Coordination Meeting 02-08-2022

You might also like

Download as pptx, pdf, or txt
Download as pptx, pdf, or txt
You are on page 1of 23

NATIONAL HIGHWAY & MOTORWAY

POLICE (NHMP) TRAINING COLLEGE,


SHEIKUPURA
INFRASTRUCTURE MASTER PLANNING
FOR REVIEW AND APPROVAL
02-AUGUST-2022
PAKISTAN PUBLIC WORKS DEPARTMENT, GUJRANWALA

NATIONAL ENGINEERING SERVICES PAKISTAN (PVT) LIMITED


DISCUSSION POINTS
 PROJECT BACKGROUND

 MASTER PLAN

 TOPOGRAPHIC SURVEY

 GEOTECHNICAL INVESTIGATIONS

 GEOMETRIC LAYOUT OF ROADS, R.O.W., CROSS SECTIONS

 CONCEPT DESIGN OF SEWERAGE, WATER SUPPLY AND


STORM WATER

 UNDER GROUND ELECTRICITY

 MAIN GATE DESIGN, RCC RETAINING WALL DESIGN

 OVERHEAD WATER TANK

 EXTENSION DEVELOPMENT
PROJECT
PROJECT BACKGROUND BACKGROUND

 Project was awarded to M/S NESPAK by Competent Authority dated


March 30, 2022.
 NESPAK submitted its final Proposal dated May 24, 2022 after detailed
discussion and meeting with Pak PWD.
 Consultancy Agreement was signed between Pak PWD and M/S
NESPAK dated June 24, 2022.
 In the mean time NESPAK Expert Team Visited the Project site and
conducted detail meetings with all stake holders.
 Master Plan was discussed and general approval was given by Deputy
Commander NHMP in a meeting conducted at Sheikhupura in last week
of June 2022.
 NESPAK submitted Preliminary Design Drawings as per CA dated July
01, 2022.
 Some changes/improvements were suggested in preliminary design by
XEN office which was incorporated in design.
 The improved concept design shall be discussed in this meeting for final
approval and onward proceeding.
TOPOGRAPHIC SURVEY
 Survey has been carried out using drone technology
TOPOGRAPHIC SURVEY
MASTER PLAN
GEOTECHNICAL INVESTIGATION PLAN
GEOMETRIC DESIGN

24 ft Main Double Road

4 feet Green Belt

18 feet Internal Roads

Road Name Length


(Feet)
Main Double Road 1,287
Periphery Road 4,872
Internal Roads 7,352

Total Length (Feet) 14,798


CROSS SECTIONS OF ROADS
CROSS SECTIONS OF ROADS
CROSS SECTIONS OF ROADS
SEWERAGE

Sewerage
Disposal
Station
SEWERAGE
WATER SUPPLY

OHWT
OVER HEAD WATER TANK

 25,000 Gallons Capacity.


STORM WATER DRAINAGE

Rain water Harvesting system is not advisable in this area due to the following
reasons:

 Ground water table is about 30 to 40 feet from NSL in the Project Area, this
system shall have a very minimal effect of recharging the ground water table.

 A minimum of about 1.5 lacs gallons to 2 lacs gallons capacity Underground


water tank would be required which shall be very costly (about 35 to 40 million)

 A proper drainage system would cost ranging from 100 to 120 millions

 Maintenance issues, cleaning of drains and underground water tanks

 ROW issues
UNDER GROUND ELECTRICITY
STREET LIGHTING (General Layout Plan)
GATE DESIGN

NHMP
EXTENTION DEVELOPMENT
BOUNDARY WALL DESIGN OPTIONS

OPTION-1 OPTION-2 OPTION-3


RAMP DESIGN DETAIL

MOTORWAY
MAIN GATE

GREEN BELT

SERVICE ROAD
RAMP
Thanks

You might also like