Download as pptx, pdf, or txt
Download as pptx, pdf, or txt
You are on page 1of 216

WELCOME

TO
THE PRESENTATION
ON
RECAST EPR FOR BLOCK-B OCP
(3.5 to 8.0 Mty)

NORTHERN COALFIELDS LIMITED


SINGRAULI (MP)
Date:15.01.2019
Background
• Block-B OCP (3.5 Mtpa) on 7th July, 2006
• Recast Project Report (RPR) for Block-B OCP
(3.5 Mtpa) was approved on 28/06/2011 for
Rs 535.10 Crs with overburden outsourcing
option
• 3.5 Mtpa Project has been completed in the
year 2015 with completion cost of Rs 550.32
Crs
Background
• Expansion PR (EPR) of Block-B OCP (8 Mtpa)
was prepared by CMPDI in Dec 2015
• EPR was considered by ESC of CIL Board on
31/03/2017 with updated cost estimate (UCE)
• PR was resubmitted with compliance of
directives of ESC in its next meeting held on
31/08/2017, however, it was deferred due to
paucity of time
Need for Expansion
• Block-B OCP is extracting coal at 5.47 Mtpa
• At this rate, balance life is about 7 years
• As per revised 1 Bt Plan of CIL, Project is
planned to contribute coal production from
2020-21
Recast EPR of Block-B OCP
• Recast EPR has been prepared as:
– the base date of UCE was July 2016
– cost of tenancy land as per RFCTLARR Act 2013
has gone up causing change in required land use
area
• Recast EPR includes additional reserve from
part of Block-B Extension Block for 8.0 Mtpa
coal production over the life of 19 years.
Geological Map of Moher Sub-basin

Jhingurdah

Block-B
Extn.
Block-B

kri
Ka
Jayant

Nigahi Dudhichua

a
Bin
Amlohri

Khadia ra k
Mar
Gorb
i Mine

Pvt Industry
NH 75E
External
Village Dump Rail Line

Bijul
Block-
B Extn.
Proposed E xtn.
hi Dip
External Niga
Dump
c ks with SPL
Blo
Mineable Coal Reserve (Mt) OB (Mm3) & SR
(m3/t)

3.5 Mtpa mine 8.0 Mtpa


Particulars Extracted till Balance as Total as on
31/03/2018 on Additional 01/04/2018
01/04/2018
Purewa 19.57 54.65 74.22
44.78
Turra 23.32 40.53 63.85
Total Coal 44.78 42.89 95.18 138.07
Overburden 172.22 117.92 479.50 597.42
SR 3.85 2.75 5.04 4.33

Average Grade of Coal: G9 (4601-4900 Kcal/kg)


Options considered in PR
• Option-I: Coal & OB both departmental with shovel dumper
• Option-II: Coal departmental & total OB outsourcing
• Option-III: Coal departmental & total OB outsourcing
considering old Gorbi mine for part OB dumping:
– III(a): transportation of part OB by dumper to old Gorbi mine
– III(b): (crushing & conveying of partial OB to old Gorbi mine);
Coal Handling Plant
• Existing:
– Phase-I:- Interim CHP (2.5 Mty)
– Phase-II:- 3.5 Mty: (-)100 mm size output, 3000 T
Silo with RLS, 20000 T GB
• Proposed:
Semi-mobile crushing plant with secondary crushing
for (-)100 mm size output
Land Requirement
Possessed Balance
Total as on to be
Type of Land Requirement 31.03.2018 acquired

Forest Land 1070.25 447.00 623.25


Non-Forest Land 1186.92 1065.81 121.11
Govt. Land 51.78 - 51.78
Tenancy Land 1135.14 1065.81 69.33
Total 2257.17 1512.81 744.36
HEMM for Option-II
A: Overburden - outsourced
  Option-II
PR Provn. Existing As per
Sl. as on Comple- Balance Total
HEMM Size/ Cap. (3.5
No. Mtpa) 31.03.18 tion Provision Provision
Report (4.5 Mtpa) (8 Mtpa)
B COAL
1 Hyd. Shovel 10-12m3 1 - 1* 1 2
Diesel Hyd.
2 Backhoe 10-12m3 1 1 1 - 1
3 Rear Dumper 85 T - 1 - - -
4 Rear Dumper 100 T 10 14 15 5 20
5 RBH Elect. Drill 160mm 3 4 5 1 6
6 Dozer 410 HP 2 2 2 1 3

* 1 No. 10-12m3 Hyd. Shovel transferred to other project in Completion Report.


  Option-II
PR As per
Existing
Sl. HEMM Size/ Cap. Provn. as on Compl- Balance Total
No. (3.5 etion Provision Provision
31.03.18
Mtpa) Report (4.5 Mtpa) (8 Mtpa)
C COMMON
1 FE Loader 5.74m3 1 1 1 - 1
2 FE Loader 10-12m3 - - - 1 1
3 Motor Grader 280 HP 2 2 2 2 4
4 Hyd. Backhoe 2.8/3.5m3 2 1 2## - 2
5 Mobile Crane 30/50T 2 2 2 - 2
6 Mobile Crane 8-10T 2 2 2 3 5
Wheel
7 410 HP 1 1 1 - 1
Dozer/Dozer
D RECLAMATION
1 Dozer 410 HP 2 4 4 1 5
2 Motor Grader 280 HP 1 2 - 1 3
3 Water Sprinkler 28 KL 3 3 4** - 2
4 Water Sprinkler 70 KL - - - 1 2(1+1**)
Road Sweeping
5 - - 1     1
Machine
6 Mist Spray Gun   - - - 2 2

** 2 No. 28 KL Water Sprinkler to be upgraded to 1 No. 70 KL Water Sprinkler.


## 1 No. 2.8 m3 Hyd. Shovel transferred to other project in Completion Report.
Mine Closure Plan
• Mine Closure Plan has been prepared as per
Guidelines issued by MoC
• Mine closure cost has been estimated for WPI
of Sept 2018
• Annual amount to be deposited has been
escalated by 5% as per guidelines
• Thus, balance amount of Rs 26068.46 Lakhs
has been estimated for depositing to ESCROW
account for Mine closure
Manpower
Particulars Option-I Option-II & III
Incremental Integrated Incremental Integrated
Manpower 1487 2097 658 1268
OMS 12.52 16.02 31.57 28.29
EMS 3233.32 3297.11 3248.17 3346.53
Capital Investment

Sl. Particulars Option-I Option-II Option-III Option-III


No. (a) (b)

1 Total Capital 4091.48 1549.03 1627.51 1549.22


2 Existing Capital 510.96 510.96 510.96 510.96

Committed Capital for


3 Existing 39.36 39.36 39.36 39.36

4 Additional Capital for 3541.16 998.71 1077.19 998.90


Sanction
Financial Evaluation
Option-I Option-II
Without
Expansion
Particulars Unit Existing Incre- With Incre- With
(3.5 mental Expansion mental Expansion
Mtpa) (4.5 Integrated (4.5 Integrated
Mtpa) (8 Mtpa) Mtpa) (8 Mtpa)
Total Capital Outlay Rs Crs 550.32 3541.16 4091.48 998.71 1549.03
Specific Investment Rs/t 1572.34 7869.24 5114.35 2219.36 1936.29
Cost of Production
At 100% Prodn. Rs/t 1045.25 2077.31 1449.05 1097.45 1073.56
At 85% Prodn. Rs/t 1137.62 2348.68 1639.70 1169.11 1154.50
Wt. Av. Selling Price Rs/t 1386.83 1386.83 1386.83 1386.83 1386.83
Profit
At 100% Prodn. Rs/t 341.58 -690.48 -62.23 289.38 313.26
At 85% Prodn. Rs/t 249.20 -961.86 -252.87 217.72 232.33
Financial IRR
At 100% Prodn. % 40.34% -ve -1.00% 29.15% 81.02%
At 85% Prodn. % 28.80% -ve -ve 16.72% 39.21%
Desired selling price to yield 12% FIRR
At 100% Prodn. Rs/t 1096.54 2532.72 1640.12 1241.44 1170.71
At 85% Prodn. Rs/t 1189.10 2882.16 1862.96 1326.60 1259.39
Financial Evaluation
Option-III (a) Option-III (b)
Without
Expansion Incre- With Incre- With
Particulars Unit mental Expn. mental Expn
Existing (3.5
(4.5 Integratd (4.5 Integrat
Mtpa) Mtpa) (8 Mtpa) Mtpa) (8 Mtpa)
Total Capital Outlay Rs Crs 550.32 1077.19 1627.51 998.90 1549.22
Specific Investment Rs/t 1572.34 2393.76 2034.39 2219.78 1936.53
Cost of Production
At 100% Prodn. Level Rs/t 1045.25 1166.35 1111.40 1260.56 1162.30
At 85% Prodn. Level Rs/t 1137.62 1240.44 1193.67 1336.81 1245.65
Weighted Avg. Selling Rs/t 1386.83 1386.83 1386.83 1386.83 1386.83
Price
Profit
At 100% Prodn. Level Rs/t 341.58 220.48 275.43 126.27 224.53
At 85% Prodn. Level Rs/t 249.20 146.38 193.15 50.02 141.18
Financial IRR
At 100% Prodn. Level % 40.34% 18.40% 72.07% 11.15% 65.28%
At 85% Prodn. Level % 28.80% 10.79% 30.95% 5.20% 25.00%
Desired selling price to yield 12% FIRR
At 100% Prodn. Level Rs/t 1096.54 1315.56 1208.87 1396.89 1250.01
At 85% Prodn. Level Rs/t 1189.10 1404.59 1299.54 1486.52 1340.89
Conclusion
• financial IRR for the incremental project at 85%
production level is highest and more than 12% for
Option-II i.e. Total Coal Departmental & Total OB
Outsourcing
• Option-II involves additional capital investment of
Rs 998.71 Crores.
• Recommendation of ESC is required for placing the
proposal for consideration of NCL Board
PRESENTATION OVERVIEW
1. PROJECT BACKGROUND - 3 4 5 6 7
MARKETABILITY 8
2. LOCATION 9 10
3. SALIENT FEATURES 11
4. GEOLOGY 14
5. MINING 12 13 15 16 17 18 19 20 21 22 23 24
6. MAIN INFRASTRUCTURE 25
7. LAND REQUIREMENT, ENVIRONMENTAL MANAGEMENT and R & R 26 27 28
8. MINE ECONOMICS
- CAPITAL INVESTMENT 29
- COST OF PRODUCTION 32 33
- COMPARISON OF INDICATIVE PARAMETERS 30 31
- SENSITIVITY ANALYSIS 34 35 36 37
PROJECT BACKGROUND
 PR Name : Recast EPR for Block-B OCP
 Target Capacity (Mtpa) : 8.00 Mtpa (Peak 10.00 Mtpa)
 Block :(Block-B & Block-B Extn.)
 Coalfield : Singrauli Coalfield
 District, State :Singrauli, (MP)
 Nearest Town, Rly Station : Singrauli, Mahdeiya (7-8 Km.)
 Access to Project : By Road; By Rail
(Ranchi-Rewa NH-75E; Katni-Chopan
Branch line of ECR; )

