TSS New 5G

You might also like

Download as pptx, pdf, or txt
Download as pptx, pdf, or txt
You are on page 1of 114

TSS & SDE START

TSS SDE
TECHNICAL SITE SURVEY & SDE

Presenter
MAZRILHISHAM MANSOR
01 INTRODUCTION
Site Engineering Workflow

02 PREPARATION
Tools & Checklist

TABLE OF
CONTENT 03 SITE SURVEY
What We Do

04 SDE
Site Design Engineering

05 Q&A
Conclusion

Specially Crafted by | Mazrilhisham Mansor 3


TSS
INTRODUCTION
Site Engineering Workflow
Preparation

Site Investigation

Customer
Site Dependent

Material

Drawings

Allocation and
Cabling documents

TSSR/SID Compilation
and Delivery
Fibre Optic
Microwave
Fibre Optic
ENCLOSURE

| 2021-05-10 | Ericsson Confidential | Page 12 of 12


AIR 6419 – 3.5 GHZ

| 2021-05-10 | Ericsson Confidential | Page 13 of 12


AIR 3268 – 3.5 GHZ

| 2021-05-10 | Ericsson Confidential | Page 14 of 12


KATHREIN ANTENNA – KRE 101 2412/1

| 2021-05-10 | Ericsson Confidential | Page 15 of 12


RADIO 4432 – LTE 700 MHZ
(ANCHOR BAND)

| 2021-05-10 | Ericsson Confidential | Page 16 of 12


MINI-LINK 6352/2 80/CD

O&M port Traffic -48V / PoE


| 2021-05-10 | Ericsson Confidential | Page 17 of 12
ANT2 C 0.6 80 HP

| 2021-05-10 | Ericsson Confidential | Page 18 of 12


L7N3 – CONFIGURATION (TYPE SITE 1)
 Baseband 6648
 3.5G 64T64R and L700

700 MHz – 4 ports

Coaxial jumper Coaxial jumper S3


S1 S2
AIR 6419
Radio 4429 = B28 N42
S1 S2 S3

OPT 1
To Port D

To Port C
To Port B
To Port A

To Port E To Port F

To Port G
To Port H

To Port J

Alarm
CPRI CPRI

Power

To Breaker TN A BB1 6648


To Router
MICROWAVE

Kat
700Mhz

1 x Baseband 6648
1 x Cell Site Router (CSR) –Router 6672
Air 3227
3500Mhz

PDU

Radio 4432 ENCLOSURE


6140
Sector 1 Sector 2

Air 3268 Kat


Air 3268 3500Mhz 700Mhz
3500Mhz

Kat
700Mhz

Radio 4432

Radio 4432
TSS
PREPARATION
TOOLS
• CIDB, WAH CERT
• CAMERA – 30MP AND ABOVE
• GPS – LOCATION, ALTITUDE
• COMPASS
• MEASURING TAPE 7, 50,100m
• YELLOW TAPE
• BASIC TOOLS
• STATIONERY – PENCIL, PEN, PAPER,
• SAFETY & PPE – HARNEST, BOOTS, GLOVE,
HELMET
• PORTABLE FIRE EXTINGUISHER
• FIRST AID KIT
• BANNER
ACCESS & LOCATION - GOOGLE EARTH &
MAP
Folder
&
Checklist
SDE
TSS
SITE SURVEY
FRONT
PAGE
SITE PROPOSED INFO
SITE PROPOSED INFO
SITUATION PLAN - GOOGLE EARTH &
GPS

