all Electro-Mech Equipments completed.
Installation of 15 T EOT crane done.
Installation of Pumps alongwith delivery lines,flap
valves etc done.
Installation of Electrical equipments viz Transformer,
HT & LT panel, Capacitor Bank , DG set will be started
soon.
Progress of works
Physical Progress: 75%
Financial Progress:61%

Expected Date of completion: 31.10.2021


Installation of EOT Crane
Pump Installation works
Installation of Delivery pipes
Removable screen & Trashrack