 Date of Approval of EPR (Dec’15) by NCL Board for Option II: 18.12.2015

 Date of recommendation of UCE (Aug’ 16) by NCL Board for Option II : 09.01.2017

 ESC considered the proposal on 31.03.2017 and directed to include economic evaluation
based on avg. actual sale price also.

 UCE prepared in May- 17 incorporating the economic evaluation based on avg.


actual sale price also.

 The above UCE was recommended by NCL Board on 26.05.2017 for Option II.
 The UCE of Block-B OCP was considered in Empowered Sub-committee of CIL Board on 31.08.2017.
The Empowered Sub-committee deferred the Report for next ESC meeting.
 As the earlier UCE was prepared with base date of July, 2016 and for inclusion of land rate as per
RFCLARR-2013, NCL desired to recast the EPR vide letter No. NCL/CP/Project Monitoring/671, dated
24.11.2017 and NCL/CP/Minutes/709, dated 08.12.2017.
 In this connection, a meeting was held on 18.04.2018 at CMPDI (HQ), Ranchi with officials from
GM(OC) & other officials of CMPDI (HQ), officials from CMPDI, RI-VI and officials of NCL for
preparation of Recast EPR of Block-B OCP (8 Mtpa).
 
 Accordingly, the Recast EPR for Block-B OCP (8 Mtpa) has been prepared in the following
options:
 
Option-I - Coal & OB both departmental with shovel dumper

Option-II - Coal departmental & total OB outsourcing with Shovel-Dumper  

Option-III - Considering old Gorbi mine for part OB dumping:


 
III(a) - Coal departmental & total OB outsourcing with shovel- dumper
(transportation of part OB by shovel dumper to old Gorbi mine);
 
III(b) - Coal departmental & total OB outsourcing with shovel- dumper
(with implementation of crushing & conveying by conveyor of part OB to
old Gorbi mine);
PROJECT BACKGROUND

 This is an expansion project from 3.50 Mtpa to 8.00 Mtpa


Last Sanctioned Capacity : 3.50 Mtpa
Last Sanctioned Capital : ` 535.10 Crores
Last Sanction Date : 28.06.2011

 Brief status of last sanctioned PR:


PR for 3.5 Mtpa is completed on 18.12.2015 for ` 550.32 Crs.

 EC status- Existing EC of 5.47 Mtpa with effect from 06.08.2014


 FC status- Total Forest land for 8.0 Mtpa is 1070.25 Ha out of which 447 Ha
forest land has been acquired & Balance 623.25 Ha land has to be acquired.
PROJECT BACKGROUND
Actuals Production, Profit/Losses & Selling price in last three years

Sl. Coal OBR S.R CPT Selling Profit/ Losses


No. Year (Mt) (Mm3) (m3/t) (`/t) Price (`/t) (`/t)

1. 2015-16 4.10 26.97 6.58 569.28 1534.21 (+)964.93

2. 2016-17 5.23 33.33 6.37 682.37 1455.79 (+)773.42

3. 2017-18 5.47 25.87 4.37 818.06 1579.27 (+)761.21

Actual selling
PROJECT BACKGROUND

ORIGINAL RESERVES (as per sanctioned PR 3.5 Mtpa)


Coal (Mt) 87.67
OB (Mm3) 290.14
S.Ratio (m3/t) 3.31
Coal extracted till date (As on 31.03.2018) Mt 44.78

Balance Coal Reserves (As on 01.04.2018) Mt 42.89

As on 01.04.2018
RECAST EXPANSION PROJECT REPORT (8.0 Mtpa)

Coal (Mt) 138.07


OB (Mm3) 597.42
Stripping Ratio (m3/t) 4.33
MARKETABILITY

Demand on NCL

Sl. No. Details 2017-18 2018-19 2019-20


(Actual)

1 Production 90.03 100.00 105.67


2 Total Demand 109.25 115.30 116.50

3 Surplus/Deficit -16.22 -15.30 -10.83

Supply of coal from Block-B Expansion OCP:


Sl. No. Power Plant Capacity (MW) ACQ (Mty)

1 Kota TPS 1240 3.65

2 Suratgarh TPS 1500 0.50

3 Obra TPS 1278 4.66

4 Basket Linkage As & when required


LOCATION

BLOCK-B
LOCATION

Block-B
OCP

Location Plan pdf


SALIENT FEATURES

 GEOLOGICAL RESERVES (Mt) : 144.61 (as on 01.04.2018)


 BOREHOLE DENSITY (no. of BHs/sq.km) : 11
 MINEABLE RESERVES (Mt) : 138.07 (as on 01.04.2018)
 TOTAL VOLUME OF OB (Mm3) : 597.42
 AVERAGE STRIPPING RATIO (m3/t) : 4.33
 TOTAL NO. OF SEAMS : 02 (Purewa Merged, Turra)
 NO. OF SEAMS CONSIDERED : 02 (Purewa Merged, Turra)
 TOTAL COAL THICKNESS (m) : 41.85
 EFFECTIVE THICKNESS (m) : Purewa Merged- 22.75
: Turra- 19.10
 DIP ::40-220 (Easterly)
 STRIKE :North- South
 COAL QUALITY : Avg. Grade - G-9
MINING

Recast EPR for Block-B OCP (8.0 Mtpa) has been prepared in the following
Options:
• Option-I : Coal & OBR Both, Departmental
• Option-II : Total Coal production with Departmental
& Total OBR with outsourced
• Option-III : Considering old Gorbi mine for part OB dumping

• Option III(a) : Coal departmental & total OB outsourcing with shovel dumper
(transportation of part OB by shovel dumper to old Gorbi mine)

• Option III(b) :Coal departmental & total OB outsourcing with shovel- dumper
(with implementation of crushing & conveying by conveyor of part OB to old Gorbi mine)

• TECHNOLOGY:
Option I, II & III(a&b)- Coal & OB Both with Shovel-Dumper combination
MINING

PDF
MINING
 YEAR OF ACHIEVING TARGET : 4th Year

PRODUCTION BUILD-UP TILL TARGET

Year Coal (Mt) OBR(Mm3)

Year-1(18-19) 5.47 22.56


Year-2 5.47 32.80
Year-3 5.47 32.80
Year-4 8.00 40.00

 QUARRY SURFACE AREA (Ha) : 709 Ha, (on surface); 409.79 Ha (on
floor)
 LIFE OF MINE : 19 years
 DEPTH RANGE : Existing Depth: 175m
Calendar Program :
Option I Maximum Year-wise GCV-wise Coal Production
Option II
Depth : 285m
Option III (a) & (b)
Lithology of Representative Borehole

PDF
MINING

 Based on the floor gradient pattern, the entire mine has been divided into two sub-
blocks i.e. Gorbi-B & C and Vindhya-I & II.

 In Vindhya-I & II floor gradient varying from 4o to 12o.


