Professional Documents
Culture Documents
Al Quds University: Dual Study Industrial Engineering
Al Quds University: Dual Study Industrial Engineering
Al Quds University: Dual Study Industrial Engineering
DUAL STUDY
INDUSTRIAL ENGINEERING
Presentation (6)
National Aluminum & profile
company (NAPCO)
DR.RAED MAALI
ENG.MOHAMMAD SHAHEEN
Introduction :
page1
About NAPCO
page2
NAPCO has a seven production lines :
• Cast House
• Extrusion Line
• Powder Coating
• Anodizing
• Wood Effects
• Thermal break line
• Packaging & Delivery
page3
:ACTIVITIES ACHIEVED (PROGRESS)
In maintenance department:
1. Make check list to the main air compressors in the company , in this
check list , we checked the maximum and minimum pressure , the
temperature , leaking and noise.
2. Make a daily work very important like a check oil level to extortion line
press tank cold and hot saw dies furnace a and make check
temperature for container, oil pumps, tie rods, dies furnace and
container pressure .
3. Taking gas, water and electrical meters reading monthly for all
company lines, to calculate the company consumption.
Page 4
:ACTIVITIES ACHIEVED (PROGRESS)
4. Follow up external company's to maintenance some machines in
company like (forklifts, elevator and air conditions device) and take the
maintenance nots machines to registration in technical department.
Page 5
:ACTIVITIES ACHIEVED (PROGRESS)
Page 6
:ACTIVITIES ACHIEVED (PROGRESS)
8. Checking the electrical equipment's in the electrical panels:
relays, photo electrical sensor, proximity sensor, push button,
selector switch limit switches , over loads , contactors, circuit
breakers, timers and sensors by the digital multi meter
(DMM).
10. I can connect 1 phase, and 3 phase motors in star and delta methods,
and how to calibrate the 3 phase motor, and calibrate the belts for any
motor and install limit switch, proximity sensors, photo electrical sensor
to the machines in the production lines.
Page 7
:ACTIVITIES ACHIEVED (PROGRESS)
11. If The electricity lost, I restarted the production lines in the company, and
restarted the compressors in the powder line.
12. Receive gas to fill gas tanks in the company, and receive diesel to fill
generator tank and public services tank.
13. Fixing the cranes in all production lines in the company, like: the
extrusion line crane, all cranes in the warehouse, the cast house crane,
anodizing crane, soda crane, dies crane and I can to change the remote
control to any crane.
14. I can to solve any electrical problem in lighting and power distribution in
company.
page8
:ACTIVITIES ACHIEVED (PROGRESS)
14. Add oil (68 hydraulic) to the press piston hydraulic tank in extrusion
line we turn off the filtration pump and installation pipes from pipes
drain and turn on filtration pump to add oil.
16. I can to Maintenance the air compressors 1+2+3 we changed oil filter
and separators changing a cooling fan to any compressors.
page9
:RECOMMENDATIONS
I hope in the next practical periods from the company to develop my training by
page10
:CONCLUSION
how to deal with machines, and workers, obligation in the work , work clothes,
listening to the advices, speed in work, respect all , I learned to work in all
working conditions in hard, and comfortable work, and work in any section in
the company is help me to develop my experience, to make me successful
engineer.
page11