Progress Review Presentation 24 Feb 2023 To 2 Mar 2023
Progress Review Presentation 24 Feb 2023 To 2 Mar 2023
Prepared By:
Content
01 02 03 04
Master Plan Project District Cooling Construction
Layout Priorities & and Gas Network KPI
Milestones Progress
Summary
05 06 07
Engineering/ HSE Update QA/QC
Procurement &
Progress Status RFI status
08 09
Critical Activities Photographs
&
Issues & Concerns
2
01 DataDate:
Master Plan Layout 02 Mar 2023
3
02 Data Date:
Project Priorities & Milestones 02 Mar 2023
Original
Approved
S No. Milestone Description Completion Revise Baseline Dates Variance Remarks
Baseline Dates
Date
1 Project Start 15-Nov-21A 15-Nov-21A 15-Nov-21A Completed
0
4
02 Data Date:
Project Priorities & Milestones 02 Mar 2023
4
02 Data Date:
Project Priorities & Milestones 02 Mar 2023
31 31 0 0 31 31 0
31 31 0 0 31 31 0
31 31 0 0 31 31 0
31 16 0 2 31 18 0
31 31 0 0 31 31 0
31 16 0 0 31 16 0
4
02 Data Date:
Project Priorities & Milestones 02 Mar 2023
4
02 Data Date:
Project Priorities & Milestones 02 Mar 2023
81 81 0 0 81 81 0
81 78 0 1 81 79 0
81 78 0 1 81 79 0
81 78 0 0 81 78 0
81 75 0 0 81 75 0
57 54 0 3 57 54 0
76 11 0 7 76 18 0
81 0 0 0 81 0 0
4
03 District Cooling and Gas Data Date: 2
02 Mar 2023
Network Progress Weekly
Note : All Values has been taken as per Revised Baseline
Engineering DC and Gas 100.00% 100.00% 0.00% 0.00% 0.00% 0.00% 100.00% 100.00% 0.00% Completed
Procurement Dc and Gas Network 100.00% 99.48% -0.52% 0.00% 0.39% 0.39% 100.00% 99.87% -0.13%
Construction DC and Gas 100.00% 97.99% -2.01% 0.38% 100.00% 98.37% -1.63%
0.00% 0.38%
network
Section 1 DC and Gas Network 100.00% 100.00% 0.00% 0.00% 0.00% 0.00% 100.00% 100.00% 0.00%
Section 3 DC and Gas Network 100.00% 97.86% -2.14% 0.00% 0.41% 0.41% 100.00% 98.27% -1.73%
Testing and Commissioning 100.00% 51.83% -48.17% 0.00% 0.71% 0.71% 100.00% 52.54% -47.46%
Overall DC And Gas Network 100.00% 96.34% -3.66% 0.00% 0.38% 0.38% 100.00% 96.72% -3.28%
9
05 Data Date:
Engineering/ Procurement 02 Mar 2023 7
Progress Status 14
Shop Drawing Submittal
Gas Line 68 2 0 2 62 3 0 68
10
05 Data Date:
Engineering/ Procurement 02 Mar 2023 7
Progress Status 14
As Built Drawing Submittal
Gas Line 8 8 0 0 0 0 0 8
Total 42 42 0 0 0 0 0 42
11
06 Data Date:
02 Mar 2023
HSE Update 14
Manpower Status
Project Team 10 9 1
Equipment Operator 4 7 3
Grand Total 38 30 8
12
06 DataDate:
02 Mar 2023
HSE Update 14
Equipment Status
Equipment 4 7 3
13
06 DataDate:
HSE Update 02 Mar 2023
HSE Statistics
8 HSE NCR 0 03 0
07 DataDate:
02 Mar 2023
QA/QC & WIR status
14
Work Inspection Request (WIR)
WIR Submittal
15
07 DataDate:
QA/QC & RFI status 02 Mar
20232
1
Method Statement
4
Under Issued Issued Issued Issued For CODE
Discipline Submitted Overdue
Review Code A Code B Code C Information Sub Total
Gas Line 1 0 0 0 1 0 0 1
Total 8 0 0 1 7 0 0 8
16
07 DataDate:
QA/QC & RFI status 14 02 Mar
2023
Request For Information RFI
Total 7 0 0 7 0 100%
17
07 DataDate:
02 Mar 2023
Internal NCR status 14
Internal Non-Conformance Report NCR (QHSE)
18
11 DataDate:
Progress Photos 14
02 Mar 2023
19
11 DataDate:
Progress Photos 14
02 Mar 2023
20
09 DataDate:
02 Mar 2023
Progress Photos 14
Activity: Addition of Two more Pumps for Chemical flushing for District Cooling Network
21
THANK YOU