CEILING

ENCLOSURE
BY TEKTON STRONG BUILDERS CORP
SCOPE OF WORK

• The purpose of this work statement for


the installation of ceiling enclosure is to
outline and describe in detail the safe
procedure of ceiling enclosure including
other related activities such as survey &
layout, delivery/handling, installation of
ceiling framing, expansion bolt and other
related works to complete the scope.
ALL PLANT AND EQUIPMENT

CORDLESS DRILL ELECTRIC DRILL TAPE METER


ALL PLANT AND EQUIPMENT

CORDLESS DRILL 3-STEPLADDER WORKING


PLATFORM
**PRIOR TO START CEILING FRAMING &
ENCLOSURE ACTIVITY**
- All workers must undergo work activity training (WAT)
prior to mobilization Secure permits prior to painting works
- Secure material transmittal form per delivery
WORK (warehouseman)

EXECUTION - Check all materials if in good condition before application

- Ensure request inspection to QA for Ceiling before a


Ceiling Framing & Enclosure
- Secure permits prior to painting works
1. MATERIAL HANDLING, STORAGE
AND PROTECTION

a. Deliver materials to the project site in


WORK untouched packaging or in container must
have the following information listed
EXECUTION below
• Product Name
• Product Description
• Manufacturers date & Expiration date (depends on
the item material)
1. MATERIAL HANDLING,
STORAGE AND PROTECTION

WORK b. Store materials that are not in use


EXECUTION in a tightly covered container and in
a well-ventilated areas
• Maintain containers in good condition
• Remove away any unnecessary items or
chemicals that could cause contamination
• Keep the storage area clean and dry
1. MATERIAL HANDLING,
STORAGE AND PROTECTION

c. Manual Hauling Materials


WORK
• Ensure proper lighting inside and outside of the
EXECUTION storage area
• Remove objects that can cause slip, trip and
cuts to workers
• Use of rubber knitted gloves as hand
protection, safety shoes, hard hat during
hauling of materials
2. PRE-INSTALLATION /
APPLICATION
REQUIREMENTS

• Assure all methodologies, materials, mock-ups, and


WORK shop drawings are approved prior start of activity.
EXECUTION • Secure material transmittal form inspection per
delivery
• Assure proper handover procedure is implemented
on-site.
• Secure all necessary permits prior to work activity
(work request, tools permits, etc.)
2. PRE-INSTALLATION / APPLICATION
REQUIREMENTS

• Ensure the gypsum boards and accessories


material undergone sorting with reference to
its code, design, size and no damages. Use of
WORK complete PPE such as hand protection
(gloves)
EXECUTION • Before to start suspended ceiling works,
QA/QC engineer should follow up all balance
work to concerned parties.
• QA/QC procedures shall follow work
inspection request, inspection shall be carried
out different work tiers and clearances. It
should be obtained at progressive levels as
mentioned therein
3. WORK PROCEDURE

INSTALLATION CEILING GUIDE

WORK • Apply leveling hose or a leveling laser to level


every corner of the ceiling wall to determine the
EXECUTION perimeter height to ensure that the ceiling
installation is even. After that, set a guideline for
it.
• Attach the wall angle to the perimeter wall by a
concrete nail or any fastening materials.
• Fix & align accurately the steel angle with
maximum interval of 1220 mm (4ft).
• Tie the suspension rod securely to the steel angle.
3. WORK PROCEDURE

INSTALLATION CEILING GUIDE

WORK • Attach the carrying channel to the


suspension clip using rod joiner.
EXECUTION • Connect the furring channel to carrying
channel using the w-clip. Furring channel
can be spaced at 406 mm or 16 inch. up to
610 mm or 24 inch
• Ceiling boards (gypsum board) are
attached to the furring by gypsum screw.
CEILING CHANNEL
• - WALL RUNNER / WALL ANGLE
• - DOUBLE FURRING CHANNEL
• - DOUBLE FURRING CLIP
• - SINGLE FURRING CHANNEL
• - SINGLE FURRING CLIP
• - SUSPENSION ROD HANGER
• - SUSPENSION ROD
• - CARRYING CHANNEL
• - CARRYING CHANNEL JOINER
• - CARRYING CHANNEL
HANGER
3. WORK PROCEDURE

INSTALLATION OF STEEL FRAMING FOR


SUSPENDED CEILING
WORK • Apply leveling hose or a leveling laser to level every
corner of the ceiling wall to determine the perimeter
EXECUTION height to ensure that the ceiling installation is even. After
that, set a guideline for it.
• Attach the wall angle to the perimeter wall by using a
screws, stub nails or drywall fasteners depending on the
wall type.
• The ceiling is to be set out from the center to balance the
width of the boards at the perimeter. Center to center
distance for main runners and cross tees at 2ft x 2ft or 2ft
x 4ft
• Maximum distance from wall to first hanger is 2ft.
3. WORK PROCEDURE

