CZF-QS-Rainy Season-REV05

You might also like

Download as pptx, pdf, or txt
Download as pptx, pdf, or txt
You are on page 1of 72

Rainy Season Preparation-2020/2021

Qatar South
Catchment Zone Framework
METITO (Overseas) Qatar

20/07/2020
Table of content
Rainy Season Management Concept- Qatar South

Specific Qatar South Zone

Area of concern

Plan for 2022 World Cup

PM activities
Rainy Season Management System-RSMS- QS
Rain Events Management Committee:
Rain Event Committee Duties of the rain Management Rain Event Manager.
Committee Who :
Framework Manager • One of the committee member
•Implement new strategy • Review individual section • Change every 12 hours.
Operation manager •Train the staff planning
•Carry out drills • Develop overall plan and Authority :
Customer service manager strategy
• Integrate the service . • Acts on behalf of company.
Works Manager –Network Plan • Have the authorities to control all
Act
sections.
Works Manager – PTP
• Have the authority to get
Works Manager –PS additional resources and
Check Do material.
Works Manager –TWN •Review the zonal flow. Assign the resources. Supported by :
•Review operation record •Control PM activities
Works Manager –DS-STW •Update rain strategy and •Manage the rain event • Team in ECC
procedure • Emergency coordinator for each
Works Manager –IA-STW
section
Rainy Season Management System-RSMS
Rain Planning
Before rain During rain After rain
• Plan Starts ECC Site
• Review history • Rain Event Manager • Clear the area .
• Section plans. • DNMC coordinator • Section wise restore BAU
• Integrated plan. Review
• Pumping station
• Allocate resources. • Submit reports with flow records.
representative
• Coordination with authorities . • Review the overall status
• Network representative
• Coordinate with Other PFC • Generate lesson learnt file
• Preventative maintenance Site Move Forward
• Individual sections • 24/7 attendance • Update the plans based on event
• Training and drill • Execute Rain emergency lesson learnt.
• Train staff procedure section wise • Prepare for next event
• Check equipment readiness • Rain Operation team
Escalation structure & planning
Escalation structure & planning
Customer
RRRU team Public relation Rain Event DNMC Service
Manager coordinator
Hot Spot

TSE Foul Stream SGW Water

Foul Sewer – Pumping station


DS-STW IA-STW PTP SGW N
Hot Spot SGW & FS

Blockage
TSE PS TSE PS removal SGW –FMP

ECC based Each section provide day/night shift coordinator who Each section – rain emergency organization chart and
When Required
coordinate with all site activities resources to be approved by area engineers
Before the rain
Before The Rain
General all sections to plan the resources and assign 24/7 emergency team
Surface Ground Water Network SGW Pumping Station Customer service
• Review historical and plan FMP`s • To check the historical data . • Review historical data of flooding complaints
• Check the site to do any prearrangement. • Plan and coordinate with PWA to ensure • to decide the hotspot
• PM – cleaning and inspection for : availability of standby /spare equipment • Allocate the resources near the hot spots
• Pipeline. • Clean wet well.
• Gully P1,2,3, underpass gullies, • Trial for underpasses and discharge points. STW &PTP
• storage tanks ,outfall , lagoon and deep well • Complete pumps maintenance and
injection overhauling before rainy season. • Plan resources and emergency equipment
• Assign resources and tankers • Check Waqood tanks and standby generator
• Train the staff Foul Sewer Network • Reduce lagoon levels -
• Prepare SOP for different operation scenario
• To check the historical data .
• Plan and coordinate with PWA to ensure
Foul Sewer Network TWN
availability of standby /spare equipment.
• Review historical data to decide the hotspot • Check accessibility of over pumping. • Review historical data.
• Additional cleaning cycle for hotspot area • Assign resources , Mobile pumps , standby • Minimize lagoon level in coordination with
generators and pumps, tankers….etc . PTP &STW
• Check standby generator and fuel supply • Monitor deep well injection
During The Rain
During The Rain
One coordinator per shift to coordinate between ECC and remaining team, team to record flow through tankers and running hours of the pumps

