Professional Documents
Culture Documents
Variations (Gloria)
Variations (Gloria)
1
Instructions (AI)
1. Written Instructions
• Clause2(3)
Architect’s instructions must be confirmed in writing
->If not, MC does not need to comply
• Clause 2(1)
Architect’s written instructions
MC must comply
2
Instructions (AI)
2. Oral Instructions
• Clause2(3)
Allow the architect to give oral instructions
-min. delay in the time taken to written & deliver a written instruction
-MC should get the instruction in writing
if no record, MC runs the risk of losing payment / cannot recall items
- instructions given on site, should be written on site record book by MC & signed by architect
• Normal Procedure, MC to write to the architect within 7 days confirming the instruction
-if architect doesn’t dissent in writing within 7 days of receiving the MC confirmation, then the instruction will take effect
3
Instructions (AI)
3. Clerk of Works Directions
• The clerk of works acts only as an inspector on behalf of the employer under the direction of the architect
- if any instructions are given by clerk of work / architect’s representative
->no effect unless confirmed in written by architect within 2 working days
->if confirmed -> architect instruction
• In practice, clerk of works will usually be treated as architect’s instructions
4
Variations
5
Variations
6
Variations
(c) Work that cannot be properly measured or valued -> use dayworks
7
Variations
Dayworks Basis
-> rates for labour must be those offered by MC in the contract bills
->if the MC didn’t include daywork rates in the contract bills then the rates will be those
given in the current Standard Day Labour Schedules & current Plant
Hire Schedules
-> Materials provided specifically for the variation work will be valued at its actual cost plus
the cost of packing, carriage & delivery with an additional of 15% for overheads & profit
8
Variations
(e)If required by the architect, the MC shall within 14 days of the architect’s
written request, submit a detailed estimate of value of the variation
9
Variations
Pro-rate Rates
• Derivation
• Analogy
• Reconciliation of analysis
10
Variations
Pro-rate Rates
• Derivation
From 2 or more similar unit rates in the contract bills, e.g.
11
Variations
Pro-rate Rates
• Analogy
12
Variations
Fair Valuation
• Estimate of the cost including overheads & profit
- Build up a unit rate from basic principles
- Obtain prices from building price books
-Extract unit rates from BQ on jobs of similar nature
13
Provisional Sums
14
Prime Cost Sums
15
Thank you
16