MGT 312
4
Management of Projects
1. Planning – Includes goal setting, defining
the project, team organization
2. Scheduling – This phase relate people,
money, and supplies to specific activities
and activities to each other
3. Controlling - monitor resources, costs,
quality, and budgets; revise plans and shift
resources to meet time and cost demands
Project Management Activities
► Planning
► Objectives ► Scheduling
► Resources ► Project activities
► Controlling
► Monitor, compare, revise, action
Project Planning, Scheduling, & Controlling
Figure 3.1
Project Planning, Scheduling,
Time/cost
Budgets
estimates
and Controlling
Engineering diagrams
Cash flow charts
Material availability details
Budgets
Delayed activities report
Slack activities report
CPM/PERT
Gantt charts
Milestone charts
Cash flow
Figure 3.1schedules
Project Planning
► Establishing objectives
► Defining project
► Creating work
breakdown structure
► Determining
resources
► Forming organization
Human Quality
Resources Marketing Finance Design Production
Mgt
Figure 3.2
Matrix Organization
Marketing Operations Engineering Finance
Project 1
Project 2
Project 3
Project 4
Level
1. Project
2. Major tasks in the project
3. Subtasks in the major tasks
4. Activities (or “work packages”)
to be completed
Work Breakdown Structure
Project Scheduling Techniques
21
Gantt Chart
22
Gantt Chart
• It shows the relationship of each activity to
others and to the whole project.
• 2. It identifies the precedence relationships
among activities.
• 3. It encourages the setting of realistic time
and cost estimates for each activity. 4. It helps
make better use of people, money, and
material resources by identifying critical
bottlenecks in the project.
Example Gantt Chart
24
Example Gantt Chart
Activity Predecessor Duration (days)
A - 2
B A 3
C B 4
D C 3
25
PERT and CPM
• Network techniques
• Developed in 1950’s
• CPM
• PERT
Consider precedence relationships and interdependencies
Each uses a different estimate of activity times
26
PERT (Program Evaluation and Review
Technique)
CHAPTER - 11 27
Six Steps PERT & CPM
CHAPTER - 11 28
Characteristics of the Critical Path
CHAPTER - 11 29
A Comparison of AON and
AOA Network Conventions
Activity on Activity
Activity on
Node (AON) Meaning
Arrow (AOA)A comes
(a) A B C before B,
which comes A B C
before C
A A
A and B must
(b) C both be
completed before C
B C can start B
B
B and C cannot
(c) A begin until A is B
completed A
C C
CHAPTER - 11 30
Example CPM
Activity Predecessor Duration (days)
A - 2
B A 3
C B 4
D C 3
CHAPTER - 11 31
Example CPM
Activity Predecessor Duration (days)
A - 2
B A 3
C B 4
D C 3
A B C D
Start End
2 3 4 3
12 days
CHAPTER - 11 32
Determining the Project Schedule
Latest LS LF Latest
Start 2 Finish
Activity Duration
EF = ES + Activity time
LS = LF – Activity time
After computing the ES, EF, LS, and LF times for all activities,
compute the slack or free time for each activity
Slack = LS – ES or Slack = LF – EF
Immediate
Activity Description Predecessors
A Build internal components —
B Modify roof and floor —
C Construct collection stack A
D Pour concrete and install frame A, B
E Build high-temperature burner C
F Install pollution control system C
G Install air pollution device D, E
H Inspect and test F, G
ES/EF Network
ES EF = ES + Activity time
