Professional Documents
Culture Documents
Capital Cost Estimation Dr. Rakesh Kumar
Capital Cost Estimation Dr. Rakesh Kumar
• The capital necessary for the operation of the plant is termed the working
capital(WC).
• The sum of the fixed-capital investment and the working capital is known
as the total capital investment(TCI)
• The ratio of working capital to total capital investment varies with different
companies, but most chemical plants use an initial working capital
amounting to 10 to 20 percent of the total capital investment
Types of Capital Cost
Estimate
1. Order of Magnitude Estimate: Based on similar cost data
For a Class 4 estimate, from Table 5.2, the expected accuracy range is between 3 and
12 times that of a Class 1 estimate. A Class 1 estimate can be expected to vary from
+6% to -4%. We can evaluate the narrowest and broadest expected capital cost
ranges as:
Lowest Expected Cost Range
High value for actual plant cost ($2.0 x 106)[1 + (0.06)(3)] = $2.36 X 106
Low value for actual plant cost ($2.0 x 106)[1 - (0.04)(3)] = $1.76 x 106
The actual expected range would depend on the level of project definition and effort. If
the effort and definition are at the high end, then the expected cost range would be
between $1.76 and $2.36 million. If the effort and definition are at the low end, then
the expected cost range would be between $1.04 and $3.44 million.
Estimating Purchased Equipment Costs
Vendor quote
Most accurate
Convenient
Effect of Size (Capacity)
Cost Exponent
where
Effect of Capacity
Effect of Size (Capacity) cont.
n = 0.4 – 0.8 Typically
Often n ~ 0.6 and referred as the (6/10)’s
Rule
Assume all equipment have n = 0.6 in a
process unit and scale-up using this method
for whole processes
Order-of-Magnitude estimate
Effect of Capacity on Purchased
Equipment Cost
Economy of Scale
Example:
Use the six-tenths-rule to estimate the % increase in purchased
cost when the capacity of a piece of equipment is doubled.
C = Cost
I = Value of cost index
1,2 = Represents points in time at which costs
required or known and index values known
Cost Indicies
• Marshall & Swift Equipment Cost Indexes
• All-industry equipment index - arithmetic average of indexes for 47
different types of industrial, commercial, and housing equipment
• Based on an index value of 100 for the year 1926
• Account for cost of machinery and major equipment plus costs for
installation, fixtures, tools, office, and minor equipment
600
f(x) = 0.000000122391 x ⁶ − 0.00142696 x ⁵ + 6.92977 x ⁴ − 17942.2 x³ + 26121800 x²
− 20275400000 x + 6554820000000
500 R² = 0.99466207071883
400
300
200
100
0
1950 1960 1970 1980 1990 2000 2010
Effect of Time
Marshal & Swift and CEPCI
Basis for the CEPCI
Components of Index Weighting of Component (%)
Total 100
Example:
The purchased cost of a heat exchanger of 500 m2 area in 1990 was $25,000.
a. Estimate the cost of the same heat exchanger in 2001 using the two indices
introduced above.
b. Compare the results.
The capital cost of a 30,000 metric ton/year isopropanol plant in 1986 was
estimated to be $7 million. Estimate the capital cost of a new plant with a
production rate of 50,000 metric tons/year in 2001.
Example: 2 heat exchangers, 1 bought in 1990 and the other in 1995 for
the same service
A B
Area = 70 m2 130 m2
Time= 1990 1995
Cost = 17 K 24 K
I = 358 381
The capital cost of a 30,000 metric ton/year isopropanol plant in 1986 was
estimated to be $7 million. Estimate the capital cost of a new plant with a
production rate of 50,000 metric tons/year in 2001.
Example: Heat exchangers, 1 bought in 1990 and the other in 1995 for
the same service
A B
Area = 70 m2 130 m2
Time= 1990 1995
Cost = 17 K 24 K
I = 358 381
What is the Cost of a 80 m2 Heat Exchanger Today 2008 ? CI(2008)
= 575
• Must First Bring Costs to a Common Time
A = 70
B = 130
Off-sites and COff Raw material and final product storage &
utilities loading & unloading facilities; all equipment
necessary to supply required process utilities;
central environmental control facilities; and
fire protection systems
Capital Cost Modules
1. Total Module Cost (Lang Factor)
2. Bare Module Cost
Example: