Professional Documents
Culture Documents
Overall Equipment Effectiveness (Oee)
Overall Equipment Effectiveness (Oee)
1
Overall Equipment Effectiveness (OEE)
Fundamental Concept
of plant Effectiveness
2
Overall Equipment Effectiveness (OEE)
Overall equipment effectiveness (OEE) is a hierarchy of metrics to
evaluate how effectively a manufacturing operation is utilized.
3
Elements Of OEE
Overall Performance
Equipment losses
Effectiveness Unclear Design Specs., Poor Maintenance History, Incorrect Settings, Poor
Speed
Training, Speed Deliberately Reduced, Inconsistent Material
losses
Start-up Poor Product Changeover, Inconsistent Materials, No start-up check lists, Waiting
losses for Temp. Pressures, Minor adjustments
Quality
losses Environmental Conditions, inconsistent Materials, Process not followed, Poor
In process
Calibration, Gauges not calibrated properly etc.
losses
4
OEE is the way to Measure Effectiveness
OEE is the way to measure how effectively Machine / Equipment hours are used.
Total time
OEE goes down due to following Losses
e.g. 480 min. (1 shift)
- breakdowns, repairs
Running time Downtime - changeover
- adjustment
- start up
- machine speed
Productive time Performance - short stoppages
Losses - lower yield
- scrap
Effective time Quality Losses - reject
- rework
5
Prime Cause of Production Loss
A production line seldom operates at optimum speed. A variety of reasons or Negative
Performance Impacts, mostly in combination, cause losses in productivity and therefore loss
of money. These include:
•Line Saturation
There is no place for more output from the machine.
•Equipment Failure
Machines break down, wear out, are not used properly and so on. All ends up in lost production
time.
•Product changes
During the change over from one product to another the machine settings must be changed,
breakdown may occur and speed must be reduced.
•Short Stops
For example, thread breakage. These short but frequent events can be the reason for major time
loss.
•Operator Inefficiency
The operators like to have it nice and easy. They run with lower speed in order to guarantee smooth
operation.
6
Prime Cause of Production Loss
•External reasons
Sometimes, the production runs out of orders and the machines have to shut down. Or there can
be a failure in the electrical power network far away from the factory.
•Product Type
Some products are more difficult to make. There are more breakdowns and quality problems.
•Speed Losses
For one reason or another, the speed of the machine is not optimum. In order to save costs,
someone has purchased cheap but poor quality raw material.
•Quality
Although the machine is running, the products are not good enough for the customers. These are
the most expensive kinds of losses.
•Missing Material
The raw material storage is empty and machines can not produce any more.
7
How to Calculate OEE
8
Overall Equipment Effectiveness Calculation
Productive Performance=
Running time - Performance loss X
Running time
Quality =
Total peaces produced – Defective peaces X
Total Peaces Produced
270 - 20
=
270
factor 92.6%
9
World Class OEE
OEE is essentially the ratio of Fully Productive Time to Planned Production Time. In
practice, OEE is calculated as the product of its 3 contributing factors
This type of calculation makes OEE a severe test. For example, when all 3 factors are
at 90%, OEE would be 72.9%. The following table shows generally accepted World
Class goals for each factor
Worldwide studies show that the average OEE rate in manufacturing plants is 60%
How to Improve OEE ?
Data collection is the most important action to increase OEE
Collect data for all downtimes Data analysis and Make improvements
and losses on the machine visible measure visible and implement
35
Analysis
Repairs 30 Autonomous Maintence.
25
20
Change over, Adjustm. 15 Preventive Maintenance
10
5
Tool change Changeover reduction
Repair Changeover Tool change Scrap Minor Stopp.
Minor stoppages 33 26 16 7 3
Standardize tooling
Scrap, rework OEE Trend Improved machine
Target 2003 reliability
Standardisation
J F M A M J J A S O N D
11
Fundamental Concept of Plant Effectiveness
16 Kinds of loss
Speed Losses
Shutdown
12
Exercise – OEE Calculation
13
14
Let,
•Working hours per day: 10 hours x 60 min = 600 min
•Shut down (SD): 35 min
•Loading time: (600-35) = 565 min
•Equipment stoppage/ down time: (30+20+25) = 75
(a) Failure : 30 min
(b) Set up : 20 min
(c) Adjustment : 25 min
•Operating time : (565 - 75) = 490 min
•SAM = 0.35 min/ pieces
•Processing quantity : 550 pieces/ day
•Defective : 30 pieces.
15
Loading time – Down time
Availability = ……………………………………………. X 100
Loading time
565 – 75
= ………………….. x 100
565
= 86.72%
= 40.35%
16
Processing quantity – Defective quantity
Quality product rate =
……………………………………………………………………. X 100
Processing quantity
550 – 30
= …………….. x 100
550
= 94.54%
= 33.08%
17
S.no Operator Operation SAM Available Production Total Defective
Name minutes (pieces) Off Peace
std
time
(mins)