Surface Ground Water Network SGW Pumping Station Customer service


• Attending FMP for hotspots (Tankers- • All stations and underpasses to be manned • Remove blockage form house connection
Pumps). • Coordinate with the team to utilize any spare • Coordinate with other authorities
• Standby Cleaning team for any blockage, capacity. • Remove flood and rainwater to nearest
specially underpass • Control the diversion to AS01 , shaft levels discharge point
• Monitor the level of lagoons and outfalls and tunnels
• Operation team controlling flow diversion and • Report to Ashghal with photos of critical area STW &PTP
penstocks
• Support the other team through GIS and • optimize operation cycle.
allocating drainage manholes and rising • Utilize off spec lagoons to store excess
Foul Sewer Network sewage and recycle at later stage
mains
• To maintain Pumps station running condition • Operate stand by equipment if needed
Foul Sewer Network
and take immediate action for failure of any
• Clean and remove blockage for any area equipment. TWN
with repeated complaint • Coordinate with the team/SCADA to utilize • Coordinate with the team the discharge of
• Support the other team through GIS and any spare capacity. TSE specially with the reduced demand to
allocating drainage manholes and rising • monitor wet well levels injection wells and wet lagoons
mains • Utilize emergency equipment
After The Rain
After The Rain
Report the flow and quantity of the water removed
Surface Ground Water Network SGW Pumping Station Customer service
• Continue to clear the streets • All stations and underpasses continue to be • Remove flood and rainwater till streets are
• Provide overall data for amount of rain manned until level return to normal clear
removed. • stations to return to auto mode. • Update rain emergency procedure.
• Clean any clogged pipes and gullies . • Report total flow and running hours.
• Update rain emergency procedure. • Update rain emergency procedure.
STW &PTP
• Recycle and empty the sewage lagoons
• Update rain emergency procedure.
Foul Sewer Pumping station

Foul Sewer Network • Monitor the operation until the level return
back to normal
• Clean and remove blockage for any area • Coordinate with the team/SCADA TWN
with repeated complaint • Report flow and timing • Update rain emergency procedure.
• Update rain emergency procedure • monitor wet well levels
• Update rain emergency procedure.
Qatar South Operational plan
Qatar South Operational plan
Outfalls that discharge Qatar south Surface Ground Water Photo

Not connected to PS; MIA North


MIA South & MIA outfall has one damaged section
Islamic museum
North Outfall
inspected by CCTV

Photo
Ras Bu Inspected by CCTV line is
NDIA2 PS Ras Bu Abboud
Abboud road clear with little accumulated
network Outfall
network
sand and there is
refurbishment work ongoing
under QTCG.
Photo

Inspected by CCTV line is


Corniche Museum New Musuem
street lagoon. Outfall damaged need immediate
rehabilitation.
Qatar South Operational plan
Outfalls that discharge Qatar south Surface Ground Water Photo

Refurbishment work ongoing


Grand hamad street Corniche Outfall
under QTCG.

Photo
Al Saad, Al Nasr, Refurbishment work ongoing
Najma, Free Bin SW1 & SW1A
Mahmoud and Partly Outfalls under QTCG.
Mamoora

Photo

Souq Street/ Diwan Area outfall.


Diwan Amiri Area Diwan outfall In the good condition.
Inspected by CCTV line is good
Qatar South Operational plan
Outfalls that discharge Qatar south Surface Ground Water

SW1/AG-0 Photo
MUBT PS RUP/SW1
Outfall interface point with north
catchment to transfer water
Mesaimeer
MUBT
System
AS01 from north to south.

Photo

Blue Lagoon Mesaimeer


AS01(4.25 m3/s)
(6m/s) System
Qatar South Operational plan
UnderPass Ps Name Concern
Photo
Industrial interchange   Operation philosophy for PS 22A, 22 is required
Al Ghanim  
Shaft 10/shaft8/Sw5
Alzizyya
Wholesale
Al-Bustan
Al-Mamoura Alobidliy Tunnel Under Construction, Should be ready before the rainy
season
Al asiri   Photo
Al Attiya SIC
IC 26 IC 25 +Lagoon + Mesaimer System Lagoon should be connected to Mesaimer System

IC 25 IC 25+ Lagoon + Mesaimer System Lagoon should be connected to Mesaimer System

