NNPC SPDC
Content
Project Overview
I. Project Summary
II. Scope of Work
III. Project Location
IV. Base Location
V. Project Master Plan
VI. Project Execution Plan
Contract NG01016919: EPU Phase 2 Development Project – Package 1
(Installation of Pipelines and Fibre Optic Cables)
I. Project Summary
• EPU Phase 2 Development Project – Package 1 (Installation
PJ NAME
of Pipelines and Intersite Composite Cables)
MORPOL
PH OFFICE
Contract NG01016919: EPU Phase 2 Development Project – Package 1
(Installation of Pipelines and Fibre Optic Cables)
1. Engineering Management
2. DCC
SPDC
(Port Harcourt)
PlanEvent
S/N Date
1 Contract Award (Effective Date) 31st Jan, 2023
2 Commence Detailed Design Work 29th Apr, 2023
3 FEED Verification Completion 10th Jul, 2023
4 Placement of PO for LLIs 6th May, 2023
5 Conduct Constructability Workshop 29th Sept, 2023
6 Detailed Design Completion 30th Jan, 2024
7 Delivery of Line pipe to the Coating Yard 15th Nov, 2023
8 Commencement of Site Construction Activities 16th Dec, 2023
9 Start Load Out of First Batch of Coated Line pipes from Coating Yard 20th Dec, 2023
10 Commence Welding & Laying 13th Jan, 2023
11 Achieve Mechanical Completion 26th Jun, 2025
12 RFC 15th Jul, 2025
Contract NG01016919: EPU Phase 2 Development Project – Package 1
(Installation of Pipelines and Fibre Optic Cables)
03. Project Execution Strategy & Mobilization Plan
Mobilization Timelines
2023 2024
S/N ACTIVITIES
1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7
Mobilisation of Engineering
1 (31 Mar-23)
Office
Mobilisation for Engineering
2 (11 Jan-23)
Survey
Mobilisation for Procurement
3 (06 Mar-23)
Activities
Mobilisation of Construction
4 (18 Oct-23)
Bases (Gbaran & Satelite Camp)
Mobilisation Precom/Comm
6 (22 Apr 24)
Works
Contract NG01016919: EPU Phase 2 Development Project – Package 1
(Installation of Pipelines and Fibre Optic Cables)
03. Project Execution Strategy & Mobilization Plan
Mobilization of Key
The Key Personnel's to bePersonnel's
mobilized to head important offices include
but not limited to these positions will
• Project Manager
• Construction Manager
• HSE Manager
• Quality Manager
• Nigerian Content Manager
• Project Controls Manager
• Finance Manager
• Engineering Co-ordinator
• Procurement Manager/Sub-contracts Manager
• Materials Co-ordinator
• Logistics Co-Ordinator
• Interface Co-ordinator
• Pre- Commissioning Manager
• HSE Co-Ordinator
• Journey Manager
Contract NG01016919: EPU Phase 2 Development Project – Package 1
(Installation of Pipelines and Fibre Optic Cables)
03. Project Execution Strategy & Mobilization Plan
Mobilization of Key Personnel's Cont’d
• Sustainable Development / Community Affairs Manager;
• Security Manager;
• Senior Planner;
• Information Management Lead;
• OR & A and CMMS Co-ordinator;
• Electrical Lead
• Environmental Lead
• NC Co-Ordinator
• DCC
NB:
