Download as pptx, pdf, or txt
Download as pptx, pdf, or txt
You are on page 1of 19

Department

of
Electrical Power Engineering
Presenter Name: Maduna Sandile

Supervisor: Prof. I. E. Davidson


Design title

Design of LV distribution kiosk and


distribution board based on the load estimate
to accommodate circuits feeding a warehouse.
LV
NETWORK Outline of Presentation

• Introduction
• Aims
• Design constraints
• LV background
• Prototype simulation and results on EcoStructure Power
Design software tool
• Prototype design
• Bill of materials and prototype budget
• Conclusion
LV
NETWORK

Introduction

• Power systems deliver power to loads that perform a


function.
• It contains protective devices to prevent injury or
damage during failure.
LV
NETWORK

Aims and objectives

• To design a LV distribution board that will


accommodate the warehouse loads.
• To verify the voltage drops on the LV distribution
network.
• Verify the cable and circuit breaker sizing.
LV
NETWORK

Design constraints

• Nature of the project.


• Project minimization.
😒
LV
NETWORK
LV network background

• According to SANS 1019,


LV networks are defined
as networks having a
voltage level of 0 to
1000V.
• SANS 10142-1 5%
voltage drop level.
Figure 1; LV distribution network.
LV
NETWORK

Background cont’d

DB components
• Miniature circuit breakers
• Earth leakage circuit breakers
• Surge protection device

Figure 2; Single-phase DB
LV
NETWORK Prototype simulation and
results
LV
NETWORK
CB sizing results
LOAD CB SIZE

1. Light load (72 W) 10 A


2. Switched socket load (4 kW) 20 A
3. Main Supply (14.5 kVA load) 63 A

Cable sizing and voltage drop results


Loads Length (m) Cable size (mm2) Voltage drop (%)

Source - 10 400 (aluminium) -


transformer
Transformer – kiosk 5 240 (copper) 0,065

Kiosk – DB 30 10 (copper) 1,11


DB – SSO load 10 2,5 (copper) 2,45
DB – Lighting load 5 1,5 (copper) 1,15
Prototype design

Figure 3; DB layout
Prototype design

Figure 4; DB with loads.


LV
NETWOR Prototype design
K

Figure 5: Single-phase DB voltage testing.


LV
NETWORK
Prototype design

Figure 6; DB with a spare CB.


LV
NETWORK Prototype design
LV
NETWORK Bill of materials and
prototype budget
S/N Item/Component Unit Cost (in
Rand)
1 63A earth leakage 2-pole 1 R199.95
2 20A circuit breaker 1-pole 2 R73.96
3 10A circuit breaker 1-pole 1 R33.32
4 PVC Single Switched socket 1 R78.00
5 PVC 1-lever 2-way light switch 2 R72.00
6 1-Pole Surge protector DIN rail 1 R150.00
7 2.5 mm2 Twin and Earth flat cable 8m R208.00
8 4 way DB box 1 R130.00
9 Wall box 4×4 PVC 1 R12.45
10 Wall box 4×2 PVC 1 R6.05
11 20mm PVC glands 7 R15,75
12 Lamp holder 1 R10.10

Total budget = R989.58


Overcurrent and short circuit in
an electric design can lead to
faulty design.

Correct circuit breaker sizes must


be used so that the electrical Conclusion
network should work properly.

When selecting proper size


conductors for supplying power
from the source to the load, the
designer of a DB must adhere to
appropriate standards.

You might also like