QP UP RUP-1
Sharq intch RUP-2
Muntazah street underpasses KUR-PS / WU-PS / BAR-PS / Currently not connected because of stopper located in Photo
total of 5 underpasees BRCT-PS / EIUP-PS the connection between Muntazah tunnel &
Mesaimeer system.
Al jawan Sw1 Al Saad connection should be reviewed along with
Al Saad JUP Ps upgrade.
Al Rayan RUP/SW1 (Only PS) Communication procedure between QSC & QNS
Qatar South Operational plan
Lagoon Ps Name Concern Photo
Blue Lagoon AS01 Shaft 11 should be connected with
permanent power
IC 25/IC26 Not connected IC 25/IC26 Not connected to the tunnel
GraveYard GY PS Not connected to the tunnel, PWA
workshop should provide 14” Diesel
Pump
56/EFA EI PS No discharge point is available Photo
56/728/EFA4 Negative system with Injection well Bar Screen is required
Tanks PS Concern
5 tanks located in Muntazah KUR-PS / WU-PS / BAR-PS / Currently not connected because of
street BRCT-PS / EIUP-PS stopper located in the connection
between Muntazah tunnel & Mesaimeer
system. Photo
Outfall PS Concern
SW1,RA, Cornish SW1,NDIA2 Under Rehabilitation with QTCG
Penstocks PS Concern
AG01 RUP Operation Responsibility
Qatar South Catchment
Qatar South- O&M plan- Network

1. PS SW9 11. PS SW7


2. PS IC25 UP 12. PS SW5
3. PS IC26 UP 13. PS SIC
4. PS GJUP 14. PS BTT
5. PS RAUP 1 15.PS RAUP2

6. PS RUP 16. PS GRAVEYARD


7. PS MUP 17. PS SHO8
8. SW1 18. PS SH10
9. PS OBA 19. PS SHO1
10. PS RCOM
Qatar South Negative System & Contingency Plan
DW013 Contingency Plan(Sailiya)

Existing HDPE pipe will be used

FPS-09 injection well


DW013 Contingency Plan (Sailiya)
• 5 Nos 12’’ Diesel pumps will be installed at the highlighted collection point of the
catchment and water will be pumped to deep injection well located in Mebaireek
during rain emergency
• There is an existing HDPE pipe using by other contractor, we will check the size if
its applicable we will connect our pumps otherwise we will install different pipe
with required road crossings

I. Concern
• Non-BAU BOQ workshop not held yet, we need to finalize that matter to be able to
proceed with NBAU activities such as road crossings, ramps, dewatering pumps,
grating covers….etc
DW015 Contingency Plan(Zone 53)

Discharging area
DW015 Contingency Plan (Zone 53)

• 6’’ submersible pump will be installed at the highlighted collection point of the
catchment and water will be pumped to open area during rain emergency
• Road crossing required

• Generator will be installed for the pump


• HDPE pipe 6’’ will be installed as a discharging hose
• Lagoon will be constructed with depth of 1 meter, length 10 meters and width 5 meters

I. Concern
• Non-BAU BOQ workshop not held yet, we need to finalize that matter to be able to
proceed with NBAU activities such as road crossings,ramps,dewatering pumps,
grating covers, civil works….etc
Preventative Maintenance activities
PM progress-Gully Cleaning Plan vs Actual
PM progress-Soakaway Cleaning Plan vs Actual
PM progress-Pipeline Cleaning & Inspection Plan vs Actual
PM progress
* Visual inspection completed for 33 tanks and latest status shared
with asset management for confirmation, total of 8 tanks required
cleaning.
PM progress
PM progress
GULLY DATA SHEET AS PER PRIORITY WISE - SGW

Priority 3
Priority 2 Priority 1
80% completed
will COMPLETE THIS Starts Next Month
MONTH
QS Underpass & Rainy season Preparation
Underpasses in South Catchment
• Total number of underpasses in south catchment zone is 20

• Inspection started on July 18,2020 in Al Ghanim underpass

• Cleaning of the underpasses as per PM plan will start from Aug 1,2020
PRIORITY 1 UNDERPASSES
CCTV INSPECTION FOR PRIORITY 1 UNDERPASSES AL SADD UNDERPASS

12-Mar-2020
PRIORITY 1 UNDERPASSES
PRIORITY 1 AL SADD UNDERPASS MOBILIZATION

12-Mar-2020
PRIORITY 1 UNDERPASSES
PRIORITY 1 AL SADD UNDERPASS MOBILIZATION

12-Mar-2020
PRIORITY 1 UNDERPASSES
PRIORITY 1 GULF MANNAI UNDERPASS

12-Mar-2020
PRIORITY 1 UNDERPASSES
PRIORITY 1 GULF MANNAI UNDERPASS

12-Mar-2020
PRIORITY 1 UNDERPASSES
PRIORITY 1 QP UNDERPASS
PRIORITY 1 UNDERPASSES
PRIORITY 1 QP UNDERPASS
PRIORITY 1 UNDERPASSES
PRIORITY 1 RAS ABU ABBOUD UNDERPASS
PRIORITY 1 UNDERPASSES
PRIORITY 1 RAS ABU ABBOUD UNDERPASS
Tanks and Lagoons
FID TANK
1
2
SW13
SA-03 Critical tanks
3 SA-04 FID Lagoon
4 SA-07
5 SA-05 1 56/728/EFA4
6
7
SA-06
M16/HT
1. AL Aziziya tank 2 GraveYard 
3 56/EFA
8
9
M113/7/HOLDING*
EINDUP1/STTK05 2. Barwa tunnel tank 4 DSLGN‐1A
10 BARUP1/STTK03
11 KARUP1/STTK01
12 SA-01
13
14
SA-02
BARCT1/STTK02
Critical Lagoons
15
16
WUP1/STTK01
CM/ATTN1
3. Blue Lagoon
17
18
CM/ATTN2
CM/ATTN3 4. Graveyard Lagoon
19 CM/ATTN4
20 CM/ATTN5 5. IC25
21 CM/ATTN6
22
23
CM/ATTN7
SWSI/UPT
6. IC26
24 SWSI/MT
25 SA-08
26
27
Ras Bu Abboud
Ras Bu Abboud • Tanks inspected, some of them attached with the PS assets, some are buried and the
28 QBA/SW/T
29
30
Rawdat Al Khail
AS/TANK
remaining related to SGWN
31
32
AJ-TANK1
Aspire
• Lagoons inspected, some of them are empty and the others are emptying by a diesel
33 MBTSW/T
pumps arrangement such as (IC26, Graveyard)
• Graveyard lagoon should be connected to Muntaza Tunnel
• IC26 lagoon, Metito proposed to connect the lagoon direct to AbuHamour tunnel
Qatar South Operational plan
Qatar South Operational plan
Operational Philosophy
Before rain starts Business As Usual –– Metito should maintain lowest level of water in storage assets such as
 Blue Lagoon water level should be reduced with minimum level by open lagoon discharge to Mesaimeer system, this action will be taken
when lagoon level exceed 50% of its capacity, the action will be carried out by Metito PS team by opening the penstock for shaft 11 with
coordination with Ashghal’s team and they have to be sure AS01 is in operation mode with full capacity .
 Installation of level Indicator required
 SW5 over pumping should be normally open during BAU and NBAU this should be monitored
 Lekhwiya tank to be emptied to lowest level by opening the discharge penstock and/or using submersible pumps facility, the action will be
carried out by Metito Network team. Water will be discharge direct to shaft 10 and then to blue lagoon, this procedure has to be done before
open the discharge of blue lagoon.
 Aziziya tank ensure water level the lowest by opening the discharge penstock and/or using deep injection facility, the action will be carried
out by Metito SGWN team.
 IC25 / IC26 Lagoons to be emptied to lowest level by pumping the water to Measimeer tunnel by diesel pumps, this action will be carried out
by SGWN team.
 PWA Work shop to provide the required Diesel pumps for IC25 lagoons
Qatar South Operational plan
 GraveYard Lagoon Lagoons to be emptied to lowest level by pumping the water to Measimeer tunnel by diesel pumps, this action will be
carried out by SGWN team.
 RUP-PS will remain discharging to AG0 outfall during BAU and NBAU.
 AG1 penstock will be closed during BAU. North Contractor responsibility.
 Shaft 8 will be in Standby Mode.
 All underpasses tank should maintain lowest water level and ready for rainy season.
 All soakaway in main roads to be inspected for further action.
 All deep injection system will be inspected and cleaned before next rain event.
 P1 & P2 for gullies will be inspected for further action.
 EFAs should maintain lowest water level and ready for rainy season.
 Customer service team will carry out the regular inspection for the repeated complaint to check the status of the network and take further
action.
Qatar South Operational plan
During the rain- Alert Status – The gates/penstocks to be closed/opened so that the use of available storages can be maximized
as per the following plan.
 AG1 penstock to be opened and flow to be discharged through AS01 (North Contractor)
 SW5 over pumping valve remain open -Overflow diverted to Tunnel – ( Valve is controlled by ??)
 RUP penstock will remain close to divert flow to AG0 outfall (PS Team)
 Lekhwiya tank penstock to be opened 50% (PS Team)
 To ensure discharge penstock for shaft 10, 22,22A are open and flow diverted to blue lagoon. (PS Team)
 AS01 to remain operated as manned station and diesel supply to be secured .
 All underpasses PS including SW1, SW5,RUP,IC25, IC26,AS01,JUP,MUBT and shafts 10,22,22A will be man operation mode
 Shaft 8 will be standby
 Ramada signal pump will be manned operation mode
 Mobilization for assigned hotspots
 Customer service team to ensure all dewatering facilities through network is stopped
 Customer service team start to mobilize teams to critical negative area such as wakra lagoon,wukair,sailyia, Bu sidra ,Mauither, Mebaireek,
Mamoura, Ain khalid and Bu hamour.
Qatar South Operational plan
During the rain - Incident Status – Certain real time controls need to be operated as per the stated procedures, once the
water level in the system reaches to a certain level. These controls are required to be operated remotely from the ECC room as per the
followings:
 DNMC coordinators will monitor the water level and take necessary action to report to concern person
 DNMC coordinators should keep updating the staus to PWA staff and Metito staff as well
 Customer service team will carry out the responsibility of customer complaints related to rain flooding during the rain event.
 Customer service team will aasign stand by team to carry out any required maintenance related to SGW assets during the incident
After Rain Event – The works shall be done by Ashghal’s Assets Affairs so that the assets are drained and resumed to business
as usual status to ensure readiness for possible further rains as per the followings:
•  The lagoons will be drained to maintain lowest water level as per the priority
•  Tanks to be drained to maintain lowest water level
• EFAs drained to maintain lowest water level
•  Any negative storage system to be emptied
•  Required reports will be submitted to PWA after rain event
•  Any new hotspots will be reported to PWA
•  
Hot Spot current data
• No. of Hotspots : 60 Hotspots. ( 29 HS SGW/ 31 Customer Complaints)
• No. of Areas : 5 Areas. ( Area 12,13,14,15,and 16).
• No. of School Hotspots : 10 Schools.
• No of Critical Substation : 3 Substations ( P047,P354,P592) Doha Industrial Area A & G, Wakra North Substation.
• No.of Stadium : 4 Nos ( Wakra, Ras Abu Abood, Khalifa, Thumama)
• No. of Current Infrastructure Projects: 8 Projects
P010 West Corridor ( J&P) contractor .
P023- C3 Musaid Salwa Road ( Jaber& Lighnton) contractor.
P017-C2 East Industrial Raod ( TEKFEN).
P008-C2 Musaimeer Road ( CCC& Teyseer ) Contractor.
P023-C1 Doha port orbital Highway ( J&P) Contractor.
P015 Wakra Bypass Road ( L&T ) Contractor.
P017-C1-IN Wakra Main Road , ( Boom Constructions).
P011 East Corridor ( China Harbor) Contractor.
Qatar South Hotspots and Projects Layout
General Hotspots
Customer Complaints Hotspot.
Qatar South RPD Projects
Qatar South FRP Projects
Qatar South Beautification Projects
Zone 43 Al Mamoura Customer Compliant Interim Solution

m3
K 3 GE
TAN TORA
00
S
HOTSPOT
Qatar South Operational plan
Doha South STW :  Metito is going to use IDRIS as storage facility during the Rainy season
2020/2021 for the area’s with negative system to reduce the hydraulic load
Connection to IDRIS on the FS Ps as following:
1. Rain water will discharge to the FS PS
2. Excessed flow will divert to the tunnel by opening the Penstock.
3. storage water will be recirculated again to the FS Ps during the BAU.

Critical Area will be serve By IDRIS

4. Muberak
5. Ain Khaled
6. Busaidra
7. Mamoura

• PS-30  (63,500 m3/day)


• Ps-40  (100,000 m3/day)
• PS-44  (60,000 m3/day)
• PS-46  (6,000 m3/day)
Area of concern
Area of concern
Workshop equipment removed –Capacity –
Flow- Hydraulic pumps 1. During rain alert SW5 over pumping valve to be
open ,Overflow shall be diverted to tunnel, This
Historical information- Foul sewage PS- Surface valve operating by other contract ,So network
ground Water PS- Underpasses team need to clarify .
2. PS-BTT need dewatering arrangements during
Operation of Lakhoya Lagoon- QN –AS01- rain emergency
Diesel generator- penstock location- Diesel 3. Excess water over flow from Qatar airways
building to PS-17 and SW9 MCC room , so need
Wakra and Wakair FMP , lagoons under PWA to open main inlet chamber for PS-17 as well
Project  SW9 to drain
4. In JUP Two submersible pump arrangement was
Coordination with other zone contractor for there in last rainy session with 45 KW and 18 KW
discharge point . operating by portable generator, Now removed by
Boarder clarifications especially Cornish road. Workshop Ashghal
Plan ongoing Project. 5. In PS1 and SW1 diesel Engine arrangements kept
in station, Now removed by Ashghal
PS & Treatment Facility operation records during 6. PSG-WI,WT,SW11,SW12,SW14,MUP,MUPT not
the previous rain emergency./ Historical Data yet taken over , Need to study the requirements
and historical operation
Area of concern- Pumping station
No. PS Concerns
1 PSG-SHAFT 10 Station access is blocked
2 PSG-SHAFT 22 Station access is blocked
3 PSG-SHAFT 22A not taken over yet
4 PSG-WUP1 The pumps are small to handle the flow, Rain emergency equipment is required
5 PSG-BARUP1 The pumps are small to handle the flow, Rain emergency equipment is required
6 PSG-BARCT1 The pumps are small to handle the flow, Rain emergency equipment is required
7 PSG-KARUP1 The pumps are small to handle the flow, Rain emergency equipment is required
8 PSG-EINDUP1 The pumps are small to handle the flow, Rain emergency equipment is required
9 PSG-EIEFA1 The lagoon capacity is small and there's no discharge for it
10 PSG-MSIW Not taken over yet
11 PSG-IC25 There's no discharge for the lagoon
12 PSG-IC26 The lagoon capacity is small, the station is continuous running
13 PSG-RCOM  Emergency equipment to be provided
14 PSG-GRAVEYARD The station is controlled by SCADA, Emergency equipment to be provided
15 PS-SW14 Not taken over yet
16 PSG-AS01 Hydraulic pumps removed from the site. Spare pump is required
Not taken over yet.
17 PSG-NDIA1
The rainwater accumulated inside the station boundary. Diesel/submersible pump is required
18 PSG-NDIA2 The tank capacity is small, The diesel pump removed by PWA
19 PSG-SIC Submersible Pump and generator removed from the site
Area of concern- Pumping station

1)PS W12-Road elevation is above the station level. Diesel pump should be available during rainy season.

2)PS 17& SW9- road elevation is above the station level. Diesel pump should be available during rainy season.

3)WUP1- wet well capacity is less and cannot manage the flow during rainy season and rising main line is small(150mm).

4) BARUP1 - wet well capacity is less and cannot manage the flow during rainy season and rising main line is  small(150mm).

5) KARUP1 - wet well capacity is less and cannot manage the flow during rainy season and rising main line is small(150mm).

6)NDIA2 -wet well capacity is  less and cannot manage the flow during rainy season.
Area of concern
1. The operation philosophy is required for shaft 10,22, 22A.moreover, we need to know there is another facility to discharge the water directly
to abo humor tunnel and by passing the blue lagoon in case of the emergency.
2. DC chamber Drawings and details which connected to SW5
3. Flow chart diagram and drawings for all tunnels in Doha south showing the connection points
4. Flow chart diagram for all EFA systems
5. Location of all operational penstocks
6. Flow chart diagram for interim solution projects including the temporary solution for the assets not connected
7. Coordination procedure between PWA workshop and Metito during rainy season
8. Agreement with PWA workshop to keep some arrangements such as hoses, temporary pipes and facilities which currently are using to
connect isolated systems with discharge point to be used by Metito till ongoing projects handed over and be in operational mode.
9. Metito Requests from PWA to provide portable access on tablets to monitor the asset’s operation such as penstocks, valves, pumps, flow…
etc
10. Penstocks and weir information for Shaft 11
11. Manual operation for penstocks
12. Operation philosophy for shaft 22A roller gate
13. Operational philosophy for Distribution chamber for shaft 10 and shaft 22
14. The locations of the sensors located in the network
15. Coordination plan between south contractor and north contractor during rain emergency
Plan for 2022 World Cup
Plan for 2022 World Cup
Target MUNICIPALITIES
To Avoid Tankers
Media –Restricted Movement
MINISTRY OF
MUNICIPALITY AND
To achieve ENVIRONMENTAL
Solution for
Negative system

Solution QATAR FOUNDATION


Mutual Efforts
from authorities QATAR SPORTS SUPREME
COMMITTEE

SCHOOLS
Plan for 2022 World Cup
RAINWATER
Network Solution Alternative Solutions
Transfer to Utilize in Place ( Reuse)
Outfall
Transfer Storage
Emergency Concrete channel Filtration Under ground
Separate Combined (landscaping) tank
Combined
system system
System
Deep Well
Artificial Lakes Landscaping
IDEAL SOLUTION
Injection
100% SEPARATE SYSTEM CASE STUDY
BUDGET TIME RESTRICTIONS DISTURBANCE TO PUBLIC FROUSIYAH AND ASPIRE
Plan for 2022 World Cup
NETWORK SOLUTION:
• ONCE HYDRAULIC MODELING IS READY AND HISTORICAL INFORMATION IS AVAILABLE.
• GENERAL REVIEW OF THE NETWORK INCLUDING PUMPING STATIONS AND SURFACE GROUND WATER AND FOUL GROUND WATER THEN
CLASSIFY THE AREA AS FOLLOWS :
• Type 1 : Area Covered by Separate system with sufficient pumping capacity 
• Type 2 : Area Covered by Foul Sewer Network only and Negative Surface Ground Water Network:
• Type 2 A - Foul Sewer Network (RM) & Pumping Station can accept the flow without impacting the house connections.
• Type 2 B - Foul Sewer network (RM) can accept additional flow, but Pumping station are loaded.
• Type 2 C - Foul Sewer network (RM) and Pumping station loaded and network is surcharged
• Type 3 : No Foul Sewer Network and No Surface Ground Water Network (very rare).
Type Proposed Recommended Solutions
Type 2A Automatic penstock mechanism to discharge to network in
emergency only
Type 2 B Upgrade Pumping Stations – At least one bigger capacity
pump fed by VFD
Type 2C Separate SGWN or Artificial lagoon or deep well injection

Type 3 Separate SGWN or Artificial lagoon or deep well injection


Plan for 2022 World Cup
ALTERNATIVE SOLUTION: Re-Use of Rainwater Utilize in landscaping
•Idea`s to be developed in coordination with Landscaping Save Potable water and TSE
other authorities for type 2 C and 3 such as : Artificial lakes
 Stadium . Fountains
 Municipalities (Parks ,large landscaping Cooling Tower makeup
area , malls …etc). Save potable water & TSE
 Schools and Qatar foundation.
•Utilizing available irrigation tanks / Artificial
lakes ( Existing or New) with fountains.
•Construct temporary storage tanks
underground or landscaping to store and filtrate
the water. Storage In Lakes
•Reuse the water in TSE network Save long pipeline , additional pumping
stations .

Rain Channel- Under roads


Minimum Disruption to traffic
No need for deep excavation
Covered by concreate slaps to be used for cycling or walkways
Thanks For Your Attention