1. The Contractor have mobilized the Key Personnels within the her organization.
2. The Outstanding Key personnel Positions will be sourced within Country
3. All Key Personnel must possess the mimimum requirement for such position
Contract NG01016919: EPU Phase 2 Development Project – Package 1
(Installation of Pipelines and Fibre Optic Cables)
03. Project Execution Strategy & Mobilization Plan
Mobilization Plan for Construction Personnel & Equipment
Contract NG01016919: EPU Phase 2 Development Project – Package 1
(Installation of Pipelines and Fibre Optic Cables)
CONSTRUCTION EQUIPMENTSCHEDULE
03. Project Execution Strategy & Mobilization Plan EQUIPMENTSCHEDULE
Mobilization
M1 of
M2 Construction
M3 Personnel
M4 M5 & Equipment
M6 M7Cont’dM8 M9 M10 M11 M12
Pe a k
S No DESCRIPTION Unit
Qty
May-24
Aug-24
Dec-23
Mar-24
Nov-24
Apr-24
Jun-24
Oct-24
Sep-24
Jan-24
Feb-24
Jul-24
1 MAINLINE WORKS 42 69 135 138 147 152 137 137 118 65 56 47
CREW 3 45 14 23 45 44 44 44 39 39 34 19 16 13
Exc a v a to rs No s 6 3 3 6 6 6 6 6 6 6 2 2 2
Sw a m p Exc a v a to rs No s 1 1 1 1 1 1 1 1 1 1 0 0 0
Do ze rs 1 1 1 1
Su rv e y In stru m e n t No s 1 1 1 1 1 1 1 1 1 1 1 1 1
Pip e La ye rs No s 2 0 0 2 2 2 2 2 2 2 1 1 0
Am b u la nc e s No s 1 1 1 1 1 1 1 1 1 1 1 1 1
We ld in g Ma c h in e (Sing le Ho ld e rs) No s 4 0 0 4 4 4 4 1 1 1 1 0 0
We ld in g Ma c h in e (Sing le Ho ld e rs) No s 3 0 0 3 3 3 3 2 2 2 1 1 1
G rin d ing Ma c h in e Big No s 4 0 0 4 4 4 4 4 4 4 1 1 1
G rin d ing Ma c h in e Sm a ll No s 4 0 4 4 4 4 4 4 4 4 1 1 1
Tra c to rs No s 2 1 2 2 2 2 2 2 2 1 1 1 1
Pip e C la m p No s 2 0 2 2 2 2 2 1 1 0 0 0 0
Bu se s (14 Se a te r) No s 4 2 2 4 4 4 4 4 4 3 3 2 1
Hilu x No s 4 2 2 4 4 4 4 4 4 4 2 2 2
Se c u rity Hilu x No s 6 2 4 6 6 6 6 6 6 4 4 3 2
Contract NG01016919: EPU Phase 2 Development Project – Package 1
(Installation of Pipelines and Fibre Optic Cables)
03. Project Execution Strategy & Mobilization Plan
Mobilization of Construction Personnel & Equipment Cont’d
B CABLE INSTALLATION 20 0 0 0 6 15 20 20 20 16 8 8 8
CREW 1 10 0 0 0 6 8 10 10 10 8 4 4 4
Exc a v a to rs No s 6 0 0 0 2 4 6 6 6 4 2 2 2
Ca b le Sp o o le r No s 1 0 0 0 1 1 1 1 1 1 0 0 0
Bus (18 Se a te r) No s 2 0 0 0 2 2 2 2 2 2 1 1 1
Hilux No s 1 0 0 0 1 1 1 1 1 1 1 1 1
CREW 1 10 0 0 0 0 7 10 10 10 8 4 4 4
Exc a v a to rs No s 6 0 0 0 0 4 6 6 6 4 2 2 2
Ca b le Sp o o le r (Sa m e a s a b o v e ) No s 1 0 0 0 0 1 1 1 1 1 0 0 0
Bus (18 Se a te r) No s 2 0 0 0 0 1 2 2 2 2 1 1 1
Hilux No s 1 0 0 0 0 1 1 1 1 1 1 1 1
2 RIVER/ ROAD CROSSING 2 0 2 2 2 2 2 2 0 0 0 0 0
HDD EQUIPMENT SPREAD No s 1 0 1 1 1 1 1 1 0 0 0 0 0
Thrust b o ring m a c hine No s 1 0 1 1 1 1 1 1 0 0 0 0 0
3 PRECOMMISSIONING 8 0 0 0 8 8 8 8 8 8 8 8
Co m p re sso rs No s 2 0 0 0 0 2 2 2 2 2 2 2 2
Wa te r Pum p s No s 4 0 0 0 0 4 4 4 4 4 4 4 4
Hyd ro te st Pum p s No s 2 0 0 0 0 2 2 2 2 2 2 2 2
No s -
Contract NG01016919: EPU Phase 2 Development Project – Package 1
(Installation of Pipelines and Fibre Optic Cables)
03. Project Execution Strategy & Mobilization Plan
Mobilization of Construction Personnel & Equipment Cont’d
4 GENERAL 38 20 36 38 38 38 38 37 35 32 32 32 30
Lowb e d Truc ks Nos 3 2 3 3 3 3 3 2 2 1 1 1 1
Se lf Loa d e rs Nos 1 1 1 1 1 1 1 1 1 1 1 1 1
Buse s (18 Se a te r Buse s) Nos 2 1 2 2 2 2 2 2 2 2 2 2 2
Ra d io gra p hy Se t Nos 1 0 1 1 1 1 1 1 1 0 0 0 0
Hilux Nos 6 2 4 6 6 6 6 6 4 4 4 4 4
Fla tb e d Truc ks Nos 4 2 4 4 4 4 4 4 4 4 4 4 2
Cra ne s Nos 2 2 2 2 2 2 2 2 2 2 2 2 2
Holid a y Ma c hin e Nos 1 0 1 1 1 1 1 1 1 0 0 0 0
Hilux (Se c urit y) Nos 18 10 18 18 18 18 18 18 18 18 18 18 18
Contract NG01016919: EPU Phase 2 Development Project – Package 1
(Installation of Pipelines and Fibre Optic Cables)
03. Project Execution Strategy & Mobilization Plan
Mobilization of Construction Personnel & Equipment Cont’d
DIRECTMANPOWER SCHEDULE
Pe a k M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12
S No DESCRIPTION Unit
Qty
Ma y - 24
Au g - 24
De c - 2 3
Ma r- 2 4
No v - 2 4
Ja n- 2 4
Fe b - 2 4
Se p - 2 4
Ap r- 2 4
Ju n - 2 4
O c t- 24
Ju l- 2 4
TOTAL DIRECTMANPOWER 133 247 292 308 342 362 362 297 282 230 203 188
A TOTAL PIPELINES 195 72 150 186 195 195 195 195 168 150 117 96 84
A1 PIPELINE SPREAD 1(EPU-NAG to TAYLOR CREEK) Ca te g o ry 130 48 100 124 130 130 130 130 112 100 78 64 56
CREW 1 (Ta y lo r Cre e k to Nun Rive r) 65 24 50 62 65 65 65 65 56 50 39 32 28
Pip e lin e Sup e rv iso r No s Skille d 1 1 1 1 1 1 1 1 1 1 1 1 1
Exc a v a to r O p e ra to rs No s Skille d 6 3 3 6 6 6 6 6 1 6 2 2 2
Sid e b o o m O p e ra to rs No s Skille d 2 0 0 2 2 2 2 2 0 2 1 1 0
We ld e rs No s Skille d 8 0 8 8 8 8 8 8 8 4 4 2 2
G rin d e rs No s Skille d 8 0 8 8 8 8 8 8 8 4 4 2 2
Pip e J o in t C o a te rs No s Skille d 4 0 0 0 4 4 4 4 4 4 2 2 1
Su rv e yo rs No s Skille d 1 1 1 1 1 1 1 1 1 1 1 1 1
C h a inm e n No s Se m i-Skille d 2 2 2 2 2 2 2 2 2 2 2 2 2
Bu s Driv e rs No s Se m i-Skille d 4 2 2 4 4 4 4 4 4 3 3 2 1
Rig g e rs No s Skille d 4 4 4 4 3 3 3 3 3 2 2 2 2
Pe rm it Ho ld e rs No s Skille d 1 1 1 1 1 1 1 1 1 1 1 1 1
Liftin g C h a m p io n No s Skille d 1 1 1 1 1 1 1 1 1 1 1 1 1
He lp e rs No s Un skille d 4 3 4 4 4 4 4 4 4 4 3 3 3
Contract NG01016919: EPU Phase 2 Development Project – Package 1
(Installation of Pipelines and Fibre Optic Cables)
03. Project Execution Strategy & Mobilization Plan
Mobilization of Construction Personnel & Equipment Cont’d
CREW 2 (Nun Rive r to EPU-3) 65 24 50 62 65 65 65 65 56 50 39 32 28
Pip e line Sup e rv iso r No s Skille d 1 1 1 1 1 1 1 1 1 1 1 1 1
Exc a v a to r O p e ra to rs No s Skille d 6 3 3 6 6 6 6 6 1 6 2 2 2
Sid e b o o m O p e ra to rs No s Skille d 2 0 0 2 2 2 2 2 0 2 1 1 0
We ld e rs No s Skille d 8 0 8 8 8 8 8 8 8 4 4 2 2
G rind e rs No s Skille d 8 0 8 8 8 8 8 8 8 4 4 2 2
Surv e yo rs No s Skille d 1 1 1 1 1 1 1 1 1 1 1 1 1
C ha inm e n No s Se m i-Skille d 2 2 2 2 2 2 2 2 2 2 2 2 2
Rig g e rs No s Skille d 4 4 4 4 3 3 3 3 3 2 2 2 2
DFA No s Skille d 1 1 1 1 1 1 1 1 1 1 1 1 1
Pe rm it Ho ld e rs No s Skille d 1 1 1 1 1 1 1 1 1 1 1 1 1
Lifting C ha m p io n No s Skille d 1 1 1 1 1 1 1 1 1 1 1 1 1
He lp e rs No s Unskille d 4 3 4 4 4 4 4 4 4 4 3 3 3
Contract NG01016919: EPU Phase 2 Development Project – Package 1
(Installation of Pipelines and Fibre Optic Cables)
