Professional Documents
Culture Documents
Comparision of Condition of Contract
Comparision of Condition of Contract
BaTCoDA 1987
vs
MoWUD 1994
Duties and powers of the Engineer
BaTCoDA 1987 standard conditions MoWUD 1994 standard conditions
(d) Variations exceeding 15% under clause (d) Variations exceeding 10% under clause
52(3); 52(3)
( i ) Time Extension under clause 44 where ( i ) Time Extension under clause 44 where
the cumulative Time Extension granted the cumulative Time Extension granted
under the clause 44 exceeds 15% of the under the clause 44 exceeds 25% of the
Contract Time Contract Time
Performance bond
BaTCoDA 1987 standard conditions MoWUD 1994 standard conditions
Clause 10 Clause 10
The Contractor undertakes to enter into a The Contractor undertakes to enter into a
bond for the due and proper performance bond within 30 days after the receipt of the
of the contract and observance of all letter of acceptance for the due and proper
provisions, covenants, conditions and performance of the contract and
stipulations therein after provided for in observance of all provisions, covenants,
the sum of 10% of the contract price until conditions and stipulations therein the sum
the completion of the works….. of 10% of the contract price. The bond
shall be in the form as may be agreed
between the employer and the
contractor….
Variations
BaTCoDA 1987 standard conditions MoWUD 1994 standard conditions
Sub-clause 52-3 Sub-clause 52-3
If, on certified completion of the whole of If, on certified completion of the whole of
the works it shall be found that a reduction the works it shall be found that a reduction
on increase greater than 15% other sum or increase greater than 10% other sum
named in the contract excluding all fixed named in the contract excluding all fixed
sums, provisional sums and allowances for sums, provisional sums and allowances for
day works, if any, results from: day works, if any, results from:
(a)the aggregate effect of all variation (a)the aggregate effect of all variation
orders, and orders, and
(b) all adjustment upon re-measurement of (b) all adjustment upon re-measurement of
the estimated quantities set out in the bill the estimated quantities set out in the bill
of quantities, … of quantities, …
Advance payment
BaTCoDA 1987 standard conditions MoWUD 1994
standard conditions
Sub-clause 60-1, 60-2, 60-4
(1)… and advance payment equal to that stated in the tender
Not mentioned.
proposal shall be made to the contractor by the employer within
15 days of the receipt of the payment guarantee or performance
bond whichever comes last…
The contract price shall be deemed to have The contract price shall be deemed to have
been calculated in the manner set out been calculated in the manner set out
below and shall be subject to the below and shall be subject to the
adjustment in the specified hereunder:- adjustment in the event specified
hereunder:-
(b) If the said rates of wages and other (b) If the said rates of wages and other
emoluments and expense are increased or emoluments and expense are increased or
decreased by any act, statute, decree, decreased by any act, statute, decree,
regulation and the like after the said date regulation and the like after the said date
of bid pricing, then the net amount of the of bid pricing, then the net amount of the
increased or decreased of the emoluments increased or decreased of the emoluments
and expenses shall form an addition or and expenses shall, after due consultation
deduction as the case may be to or from with the employer and the contractor, be
the contract price and be paid to or determined by the engineer and shall form
allowed by the contractor accordingly. addition or deduction as the case may be to
or from the contract price and be paid to or
allowed by the contractor accordingly.
Increase or decrease of costs
BaTCoDA 1987 standard conditions MoWUD 1994
standard conditions
e)The rates contained in the priced bill of quantities are based
upon the market prices of the materials and goods specified in Not mentioned
the appendix to the bill of quantities and current at the date of
bid pricing (hereinafter referred to as “the basic prices”. The
contractor shall state in the said schedule the basic prices of
such materials and goods. Such prices shall be paid to or
allowed by bona-fide quotations from suppliers.
BaTCoDA conditions do not explicitly state the time limit. And this may lead to a
dispute, as performance bond is a condition to make an advance payment.
Advance payment
In the case of MoWUD conditions, the amount is served as a criterion for bid
evaluation. Those who requested advance payment and those who do not are not
thus equally evaluated. The interest on the requested amount is considered to be an
opportunity cost to the employer and is added to the contract price submitted.
However in the case of BaTCoDA conditions, the advance payment is not used as a
criterion for evaluation. The employer/consultant should indicate in the special
conditions its amount irrespective of the bidder’s request and this will not affect the
bid evaluation. This is an important provision since most domestic contractors lack
the financial capacity to cope with the high working capital demand of construction.
Recommendations
Liquidated damage
MoWUD conditions have the maximum limit of the liquidated damage to be 20 %. This
is punitive to the contractor than beneficial to the employer, as the limit exceeds the
profit margin. this leads to bankruptcy of the contractor.
BaTCoDA conditions have the maximum limit of the liquidated damage to be 10 %.
This is relatively more fair for both parties and do not discourage the local contractors
as the limit do not exceed their profit margin.
Price escalation
MoWUD conditions assume the market to be a stable one. In the absence of such an
adjustment, contractors are obliged to cover the incurred extra expenses offsetting the
balance from their profit margin. These conditions do not explicitly address an increase
or decrease in cost of labor or materials with respect to the country’s market but rather
dealt with only increase or decrease of rates of wages and other emoluments and
expenses subsequent to change in legislation. Most local contractors have been
discouraged because of this wrong assumption.
In case of BaTCoDA, Price escalation is entertained. The only adjustments to be
allowed are on the difference between the basic prices and market prices of the materials
and goods listed in the appendix to the bill of quantities after the bid pricing date. These
provisions try to address the inconsistency of the market prices and are relatively better.
•
Recommendations
Variations
MoWUD conditions allow a change or alteration of the original work or
simply an addition to or omission from it up to 10% by the engineer.
Exceeding 10%, the Engineer requires the specific approval of MoWUD.
Procedure of Claims