0500760 (OMR.21.

100) POTABLE WATER SYSTEM


UPGRADE IN TRAIN-1&2 AT RUWAIS

Weekly Progress Meeting #63

21st September 2022


(14/09/2022 – 20/09/2022) 1
Total Solutions in EPCM
ENGINEERING CONSULTANT ACTIVITIES

Activities Conducted (Week 62) Activities Planned (Week 63)


14/09/2022 – 20/09/2022 21/09/2022 – 28/09/2022

 3D MODEL REVIEW TAG CLOSE OUT COMPLETED WITH COMPANY FOR  P&ID MARK-UP & IFC ISSUANCE
ALL THE AREAS EXCEPT THE GRE LINES.  COORDINATION WITH TVI FOR GA & ISO EXTRACTION OF GRE LINES
 STRESS REPORT FOR SYSTEM 1, 4 & 3 HAVE BEEN ISSUED TO TVI FOR  PROGRESSIVE EXTRACTION OF SUBSEQUENT REVISIONS OF SS LINES PIPING
MODELLING. GAs & CIVIL GAs
 PIPE SLEEPER (PLANT SIDE) PIPING GAS (7 NOS.) IFR ISSUED TO  TAG CLOSEOUT FOR THE GRE AREAS PLANNED BY 21-SEP-22 FOLLOWED BY
COMPANY EXTRACTION UNTIL 27-SEP-22 AND IFC ISSUE TO COMPANY BY END OF SEP’22.
 CW PUMP HOUSE – PIPING GAS (3 NOS.) IFC ISSUED TO COMPANY
 CW DISCHARGE TOWER – PIPING GAS (1 NOS.) IFC ISSUED TO COMPANY
 CAUSTIC STORAGE – PIPING GAS (2 NOS.) IFC ISSUED TO COMPANY
 C3 LOOP TRAIN 01– PIPING GAS (2 NOS.) IFC ISSUED TO COMPANY
 JETTY – CIVIL GAS (1 NOS.) EXTRACTED AND REVIEW IN PROGRESS
 FINISH GRADING AND U/G LAYOUT OFFSITES – IFR ISSUED TO COMPANY
 STRESS ANALYSIS REPORT FOR 6” AND 8” HEADER TO FRESH WATER
COOLING SYSTEM (SYSTEM-4) – IFC ISSUED TO COMPANY
 PIPING ISOMETRICS - C3 LOOP TRAIN-1 AREA – IFI ISSUED TO COMPANY
 PIPING ISOMETRICS - COOLING WATER DISCHARGE TOWER AREA – IFI
ISSUED TO COMPANY
 PIPING ISOMETRICS - C3 LOOP TRAIN-2 AREA – IFI ISSUED TO COMPANY
 PIPING ISOMETRICS - JETTY AREA – IFI ISSUED TO COMPANY
 PIPING ISOMETRICS - COOLING WATER PUMP HOUSE – IFI ISSUED TO
COMPANY
 PIPING ISOMETRICS - DEO PROPANE EXPORT FACILITY AREA – IFI ISSUED
TO COMPANY

2
Total Solutions in EPCM
ENGINEERING CONSULTANT ACTIVITIES

PRIORITY AREAS DRAWING ISSUE STATUS

IFR Response IFR Response IFA/IFC Approval Approval


Sl.No. Area   SCOPE IFR Issued to Received from Awaited from Issued to Awaited from IFI Awaited from
AGP AGP AGP AGP AGP AGP

1 Utility Area P-GA 17 17 17 0 17 1    


  Utility Area C-GA 13 13 13 0 8 0    
  Utility Area ISO 95         0 95 0

2 Process Train-1 P-GA 41 41 41 0 41 0    

  Process Train-1 C-GA 23 23 20 3 17 4    


  Process Train-1 ISO 112         0 112 112
3 Process Train-2 P-GA 42 42 41 1 41 41    
  Process Train-2 C-GA 23 23 19 4 8 0    
  Process Train-2 ISO 112         0 106 106
4 Train 2 to Train 3 P-GA 5 5 5 0 28-Sep-22      
  Train 2 to Train 3 C-GA 5 5 5 0 5 0    
  Train 2 to Train 3 ISO 1        27-Sep-22      
5 Storage area P-GA 29 29 29 0 27 1    
  Storage area C-GA 25 25 25 0 20 0    
  Storage area ISO 25         0 25 25

3
Total Solutions in EPCM
Thank you.