1
February 4th,2019
the trench for building the veranda is being dug
2
The beams of the roof are being painted to prevent
worms assault
3
Paiting the poles for the veranda
4
The new doors and windows have arrived
5
A year later : February 7th, 2019 at school during break
time
6
Making the ceiling in the offices
The building has been wired and the main switcher installed
in the office. Workers are plastering the training room
The newly built veranda and the newly painted doors and windows
Soon the floor of the three classrooms will be
made
First and second blocks: the construction is completed
The windows painted “forest green”, that’s