 In Gorbi B & C floor gradient varies from 12o to 22o.
 Opencast mining by shovel dumper combination is in use in existing Mine (3.5 Mtpa)

 The same Opencast mining by shovel dumper combination has been proposed in expansion
project also.
CROSS-SECTION

CROSS SECTION PDF


MINING

MANPOWER & OMS

Option-I Option- II,III(a) & III(b)

Particulars
Incremental Integrated Incremental Integrated
(4.5 Mtpa) (8.0 Mtpa) (4.5 Mtpa) (8.0 Mtpa)

Manpower 1487 2097 658 1268

OMS 12.52 16.02 31.57 28.29

Appendix B1
Option I
Option II, III(a) & III(b)
MINING
LIST OF HEMM REQUIREMENT : Option-I
OBR

HEMM
Sanctioned as per Option-I
Sl. HEMM Size/ Provision Existing as on Integrated
No. Cap. 01.04.2018 Completion
(3.5 Mtpa) (8.00 Mtpa)
Report

Elect. Rope
1 20 m3 8
Shovel

2 D. Hyd. Backhoe 10-12 m3 Outsourcing 2

Outsourcing

Outsourcing
3 Rear Dumper 190-210 T 64

4 Rear Dumper 100T 20

5 RBH Drill 250 mm 10

6 Dozer 850 HP 8
7 Dozer 410 HP 2
MINING
LIST OF HEMM REQUIREMENT : Option-I
Coal
HEMM
Sanctioned Existing as as per Option-I
Sl. HEMM Size/ Provision on Integrated
No. Cap. Completion
(3.5 Mtpa) 01.04.2018 (8.00 Mtpa)
Report

1 D. Hyd. Shovel 10-12 m3 1 - 1* 2

2 D. Hyd. Backhoe 10-12 m3 1 1 1 1

3 Rear Dumper 85T - 1 - -

4 Rear Dumper 100T 10 14 15 20

5 RBH Diesel Drill 160 mm 3 4 5 6

6 Dozer 410 HP 2 2 2 3

* 1 No. 10-12m3 Hyd. Shovel transferred to other project in Completion Report


MINING
LIST OF HEMM REQUIREMENT : Option-II, III(a) & III(b)
OBR

HEMM Option-II, Option-II,


Sanctioned Existing as as per III(a) & III(b)
Sl. HEMM Size/ Provision on
III(a)&III(b)
Inte-
No. Cap. Completion Incremental
grated
(3.5 Mtpa) 01.04.2018 (4.50 Mtpa)
Report (8.00 Mtpa)

Elect. Rope
1 20 m3
Shovel
Diesel Hyd.
2 10-12 m3
Outsourcing

Outsourcing

Outsourcing

Outsourcing

Outsourcing
Backhoe
3 Dumper 190 -210T
4 Dumper 100 T
5 RBH Drill 250 mm
6 Dozer 850 HP
7 Dozer 410 HP
MINING
LIST OF HEMM REQUIREMENT : Option-II, III(a) & III(b)

Coal
HEMM Option-II,
Option-II,
Sl. Size/ Sanctioned Existing as as per III(a) & III(b) III(a) & III(b)
HEMM Provision on Completion Increm-
No. Cap. (3.5 Mtpa) 01.04.2018 tal Integrated
Report (8.00 Mtpa)
(4.50 Mtpa)

1 Hyd. Shovel 10-12 m3 1 - 1* 1 2

2 D. Hyd. Backhoe 10-12 m3 1 1 1 - 1

3 Rear Dumper 85T - 1 - - -

4 Rear Dumper 100T 10 14 15 5 20

5 RBH Diesel Drill 160 mm 3 4 5 1 6

6 Dozer 410 HP 2 2 2 1 3

* 1 No. 10-12m3 Hyd. Shovel transferred to other project in Completion Report


MINING
LIST OF HEMM REQUIREMENT : Option-I, II, III(a) & III (b)
Option-II,III(a)
Option-I & III (b)
HEMM
PR Existing as per
Sl. Provn.
No.
HEMM Size/ Cap.
(3.5 As On Comp-
01.04.18 letion Incremental Integrated Incremental Integrated
Mtpa)
Report (4.5 Mtpa) (8 Mtpa) (4.5 Mtpa) (8 Mtpa)

COMMON
1 FE Loader 5.74m3 1 1 1 - 1 - 1
2 FE Loader 10-12 m3 - - - 1 1 1 1
3 Motor Grader 280 HP 2 2 2 2 4 2 4
4 Hyd.Backhoe 2.8/3.5m3 2 1 2## - 2 - 2
5 Mobile Crane 30/50t 2 2 2 - 2 - 2
6 Mobile Crane 8-10t 2 2 2 3 5 3 5
7 Wheel Dozer/Dozer 410 HP 1 1 1 - 1 - 1
RECLAMATION
1 Dozer 410 HP 2 4 4 1 5 1 5
2 Motor Grader 280 HP 1 2 - 1 3 1 3
3 Water Sprinkler 28 KL 3 3 4** - 2 - 2
4 Water Sprinkler 70 KL - - - 1 2(1+1**) 1 2(1+1**)
5 Road Sweeping Machine - - 1 - - 1 - 1
6## 1Mist Spray3 Gun
No. 2.8m Hyd. Shovel transferred- to other project -
- in Completion Report - 2 2 2 2
** 2 No. 28 KL Water Sprinkler to be upgraded to 1 No. 70 KL Water Sprinkler.
MINING

OB Dumping For Option I & II

Quantity Height from


SI.
No.
Particulars
(Mm3) Percentage Area (Ha) ground level
(m)

1 Internal Dump 114.69 19.20% - 90

Balance cap. in
90.24 409.68
Existing Dump

External Proposed 392.49 600.17 90


2
Dump

Total 482.73 80.80% 1009.85


MINING

OB Dumping For Option III (a) & (b)

SI. Height from


No.
Particulars Quantity (Mm3) Area (Ha)
ground level (m)

1 Internal Dump 114.69 - 90

Balance cap. in
Existing Dump 90.24 409.68

Proposed in
248.73 600.17
External Dump
External 90
2 Dump Proposed OB in 143.76 -
Old Gorbi Mine

Total 482.73
MINE INFRASTRUCTURE
Coal Handling Plant
 Main CHP Existing (3.5 Mtpa)
 One mumber receiving pit with 170t hopper
 One number 1600 TPH Gyratory crusher to crush ROM coal from (-)1500 mm to(-)100 mm.
 One number Self-flowing storage bunker of 20000t capacity.
 Four number 1800TPH Plough feeders for reclamation of coal from the bunker.
 Two number 1800 TPH Silo loading conveyors.
 1 No. 3000 Te capacity Silo.
 Railway Siding is under construction.
 Proposed CHP (Incremental 4.5 Mtpa)
 One number of semi- mobile crushing plant of 1600 TPH capacity comprising of receiving hopper-
apron feeder and twin shaft sizer to crush ROM coal from (-) 1500 mm to (-) 100 mm size. Receiving pit
with 170t hopper with secondary sizer.
 This CHP is linked with main CHP for storage and dispatch.
LAND REQUIREMENT AND R & R
Total Land Details
Type of Land Area (Ha) Percentage(%)
NON-FOREST LAND 1186.92 52.58
FOREST LAND 1070.25 47.42
TOTAL 2257.17 100.00

Break-up of Balance Land Acquisition: 744.36 Ha


Balance Land
Total Existing as on Existing other Balance Land Required
Type of Land Provision 31.03.2018 (3.5 Required
land possessed (4.5 Mtpa)
(8 Mtpa) Mtpa) (4.5 Mtpa)
(Breakup in %)

Forest Land 1070.25 447 623.25 83.73

Non-Forest
Land 1186.92 892 173.81 121.11 16.27

Total 2257.17 1339 173.81 744.36 100.00

Capital Provision for Balance Tenancy Land (69.33 Ha) : 197.67Crs.

NPV for Balance Forest Land (623.25 Ha) :57.34 Crs


Compensatory Afforestation for Balance Forest Land: 124.65 Crs.
LAND REQUIREMENT AND R & R

Capital Provision for Tenancy Land as per RFCTLARR, Act


Rs. 197.67 Crs.
2013
Capital Provision for Forest Land NPV @ Rs. 9.20 Lakhs/Ha Rs. 57.34 Crs.
Compensatory Afforestation @ Rs. 10 Lakhs/Ha Rs. 124.65 Crs.

 Capital Provision for R&R: Rs. 159.92 Crores.

 No. of PAPs: 207

1) Appendix A1 (Land details)


2) Appendix A8.1 (R&R)
3) Land details and cost as given by Project
ENVIRONMENTAL MANAGEMENT

EMP Capital Total: Option I Option II Option III(a&b)


` 181.39 Crs ` 178.62 Crs ` 178.62 Crs

 EMP Status : The project has EC for capacity of 5.47 Mtpa vide letter
No. J-11015/80/2013-IA.II (M) dated 06.08.2014.

Mine Closure Cost (`/t): ` 18.88 APPENDIX- F:


Option I
Option II
Option III (a) & (b)
COMPARISON OF HEAD WISE CAPITAL INVESTMENT

(Amt. in ` Lakh)
Option -I Option -II Option III (a) Option III (b)
SL
PARTICULARS Integrated Incremental Integrated Incremental Integrated Incremental Integrated Incremental
NO
(8 Mtpa) (4.5 Mtpa) (8 Mtpa) (4.5 Mtpa) (8 Mtpa) (4.5 Mtpa) (8 Mtpa) (4.5 Mtpa)
1 Land 25522 19767 25522 19767 25522 19767 25522 19767
2 Buildings
  a) Service 10069 9773 5846 5550 5846 5550 5846 5550
  b) Residential 11534 9779 5158 3402 5158 3402 5158 3402
  Sub Total 21603 19551 11004 8953 11004 8953 11004 8953
3 Plant & Machinery
  a) H. E. M. M. 252808 244748 13826 5766 13826 5766 13826 5766
  b) CHP 33584 10182 33584 10182 33584 10182 33584 10182
  c) Pumping 781 621 781 621 781 621 781 621
  d) Electrical 4909 4407 2996 2493 2996 2493 3015 2512
  e) Workshop 3535 3291 1966 1722 1966 1722 1966 1722
  f) Other P&M 127 62 127 62 127 62 127 62
  Sub Total 295745 263311 53280 20846 53280 20846 53299 20865
4 Furniture & Fittings 293 74 277 58 277 58 277 58
5 Railway Siding 8516 0 8516 0 8516 0 8516 0
6 Vehicles 939 711 939 711 939 711 939 711
7 Prospecting & Boring 44 0 44 0 44 0 44 0
8 Development
Capital Outlay in 37839
8.1 40695 37839 40695 37839 40695 40695 37839
Mines
8.2 Roads & Culverts 4523 3956 3712 3146 11560 10994 3712 3146
Water Supply & 5586
8.3 6972 5942 6617 5586 6617 6617 5586
Sewerage
8.4 Scientific Research 80 80 80 80 80 80 80 80
8.5 P.R. Prep. Cost 1762 1762 1762 1762 1762 1762 1762 1762
  Sub Total 54032 49579 52867 48414 60714 56261 52867 48414
Revenue Exp.
9.1 Capitalised 0 0 0 0 0 0 0 0
less Depreciation
10 Land Reclamation 2456 1123 2456 1123 2456 1123 2456 1123
  TOTAL CAPITAL 409148 354116 154903 99871 162751 107719 154922 99890
MINE ECONOMICS