Start
0 0
EF of A =
ES ES of A + 2
of A
A
Start 0 2
0 0
43
Activity Predecessor Duration
Example: Paper Manufacturing's A - 2
B - 3
ES/EF Network C
D
A
A,B
2
4
E C 4
F C 3
G D, E 5
H F, G 2
A
0 2
2 EF of B =
ES ES of B + 3
0
Start
0 of B
B
0 0 3
44
Activity Predecessor Duration
Example: Paper Manufacturing's A - 2
B - 3
C A 2
ES/EF Network D
E
A,B
C
4
4
F C 3
G D, E 5
H F, G 2
A C
0 2 2 4
2 2
Start
0 0
B
0 3
45
Activity Predecessor Duration
Example: Paper Manufacturing's A - 2
B - 3
C A 2
ES/EF Network D
E
A,B
C
4
4
F C 3
G D, E 5
H F, G 2
A C
0 2 2 4
2 2
Start
0 0
= Max (2, 3) D
0
3 7
B
0 3
3
4
46
Activity Predecessor Duration
Example: Paper Manufacturing's A - 2
B - 3
C A 2
ES/EF Network D
E
A,B
C
4
4
F C 3
G D, E 5
H F, G 2
A C
0 2 2 4
2 2
Start
0 0
B D
0 3 3 7
3 4
47
Activity Predecessor Duration
Example: Paper Manufacturing's A - 2
B - 3
C A 2
ES/EF Network D
E
A,B
C
4
4
F C 3
G D, E 5
H F, G 2
A C F
0 2 2 4 4 7
2 2 3
Start E H
0 0 4 8 13 15
0 4 2
B D G
0 3 3 7 8 13
3 4 5
LS/LF Times
A C F
0 2 2 4 4 7
2 2 3
Start E H
0 0 4 8 13 15
13 15
0 4 2
B LS = LF
D – Activity time
G
0 3 3 7 8 13
3 4 5 LF = EF
of Project
49
Example: Paper Manufacturing's
LS/LF Times
A C F
0 2 2 4 4 7
10 13
2 2 3
Start E H
0 0
LF =4 Min(LS
8 of 13 15
following activity) 13 15
0 4 2
B D G
0 3 3 7 8 13
3 4 5
50
Example: Paper Manufacturing's
LS/LF Times
LF = Min(4, 10)
A C F
0 2 2 4 4 7
2 4 10 13
2 2 3
Start E H
0 0 4 8 13 15
4 8 13 15
0 4 2
B D G
0 3 3 7 8 13
8 13
3 4 5
51
Activity Predecessor Duration
Example: Paper Manufacturing's A - 2
B - 3
C A 2
LS/LF Times D
E
A,B
C
4
4
F C 3
G D, E 5
H F, G 2
A C F
0 2 2 4 4 7
0 2 2 4 10 13
2 2 3
Start E H
0 0 4 8 13 15
0 0 4 8 13 15
0 4 2
B D G
0 3 3 7 8 13
1 4 4 8 8 13
3 4 5
52
Example: Paper Manufacturing's
After computing the ES, EF, LS, and LF times for all activities,
compute the slack or free time for each activity
Slack = LS – ES or Slack = LF – EF
53
Example: Paper Manufacturing's
SA = 0 SC = 0 SF = 6
A C F
0 2 2 4 4 7
0 2 2 4 10 13 SH = 0
2 2 SE = 0 3
Start E H
0 0 4 8 13 15
0 0 4 8 13 15
0 4 2
B D G
0 3 3 7 8 13
1 4 4 8 8 13
3 4 5
SB = 1 SD = 1 SG = 0
54
Example: Paper Manufacturing's
A 0 2 0 2 0 Yes
B 0 3 1 4 1 No
C 2 4 2 4 0 Yes
D 3 7 4 8 1 No
E 4 8 4 8 0 Yes
F 4 7 10 13 6 No
G 8 13 8 13 0 Yes
H 13 15 13 15 0 Yes
55
Activity Predecessor Duration
A - 2
B - 3
C A 2
Critical Path for Milwaukee Paper D
E
A,B
C
4
4
F C 3
G D, E 5
H F, G 2
A C F
0 2 2 4 4 7
0 2 2 4 10 13
2 2 3
Start E H
0 0 4 8 13 15
0 0 4 8 13 15
0 4 2
B D G
0 3 3 7 8 13
1 4 4 8 8 13
3 4 5
ES – EF Gantt Chart C
D
E
A
A,B
C
2
4
4
F C 3
G D, E 5
H F, G 2
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
A Build internal
components
B Modify roof and floor
C Construct collection
stack
D Pour concrete and
install frame
E Build high-temperature
burner
F Install pollution control
system
G Install air pollution
device
H Inspect and test
57
Example: Paper Manufacturing's
LS – LF Gantt Chart
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
A Build internal
components
B Modify roof and floor
C Construct collection
stack
D Pour concrete and
install frame
E Build high-temperature
burner
F Install pollution control
system
G Install air pollution
device
H Inspect and test
58
Project Completion date?
A - 3
B - 2
C A,B 4
D C 3
E B 2
F D,E 2
? 60