GLS Construction Progress Report (Sual, Pangasinan)

You might also like

Download as pptx, pdf, or txt
Download as pptx, pdf, or txt
You are on page 1of 2

Sual, Pangasinan Branch

Construction Progress
Date: Dec.22,2022
Scope of Works Percent Completion
Contractor: Balfor Construction and
Demolition & Clearing Works 100%
Development Corporation
Partition & Masonry Works 100%
Start Date: November 19, 2022
Doors & Windows 100%
Target Completion Date: Dec. 3, 2022
Flooring Works 100%
Ceiling Works 100%
Painting Works 100%
Specialties (Counters, Accent wall) 100%
Electrical Works 100%
Mechanical Works 100%
Plumbing Works 100%
Miscellaneous 100%
Site Photos

Store Front Supermarket Area Staff Counter & Check-out Counter

Storage Room Toilet Dealers Area