03. Project Execution Strategy & Mobilization Plan
Mobilization of Construction Personnel & Equipment Cont’d
A2 PIPELINE SPREAD 1(K-NAG to CPF) Ca te g o ry 65 24 50 62 65 65 65 65 56 50 39 32 28
CREW 3 65 24 50 62 65 65 65 65 56 50 39 32 28
Pip e line Sup e rv iso r No s Skille d 1 1 1 1 1 1 1 1 1 1 1 1 1
Exc a v a to r O p e ra to rs No s Skille d 6 3 3 6 6 6 6 6 1 6 2 2 2
Sid e b o o m O p e ra to rs No s Skille d 2 0 0 2 2 2 2 2 0 2 1 1 0
We ld e rs No s Skille d 8 0 8 8 8 8 8 8 8 4 4 2 2
G rind e rs No s Skille d 8 0 8 8 8 8 8 8 8 4 4 2 2
Surv e yo rs No s Skille d 1 1 1 1 1 1 1 1 1 1 1 1 1
C ha inm e n No s Se m i-Skille d 2 2 2 2 2 2 2 2 2 2 2 2 2
Rig g e rs No s Skille d 4 4 4 4 3 3 3 3 3 2 2 2 2
DFA No s Skille d 1 1 1 1 1 1 1 1 1 1 1 1 1
Pe rm it Ho ld e rs No s Skille d 1 1 1 1 1 1 1 1 1 1 1 1 1
Lifting C ha m p io n No s Skille d 1 1 1 1 1 1 1 1 1 1 1 1 1
He lp e rs No s Unskille d 4 3 4 4 4 4 4 4 4 4 3 3 3
Contract NG01016919: EPU Phase 2 Development Project – Package 1
(Installation of Pipelines and Fibre Optic Cables)
03. Project Execution Strategy & Mobilization Plan
Mobilization of Construction Personnel & Equipment Cont’d
B CABLE INSTALLATION (PER SPREAD) Ca te g o ry 44 2 2 2 6 38 44 44 24 32 24 22 22
Pe rm it Ho ld e rs No s Skille d 1 0 0 0 1 1 1 1 1 1 1 1 1
C a b le Pulle rs No s Unskille d 5 0 0 0 0 5 5 5 2 2 1 2 2
Pe rm it Ho ld e rs No s Skille d 1 0 0 0 1 1 1 1 1 1 1 1 1
C a b le Pulle rs No s Unskille d 5 0 0 0 0 5 5 5 2 2 1 2 2
Sw a m p Exc a v a to r O p e ra to rs No s Skille d 3 1 2 2 3 3 3 3 3 3 3 2 1
Am b ula nc e Driv e rs No s Se m i-Skille d 8 4 6 6 6 8 8 8 5 2 2 2 2
C P C re w No s Skille d 4 0 0 4 4 4 4 4 4 4 2 2 2
C a b le Sp o o le r O p e ra to r No s Skille d 1 1 1 1 1 1 1 1 1 1 1 1 1
C o m m unity Wo rke rs 25 25 25 25 25 25 25 25 25 25 25 25 25
E PRECOMMISSIONING 14 0 0 0 0 0 14 14 14 14 14 14 14
C o m p re sso rs O p e ra to r No s Skille d 2 0 0 0 0 0 2 2 2 2 2 2 2
Hyd ro te st Pum p O p e ra to r No s Skille d 2 0 0 0 0 0 2 2 2 2 2 2 2
Hyd ro te st C re w No s Skille d 10 0 0 0 0 0 10 10 10 10 10 10 10
Contract NG01016919: EPU Phase 2 Development Project – Package 1
(Installation of Pipelines and Fibre Optic Cables)
03. Project Execution Strategy & Mobilization Plan
Mobilization of Construction Personnel & Equipment Cont’d
INDIRECTMANPOWER LOADING
S/
DESCRIPTION
No 2023 2024 2025
1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6
TOTAL 57 68 76 76 76 75 75 69 73 77 78 83 86 86 86 86 86 86 86 85 85 86 86 86 76 74 73 67 67 67
14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14
A PROJECT MANAGEMENT
1 Project Manager 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
2 Construction Manager 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
3 SP Manager 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
4 HSSE Manager 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
5 Project Control Manager 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
6 Finance Manager 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
7 Qaulity Manager 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
