Terms of COD

Sirodzul Munir
PT. Indokoei International
June 19, 2023

06/26/2023 aek sibundong mhpp 2x4 mw 1


Contents

TERMS OF WATER TERMS OF TERMS OF INTERFACING COD


READINESS TRANSMISSION LINE COMMISSIONING
READINESS

06/26/2023 aek sibundong mhpp 2x4 mw 2


Terms of Water Readiness – by
Paesa
No Description Status Date of Availability
1 Weir and appurtenances have been constructed Not finished yet
already
2 Gates and Stoplogs have been installed and Not installed and tested yet
operating properly
3 Tailrace and Stoplogs have been constructed Tailrace not finished yet, Stoplogs installed already
including submersible pumps but not tested yet
4 Waterway GRP not finished yet
5 Penstock Not finished yet
a. Tie-in Joint Flanges Steel Penstock - GRP Not finished yet
b. Tie-in MIV Spool Pipe – Steel Penstock Not finished yet
c. Anchor Blocks (AB-5 & AB-6), Slab and Saddles Not constructed yet
under Steel Penstock
d. Stairs beside Steel Penstock Not constructed yet
06/26/2023 aek sibundong mhpp 2x4 mw 3
Terms of Transmission Line – by PSP and
ASE
Date of
No Description Status PIC
Availability
1 Poles Construction for SUTM including Not finished and tested yet PSP 25 July 2023
accessories ASE for
Hindrance: Pangasean, Sigalogo Pangasean
2 Underground Cable Line including jointing and Not installed and tested yet PSP 15 July 2023
accessories
3 Cubicles installation and testing to be carried out after cubicles on site and ASE, PSP 28 July 2023
cubicle building ready
4 SLO for transmission Line To be carried out after 3 points above done PSP, SLO Consultant 26 July 2023

5 Back feeding To be carried out after GH ready of all PSP, GH, GI Dolsa, 29 July 2023
equipment and instrumentations and ready SLO Consultant
for individual test
6 Synchronization of Grid To be carried out once GH for RR Test PSP, GH, GI Dolsa, 1 Agustus 2023
SLO Conmsultant

Note: ASE must drop a notification letter to PLN UID Sumut once backfeeding and RR Test are ready
06/26/2023 aek sibundong mhpp 2x4 mw 4
Terms of Commissioning – by GH

No Description Status PIC Date of


Availability

1 Mechanical Installation On going GH 18.07.2023

2 Electrical and Instrumentation Not carried out yet GH 01.08.2023

3 Individual Test (Dry and Wet Test) To be carried out once water and back GH, PSP, GI Dry: 18.08.2023
feeding are ready Dolsa, ASE, SLO Wet: 28.08.2023
Consultant

4 Run and Reliability (RR) Test 3x24 hrs To be carried out once grid GH, PSP, GI 06.09.2023
synchronization are ready Dolsa, ASE, SLO
Consultant

5 Training OnM To be scheduled after RR Test GH, ASE 07.09.2023

06/26/2023 aek sibundong mhpp 2x4 mw 5


Interfacing Scheme

Terms of
Terms of
Transmission Line
Terms of Water Commissioning
• Back feeding
Readiness • Individual Test
• Grid
• RR Test
Synchronization

LOT 1 LOT 2 LOT 3

06/26/2023 aek sibundong mhpp 2x4 mw 6


COMMERCIAL Road to COD:
1. All terms of water readiness, transmission line and
OPERATION 2.
commissioning are in place and done properly
ASE submits request for NIDI by uploading
DATE appropriate documents needed to website
siujanggatrik
3. ASE appoints SLO Consultant
4. SLO Consultant conducts and checks all necessary
documents and tests
5. SLO Consultant proceed SLO Certification
6. PLN issues SLO Certificate

06/26/2023 aek sibundong mhpp 2x4 mw 7