Salient Features of all the Options


Option-I Option-II Option-III (a) Option-III (b)
Latest
Particulars Unit Sanctioned
(3.5Mtpa) Incre-mental Integrated Incre-mental Integrated Incre-mental Integrated Incre-mental Integrated
(4.5 Mtpa) (8 Mtpa) (4.5 Mtpa) (8 Mtpa) (4.5 Mtpa) (8 Mtpa) (4.5 Mtpa) (8 Mtpa)

Capital Investment

Total
Capital ` Crores 535.1 3541.16 4091.48 998.71 1549.03 1077.19 1627.51 998.90 1549.22
Outlay

Specific
`/t 1528.86 7869.24 5114.35 2219.36 1936.29 2393.76 2034.39 2219.78 1936.53
Investment

Cost of Production

At 100%
`/t 689.8 2077.31 1449.05 1097.45 1073.56 1166.35 1111.4 1260.56 1162.3
Prodn. Level

At 85%
`/t 748.35 2348.68 1639.7 1169.11 1154.5 1240.44 1193.67 1336.81 1245.65
Prodn. Level

Weighted
Avg. Selling `/t 1099.84 1386.83 1386.83 1386.83 1386.83 1386.83 1386.83 1386.83 1386.83
Price
MINE ECONOMICS
Salient Features of all the Options
Option-I Option-II Option-III (a) Option-III (b)
Latest
Particulars Unit Sanctioned Incre-mental Integrated Incre-mental Integrated Incre-mental Integrated Incre-mental Integrated
(3.5Mtpa) (4.5 Mtpa) (8 Mtpa) (4.5 Mtpa) (8 Mtpa) (4.5 Mtpa) (8 Mtpa) (4.5 Mtpa) (8 Mtpa)

Profit
At 100%
`/t 410.04 -690.48 -62.23 289.38 313.26 220.48 275.43 126.27 224.53
Prodn.Level
At 85%
`/t 351.5 -961.86 -252.87 217.72 232.33 146.38 193.15 50.02 141.18
Prodn. Level

Financial IRR
At 100%
% 104.05% -ve -1.00% 29.15% 81.02% 18.40% 72.07% 11.15% 65.28%
Prodn. Level
At 85%
% 68.45% -ve -ve 16.72% 39.21% 10.79% 30.95% 5.20% 25.00%
Prodn. Level

Desired selling price to yield 12% FIRR

At 100%
`/t 672.27 2532.72 1640.12 1241.44 1170.71 1315.56 1208.87 1396.89 1250.01
Prodn. Level

At 85%
`/t 731.92 2882.16 1862.96 1326.6 1259.39 1404.59 1299.54 1486.52 1340.89
Prodn. Level

NPV at 12%
At 100%
` Lakhs 93258.62 -307155.78 -111665.16 38969.55 132692.77 19102.54 112825.76 -2696.6 91413.8
Prodn.Level
At 85%
` Lakhs 53170.34 -340701.03 -193517.78 13721.12 73551.67 -4047.36 55783.19 -22714.14 37489.07
Prodn. Level

OB Rs. 110.88 Rs. 110.88


Outsourcing (Av. Lead 5.25 Kms.) (Avg. Lead 5.25.kms)
      110.88
rate (Rs. Rs. 138.60 Rs. 175.48
B.m3) (Lead 7.0 Kms.) (Crushing & Conveying)

Financial Analysis based On Actual Avg.Sale Price of Last Three years


COMPARISON OF COST OF PRODUCTION (`\t)
(`/t)
Option-I Option-II

(Integrated) (Incremental) (Integrated) (Incremental)


Sl. No. Particulars
At 100% At 85% At 100% At 85% At 100% At 85% At 100% At 85%
Capacity Capacity Capacity Capacity Capacity Capacity Capacity Capacity
1 Salary & Wages 238.47 280.55 296.32 348.62 146.49 172.34 129.09 151.87

2 Stores 625.73 687.79 964.48 1061.69 156.14 168.48 109.35 116.01

3 Power 82.27 93.16 118.45 134.12 34.83 39.43 32.15 36.41

4 Misc. Expenses 86.42 94.79 121.22 132.10 36.07 40.34 29.54 32.96

5 Adminstrative Cost (Cash) 3.62 4.26 3.62 4.26 3.62 4.26 3.62 4.26

6 Mine Closure Cost 18.88 22.21 13.88 16.33 18.88 22.21 13.88 16.33

7 OB Outsourcing 18.12 18.12 11.88 11.88 479.78 479.78 569.78 569.78

8 COAL Outsourcing 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

9 Interest on Working capital 51.89 58.04 73.94 82.60 42.33 44.80 42.89 44.84

10 Total Cash Cost 1125.39 1258.92 1603.78 1791.59 918.14 971.65 930.30 972.46

11 Interest 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

12 Adminstrative Cost (Notional) 30.91 36.36 30.91 36.36 30.91 36.36 30.91 36.36

13 Depreciation 292.76 344.42 442.62 520.73 124.51 146.49 136.24 160.28


  Total 1449.05 1639.70 2077.31 2348.68 1073.56 1154.50 1097.45 1169.11
COMPARISON OF COST OF PRODUCTION (`\t)
(`/t)
Option-III(a) Option-III(b)
Sl. (Integrated) (Incremental) (Integrated) (Incremental)
Particulars
No. At 100% At 85% At 100% At 85% At 100% At 85% At 100% At 85%
Capacity Capacity Capacity Capacity Capacity Capacity Capacity Capacity
1 Salary & Wages 146.49 172.34 129.09 151.87 146.49 172.34 129.09 151.87
2 Stores 156.14 168.48 109.35 116.01 156.15 168.48 109.35 116.02
3 Power 34.83 39.43 32.15 36.41 52.19 59.10 65.23 73.86
4 Misc. Expenses 37.89 42.48 32.84 36.85 36.07 40.35 29.54 32.97
5 Adminstrative Cost (Cash) 3.62 4.26 3.62 4.26 3.62 4.26 3.62 4.26
6 Mine Closure Cost 18.88 22.21 13.88 16.33 18.88 22.21 13.88 16.33
7 OB Outsourcing 508.64 508.64 622.33 622.33 364.33 364.33 359.54 359.54
8 OB Crushing & Conveying Cost         182.71 182.71 332.73 332.73
9 COAL Outsourcing 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10 Interest on Working capital 43.81 46.30 45.59 47.56 46.42 49.00 50.41 52.57
11 Total Cash Cost 950.29 1004.14 988.85 1031.62 1006.87 1062.79 1093.39 1140.14
12 Interest 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

13 Adminstrative Cost 30.91 36.36 30.91 36.36 30.91 36.36 30.91 36.36
(Notional)
14 Depreciation 130.20 153.17 146.59 172.46 124.52 146.50 136.26 160.31
  Total 1111.40 1193.67 1166.35 1240.44 1162.30 1245.65 1260.56 1336.81
MINE ECONOMICS – SENSITIVITY ANALYSIS
Capacity Utilisation
Sl. Option – I (Integrated 8 Mtpa) Option – I (Incremental 4.5 Mtpa)
No Particulars
.
100% 90% 85% 80% 75% 100% 90% 85% 80% 75%

Capacity Utilisation
A
(Base Case)
-1.00% -10.53% -ve -ve -ve -ve -ve -ve -ve -ve
Increase in Capital
1)5% -1.80% -11.05% -ve -ve -ve -ve -ve -ve -ve -ve
B
2)10% -2.53% -11.51% -ve -ve -ve -ve -ve -ve -ve -ve
3)15% -3.21% -11.91% -ve -ve -ve -ve -ve -ve -ve -ve
Increase in Operating Cost
C 1)5% -5.70% -ve -ve -ve -ve -ve -ve -ve -ve -ve
 
  2)10% -14.62% -ve -ve -ve -ve -ve -ve -ve -ve -ve
3)15% -ve -ve -ve -ve -ve -ve -ve -ve -ve -ve
Decrease in Sales
D 1)5% -6.78% -ve -ve -ve -ve -ve -ve -ve -ve -ve
 
  2)10% -ve -ve -ve -ve -ve -ve -ve -ve -ve -ve
3)15% -ve -ve -ve -ve -ve -ve -ve -ve -ve -ve
Increase in Capital + Operating Cost
E  1)5% -6.40% -ve -ve -ve -ve
-ve -ve -ve -ve -ve
 
  2)10% -15.27% -ve -ve -ve -ve -ve -ve -ve -ve -ve
3)15% -ve -ve -ve -ve -ve -ve -ve -ve -ve -ve
Option I (Integrated) Appendix C3 Appendix C4
Option I (Incremental) Appendix C3 Appendix C4
MINE ECONOMICS – SENSITIVITY ANALYSIS
Capacity Utilisation
Sl. Option – II (Integrated 8 Mtpa) Option – II (Incremental 4.5 Mtpa)
No Particulars
.
100% 90% 85% 80% 75% 100% 90% 85% 80% 75%

