Professional Documents
Culture Documents
Minggu Ke 10 - Keadah-Keadah Pengurusan Projek
Minggu Ke 10 - Keadah-Keadah Pengurusan Projek
Minggu Ke 10 - Keadah-Keadah Pengurusan Projek
ALAT-ALAT PENGURUSAN
PROJEK
6–3
Project Planning
6–4
Project Planning Tools
6–5
Project Planning Tools
6–9
PERT
6–
10
PERT Chart
6–11
Advantages/ Limitations of
PERT
Advantages Limitation
Especially useful when scheduling Project activities have to be
and controlling large projects clearly defined, independent,
Straightforward concept and not and stable in their relationships
mathematically complex Precedence relationships must
Graphical networks help to be specified and networked
perceive relationships among together
project activities Time estimates tend to be
Critical path and slack time subjective and are subject to
analyses help pinpoint activities fudging by managers
that need to be closely watched
There is an inherent danger of
Project documentation and too much emphasis being placed
graphics point out who is
on the longest or critical path
responsible for various activities
6–
12
Critical Path Analysis
6–
15
Example of Activity on Node Diagram
(CPM)
6–
16
Advantages/ Limitations of
CPM
Advantages Limitations
It helps in ascertaining the time CPM operates on the assumption
schedule of activities having that there is a precise known time
sequential relationship. that each activity in the project
will take. But, it may not be true in
It makes control easier for the real practice.
management.
CPM time estimates are not
It identifies the most critical based on statistical analysis.
elements in the project. Thus,
It cannot be used as a controlling
the management is kept alert
device for the simple reason that
and prepared to pay due
any change introduced will
attention to the critical activities change the entire structure of
of the project. network. In other words, CPM
It makes better and detailed cannot be used as a dynamic
planning possible. controlling device.
6–
17
Example of Project Plan
6–
18
Major step to do Project Plan
6–
19
Work breakdown structure
6–
20
Example of WBS
6–
21
The project Network
6–
22
Constructing a Project
Network
Terminology
Activity: an element of the project that
requires time.
A
Example : Activity A - Design/
Procurement/ Manufacture/ Maintenance.
Merge Activity: an activity that has two
or more preceding activities on which it D
depends.
Example : Activity D , which is depended B
on activity A and B.
Example – Procurement (D) can only start
after signing of award letter (B) and Visit
factory (A).
6–
23
Constructing a Project
Network (cont’d)
Path: Is a sequence of connected and dependent activities.
A B C
Critical Path: the longest path or period through the activity network
that allows for the completion of all project-related activities.
Delays on the critical path will delay completion of the entire
project.
A B C D
6–
24
Method for Project Networks
Approaches
Activity-on-Node (AON)
Uses a node / boxes to show an activity.
Activity-on-Arrow (AOA)
Uses an arrow to show an activity.
Approval Construction
A B C
6–
25
Basic Rules to follow in Developing
Project Networks
6–
27 FIGURE 6.2
Activity-on-Node Fundamentals (cont’d)
6–
28 FIGURE 6.2 (cont’d)
Information Recorded on Each Node / Boxes
1. List all the activities and duration for the individual task in a
table from WBS.
2. Identify which activity will start first and start later. (Preceding
activities.)
3. Draw a network diagram for the project.
4. Compute the Forward Pass calculation to determine the project
duration.
5. Compute Backward Pass Calculation.
6. Identify Critical activity for the project
7. Determine Float activity for the project.
8. Draw a Gantt Chart for the project.
6–
30
Step 1 - List all the activity from WBS
and duration for the project
Duration (DAYS)
5
15
10
5
15
10
170
35
6–
31
Step 2- Identify the preceding
activity for the project
Merge activity
Merge activity
Merge activity
6–
33 FIGURE 6.5
Step 4 -Compute Forward Pass Calculation
6–
34
Computation of Forward Pass- Determine ES and EF Time
Activity A , = 0 +5 = 5
Activity B , = 5 +15 =20
Activity C , = 5 + 10 = 15
Activity D , = 5 + 5 = 10
1.Start from left to right
Activity E = Merge activity , choose highest duration for
2. Add activity duration along each path in the network ES
3. EF = ES + DURATION Activity F = Merger activity, choose , highest duration for
4.Carry the early finish (EF) to the next activity where it becomes ES
its early start (ES). Activity G = 30 +170 = 200
5. If the next succeeding activity is a merge activity, in which case Activity H = Merge activity , choose
6– highest duration, for ES
the largest EF of all preceding activities will be selected. 35
Step 5 – Compute the Backward Pass calculation
6–
36
Backward Pass Calculation- Determine LS and LF Time
ES EF
ES EF
ES EF
LS LS
LF LF
ES EF ES ES
ES EF EF
LS LF
LS
LF
LS LF LS LF LS LF
ES EF
LS LF
6–
38
Step 6 – Identify Critical Activity
Critical path: the longest path through the activity network that
allows for the completion of all project-related activities.
6–
39
Calculation for Critical Activity
Activity A, B, F, G, and H.
6–
41
Calculation for FLOAT (SL)
Float (SL)
= LS – ES OR LF –EF
6–
43 FIGURE 6.12