Foundation Power Company (Daharki) Limited – Plant Site

1
MI-2023 Preparation

Overhauling of CEP Motor-B

Prepared By: Aminullah Sharif (Engineer Electrical)


Activity In charge: Muhammad Bilal
2
MI-2023 Preparation

Contents
 KPI
 Introduction
 Objective
 Motor Specification
 Dimensional & Connection Drawing
 Job Safety Analysis
 Work Plan
 Maintenance Procedure & Inspection Check Sheets
 Manpower Details
 Spare and Consumables
 Required Tools
 Pictorial View of Activity
3
MI-2023 Preparation

Key Performance Indicator (KPI)

• NO INJURY

• NO FIRE

• NO REWORK
4
MI-2023 Preparation

Introduction

 CEP Motor is coupled with Vertical Mixed Flow Pumps, which take suction from the hot-
well of Steam Turbine Condenser and transfer it mainly to the Feedwater tank.

 CEP motor is three phase induction 240KW motor which is operating at 6KV voltage,
Motor is vertical Flange mounted.

 There are 2 condensate extraction motors are installed, out of which 1 motor remains in
service while other remain on standby condition

5
MI-2023 Preparation

Objective
 CEP Motor-B overhauling was previously perform in
 2016

 2019

Overhauling is due to completion of 3 years

 In 2021, motor vibration at “H” direction on NDE side was increasing slowly and gradually but it was
under allowable range.

 MM team decided to perform weight balancing and pump support under the recommendation of
Korea TA.
 By applying turn buckle support against motor on both sides along with 27g weight on motor fan
vane #12, both the motor and pump shaft vibration become normal under Load test. 6
MI-2023 Preparation

Motor Specification
Manufacturer HYOSUNG CORPORATION

KW(HP) 240 (322) TYPE VSFC

POLE 4 SERVICE FACTOR 1.0

VOLTAGE 6,000 [V] F. L. AMPS 28.4 [A]

FREQ 50 [Hz] PHASE 3 PH

ROTOR WT. 750 [kg] MOTOR WT. 2500 [kg]

Bearing/s DE NU 220 Bearing/s NDE 7324BDT

INS. CLASS F DATA 2008. 10.


7
MI-2023 Preparation

Dimensional & Connection Drawings

8
MI-2023 Preparation

Job Safety Analysis (JSA)

9
MI-2023 Preparation

Work Plan 05-Feb 06-Feb 07-Feb 08-Feb 09-Feb


SN Activity Detail
0800-1300 1400-1730 0800-1300 1400-1730 0800-1300 1400-1730 0800-1300 1400-1730 0800-1300 1400-1730
                   
1 Perform De-coupling of Motor from Pump
                   
                   
2 Perform Motor solo run test before overhauling and measure Vibration
                   
                   
3 Remove power cable and space heater cable, RTD cable
                   
                   
4 Measure insulation and winding resistances of Motor
                   
                   
5 Disassemble Fan cover
                   
                   
6 Disassemble fan by using gas heating torch
                   
                   
7 Disassemble motor base bolt
                   
                   
8 Disassemble motor and shift work stand
                   
                   
9 Remove motor coupling using by gas heating torch
                   
                 
10 Remove NDE side bearings housing, NDE bearing by using jack and puller
                   
                   
12 Remove DE side bearings housing, DE bearing by using jack and puller
                   
                 
14 Perform inspection of rotor, stator winding and its wedges
                   
                   
16 Measure DE/NDE bearing housing and shaft diameters
                   
                   
17 Cleaning housing and accessories
                   
                   
18 Install DE bearing and its accessories
                   
                   
19 Install NDE bearing and its accessories
                   
                   
20 Shift to its base and tighten the base bolt
                   
                   
21 Measure insulation and winding resistances of Motor
                   
                   
22 Reconnect power cable, Space heater and install instruments
                   
                   
23 Perform Motor solo run test after overhauling, measure current, vibrations for future record
                   
                   
24 Perform coupling of Motor with Pump
                   
                    10
25 Perform Motor load test after overhauling, measure current, vibrations for future record
                   
MI-2023 Preparation

Maintenance Procedure & Check Sheet


Maintenance Procedure

Inspection Check Sheet

11
MI-2023 Preparation

Manpower Plan
Electrical Team Manpower Organization

From 5th February to 8th February-2023 (04-Days)

Aminullah Sharif (Electrical


Management / Supervision Mohsin Jami (Manager Maintenance)
Engineer)

Major Activities Description Technician Technician Helper Sub Total Remarks

1 Helper from
Overhauling of CEP-B Motor 1 2 3 06 Megatech
(Contractor)

12
MI-2023 Preparation

Spare and Consumable


Sr.
Sr. No. Spares / Consumable Qty Spares / Consumable Qty
No.

DE Bearing
1 1 6 Emery Paper 10 each
(NU220)

NDE Bearing
2 2 7 Cotton Rags 10kg
(7324 BDT)

3 Grease  05 kg 8 WD-40 02

4 Loctite solution 01 9 Kerosene Oil 05 ltr

5 Silicon tube 05 10 Molycoat 01 Can


13
MI-2023 Preparation

Tools
Sr. No. Tool Description Qty. Sr. No. Tool Description Qty.

01 Technician Tool Kit 01 06 Centre punch 01

02 Babbitt material hammer 01 07 IR Tester (5kv) 01

03 Metallic Hammer 01 08 Micro ohm meter 01

04 Spanner Set (mm) 01 09 Torque Wrench 01

05 Socket set (10 to 32mm) 01 10 Inside/outside µMeter 01


14
MI-2023 Preparation

Pictorial View of Previous Activity

Motor Lifting Shift to Working Place Measure IR Before OH

15
MI-2023 Preparation

Pictorial View of Previous Activity

NDE Bearing Removal Shift to Working Place Measure IR After OH