Capacity Utilisation
A 81.02% 51.63% 39.21% 29.44% 21.88% 29.15% 20.06% 16.72% 13.75% 11.00%
(Base Case)
Increase in Capital
1)5% 77.27% 47.86% 36.17% 27.20% 20.26% 25.77% 18.27% 15.30% 12.58% 10.02%
B
2)10% 73.35% 44.24% 33.39% 25.19% 18.80% 23.24% 16.77% 14.05% 11.53% 9.13%
3)15% 69.26% 40.84% 30.88% 23.38% 17.47% 21.22% 15.46% 12.96% 10.60% 8.32%
Increase in Operating Cost
C 1)5% 64.73% 38.07% 28.61% 21.38% 15.60% 21.45% 15.28% 12.65% 10.19% 7.82%
 
  2)10% 47.67% 27.00% 20.27% 14.89% 10.31% 16.08% 11.33% 9.15% 7.03% 4.92%
3)15% 32.65% 18.62% 13.73% 9.53% 5.72% 11.82% 7.93% 6.04% 4.14% 2.22%
Decrease in Sales
D 1)5% 54.20% 32.23% 24.64% 18.62% 13.60% 19.13% 13.74% 11.35% 9.07% 6.85%
 
  2)10% 31.64% 19.26% 14.67% 10.66% 7.01% 12.55% 8.66% 6.78% 4.91% 3.01%
3)15% 17.64% 10.37% 7.22% 4.22% 1.29% 7.30% 4.21% 2.64% 1.02% -0.68%
Increase in Capital + Operating Cost
E  1)5% 60.52% 34.99% 26.38% 19.77% 14.41% 19.50% 14.00% 11.58% 9.28% 7.03%
 
  2)10% 39.95% 22.97% 17.36% 12.71% 8.63% 13.62% 9.52% 7.57% 5.64% 3.69%
3)15% 25.22% 14.79% 10.82% 7.25% 3.92% 9.25% 5.90% 4.22% 2.52% 0.76%
Option II (Integrated) Appendix C3 Appendix C4
Option II (Incremental) Appendix C3 Appendix C4
MINE ECONOMICS – SENSITIVITY ANALYSIS

Capacity Utilisation
Sl. Option – III (a) (Integrated 8 Mtpa) Option – III (a) (Incremental 4.5 Mtpa)
Particulars
No.
100% 90% 85% 80% 75% 100% 90% 85% 80% 75%

Capacity
A Utilisation (Base 72.07% 41.79% 30.95% 22.96% 16.79% 18.40% 13.13% 10.79% 8.55% 6.36%
Case)
Increase in Capital
1)5% 67.45% 38.07% 28.31% 21.10% 15.44% 16.77% 11.99% 9.81% 7.70% 5.62%
B
2)10% 62.63% 34.72% 25.99% 19.46% 14.23% 15.38% 10.98% 8.93% 6.93% 4.93%
3)15% 57.70% 31.76% 23.93% 17.99% 13.13% 14.17% 10.07% 8.13% 6.22% 4.31%
Increase in Operating Cost
C 1)5% 53.35% 29.15% 21.70% 15.95% 11.18% 13.56% 9.37% 7.39% 5.43% 3.47%
 
2)10% 35.76% 19.83% 14.62% 10.25% 6.35% 9.58% 6.06% 4.32% 2.55% 0.73%
 
3)15% 23.18% 12.87% 8.95% 5.40% 2.03% 6.13% 3.05% 1.47% -0.17% -1.89%
Decrease in Sales
D
1)5% 43.23% 24.72% 18.71% 13.81% 9.58% 12.15% 8.29% 6.43% 4.57% 2.69%
 
2)10% 23.65% 14.03% 10.25% 6.83% 3.59% 7.10% 4.01% 2.44% 0.82% -0.87%
 
3)15% 12.37% 6.34% 3.59% 0.89% -1.84% 2.64% 0.01% -1.39% -2.86% -4.44%
Increase in Capital + Operating Cost

1)5% 48.51% 26.61% 19.92% 14.65% 10.20% 12.42% 8.51% 6.63% 4.75% 2.86%
 
2)10% 29.26% 16.74% 12.33% 8.49% 4.98% 7.97% 4.76% 3.15% 1.49% -0.22%
 
3)15% 17.86% 9.93% 6.65% 3.57% 0.57% 4.34% 1.56% 0.10% -1.42% -3.03%
Option III (a) (Integrated) Appendix C3 Appendix C4
Option III (a) (Incremental) Appendix C3 Appendix C4
MINE ECONOMICS – SENSITIVITY ANALYSIS

Capacity Utilisation
Sl. Option – III (b) (Integrated 8 Mtpa) Option – III (b) (Incremental 4.5 Mtpa)
Particulars
No.
100% 90% 85% 80% 75% 100% 90% 85% 80% 75%

Capacity Utilisation
A 65.28% 34.71% 25.00% 17.96% 12.43% 11.15% 7.14% 5.20% 3.26% 1.28%
(Base Case)

Increase in Capital
1)5% 60.31% 31.43% 22.82% 16.46% 11.34% 10.17% 6.39% 4.54% 2.67% 0.76%
B
2)10% 55.20% 28.57% 20.91% 15.11% 10.35% 9.29% 5.71% 3.93% 2.13% 0.27%
3)15% 50.10% 26.09% 19.23% 13.91% 9.45% 8.50% 5.08% 3.36% 1.62% -0.19%
Increase in Operating Cost
C 1)5% 43.72% 22.28% 16.02% 11.02% 6.71% 6.79% 3.42% 1.71% -0.06% -1.91%
 
  2)10% 26.11% 13.57% 9.18% 5.31% 1.69% 3.01% 0.02% -1.56% -3.23% -5.02%
3)15% 15.20% 7.01% 3.58% 0.32% -2.94% -0.41% -3.18% -4.69% -6.32% -8.12%
Decrease in Sales
D 1)5% 34.74% 18.87% 13.68% 9.32% 5.42% 12.15% 8.29% 6.43% 4.57% 2.69%
 
  2)10% 17.19% 9.06% 5.68% 2.49% -0.63% 7.10% 4.01% 2.44% 0.82% -0.87%
3)15% 7.09% 1.68% -0.94% -3.60% -6.38% 2.64% 0.01% -1.39% -2.86% -4.44%
Increase in Capital + Operating Cost
E  1)5% 39.09% 20.31% 14.65% 10.02% 5.95% 6.10% 2.86% 1.20% -0.52% -2.32%
 
  2)10% 21.40% 11.32% 7.49% 4.00% 0.68% 2.01% -0.81% -2.32% -3.92% -5.65%
3)15% 11.62% 4.94% 1.95% -0.96% -3.92% -1.51% -4.12% -5.56% -7.12% -8.84%

Option III (b) (Integrated) Appendix C3 Appendix C4


Option III (b) (Incremental) Appendix C3 Appendix C4
THANK YOU
ADD - ON SLIDES (AS BACKUP – with hot links at relevant places in the slides
before the ‘Thank You’ slide)

• Seams, thickness, parting thickness


• SEAM-WISE GEOLOGICAL AND MINEABLE RESERVES & QUALITY
• GEOLOGICAL PLAN
• GOOGLE EARTH IMAGE OF PROJECT AREA AND ITS SURROUNDINGS
• CROSS-SECTIONS
• EQUIPMENT PHASING
• CALENDAR PROGRAM OF COAL AND OB
• COAL FLOW DIAGRAM AND EVACUATION ROUTE
• Table & chart showing land use, viz. quarry, dump, etc.
• Table / Chart showing land rates, and the impact of enhanced land rates as per
LARR Act)
• APPENDIX A (for approved variant)
• APPENDIX A (for all variants)
• APPENDIX B.1 (for approved variant)
• APPENDIX B.1 (for all variants)
• APPENDIX C/C.1 (for approved variant)
• APPENDIX C/C.1 (for all variants)
• APPENDIX D/D.1 (for approved variant)
• APPENDIX D/D.1 (for all variants)
• SELLING PRICE CALCULATION & BREAK-UP
• SENSITIVITY ANALYSIS IN THE FORM OF BAR-CHARTS
• BAR CHART SHOWING YEAR-WISE PHASING OF TOTAL CAPITAL
• ANY OTHER RELEVANT SLIDE / DETAIL
ADD - ON SLIDES

Year-wise Quality of Recast EPR for Block-B(8.0 Mtpa)


Year-wise Grade of Coal in GCV
Comb. Vindhya I&II and Gorbi B&C
Coal Prodn.
Year

(Mtpa) Turra Grade PM Grade Total Grade


Y-1 5.47 2.55 G7 2.92 G8 5.47 G8
Y-2 5.47 2.86 G7 2.61 G9 5.47 G8
Y-3 5.47 2.86 G7 2.61 G9 5.47 G8
Y-4 8.00 4.25 G8 3.75 G10 8.00 G9
Y-5 8.00 3.83 G8 4.17 G11 8.00 G10
Y-6 8.00 3.40 G8 4.60 G11 8.00 G10
Y-7 8.00 3.39 G8 4.61 G11 8.00 G10
Y-8 8.00 3.40 G8 4.60 G11 8.00 G10
Y-9 8.00 3.27 G8 4.73 G11 8.00 G10
Y-10 8.00 3.25 G8 4.75 G11 8.00 G10
Y-11 8.00 3.27 G7 4.73 G10 8.00 G9
Y-12 8.00 3.29 G7 4.71 G10 8.00 G9
Y-13 8.00 3.34 G7 4.66 G10 8.00 G9
Y-14 8.00 3.67 G7 4.33 G10 8.00 G9
Y-15 8.00 4.08 G8 3.92 G10 8.00 G9
Y-16 8.00 4.08 G8 3.92 G10 8.00 G9
Y-17 7.00 3.57 G8 3.43 G10 7.00 G9
Y-18 6.00 3.06 G8 2.94 G10 6.00 G9
Y-19 4.66 2.43 G8 2.23 G10 4.66 G9
Total 138.07 63.85 G8 74.22 G10 138.07 G9
ADD - ON SLIDES

