Professional Documents
Culture Documents
Ropeway Projects
Ropeway Projects
Since 2018,
the Indian government has been advocating ropeways for
tourism and urban transport.
They are encouraged as a low-cost, low-energy form of
transport and development that can reduce pollution
objections
“Unlike the traditional use of ropeways in the hills, the current thrust is connected
with tourism and commercial purposes.”
Issues
by creating and enhancing more transport facilities for the public & tourists.
to take measures to revive the Sukhatal Lake owing to its importance as life line and
recharge zone of the Naini Lake and
like inside the shoreline of Sukhatal, and to take other remedial measures for
mitigation of the damage caused by the illegal and unplanned construction and
developmental activities
finally
The respondent invited tenders for installation of Aerial Ropeway System at Gandhamardan Bauxite Project
on turn key basis in Orissa by issuing Notice Inviting Tender (NIT) dated 30.9.1982
Pursuant to the invitation of tender, petitioner submitted its bid to the respondent at Delhi.
the date of contract will start when Balco (respondent) pays 10% advance after issuance of letter of intent and
the contract was to be completed within a period of 22 months from the date when 10% advance was
paid.
….
o The petitioner was supposed to submit a bank guarantee for this advance of 10% of the
contract value in the Balco's prescribed format within 10 days of issuance of letter.
o The contract was to be governed by the terms and conditions as per Notice Inviting Tender
(NIT).
……
The petitioner's case is that the work on the project could not take off and was kept on hold. 10% advance was
not paid by the respondent.
There was also an agitation by the local tribal people against the project.
the project was kept on hold by it hoping that the tribal upsurge against the project would subside and the final
environment clearance would be granted by the Central Government. The correspondence on this account
continued between the parties from October 1983 onwards, when the initial letter of intent was issued
Issues which needed resolution
i. Payment for goods inspected and supplied at site.
ii. Payment and acceptance for goods and supplies ordered on account of Balco project
ready and awaiting dispatch.
it was not responsible for the contract being on hold and the circumstances,
beyond the control of the respondent were responsible for the frustration of the
contract.
the issue regarding existence of the contract itself would be one of the issues and
respondent hoped that matter would be resolved amicably between the parties.
The petitioner filed the present suit
praying the court that respondent be directed to file arbitration agreement and the disputes
between the parties be referred to Justice H.L. Anand (Retd.)
that the contract containing the arbitration agreement was void under Section 20 of the
Indian Contract Act. The arbitration agreement having become void was not enforceable.
Further stated
the conditions precedent to invoking the arbitration agreement were not fulfillled and the arbitration
agreement could not be invoked by the petitioner without fulfillling the conditions.
……..Court has no jurisdiction to entertain this suit inasmuch as according to the terms of the agreement
based on the NIT and General Conditions of the Contract,
all disputes arising out of the contract are deemed to have arisen in Bilaspur/ Ratnagiri and only the courts
at Bilaspur/ Ratnagiri shall have jurisdiction to entertain the suit.
Issues
1. Whether this Court has no jurisdiction to entertain and try this petition
2. Whether there exists a valid, subsisting arbitration agreement between the parties
3. If issue No. 2 is proved, whether the petitioner has not properly invoked the arbitration
agreement
4. What are the disputes required to be referred for arbitration.
Court
and the matter was remanded back to Single Judge to decide the entire matter afresh in accordance with
law.
Court’s Jurisdiction
clause in contract
All disputes arising out of or in any way connected with this agreement shall be deemed to
have arisen in Bilaspur/Ratnagiri and only the Courts in Bilaspur/ Ratnagiri shall have
jurisdiction to determine the same.
The venue of Arbitration proceedings shall be the Administrative Officers of the Korba/
Ratnagiri Projects
Court held
…..contract between the parties explained and filled up and it is specifically provided that
only court at Bilaspur shall have jurisdiction in respect of all disputes arising or connected
with the agreement.
It is obvious that Delhi courts will have no jurisdiction. The petitioner's office was at
Calcutta. The respondent was having works at Bilaspur/Ratnagiri.
petitioner has properly invoked the arbitration clause and issue is decided in favor
of the petitioner and against the respondent.
In case the disputes between the parties are referred to the arbitrator, all those
disputes have to be referred to the arbitrator apart from the contentions raised by
the respondent that the contract between the parties was void / frustrated.
This Court has no territorial jurisdiction and courts at Bilaspur/ Ratnagiri has
jurisdiction, the petition is hereby dismissed.
The End