8 Procurement Manager 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
9 Admin Manager 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
10 Nigerian Content Manager 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
11 Plants and Equipment Manager 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
12 CMMS Coordinator 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
13 Security Manager 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
14 DCC 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Contract NG01016919: EPU Phase 2 Development Project – Package 1
(Installation of Pipelines and Fibre Optic Cables)
03. Project Execution Strategy & Mobilization Plan
Mobilization of Construction Personnel & Equipment Cont’d
43 54 62 62 62 61 61 55 59 63 64 69 72 72 72 72 72 72 72 71 71 72 72 72 62 60 59 53 53 53
B OTHERS
1 CLOs 0 2 2 2 2 0 0 0 0 0 0 0 2 2 2 2 2 2 2 2 2 2 2 2 0 0 0 0 0 0
2 GLOs 0 0 0 0 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
3 Material Coordinator 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
4 Store Keeper 0 0 1 1 1 1 1 1 1 1 2 2 3 3 3 3 3 3 3 3 3 3 3 3 2 2 1 1 1 1
5 QAQC Coordinator 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
6 HSE Coordiantors 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
7 NCD Coordinator 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
8 PTW Coordinator 1 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1
9 Equipment Maintenace Crew 4 8 8 8 8 8 8 4 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 4 4 4 4 4 4
10 Journey Manager/Logistics 2 2 2 2 2 2 2 2 2 2 2 2 3 3 3 3 3 3 3 3 3 3 3 3 2 2 2 1 1 1
11 CAD Men 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
12 DCC 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
13 Procurement Officers 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1 1
14 Security Guards 5 5 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 6 6 6
15 Admin Officers 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
16 Camp Maintenance Crew 6 6 6 6 6 6 6 2 2 2 2 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6
17 Kitchen Services 6 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 6 6 6 6 6 6
18 Accountants 2 2 2 2 2 2 2 2 2 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3 2 2 2 2 2 2
19 Office Attendants 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
20 Cleaners 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6
21 Flag Men 0 0 0 0 0 0 0 0 0 4 4 4 4 4 4 4 4 4 4 3 3 3 3 3 2 2 2 2 2 2
22 Helpers 0 2 2 2 2 2 2 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 2 2 2 2 2
23 Planning Engineer 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
24 Envirenmental Supervisor 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Contract NG01016919: EPU Phase 2 Development Project – Package 1
(Installation of Pipelines and Fibre Optic Cables)
03. Project Execution Strategy & Mobilization Plan
Mobilization of Out Sourced Resources
Morpol will ensure timely mobilization of the outsourced resources
that will be required execute some aspects of the Project. These
resources include those for the activities listed.
• Cable Jointing.