Professional Documents
Culture Documents
Chapter 6
Chapter 6
INSTITUTE OF TECHNOLOGY
Dep’t Of Hydraulics & Water Resource
Engineering
Suppose that a site preparation and concrete slab foundation construction project consists of
nine different activities:
A. Site clearing (of brush and minor debris)
B. Removal of trees
C. General excavation
D. Grading general area
E. Excavation for utility trenches
F. Placing formwork and reinforcement for concrete
G. Installing sewer lines
H. Installing other utilities
I. Pouring concrete.
CONT
The bar chart is probably the best known of all the planning techniques. It
basically features a
plan of a project split into a logically related individual activities each
represented graphically
by scaled lines. Bar charts present the project schedule plotted to a
horizontal line scale. The
bar lines represent the time period allocated to each operation and the
relationship between
the commencement and completion of each can be readily observed.
Advantages of Bar chart:
advancement.
Disadvantages:
Interdependencies among activities are difficult to show. The bar
chart itself doesn’t provide a basis for ascertaining which activities
are critical and which are floaters.
It is not an adequate planning and scheduling tool because it doesn’t
portray a
detailed, integrated and complete plan of operations.
Can't tell what will be the effect of a delay today will have on the
timing of future activities.
:-
NETWORK SCEHDULING
Basic Assumptions:
1. The project can be broken down into a group of activities.
2. Each activities can be assigned a duration.
3. The logical relationship among activities are known and fixed in the network chains
:
Rules for Preparing the Network Diagram