CONTRACT AWARDED TO
“M/S ENERGO ENGINEERING
PVT LTD”
Total Contract Value : Rs. 187 Crores
Crusher
TP-27
House-2
TP-26
TP-25
TP-24
PH-1A
Emergency
Reclaim Hopper
TP-29 TP-28
Crusher
TP-27
House-2
Existing
CH- 1 Existing
TP-26
TP-4
TP-25 TP-24
PH-1A
Emergency
Reclaim
Hopper
TELANGANA STATE POWER GENERATION CORPORATION LIMITED
ACHP for KAKATIYA THERMAL POWER PLANT
SITE ACTIVITIES
BCN 31A/31B
9 Nos Trestles
BCN 28A/28B
Existing
Existing TP-4 TP-26
RYC CH- 1
BCN 11
BCN 27A/27B
3 nos Trestles
Index Status of works
Reclaim Hopper at EL (-)8.55m shuttering and reinforcement is in progress
Tunnel Tunnel slab completed
Pent House Completed upto plinth beam
TP-25
BCN 2A/2B 8 Nos Trestles completed upto Tie beam bottom
TP 24 Pedestals and back filling completed upto Tie beam bottom
BCN 25A/25B 3 Nos Trestles completed. Remaining 1 no completed upto bolt bottom TP-24
TP 25 7/9 completed upto tie beam bottom. First lift of remaining pedestals completed
BCN 26A/26B Not commenced BCN 25A/25B
TP26 Excavation under progress 4 nos Trestles BCN 2A/2B
Crusher House 2 Work not started. Drawings are available 8 nos Trestles
BCN 28A/28B 9 nos completed in full shape. 20 footings completed and shuttering and bolting is under
PH-1A
progress. 3Nos excavation and PCC completed
TP27 6 nos excavation completed. 4Nos footings completed. No activity from 26.10.2016
BCN 30A/30B 6/9 completed. No activity since 15.10.2016 Tunnel RC 2A/2B
TP28 civil foundation work completed. Mechanical erection work is in progress
BCN 31A/31B Not started. Clear site is available
TP29 Submission of revised drawing required
BCN 27A/27B Not yet started
BCN 29A/29B Not yet started
M/s.ENERGO has committed in MOM Dt.27.08.2016 for the following & not done so far:
1 One more contractor for Structural work shall be finalized by Energo by 10.09.2016
2 Electrical Contractor for ACHP & WFAHS area shall be finalized by Energo by 10.09.2016
3 Wet Fly Ash Handling system should be completed by 31st October 2016
4 ACHP works should be completed by 31.01.2017
5 Man power not deployed as per promise.
M/s.ENERGO has committed in MOM Dt.21.10.2016 for the following & not done so far:
1 One more Mechanical contactor for Crusher house & TP-29 will be finalized by M/s
Energo.
2 Electrical contractor of Additional CHP will be finalize by 15.11.2016.
3 M/s.ENEGO promised dates to complete Civil works is enclosed in next slide.
4 Energo has committed to deploy Manpower i.e barbenders,carpenters and helpers
excluding other supporting staff,as follows:
From Date Average man power
provided by M/s.ENERGO
100Nos from 31.10.2016 onwards 76
150Nos from 10.11.2016 onwards. 98
Average manpower per day 88
Progress of Works At a Glance
S. Name of Front Scheduled % work % Balance Remarks
No Date progress Civil works
till today
1 Emergency Reclaim Hopper 30.11.2016 35% 65%
hopper slab at (-)8.55m
2 Conveyor RC 2A/2B upto Pent 14.11.2016 85% 15%
house(Tunnel 52 Mtrs length)
3 Pent House including slab 14.11.2016 15% 85%
4 2A/2B Conveyor 20.12.2016 50% 50% 33KV line was dismantled by
(from Pent House to TP 24-Total TSGENCO on 21.10.2016
8 Nos. trestles)
5 TP 24(Total 22 Pedestals) 15.12.2016 50% 50%
6 BCN-25A/B 30.11.2016 85% 15%
(from TP 24 to TP 25-Total 8 Nos.
trestles)
7 TP 25 (Total 9 Pedestals) 30.11.2016 45% 55%
8 TP 26 30.12.2016 --- Only 54.55% of excavation is
completed. Excavation
resumed on 25.11.2016 and
work is under progress.
9 Crusher House-2 28.02.2017 --- Drawings are available and
released for construction on
22.11.2016
10 BCN 28AB 25.11.2016 25% 75%
(Crusher House -2 to TP-27 ,33
nos ground portal and 8 nos
trestles)
S. Name of Front Scheduled % work % Balance Remarks
No Date progress till Civil works
today
11 TP27 (Total- 9 nos 15.12.2016 8% 92% Excavation for 6 nos and
pedestals) RCC- Raft for 4 nos has been
completed out of 9 pedestals
12 BCN-30A/B 15.11.2016 75% 25%
(Total 9 Trestles-
from TP 27 to TP 28)
13 TP 28 --- 100% ---- Erection of structure works
commenced on 29.08.2016.
14 TP29 15.01.2017 --- On 23.11.2016 Mr Anil
Dwivedhi of M/s Energo and
their Desein engineer have
visited the site and it was
discussed in detail. M/s
Energo has to do the re-
engineering and submit the
revised drawings.
15 BCN-31A/B 31.01.2017 ---
(Total 9 Trestles,
As per construction sequence
from TP 28 to TP 29)
TP-29 has to be completed
first after that
STATUS AS ON 30.11.2016
Detailed Status of TP-26
M/s.Energo has committed to complete all civil
foundations by 31.12.2016
Present status: Excavation for TP-26 was stopped during
last week of june, 2016 and it is resumed on 25.11.2016.
Balance Civil works: Only 55% excavation has been
completed and all other works are pending.
Percentage of Civil works completed : Nil
Status of Erection works completed: Not Started
Conveyor 27A/27B
(TP 26 to existing TP 4)
STATUS AS ON-30.11.2016
Detailed Status of TP-28
All civil works have been completed.
Present status: 14 of 14 Columns First lift along with Tie
Bracing have been erected.
Status of Erection works completed: 13%
Conveyor -31A/31B from TP 28 to TP 29
(Total 9 Trestles)
Idler Frames
THANK YOU
Superintending Engineer-2
Thermal Projects Construction
TSGENCO