Built Up - Turfing Work
Built Up - Turfing Work
• Method of laying/installation -
manually/hydroseeding
• Maintenance Cost
5
6
7
COW GRASS ZOYSA GRASS BERMUDA GRASS
8
hydroseeding
9
TURFING – Example 1
DATA
Cow Grass size of 1 no.of grass assume 0.3m x 0.15m 1 no 0.60
Labour cost for excavation 1 m2 0.80
Labour cost for planting 1 m2 0.80
Maintenance Cost (up to 6 mth) 1 m2 1.50
Assume uses of grass for 1m2 6 no
Profit and overhead 15%
Wastage 5%
10
1 Turfing
unit qty rate cost/ m2
A Materials Cost
Turfing no 6.00 0.60 3.60
B Labour Cost
11
TURFING – Example 2
Supply turf including soiling 100mm t hick from approved source and peg in close t urfing to
shoulders, medians, verges and other earth slopes. (unit m2)
DATA
1. grass size 350mm x 350mm no RM 0.60
2. t op soil m3 RM15.00
3. wood peg no RM 0.20
4. skill labor wages RM100/ day
5. general labor RM60/ day
6. output
- labor for plant ing & pegging 0.2hrs/ m2 (1 skill labor + 2 general labor)
- labor for laying of topsoil manually 0.08hrs/ m2 ( 2 general labor)
7. maintaning works up t o 3 mont hs
- watering m2 RM 0.25
- fertilizing m2 RM 0.50
8. Wastage 10%
9. Profit & overhead 20%
12
1 Turfing
unit qty rate cost/ m2
A Materials Cost
i. Grass
1 no of grass = 0.35m x 0.35m = 0.12m2
No of grass/ 1m2 of turfing area
= 1m2/ 0.12m2 = 8.33nos no 8.33 0.60 5.00
13
unit qt y rat e cost / m2
B Labour Cos t
i. labor for plant ing & pegging hrs 0.20 12.50 2.50
1 x skill labor hrs 0.20 15.00 3.00
2 x General labor
hrs 0.08 15.00 1.20
ii. labor for laying of t opsoil manually
Total labor cos t per no 4.20
C Maintenance Cost
up t o 3 mont h m2 1 0.25 0.25
i. wat ering m2 1 0.50 0.50
ii. fert ilizing
Total maintenance cos t per m2 0.75
14
Turfing _ tutorial 1
DATA
Cow Grass size of 1 no.of grass assume 450mm x 200mm 1 no RM 0.50
Labour cost for excavation 1 m2 RM 1.00
Labour cost for planting 1 m2 RM 0.60
Maintenance Cost (up to 6 mth) 1 m2 RM 0.70 / month
Assume uses of grass for 1m2 4 no
Profit and overhead 15%
Wastage 5%
15
Answer: RM 9.48
16
Turfing _ tutorial 2
Supply t urf including soiling 100mm t hick from approved source and peg in close t urfing t o
shoulders, medians, verges and ot her eart h slopes. (unit m2)
DATA
1. grass size 300mm x 300mm no RM 0.40
2. t op soil m3 RM12.00
3. bamboo peg no RM 0.10
4. skill labor wages RM120/ day
5. general labor RM80/ day
6. out put
- labor for planting & pegging 0.25hrs / m2 (1 skill labor + 2 general labor)
- labor for laying of topsoil manually 0.06hrs / m2 ( 2 general labor)
7. maint aning works up t o 3 mont hs
- wat ering m2 RM 0.30
- fertilizing m2 RM 0.30
8. Wast age 5%
9. Profit & overhead 10%
17
Answer: RM 15.28