INSTALLATION OF STEEL FRAMING


FOR SUSPENDED CEILING
WORK
• Main tees (main runners) are joined together by
EXECUTION inserting a tab on the end of one section into a
slot in the adjoining section
• Cross tees are inserted in slots in the main tees
and locked in position with minimal downward
force
• When all sections have been installed,
adjustment can be made to ensure that the whole
suspension is leveled.
• ATTACHMENT
TO CONCRETE
SLAB OF
SUSPENDED
CEILING
MAIN TEE & CROSS TEE
CEILING
FRAMING
3. WORK PROCEDURE

METHODS OF GYPSUM BOARD


APPLICATION
WORK A. Measure the dimensions using tape meter.
EXECUTION B. Once the ceiling framing is complete. Black screws
are used to secure the boards to the furring channel.
C. Boards must be cut either by scoring and breaking
or by sawing.
D. Mark the placement of light fixtures and vents on
the drywall.
E. Cut edges should be smoothed to obtain neat joints
when installed
3. WORK PROCEDURE

METHODS OF GYPSUM BOARD


APPLICATION

WORK F. Raise the first piece of gypsum board to the ceiling.


Make sure that the tapered edges of the sheet are facing
EXECUTION the floor
G. Repeat the process along the wall, always ensure that
the tapered edges touch one another and are facing
down.
- The tapered edges are designed to make the process
of taping and mudding easier, so it’s should be remain
facing down
H. Permanently fasten the gypsum board to the ceiling
joists. Place the fasteners 7 inches (18 cm) apart along
the perimeter, 0.375 inches (0.95 cm) from the edges of
3. WORK PROCEDURE

METHODS OF GYPSUM BOARD


APPLICATION
WORK
I. Start the second row with a half sheet of drywall to
EXECUTION stagger the seams.
- Using a utility knife, cut through the board at the
vertical midpoint of the drywall sheet after measuring
and marking the cut line. The panel should be tipped off
the ground or table at a little angle, then pushed down
to split it in half.
- Use the same procedure to attach this half-piece of
drywall as you used on the first row of drywall.
3. WORK PROCEDURE

METHODS OF GYPSUM BOARD


APPLICATION
WORK
J. Repeat the process until the entire ceiling is
EXECUTION covered. Make sure to stagger the seams to
ensure the drywall’s stability
K. Short edges should be chamfered
L. Create holes where vents, lights, and electrical
boxes are marked after the drywall has set. To
make the cutting procedure quick and simple,
use a spiral cutout saw.
3. WORK
PROCEDURE
FINISHING OF GYPSUM
BOARD
Joint Treatment
WORK
EXECUTION a) Before filling and covering of joints, board
surface should be cleaned and free of dust.
b) First coat of joint filler (putty) should be
applied with tools of sufficient width to extend
a minimum 50 mm beyond both sides of the
center of the joint (100 mm width).
(Paleta/putty knife, plastering trowel)
3. WORK
PROCEDURE
FINISHING OF GYPSUM
BOARD
Joint Treatment
WORK
EXECUTION
c) Joint Tape should be embedded into the joint
filler to reinforce the joint between two gypsum
boards
d) Once the first coat of joint filler (putty) has
dried, a second coat of joint filler (putty)
should be applied with 100 mm width on both
sides of the center of joint tape (200 mm width)
3. WORK
PROCEDURE
FINISHING OF GYPSUM
BOARD
Joint Treatment
WORK
EXECUTION
e) A very thin third coat of joint filler (putty)
should be applied with a minimum width no
less than 150 mm beyond both sides of the
center of the joint tape (300 mm width).
f) Once third coat has dried, surface should be
sanded and smoothed.
JOINT
TREATMENT
CLEANING
At the end of each work, remove
rubbish, cut boards dust, and other After completing ceiling board
discarded materials from project site. installation, clean area from dust and
Clean the area before and after from cut boards and trims
activity

Provide final protection and maintain


conditions, in a manner suitable to At a completion of construction
installer, w/c ensures, gypsum board activities of other trades, touch up and
construction being without damage at restore damaged..
time of Substantial Completion.

Use of appropriate and complete PPE


during working hours and while inside
the site premises, such as eye Clean the area before and after work
protection (goggles), hand protection activity
(gloves), reflectorized vest and safety
shoes.
QUALITY ASSURANCE
AND CONTROL
TESTS Refer to Project-WP-ITP–Inspection and Test Plan/ Construction Specifications
INSPECTIONS Refer to ITP – Inspection Plans Refer to Forms – Inspection Checklists
and Forms

MEASURING AND TESTING EQUIPMENT TO BE CALIBRATED


Calibrated tools & equipment
Steel Tape, L-square, Level Bar
provided by TEKTON

PARTIES AND PRODUCTS REQUIRING ACCREDITATION OR CERTIFICATION

Gypsum board, J-Furring, C-Channel Wall angle, accessories


THANK YOU