Professional Documents
Culture Documents
Final Individual
Final Individual
Final Individual
Contractor’s pre-contract
work
10.1 Planning work
Taking possession of site without previous planning could be both costly and
wasteful in time caused by delays in obtaining the necessary approvals,
licenses, permits, labor, materials, equipment and information on time.
Those delegated with responsibilities can proceed with the preparation of the
following major areas of pre-contract organization:
I. Method Statement
II. Contract Program
III. Site Layout Plan
IV. Schedules and other requirements
10.2 Method Statement
It is used as a guide to everyone within the contracting firm regarding the
method and sequence of construction
During the preparation of the Method Statement the construction work should
be broken down into operations, and the labor and plant requirements
decided upon by those responsible for the documents' preparation.
This form of chart shows which activities or operations are more important
than others. Those activities which are most important are generally the ones
that need to be completed on or before the end of the durations allocated to
them.
In the same way as Bar Charts are initially dealt with, the preparation of
networks begins by :
● Listing the activities/operations of the proposed project in the approximate
order of execution,
● Calculating the durations of each activity.
● Now continue the preparation of the network as follows,
● Sketch out a network chart in a logical way after first asking the question,
'What operations can bee done first or simultaneously with others?
● Add to the chart the durations Of each activity.
● Calculate the earliest and latest start and finish times and critical path(s)
10.4 Site layout
The most convenient method of instructing a site manager as to the best positions
for hutting, temporary service points, equipment and materials is by a site layout
plan drawn to a suitable scale.
1. plant schedules
a) Mechanical
b) Non-mechanical
2. site supervisors and administration staff schedule
3. labor Requirements schedule
4. Schedule of Subcontractors' Work
a) Nominated subcontractors
b) Contractor's own subcontractors
5. materials Schedules
a) Nominated suppliers
b) Contractor's own suppliers
6. Schedule of Detail Drawings Requirements
Other arrangements
1. Insurances
2. Licenses
3. Rates
4. Public undertakings
5. Commencement Notices. Local Authority
6. Meals on-site
7. Closure or Part Closure of Highways
11
Contract work and other
considerations
11.1 Setting up site and controlling works
● The setting out of the access position for the excavator driver
● The preparation of a site grid
● The recording of site levels from a Temporary Bench Mark (TBA)
● Establishing the boundaries of the site, the building line, and improvement
line
● Setting out the positions for hutting, compounds, storage areas, stand-pipes,
etc.
● Fixing of danger signs for overhead lines and underground cables and service
positions to minimize damage.
● The actual setting out of the building, drainage and roads, using pegs,
profiles, sight rails, batter rails, etc.
Preliminary requirements
The contract manager or some responsible person at head office would have
by now requisitioned all the preliminary requirements for the site, namely: