AQUACULTURE ENGINEERING
1
General Layout of Pond Farm
3
Design/Layout of the Pond System
Pond compartments
Size depends on:
Type of production & mgt. technique
Specific uses
Topography
Availability of water
Volume of market demand
Shape
Depth
4
Design/Layout…Features of
dikes
TW
z
core trench
BW
BW = 2(zh) + TW
Where, BW, bottom width (m)
z, horizontal length (m)
h, height (m) 6
TW, top width (m)
Sample Computation
Complete the table below:
Height of dike Top width of Bottom width Side Slope
(m) dike (m) of dike (m)
1.5 1.5 ? (1) 1.5: 1
3.175 2.3 15.0 ? (2)
2.75 ? (3) 10.5 1.5:1
Solutions:
(1) BW = 2(zh)+TW = 2(1.5)(1.5m) + 1.5m = 6m
(2) z = (BW-TW)/2h = (15m - 2.3m)/[2(3.175)] = 2 ~ side
slope 2:1
(3) TW = BW – 2(zh) = 10.5m - 2(1.5)(2.75m) = 2.25m 6
Design/Layout…Determination of height of dike
Main dike
Where, ELEVm, elev. of main dike (m)
GS + Mf + F GS, ground surface (m)
ELEVm = --------------- Mf, maximum flood level (m)
1 - %S/100 F, allowance for freeboard (m)
%S, allowance for shrinkage
Secondary dike
7
Design/Layout…Location of water supply & drainage
facilities
Separated in the opposite ends
8
Design/Layout…Overflow
structures
Drainage standpipe
Monk
Open concrete gate
Emergency spillway
Mechanical or pipe From FAO Training Series 20/2, 1992
spillway
10
Design/Layout…Plans & drawings of pond
farms
Development plan
Detailed drawings
11