Professional Documents
Culture Documents
Controlling of Time and Cost Implementation by Using Earned Value Analysis
Controlling of Time and Cost Implementation by Using Earned Value Analysis
IMPLEMENTATION
BY USING EARNED VALUE ANALYSIS
(Case Study: Shrimp Cultivation Development Project with Area-
Based in Kebumen Regency)
By
ADILA CHILMAYANTI
D100 184 301
Supervisor Lecture
Based on the description above, controlling the implementation of time and cost in the
development project of shrimp farming based in the Kebumen Regency area is carried out using
the earned value analysis.
PROBLEM STATEMENT
2
What are the problems encountered in implementing the project
and what are the solutions?
In the “Manajemen Proyek” book compiled by (Nurjaman and Dimyati, 2014) the
management functions are generally divided into four:
1 Planning
2 Organizing
3
Implementing
4 Controlling
NET WORKING METHOD
The definition of the network method according to Istimawan Dipohusodo as written in the “Manajemen
Konstruksi” book written by (Widiasanti and Lenggogeni, 2013), is a graphical method used to describe
activities and events that need to be carried out to achieve the project goals that have been set.
According to Callahan in “Manajemen Konstruksi” (Widiasanti and Lenggogeni, 2013), there are four
things that need to be done first in making the network method, namely:
1. Determine activities/activities
2. Determine the duration of the activity/activity
3. Describing activities/activities
4. Define logical relationships
EARNED VALUE ANALYSIS
The earned value analysis is one method that can be used in controlling time and costs in a
project. In the construction management book written by (Widiasanti and Lenggogeni, 2013),
the earned value analysis has several benefits to increase the level of effectiveness in
monitoring and controlling project activities and can be developed to make estimates or
projections of the future state of the project.
There are three basic elements that serve as a reference in analyzing the performance of a
project based on the concept of result value, namely:
• BCWS (Budgeted Cost for Work Scheduled)
• BCWP (Budgeted Cost for Work Performed)
• ACWP (Actual Cost for Work Scheduled)
RESEARCH METHODOLOGY
Research Time and Place
Data Collection
Location : Kebumen Regency
Research Time : July 2022 1.Primary Data :
– October 2022
Type of Research
Interview
observation method
Quantitative research
2.Secondary Data :
Weekly report
Object of Research S .curve
RAB
1. Materials used
Contract documents
2. Human resources
3. Equipment used
4. Implementation methods
R F
E L
S O
E W
A C
R H
C A
H R
T
ANALYSIS & DISCUSSION
implementation ‘s’ curve plan
First addendum (1), changes made to the first addendum based on a meeting
between the Commitment Making Officer and PT. Adhi Karya (Persero) Tbl. on
April 6, 2022 according to the results of the meeting minutes regarding
adjustments to the budget, it is necessary to hold discussions regarding
adjustments to the planned budget costs stated in the contract. Based on this, PT.
Adhi Karya (Persero) Tbk. has made adjustments to the volume to be built with
the price of the work unit where the initial contract value is Rp.
167,496,914,000.- proposed change to Rp. 127,972,308,000.-
‘s’ curve after 1st Addendum
Second Addendum (2), in the implementation of the second
addendum there is a change in the contract value. After the
first addendum agreed that the contract value was
Rp.127,972,308,000.-, in the second addendum the project
value was changed to Rp. 138,977,125,000.00 (Incl. VAT).
‘s’ curve after 2nd Addendum
Third addendum (3), in the implementation of the third addendum there was a
change in the contract value which was initially Rp. 138,977,125,000.00 (Incl.
VAT). - to Rp. 140,273,517,000.00 (Incl. VAT).-.
After adding the addendum three times, it can be seen that the realization of the work in the
field is faster than the project plan on the S curve. With three addendums in the project
implementation, to carry out an analysis with earned value must adjust the value of the
applicable contract in each period.
PROJECT ACTUAL COST RECAPITULATION
Analysis by using Earned Value Method
CPI calculations are performed using BCWP and ACWP data to SPI calculations are carried out using BCWP and BCWS data to
determine the efficiency of project resource use. If the CPI value < 1 determine the efficiency of project resource use. If the SPI value > 1
indicates that the costs incurred in project realization are greater than the indicates that the project realization time is faster than the planned
planned costs. Meanwhile, if the value > 1 indicates that the costs time. Meanwhile, if the value < 1 indicates that the implementation
incurred are less than the planned costs. time is slower than the planned time.
CPI = SPI =
= =
= 1,289
= 1,10968
Calculating the ETC Value Calculating the EAC Value
EAC = ACWP + ETC
The ETC value is obtained by using the equation below: = Rp 2.383.323.234 + Rp 105.660.846.685
ETC = (Total Budget Plan – BCWP)/CPI = Rp 108.044.169.919
Below is the calculation of ETC Value in week 15 th : Based on the calculation above, in the 15th week, the estimated final
ETC = (Rp 140.273.517.000– Rp )/1,10968 project completion cost is IDR 126,408,570,824. The graph below
= Rp 105.660.846.685 shows the estimated cost of final project completion every week,
starting from the first week to the 20th week.
Calculating the ETS Value Calculating the EAS Value
RESCHEDULE
CONCLUSIONS
1. Project implementation from the first week to the 20th week did not over budget.
2. The remaining costs needed to complete the remaining work in the 20th week are IDR
82,797,929,739 in 12 weeks.
3. The project can be completed 2 weeks earlier than planned without increasing the
number of workers and days if the worker's performance is the same as the previous
weeks
CONCLUSIONS & SUGGESTIONS
SUGGESTIONS
Work on the critical path must be an important highlight to ensure project performance is
in accordance with the planned schedule.
This study uses the PDM and earned value analysis. For further research, several
more methods may be used to make it more complex.
THANK
YOU