Implementation of Proposed Google Data

Center at Mesaimeer Technical Building

Weekly Progress Report - Week 18

25 September 2021
Site Plan

| |
Project Dashboard
Timeline Summary - As per signed contract

Project Start Project Finish Total Duration Elapsed Duration Remaining Duration

15 May 21 05 Feb 22 267 days 134 133

Timeline Summary

Project Start Project Finish Planned % Achieved % Variance Remarks


15 May 21 11-Dec-21 60.04% 25.62% 34.42% TBD
Revised Start Revised project Finish Revised Planned % Revised Actual % Variance Remarks
15 May 21 05 Feb 22 25.11% 25.62% +0.51% TBD

HSE Summary
No of accidents No of Near Misses Tool Box Talks No of HSE Meetings
0 3 15 15

LLE Summary

No. of LLE Order Placed Submitted for approval Approved Under Review Revise & Resubmit Rejected

17 17 17 17 0 0 0

General Engineering Submittal Summary

Total Target Submitted Under Review Approved Revise & Resubmit Rejected Pending

677 620 612 79 378 101 30 65

| | 3
Project Dashboard
Basement Floor Activity First Floor Activity
1 Demolition of Battery Rooms Existing Walls with 100% Progress. 1 Removal of Existing Chilled Water Pipes Started at First Floor Data Hall A1.

2 Demolition of Existing Walls at MMR Rooms to make an Opening for 2 Removing of Existing Services Progress is 98% at Data Hall A1.
Proposed Door Location.
3 Installation of Cable Tray Support at First Floor in Progress.
3 Modification Work of NOVEC System at Battery Rooms in Progress.
4 Plastering Work at First Floor Electrical Rooms in Progress.
4 Rerouting Work of Fire Fighting System at Basement Floor. 5 • Ceiling Surface Preparation ( Plastering & Painting ) at Data Hall B with
5 • Rerouting of Drainage System at Basement Floor in Progress. 85% Progress.

6 • Installation of Cable Tray Support & Cable Tray at Basement Floor in 6 • Ceiling Surface Preparation ( Plastering & Painting ) at Data Hall C with
Progress. 85% Progress.

7 • Block Work at FSS,TX Rooms & LV Room-3 at Basement in Progress. 7 • Installation of Gypsum Partition Walls Started at Data Hall B with 90%
Progress.
8 • Block Work at Fuel Pump Room at Basement in Progress .
8 • Installation of Gypsum Partition Walls Started at Data Hall C with 90%
9 Progress.
10 • Form Work Started at TX Room-4. 9 • Installation of Gypsum Partition Walls at Data Hall A 1 Started with 50%
11 • Form Work Started at LV Room-1. Progress.

Ground Floor Activity Penthouse Activity


10 • Installation of Gypsum Partition Walls at Data Hall A2 Started with 75%
Progress.
1 Ceiling Surface Preparation ( Plastering & Painting ) Started at Ground Floor 1 Removal of Existing Chilled Water Pipes Started at Penthouse Chillers Area.
with 85% Progress. 11 • Rerouting Work of Fire Fighting System.
2 Removal of Existing Electrical Cables & Cable Trays Started at Penthouse
2 Block Work at Ground Floor Generator Room in Progress. Chillers Area.

| | 4
Project Dashboard
Key Issues Two Weeks Look Ahead Plan
1 Gate pass approval & entrance to site which it may delay the project
completion date. 1 • Material Submittals of Short Lead Items.
• Shop Drawing Submission.
2  PTW • Ordering of Short Lead Items.
2 • Implementing Gate Passes.
3  Generator room Layout • PTW.
3 • Civil work at Technical Building Battery Rooms Area.
4  Chillers Location Layout
4 Commencement of Mechanical Work at Basement & First Floor.
5  Chilled Water Pipes Inside Electrical Room
5 Commencement of Civil Work at Penthouse.
6  DC2 Approval

Material Arrival at Site


1 UPS Equipment

2 Transformers

3 Fuel Bulk Tanks

4 Remote Radiators

| | 5
HSE Statistics
Lease Project EHS Performance Statistics   
Average daily Head Count (Week) Average Total daily headcount (to date) 78
176
Total Hours Worked (Week) 10560 Total Hours Worked (to date)                       (THW) 88400
Lost Time Incidents (Week) Total No. of Lost Time Incidents                   (LTI) NIL
NIL
Includes any missed work shift due to injury or work related illness.
Medical Treatment Cases (Week) Total No. of Medical Treatment Cases         (MTC) NIL
NIL
Any treatment beyond first aid even in the camp for COVID-19.
First Aids cases (week) First aid cases (to date) NIL
NIL
Near Misses (Week) Near Misses (to date) 3
0
Incidents involving HRA's (Week) Incidents Involving HRA's (to date) 2
NIL
LTIR Rate (Project to date)       ((LTI +MTC)/THW)*200,000
No. of Induction (week) Total No. of Induction (to date)
15 436
• Visitors • Visitors
• Workers • Workers
No. of safety Awards / recognitions (week) Total No. Safety Awards / recognitions (to date)
0 4
No. of Disciplinary actions taken (Week) Total No. Disciplinary actions taken (to date)
3 29
No. of Inspections / Audits (week) No. of Inspections / Audits (to date)
6 72
No. of Work Permits issued (week) Total No. of Work Permits issued (to date)
84 498
No. of Safety Stand Downs (week) No. of Safety Stand Downs (to date)
• Tool-Box-Talks
61 • Tool-Box-Talks
433
• Safety Briefings • Safety Briefings
• Trainings • Trainings
- External - External
- Internal - Internal
No. of Environmental Incidents (week) Total No. of Environmental Incidents (to date)
NIL NIL
| | 6
HRAs