Recast EPR of Block-B OCP (8 Mtpa)


Calender Programme of Excavation

Coal & OB Both Departmental with Shovel-Dumper (Without considering old Gorbi Mine for Dumping)

Option -I (Coal & OB Both Departmental with Shovel-Dumper)                                      

Sl. Years of Quarry Operation


No. Life/ Year YEAR TOTAL
Y-1 Y-2 Y-3 Y-4 Y-5 Y-6 Y-7 Y-8 Y-9 Y-10 Y-11 Y-12 Y-13 Y-14 Y-15 Y-16 Y-17 Y-18 Y-19

1 Coal Production Seam wise


  Total Coal, Million tonnes 138.07 5.47 5.47 5.47 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 7.00 6.00 4.66 138.07
  Purewa Merged Seam 74.27 2.92 2.61 2.61 3.75 4.17 4.60 4.61 4.60 4.73 4.75 4.73 4.71 4.66 4.33 3.92 3.92 3.43 2.94 2.23 74.22
  Turra Seam 63.80 2.55 2.86 2.86 4.25 3.83 3.40 3.39 3.40 3.27 3.25 3.27 3.29 3.34 3.67 4.08 4.08 3.57 3.06 2.43 63.85
2 Natural OBR Parting wise (Mm ) 3

  Total OB 597.42 22.56 32.22 32.22 45.89 43.22 40.91 40.91 40.91 37.44 35.98 35.74 35.67 38.13 29.92 19.89 19.89 17.40 14.92 13.60 597.42

  Top OB above PM 416.45 14.02 23.00 23.00 32.26 31.29 30.42 30.42 30.42 28.34 27.14 26.72 26.57 28.16 20.05 10.13 10.13 8.86 7.60 7.92 416.45

  Parting bet. Turra & Purewa Merged 180.97 8.54 9.22 9.22 13.63 11.93 10.49 10.49 10.49 9.10 8.84 9.02 9.10 9.97 9.87 9.76 9.76 8.54 7.32 5.68 180.97

  AV. STRIPPING RATIO(Natural) (m3/t) 4.33 4.12 5.89 5.89 5.74 5.40 5.11 5.11 5.11 4.68 4.50 4.47 4.46 4.77 3.74 2.49 2.49 2.49 2.49 2.92 4.33

3 OBR Parting wise Adjusted


  Total OB 597.42 22.56 32.80 32.80 40.00 40.00 40.00 40.00 40.00 40.00 40.00 40.00 39.92 38.13 29.92 19.89 19.89 17.40 14.92 9.19 597.42

  Top OB above PM 416.45 14.02 23.58 23.58 26.37 28.07 29.51 29.51 29.51 30.90 31.16 30.98 30.82 28.16 20.05 10.13 10.13 8.86 7.60 3.51 416.45

  Parting bet. Turra & Purewa Merged 180.97 8.54 9.22 9.22 13.63 11.93 10.49 10.49 10.49 9.10 8.84 9.02 9.10 9.97 9.87 9.76 9.76 8.54 7.32 5.68 180.97

  Av. S.R (adjusted) (m3/t) 4.33 4.12 6.00 6.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 4.99 4.77 3.74 2.49 2.49 2.49 2.49 1.97 4.33

4 System-Wise OBR(Mm3)
  Top OBR Adjusted 597.42 22.56 32.80 32.80 40.00 40.00 40.00 40.00 40.00 40.00 40.00 40.00 39.92 38.13 29.92 19.89 19.89 17.40 14.92 9.19 597.42
  Sanctioned OB Outsouring 22.56 22.56                                     22.56
  Additional OB Outsouring 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
  Av. S.R (adjusted) (m3/t) 4.33 4.12 6.00 6.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 4.99 4.77 3.74 2.49 2.49 2.49 2.49 1.97 4.33
ADD - ON SLIDES

Recast EPR of Block-B OCP (8 Mtpa)


Calender Programme of Excavation
Coal Departmental & Total OB Outsourcing with Shovel-Dumper (Without considering old Gorbi Mine for Dumping)
Option- II (Coal Departmental & Total OB Outsourcing with Shovel-Dumper)                

Sl.
Years of Quarry Operation
No. Life/ Year YEAR TOTAL
Y-1 Y-2 Y-3 Y-4 Y-5 Y-6 Y-7 Y-8 Y-9 Y-10 Y-11 Y-12 Y-13 Y-14 Y-15 Y-16 Y-17 Y-18 Y-19
1 Coal Production Seam wise

  Total Coal, Million tonnes 138.07 5.47 5.47 5.47 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 7.00 6.00 4.66 138.07

  Purewa Merged Seam 74.27 2.92 2.61 2.61 3.75 4.17 4.60 4.61 4.60 4.73 4.75 4.73 4.71 4.66 4.33 3.92 3.92 3.43 2.94 2.23 74.22

  Turra Seam 63.80 2.55 2.86 2.86 4.25 3.83 3.40 3.39 3.40 3.27 3.25 3.27 3.29 3.34 3.67 4.08 4.08 3.57 3.06 2.43 63.85

2 Natural OBR Parting wise (Mm 3)

  Total OB 597.42 22.56 32.22 32.22 45.89 43.22 40.91 40.91 40.91 37.44 35.98 35.74 35.67 38.13 29.92 19.89 19.89 17.40 14.92 13.60 597.42

  Top OB above PM 416.45 14.02 23.00 23.00 32.26 31.29 30.42 30.42 30.42 28.34 27.14 26.72 26.57 28.16 20.05 10.13 10.13 8.86 7.60 7.92 416.45

  Parting bet. Turra & Purewa Merged 180.97 8.54 9.22 9.22 13.63 11.93 10.49 10.49 10.49 9.10 8.84 9.02 9.10 9.97 9.87 9.76 9.76 8.54 7.32 5.68 180.97

  AV. STRIPPING RATIO(Natural) (m 3/t) 4.33 4.12 5.89 5.89 5.74 5.40 5.11 5.11 5.11 4.68 4.50 4.47 4.46 4.77 3.74 2.49 2.49 2.49 2.49 2.92 4.33

3 OBR Parting wise Adjusted

  Total OB 597.42 22.56 32.80 32.80 40.00 40.00 40.00 40.00 40.00 40.00 40.00 40.00 39.92 38.13 29.92 19.89 19.89 17.40 14.92 9.19 597.42

  Top OB above PM 416.45 14.02 23.58 23.58 26.37 28.07 29.51 29.51 29.51 30.90 31.16 30.98 30.82 28.16 20.05 10.13 10.13 8.86 7.60 3.51 416.45

  Parting bet. Turra & Purewa Merged 180.97 8.54 9.22 9.22 13.63 11.93 10.49 10.49 10.49 9.10 8.84 9.02 9.10 9.97 9.87 9.76 9.76 8.54 7.32 5.68 180.97

  Av. S.R (adjusted) (m3/t) 4.33 4.12 6.00 6.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 4.99 4.77 3.74 2.49 2.49 2.49 2.49 1.97 4.33

4 System-Wise OBR(Mm3)

  Top OBR Adjusted 597.42 22.56 32.80 32.80 40.00 40.00 40.00 40.00 40.00 40.00 40.00 40.00 39.92 38.13 29.92 19.89 19.89 17.40 14.92 9.19 597.42

  Sanctioned OB Outsouring 22.56 22.56                                     22.56

  Additional OB Outsouring 574.86 0.00 32.80 32.80 40.00 40.00 40.00 40.00 40.00 40.00 40.00 40.00 39.92 38.13 29.92 19.89 19.89 17.40 14.92 9.19 574.86

  Av. S.R (adjusted) (m3/t) 4.33 4.12 6.00 6.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 4.99 4.77 3.74 2.49 2.49 2.49 2.49 1.97 4.33
ADD - ON SLIDES
Recast EPR of Block-B OCP (8 Mtpa)
Calender Programme of Excavation
Coal Departmental & Total OB Outsourcing with Shovel-Dumper (Considering old Gorbi Mine for Dumping)

Option III(a)&(b) (Coal Departmental & Total OB Outsourcing with Shovel-Dumper (Considering old Gorbi Mine for Dumping)

Sl. Years of Quarry Operation


Life/ Year YEAR TOTAL
No. Y-1 Y-2 Y-3 Y-4 Y-5 Y-6 Y-7 Y-8 Y-9 Y-10 Y-11 Y-12 Y-13 Y-14 Y-15 Y-16 Y-17 Y-18 Y-19
1 Coal Production Seam wise
  Total Coal, Million tonnes 138.07 5.47 5.47 5.47 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 7.00 6.00 4.66 138.07
  Purewa Merged Seam 74.27 2.92 2.61 2.61 3.75 4.17 4.60 4.61 4.60 4.73 4.75 4.73 4.71 4.66 4.33 3.92 3.92 3.43 2.94 2.23 74.22
  Turra Seam 63.80 2.55 2.86 2.86 4.25 3.83 3.40 3.39 3.40 3.27 3.25 3.27 3.29 3.34 3.67 4.08 4.08 3.57 3.06 2.43 63.85
2 Natural OBR Parting wise (Mm 3)
  Total OB 597.42 22.56 32.22 32.22 45.89 43.22 40.91 40.91 40.91 37.44 35.98 35.74 35.67 38.13 29.92 19.89 19.89 17.40 14.92 13.60 597.42
  Top OB above PM 416.45 14.02 23.00 23.00 32.26 31.29 30.42 30.42 30.42 28.34 27.14 26.72 26.57 28.16 20.05 10.13 10.13 8.86 7.60 7.92 416.45
  Parting bet. Turra & Purewa Merged 180.97 8.54 9.22 9.22 13.63 11.93 10.49 10.49 10.49 9.10 8.84 9.02 9.10 9.97 9.87 9.76 9.76 8.54 7.32 5.68 180.97