CAN DO BEFORE
TOWER
LEG
TOWER
LEG

D A
U

C B
SITE INFORMATION
TRANSMISSION
CHECKLIST
SITE PHOTOS – Site Access View
SITE PHOTOS – Site Access View
4 WALL
SITE PHOTOS – Surrounding Angle View
POWER SUPPLY PROPOSAL
(SITE BASIS)
DiGi Sites TM/Webe Sites Maxis Sites Other MNO
• Propose to tap at • Propose to tap at • Propose new TNB meter • Propose to tap at
existing DiGi existing TM with incoming 3-phase existing PDU/ACPDB
PDU/ACPDB PDU/ACPDB with sub- 63A • Propose new 1xPDU
• Propose new 1xDB meter • Propose new 1xPDU come with 1x3-phase
come with sub-meter, • If existing TM is using come with 1x3-phase 50A AC MCB, Alarm
RCCB, ARS, and 1x3- single phase PDU, 50A AC MCB, Alarm Terminal & Auto Reset
phase 50A AC MCB propose to tap Terminal & Auto Reset Button
• DiGi to upgrade existing temporarily at existing Button • Propose new sub-meter
PDU/ACPDB if faulty or PDU & propose new 3- only upon site owner
defected phase TNB meter request
• Propose new 1xPDU
come with 1x3-phase
50A AC MCB, Alarm
Terminal & Auto Reset
Button
POWER SUPPLY PROPOSAL
(SITE BASIS)
DiGi Sites TM/Webe Sites Maxis Sites Other MNO
• Propose to tap at • Propose to tap at • Propose new TNB meter • Propose to tap at
existing DiGi existing TM with incoming 3-phase existing PDU/ACPDB
PDU/ACPDB PDU/ACPDB with sub- 63A • Propose new 1xPDU
• Propose new 1xDB meter • Propose new 1xPDU come with 1x3-phase
come with sub-meter, • If existing TM is using come with 1x3-phase 50A AC MCB, Alarm
RCCB, ARS, and 1x3- single phase PDU, 50A AC MCB, Alarm Terminal & Auto Reset
phase 50A AC MCB propose to tap Terminal & Auto Reset Button
• DiGi to upgrade existing temporarily at existing Button • Propose new sub-meter
PDU/ACPDB if faulty or PDU & propose new 3- only upon site owner
defected phase TNB meter request
• Propose new 1xPDU
come with 1x3-phase
50A AC MCB, Alarm
Terminal & Auto Reset
Button
POWER SUPPLY PROPOSAL
(SITE BASIS)
DiGi Sites TM/Webe Sites Maxis Sites Other MNO
• Propose to tap at • Propose to tap at • Propose new TNB meter • Propose to tap at
existing DiGi existing TM with incoming 3-phase existing PDU/ACPDB
PDU/ACPDB PDU/ACPDB with sub- 63A • Propose new 1xPDU
• Propose new 1xDB meter • Propose new 1xPDU come with 1x3-phase
come with sub-meter, • If existing TM is using come with 1x3-phase 50A AC MCB, Alarm
RCCB, ARS, and 1x3- single phase PDU, 50A AC MCB, Alarm Terminal & Auto Reset
phase 50A AC MCB propose to tap Terminal & Auto Reset Button
• DiGi to upgrade existing temporarily at existing Button • Propose new sub-meter
PDU/ACPDB if faulty or PDU & propose new 3- only upon site owner
defected phase TNB meter request
• Propose new 1xPDU
come with 1x3-phase
50A AC MCB, Alarm
Terminal & Auto Reset
Button
POWER SUPPLY PROPOSAL
(SITE BASIS)
DiGi Sites TM/Webe Sites Maxis Sites Other MNO
• Propose to tap at • Propose to tap at • Propose new TNB meter • Propose to tap at
existing DiGi existing TM with incoming 3-phase existing PDU/ACPDB
PDU/ACPDB PDU/ACPDB with sub- 63A • Propose new 1xPDU
• Propose new 1xDB meter • Propose new 1xPDU come with 1x3-phase
come with sub-meter, • If existing TM is using come with 1x3-phase 50A AC MCB, Alarm
RCCB, ARS, and 1x3- single phase PDU, 50A AC MCB, Alarm Terminal & Auto Reset
phase 50A AC MCB propose to tap Terminal & Auto Reset Button
• DiGi to upgrade existing temporarily at existing Button • Propose new sub-meter
PDU/ACPDB if faulty or PDU & propose new 3- only upon site owner
defected phase TNB meter request
• Propose new 1xPDU
come with 1x3-phase
50A AC MCB, Alarm
Terminal & Auto Reset
Button
SITE PHOTOS – Incoming AC Location
SITE PHOTOS – Incoming AC Location
SITE PHOTOS – Power Source
SITE PHOTOS – Power Source
SITE PHOTOS – Power Source
SITE PHOTOS – Power Source
SITE PHOTOS – Existing MGB Location
SITE PHOTOS – Proposed MGB
Location
SITE PHOTOS – Fiber Location
SITE PHOTOS – Proposed Equipment
Location
SITE PHOTOS – Proposed Equipment
Location
SITE PHOTOS – Proposed Cable Route Sector 1 2 3 / MW
SITE PHOTOS – Top View
SITE PHOTOS – Proposed Cable Route MW
SITE PHOTOS – LOS FE
Antenna & RRU Data
– Proposed Antenna and RRU location
Sector 1 2 3
Antenna & RRU Data
– Proposed Microwave Antenna location
RF PHOTOS – View at every 10˚ direction

Panoramic Photos
• Do not shoot at
nighttime or when no
clear visibility. E.g.,
raining
• Proportion of the sky is
not more than 1/3
• Compass used should
be a standard and
calibrated compass
RF PHOTOS – View Sector
SKETCHING
Sample Sketch

Points to take note


•Reference point with North indication
•Dimension and offset
•Tower width dimension & tower leg indication
(A,B,C)
•Cable ladder dimension + Cable length
•Existing antenna info
•Proposed antenna info
•Proposed equipment info
•Grounding link info
•Power tapping info
•Transmission info
Sample Sketch cont.
TSS
SDE
SDE: https://cx-site-survey.nro.ericsson.net/

Login: syahrul.izham@stes.com.my
Password: $yahrulSS27
Mazrilhisham Mansor
0163352083
mazrilhisham@gmail.com
mazrilhisham@yahoo.com
THANK YOU!