                     

Totals
Ground Lifting Working Extreme
Mobile Material Energy Confined Hazardous infectious
Disturbanc Operatio From Driving Electrical Temperatur Noise
Equipment Handling Isolation Space Material disease
    e ns Heights e
Week
18 - 25 September
21 191 6 6 6 0 18 36 24 35 0 48 6 6 0
25 - 02 October 21 191 6 6 6 0 18 36 24 35 0 48 6 6 0
02 - 09 October 21 191 6 6 6 0 18 36 24 35 0 48 6 6 0
09 - 16 October 21 191 6 6 6 0 18 36 24 35 0 48 6 6 0

| | 7
Input Requirements / RFIs

Date Action Required Date


Issues / RFIs Action / Status
Raised with by Date Replied
Meet Me Room 1 & 2 Section 18th 23rd
1.
Details Under Review / (Open) September QDC September -
C 018 2021 2021
Reply to Additional Information 16th 21st
2. Required for Drainage Pipes in Under Review / (Open) September QDC September -
Toilets at First Floor M 008 2021 2021
22nd 27th
Change in Location of Busduct
3. Under Review / (Open) September QDC September -
Riser to Generator E 017
2021 2021

RFI Submittal Summary

Total Submitted Replied Pending

45 42 3

| | 8
Long Lead Equipment - Summary
EXPECTED
S. EXPECTED Released For ESTIMATED DELIVERY APPROVAL ORDER
ITEM QTY DELIVERY Forecast Date
NO. ORDER DATE Manufacturing DATE STATUS STATUS
DURATION 

1 4 Nos. TBD BY 15-Nov-2021


CHILLERS 14-JUN-21 OOREDOO 12 TO 14 WEEKS 28-SEP-21 AWC ORDRED
2 TRANSFORMER 8 Nos. 14-JUN-21 22-JUN-2021 12 TO 14 WEEKS 12-JULY-21 30-Aug-2021 AWC ORDRED
3 CRAH UNIT 32 Nos. 14-JUN-21 09-JUN-2021 12 TO 14 WEEKS 21-SEP-21 28-Nov-2021 AWC ORDRED

4 28 Nos.
AHU & FAHU 14-JUN-21 TBD BY QDC 10 TO 12 WEEKS 28-SEP-21 15-Nov-2021 A ORDRED
09-JUL-21
5 LS
FUEL SYSTEM 14-JUN-21 10 TO 12 WEEKS 28-SEP-21 30-Oct-2021 AWC ORDRED
COLD AISLE
6 CONTAINMNET WITH LS TBD BY 10 TO 12 WEEKS
GRILLS 14-JUN-21 OOREDOO 22-AUG-21 15-Jan-2022 AWC ORDRED
7 8 Nos.
CHW PUMPS 14-JUN-21 12-JUl-2021 10 TO 12 WEEKS 7-SEP-21 28-Oct-2021 AWC ORDRED
8 UPS & BATTERIES 13 Nos. 14-JUN-21 08-JUN-2021 12 TO 14 WEEKS 24-AUG-21 30-Oct-2021 AWC ORDRED
9 GENERATOR 8 Nos. 1-JUN-21 25-MAY-2021 14 TO 16 WEEKS 25-OCT-21 30-Oct-2021 AWC ORDRED
10 PDU / PPC 28 Nos. 7-JUN-21 22-JUN-2021 10 TO 12 WEEKS 21-OCT-21 15-Dec-2021 AWC ORDRED
BUSWAY SYSTEM & TAP TBD BY
11 LS
OFF 14-JUN-21 OOREDOO 10 TO 12 WEEKS 21-SEP-21 14-Dec-2021 A ORDRED
12 LS
IBMS 14-JUN-21 TBD 10 TO 12 WEEKS 21-SEP-21 29-Oct-2021 AWC ORDRED
13 LIGHTS LS 14-JUN-21 TBD 10 TO 12 WEEKS 18-AUG-21 30-Oct-2021 AWC ORDRED
14 FM200 LS 14-JUN-21 TBD 10 TO 12 WEEKS 7-SEP-21 28-Oct-2021 AWC ORDRED
15 LV PANELS 8 Nos. 14-JUN-21 TBD-AFTER DC2 10 TO 12 WEEKS 14-SEP-21 30-Oct-2021 A ORDRED
16 BUSDUCT LS 14-JUN-21 17-JUN-2021 10 TO 12 WEEKS 13-OCT-21 15-Nov-2021 AWC ORDRED
| | 9
17 LS
Progress Photos at Basement
 Form Work at TX Room-4.

| | 10
Progress Photos at Basement
Form Work at LV Room-1.

| | 11
Progress Photos at Basement
 Block Work at Basement

| | 12
Progress Photos at Basement
 Block Work at Basement

| | 13
Progress Photos at Basement
 Installation of UPS at UPS Rooms

| | 14
Progress Photos at Basement
Demolition of Existing Wall to Make an Opening for Proposed Door at MMR

| | 15
Progress Photos at Basement
Demolition of Existing Wall to Make an Opening for Proposed Door at MMR

| | 16
Progress Photos at Ground Floor
 Block Work at Generator Room.

| | 17
Progress Photos At First Floor
 Installation of Gypsum Partition Progress at Data Hall A2.

| | 18
Progress Photos At First Floor
 Installation of Gypsum Partition Progress at Data Hall C.

| | 19
Progress Photos At First Floor
 Installation of Gypsum Partition Progress at Data Hall B.

| | 20
Progress Photos At Penthouse
 Demolition of Existing Chilled Water Pipes & Fittings.

| | 21
Arrival of Equipment to Site
 Transformers.

| | 22