Professional Documents
Culture Documents
2101CV301 Module 2 02 Shallow Foundation
2101CV301 Module 2 02 Shallow Foundation
(2101CV031)
Module 2:
Foundations
Part 2: Shallow Foundations
Introduction
Types
Construction
Failures of foundation
Remedial measures
Footing is lowermost portion of it which is in direct contact with the soil and distributes the
load to soil.
Shallow
foundation
These are generally adopted for load bearing wall, as it provides continuous longitudinal
bearing.
Whenever wall carries light load, small width of footing required , in which is simple footing can
be provided.
Whereas, load on wall are heavy and SBC of soil is low, large base area is required to transfer
the load safely.
While in case of Stepped footing width of footing is calculated based on thumb rule T=(2t + 30)
mm where t is thickness of wall.
Typical spread (wall) footing for 20 cm, 30 cm, 40 cm walls: In next slide:
These are provided to transfer the load of individual column to soil safely.
The footing may be simple, sloped or stepped, depending on the requirement of load to be
transferred and bearing capacity of soil.
When heavy load are to transferred and spacing of column is less, isolated footing is replaced
by combined footing.
Used in Waterlogged areas, where the B.C. of soil is very low and where the steel beams may
get corroded due to subsoil water.
Bottom layer of timber planks of size 20 to 30 cm wide and 5 to 7.5 cm thick is laid, side by
side; without any gap between them.
Over this platform, a tier of wooden beams, 15 x 10 cm in size, spaced at right angles.
Timber Grillage
Foundation
1) When the allowable soil pressure is low or the building loads are heavy, the use of spread
footings would cover more than one-half of the area and it may prove more economical to
use mat or raft foundation.
2) Used where soil contains compressible lenses so that the differential settlement would be
difficult to control
3) It also needed to reduce settlement on highly compressible soils, by making the weight of the
structure and raft approximately equal to the weight of the soil excavated.
=
=
=
In case depth of soil does not exceed to 1.5 m, soil layer should replaced or removed.
The foundation concrete or masonry should not direct contact with the black cotton soil.
This can be done by making wider and deeper trenches for foundation and filling the sand
or moorum on either sides and nearly 30 cm below the foundation.
Which is well watered and rammed and then foundation concrete should be provided.
Construction done during dry season
External wall should be provided at G.L., so that moisture does not enter in foundation
during monsoon.
Pier foundation
Hand operated instruments includes spade, pick axe, crow bar, sledge hammer, boning rod, etc.
On the other hand, mechanized equipment like power shovel and trenchers can be used for
speedier excavation.
Hammer
Grow bar
Rammer
Kassi or phawrah
This implies to masonry in between the footing which is rises up to the ground level especially
in case of load bearing wall masonry.
This masonry as usual have mortar joints which is liable to shrink or compress which leads to
settlement.
1. Using thin mortar joints with proper strength and workmanship should be checked for same
on site.
2. Restricting the rate of progress to 1m per day if lime mortar is used and 1.5m if cement
mortar is used.
This specially occurs in case of cohesive soils, where the subsoil water level fluctuates.
Due rising/falling of sub soil water, swelling/shrinkage occurs in sub soil leading to differential
settlement of foundation resting on it.
It may be dangerous in expansive soil as if swelling pressure exceeds the shear strength of
soil, heaving of soil starts which results in failure of foundation.
If the wall transmitting load is subjected to lateral pressure or thrust from a pitched roof or
arch or due to wind action, then
If foundation is not designed for such situation, then it may fail in overturning or due to
generation of tensile stress on one side and high compressive stresses on the other side of the
footing.