  AV. STRIPPING RATIO(Natural) (m 3/t) 4.33 4.12 5.89 5.89 5.74 5.40 5.11 5.11 5.11 4.68 4.50 4.47 4.46 4.77 3.74 2.49 2.49 2.49 2.49 2.92 4.33

3 OBR Parting wise Adjusted


  Total OB 597.42 22.56 32.80 32.80 40.00 40.00 40.00 40.00 40.00 40.00 40.00 40.00 39.92 38.13 29.92 19.89 19.89 17.40 14.92 9.19 597.42
  Top OB above PM 416.45 14.02 23.58 23.58 26.37 28.07 29.51 29.51 29.51 30.90 31.16 30.98 30.82 28.16 20.05 10.13 10.13 8.86 7.60 3.51 416.45
  Parting bet. Turra & Purewa Merged 180.97 8.54 9.22 9.22 13.63 11.93 10.49 10.49 10.49 9.10 8.84 9.02 9.10 9.97 9.87 9.76 9.76 8.54 7.32 5.68 180.97
  Av. S.R (adjusted) (m3/t) 4.33 4.12 6.00 6.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 4.99 4.77 3.74 2.49 2.49 2.49 2.49 1.97 4.33
4 System-Wise OBR(Mm3)
  Top OBR Adjusted 597.42 22.56 32.80 32.80 40.00 40.00 40.00 40.00 40.00 40.00 40.00 40.00 39.92 38.13 29.92 19.89 19.89 17.40 14.92 9.19 597.42
  Sanctioned OB Outsouring 22.56 22.56                                     22.56

  Additional OB Outsouring(to be dumped in


Block-B Mine)
431.10 0.00 32.80 24.30 31.50 31.50 31.50 31.50 31.50 31.50 31.50 31.50 31.42 29.63 21.42 11.39 11.39 8.90 6.66 1.19 431.10

  Additional OB Outsourcing (to be dumped in Old


Gorbi Mines)
143.76 0.00 0.00 8.50 8.50 8.50 8.50 8.50 8.50 8.50 8.50 8.50 8.50 8.50 8.50 8.50 8.50 8.50 8.26 8.00 143.76

  Av. S.R (adjusted) (m3/t) 4.33 4.12 6.00 6.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 4.99 4.77 3.74 2.49 2.49 2.49 2.49 1.97 4.33
                                               
ADD - ON SLIDES

            APPENDIX - B.1
RECAST EPR FOR BLOCK- B OPENCAST PROJECT (8 Mtpa)
STATEMENT SHOWING THE CATEGROY/SCALEWISE MANPOWER
               
Option-I (Total Coal & OB Departmental)          
SL. NO. CODE CATEGORY/GRADE/SCALE OB COAL COMMON RECLAMATION TOTAL
1 CAT-1 CAT-1 0 13 89 3 105
2 CAT-2 CAT-2 60 86 130 0 276
3 CAT-3 CAT-3 0 40 39 0 79
4 CAT-4 CAT-4 0 8 35 0 43
5 CAT-5 CAT-5 0 55 68 0 123
6 CAT-6 CAT-6 0 18 21 0 39
7 SPL. GR SPL. GR 211 0 0 0 211
8 GR-A GR-A 105 15 34 0 154
9 GR-B GR-B 64 68 74 54 260
10 GR-C GR-C 12 0 101 0 113
11 GR-D GR-D 0 0 13 0 13
12 GR-E GR-E 35 20 0 0 55
13 S1 MONTHLY RATED GRADE-H 0 1 44 0 45
14 S2 GRADE-G 0 0 0 0 0
15 S3 GRADE-F 0 0 27 0 27
16 S4 GRADE-E 0 0 56 0 56
17 S5 GRADE-D 10 8 79 0 97
18 S6 GRADE-C 0 5 72 0 77
19 S7 GRADE-B 0 18 117 0 135
20 S8 GRADE-A 0 6 65 2 73
21 E1 Rs 16400-40500 0 0 0 0 0
22 E2 Rs 20600-46500 0 0 9 0 9
23 E3 Rs 24900-50500 0 5 28 1 34
24 E4 Rs 29100-54500 0 3 23 0 26
25 E5 Rs 32900-58000 0 1 18 0 19
26 E6 Rs 36600-62000 0 1 16 1 18
27 E7 Rs 43200-66000 0 1 7 0 8
28 E8 Rs 51300-73000 0 0 2 0 2
               
  TOTAL   497 372 1167 61 2097
ADD - ON SLIDES

            APPENDIX - B.1
RECAST EPR FOR BLOCK-B OPENCAST PROJECT (8 Mtpa)
STATEMENT SHOWING THE CATEGROY/SCALEWISE MANPOWER
OPTION-II, III(a)& III(b)          
SL. NO. CODE CATEGORY/GRADE/SCALE OB COAL COMMON RECLAMATION TOTAL
1 CAT-1 CAT-1 0 13 46 3 62
2 CAT-2 CAT-2 30 86 78 0 194
3 CAT-3 CAT-3 0 40 36 0 76
4 CAT-4 CAT-4 0 8 31 0 39
5 CAT-5 CAT-5 0 55 55 0 110
6 CAT-6 CAT-6 0 18 21 0 39
7 SPL. GR SPL. GR 0 0 0 0 0
8 GR-A GR-A 3 15 32 0 50
9 GR-B GR-B 0 68 79 54 201
10 GR-C GR-C 0 0 3 0 3
11 GR-D GR-D 0 0 0 0 0
12 GR-E GR-E 0 20 0 0 20
13 S1 MONTHLY RATED GRADE-H 0 1 38 0 39
14 S2 GRADE-G 0 0 0 0 0
15 S3 GRADE-F 0 0 23 0 23
16 S4 GRADE-E 0 0 23 0 23
17 S5 GRADE-D 0 8 91 0 99
18 S6 GRADE-C 8 5 57 0 70
19 S7 GRADE-B 4 18 48 0 70
20 S8 GRADE-A 0 6 33 2 41
21 E1 E1 0 0 0 0 0
22 E2 E2 0 0 7 0 7
23 E3 E3 4 5 29 1 39
24 E4 E4 0 3 13 0 16
25 E5 E5 0 1 10 0 11
26 E6 E6 1 1 21 1 24
27 E7 E7 0 1 9 0 10
28 E8 E8 0 0 2 0 2
               
  TOTAL   50 372 785 61 1268
ADD - ON SLIDES

Appendix - A

RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)

STATEMENT OF ESTIMATED CAPITAL INVESTMENT AND YEARWISE PHASING


Option - I (Total Coal & OB Departmental) - 8 Mtpa
Base Date: October, 2018

Option - I (Integrated - 8 Mtpa) (Amt. in ` Lakhs)


PHASING OF CAPITAL

TOTAL
BALANCE
SANCTION TOTAL EXISTING AS COMMITTED
SL. INCREMENTAL
PARTICULARS ED PROVN ON 31.03.18 EXPENSES Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7
NO. PROVISION
CAPITAL (8 Mtpa) (3.5 Mtpa) FOR 3.5 Mtpa
(4.5 Mtpa)
(3.5 Mtpa)

1 Land 858 25522 5755   19767   988 18779        


2 Buildings                        
  Service 2279 10069 296   9773     1955 7818      
  Residential 1371 11534 1755   9779     1956 7823      
3 Plant & Machinery                        
  a) HEMM 8298 252808 8060   244748   177605 1170 65973      
  b) Others than HEMM 23201 42937 24374   18563     5854 12709      
4 Furniture & Fittings 98 293 218   74     37 37      
5 Railway Siding 3600 8516 4889 3627                
6 Vehicles 308 939 228   711     240 471      
7 Prospecting & Boring 115 44 44                  
8 Development.                        
8.1 Capital Outlay in Mines 7125 40695 2652 204 37839   1744 33730 2365      
8.2 Roads & Culverts 2417 4523 460 106 3956     791 3165      
8.3 Water Supply & Sewerage 1842 6972 1031   5942     1188 4753      
8.4 Scientific Research 50 80     80     80        
8.5 PR Preparation Cost 497 1762     1762   1762          
9.1 Revenue Exp. Capitalised less                      
618
  Depreciation                      
10 Land Reclamation 831 2456 1333   1123     595 527      
  INITIAL CAPITAL 53510 409148 51096 3936 354116   182100 66374 105642      
ADD - ON SLIDES

Appendix - C
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Option - I (Total Coal & OB Departmental) - 8 Mtpa

Statement Showing Average Cost of Production

Option - I (Integrated - 8 Mtpa)


