DEPARTMENT OF TECHNICAL EDUCATION

ANDHRA PRADESH
Name : G. Rupakumari
Designation : Lecturer
Branch : Civil Engineering
Institute : MRAGR Govt. Polytechnic, Vizianagaram
Year/Semester : VI semester
Subject : Construction Management
Subject code : C-604
Topic : Preliminary Planning & Organisational
Aspects
Duration : 50 mins
Sub topic : Need & Factors involved in Construction
Management
Teaching Aids : PPT’s
C604.2 1
Objectives

On completion of this period, You would be able to

• Know the Need of Construction Management

• Know the Factors involved in Construction Management

C604.2 2
Recap

In the previous class we have discussed about

Construction management and its objectives

C604.2 3
Define Construction Management?

• Construction Management is a systematic

Method which involves Planning, Organising,

Coordinating and Controlling the various

activities in any Construction Industry

C604.2 4
What does an Efficient Management do?

• An Efficient Management brings the Human and

Material Resources like Machines, Materials

and Money together and Coordinates among

the various activities

C604.2 5
What are the Resources required for
Construction Management?

• Human

• Material

• Machinery

• Funds

C604.2 6
Construction Management is Necessary for

• Speedy Construction

• Control on Quality

• Optimum Utilisation of Resources

• Optimum Utilisation of Time

C604.2 7
The Need for Construction Management

• The knowledge of Construction

Management is quite necessary to achieve

the above Objectives


The Need for Construction Management

• Ability to Estimate the required Manpower Material,


Machinery and Finance

• To select and procure Materials, Manpower and


Machinery

• To have proper Coordination among the various


activities

Cont…
C604.2 9
The Need for Construction Management

• To Sequence the various activities involved in a


Project in systematic way

• To complete the work within Optimum Time and


Optimum Cost

• To maintain Quality of work

Cont…

C604.2 10
The Need for Construction Management

• Planning and Programming of different works

• To check the Progress of work with respect to

alloted Time

C604.2 11
Factors Involved in Construction
Management

• Planning, Scheduling, Organising and

Controlling

• Selection of proper Materials, its Cost including

Lead Charges

• Magnitude of Manpower and Equipment

C604.2 12
Factors Involved in Construction
Management

• Availability of Material, future Demand, and the

Probability of increase in Cost

• The appropriate Time for using a Particular

Equipment during the Construction

• Procurement of Materials and Machinery


C604.2 13
Factors Involved in Construction
Management

• Probable Time Delays due to Natural conditions

• Skills required to finish the Task

• Coordination among the different Organisations

C604.2 14
Scope of Construction Management

• Preparing Plans, Estimates, Specifications and

Project Reports

• Execution of works as per the Plans and Drawings

• Programming the Activities, Organising and

Controlling the Quality of work

Cont…
C604.2 15
• Organisational setup and the Duties of various

officers

• Scheduling of works through Management

Techniques such as CPM and PERT

• Knowledge of Contract Systems, Methods of

Execution and Accounting

Cont…
C604.2 16
• Optimum use of Manpower and Machinery

• Good Labour Relations and Labour Welfare

• Knowledge of Industrial Psychology and Labour

Acts

C604.2 17
Summary

We have discussed

• The Resources required and Need for

Construction Management

• The Factors involved in Construction

Management

C604.2 18
Quiz

1. The knowledge of Construction Management


is necessary for

A. Contractor

B. Executing Authority

C. Customer

D. All the above


C604.2 19
2. In any project management, Planning and
Scheduling are accomplished

A. Before the work starts

B. During execution

C. After completing the work

D. At any time
C604.2 20
Frequently Asked Questions

1. Describe the need for Construction Management

2. What are the factors involved in Construction

Management

C604.2 21