Total Coal OB Common
Sl. No. Particulars
(`/t) (`/t) (`/m3) (`/t)
1 Salary & Wages 238.47 39.48 13.01 142.71
2 Stores 625.73 84.12 117.26 34.24
3 Power 82.27 6.71 7.76 41.97
4 Misc. Expenses 86.42 5.96 10.75 33.95
5 Adminstrative Cost (Cash) 3.62     3.62
6 Mine closure Cost 18.88     18.88
7 OB Outsourcing Cost 18.12   4.19  
8 COAL Outsourcing Cost        
9 Interest on Working capital 51.89 6.59 7.39 13.31
10 Total cash Cost 1125.39 142.87 160.35 288.68
11 Interest        
12 Adminstrative Cost (Notional) 30.91     30.91
13 Depreciation 292.76 43.34 36.46 91.66
  Total 1449.05 186.21 196.82 411.24
14 Common cost apportioned to coal & OB   54.28 82.50  
  Total   240.48 279.31  
15 OB Cost Charged to coal   1208.57    
  Total Cost   1449.05    
ADD - ON SLIDES

Appendix - C.1

RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)

Statement Showing Estimated Year wise Operating Cost at 100% capacity utilisation
Option - I (Total Coal & OB Departmental) - 8 Mtpa
Option - I (Integrated - 8 Mtpa) (Amt. in ` Lakhs)
% of
Sl. Avg Cost
Particulars Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total Cost Total
No. (`/t)
Cost

1 Salary & Wages 11308.53 11308.53 14585.45 18253.08 18253.08 18253.08 18253.08 18253.08 18253.08 18253.08 18253.08 18253.08 18253.08 18253.08 18253.08 18253.08 18253.08 18253.08 18253.08 329251.84 238.47 16.46

2 Stores 8103.21 36278.53 37085.86 49647.68 49647.68 49647.68 49647.68 49647.68 49647.68 49647.68 49647.68 49640.56 49481.21 48750.36 47857.49 47857.49 47596.83 47337.05 46774.70 863944.73 625.73 43.18

3 Power   2681.64 3719.81 5240.76 5622.57 6302.59 6982.62 7075.65 7082.20 7088.74 7095.29 7095.29 7095.29 7095.29 7095.29 7095.29 6762.95 6394.90 6062.57 113588.75 82.27 5.68

4 Misc. Expenses 1670.69 4453.33 4744.33 6344.97 6840.50 6840.50 6840.50 6840.50 6840.50 6840.50 6840.50 6840.50 6840.50 6840.50 6840.50 6840.50 6761.75 6683.00 6577.47 119321.50 86.42 5.96

5 Adminstrative Cost (Cash) 198.00 198.00 198.00 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 253.39 217.19 168.68 4997.84 3.62 0.25

6 Mine Closure Cost 853.47 896.14 940.95 987.99 1037.39 1089.26 1143.73 1200.91 1260.96 1324.01 1390.21 1459.72 1532.70 1609.34 1689.81 1774.30 1863.01 1956.16 2053.97 26064.03 18.88 1.30

7 OB Outsourcing 25015.16                                     25015.16 18.12 1.25

8 Coal Outsourcing                                            

Interest on Working
9 2278.87 2697.78 2961.60 3903.60 3948.39 3983.76 4019.26 4026.52 4029.74 4033.11 4036.62 4039.64 4035.46 4003.84 3964.58 3968.66 3938.73 3907.33 3861.37 71638.89 51.89 3.58
capital

1553822.7
10 Total Cash Cost 49427.93 58513.95 64235.99 84667.67 85639.19 86406.47 87176.46 87333.93 87403.74 87476.70 87552.96 87618.37 87527.83 86842.00 85990.33 86078.90 85429.74 84748.72 83751.85 1125.39 77.66
3

11 Interest                                            

Adminstrative Cost
12 1690.68 1690.68 1690.68 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2163.57 1854.49 1440.32 42674.94 30.91 2.13
(Notional)

13 Depreciation 3600.24 13057.87 17010.92 23180.46 23183.59 23183.59 23184.01 23184.01 23197.46 23198.06 23198.66 23199.35 23199.35 23199.35 23199.35 23199.35 23199.35 23199.35 22635.33 404209.63 292.76 20.20

2000707.3
  Total 54718.85 73262.49 82937.58 110320.79 111295.44 112062.72 112833.12 112990.60 113073.86 113147.42 113224.28 113290.37 113199.84 112514.00 111662.33 111750.91 110792.66109802.56107827.50 1449.05 100.00
1

  Cost (`/t) 1000.34 1339.35 1516.23 1379.01 1391.19 1400.78 1410.41 1412.38 1413.42 1414.34 1415.30 1416.13 1415.00 1406.43 1395.78 1396.89 1582.75 1830.04 2313.89 1449.05    

  Fixed Cost (`/t) 422.02 970.77 1136.56 1032.60 1043.53 1050.89 1058.29 1059.96 1060.98 1061.87 1062.81 1063.73 1064.69 1065.69 1066.75 1067.86 1213.04 1406.24 1785.12 1080.32   74.55

  Variable Cost (`/t) 578.32 368.58 379.67 346.41 347.66 349.89 352.12 352.43 352.45 352.47 352.49 352.40 350.31 340.73 329.03 329.03 369.71 423.80 528.78 368.73   25.45

1914790.8
  Total Sales (` in Lakhs) 95384.32 87101.30 87101.30 111999.99 107816.29 105646.59 106774.26 106823.68102211.38103605.64106770.87108376.16117849.17120733.69106088.65106088.65 92827.57 79566.49 62024.82 1386.83  
2

2000707.3
  Total Cost (` in Lakhs) 54718.85 73262.49 82937.58 110320.79 111295.44 112062.72 112833.12 112990.60 113073.86 113147.42 113224.28 113290.37 113199.84 112514.00 111662.33 111750.91 110792.66109802.56107827.50 1449.05  
1

  Total Profits (` in Lakhs) 40665.47 13838.80 4163.72 1679.20 -3479.15 -6416.12 -6058.86 -6166.91 -10862.48 -9541.77 -6453.40 -4914.21 4649.33 8219.69 -5573.68 -5662.26 -17965.09 -30236.08 -45802.68 -85916.49 -62.23  
ADD - ON SLIDES

Appendix - C.2

RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)


Statement Showing Estimated Year wise operating cost at 85% capacity utilisation
Option - I (Total Coal & OB Departmental) - 8 Mtpa
(Amount in Rs. Lakhs)

Option - I (Integrated - 8 Mtpa)

Sl. % of
Avg Cost
No Particulars Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total Cost Total
(`/t)
. Cost

1 Salary & Wages 11308.53 11308.53 14585.45 18253.08 18253.08 18253.08 18253.08 18253.08 18253.08 18253.08 18253.08 18253.08 18253.08 18253.08 18253.08 18253.08 18253.08 18253.08 18253.08 329251.84 280.55 17.11

2 Stores 7423.80 33826.56 34590.80 46340.53 46340.53 46340.53 46340.53 46340.53 46340.53 46340.53 46340.53 46334.48 46199.04 45577.81 44818.87 44818.87 44597.31 44376.50 43898.50 807186.82 687.79 41.95

3 Power   2581.08 3580.32 5044.23 5411.72 6066.25 6720.78 6810.32 6816.62 6822.92 6829.22 6829.22 6829.22 6829.22 6829.22 6829.22 6509.34 6155.10 5835.22 109329.17 93.16 5.68

4 Misc. Expenses 1576.03 4121.07 4407.33 5883.33 6378.86 6378.86 6378.86 6378.86 6378.86 6378.86 6378.86 6378.86 6378.86 6378.86 6378.86 6378.86 6311.92 6244.99 6155.29 111246.29 94.79 5.78

Adminstrative
5 198.00 198.00 198.00 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 253.39 217.19 168.68 4997.84 4.26 0.26
Cost (Cash)
Mine Closure
6 853.47 896.14 940.95 987.99 1037.39 1089.26 1143.73 1200.91 1260.96 1324.01 1390.21 1459.72 1532.70 1609.34 1689.81 1774.30 1863.01 1956.16 2053.97 26064.03 22.21 1.35
Cost
7 OB Outsourcing 21262.89                                     21262.89 18.12 1.10

8 Coal Outsourcing                                            

Interest on
9 2060.10 2558.35 2817.97 3711.94 3756.04 3790.18 3824.45 3831.54 3834.75 3838.10 3841.61 3844.67 3841.65 3815.33 3782.54 3786.62 3759.76 3731.48 3690.96 68118.05 58.04 3.54
Working capital

10 Total Cash Cost 44682.81 55489.72 61120.81 80510.70 81467.22 82207.76 82951.02 83104.83 83174.39 83247.09 83323.09 83389.62 83324.14 82753.23 82041.96 82130.54 81547.81 80934.49 80055.71 1477456.93 1258.92 76.78

11 Interest                                            

Adminstrative
12 1690.68 1690.68 1690.68 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2163.57 1854.49 1440.32 42674.94 36.36 2.22
Cost (Notional )

13 Depreciation 3600.24 13057.87 17010.92 23180.46 23183.59 23183.59 23184.01 23184.01 23197.46 23198.06 23198.66 23199.35 23199.35 23199.35 23199.35 23199.35 23199.35 23199.35 22635.33 404209.63 344.42 21.01

  Total 49973.73 70238.27 79822.41 106163.82 107123.46 107864.01 108607.68 108761.49 108844.51 108917.80 108994.40 109061.62 108996.14 108425.23 107713.97 107802.54 106910.73 105988.34 104131.36 1924341.51 1639.70 100.00

  Cost (`/t) 1074.82 1510.66 1716.80 1561.23 1575.35 1586.24 1597.17 1599.43 1600.65 1601.73 1602.86 1603.85 1602.88 1594.49 1584.03 1585.33 1796.82 2078.20 2628.92 1639.70    

  Fixed Cost (`/t) 496.50 1142.08 1337.13 1214.82 1227.68 1236.34 1245.05 1247.01 1248.21 1249.26 1250.37 1251.45 1252.58 1253.76 1255.00 1256.30 1427.11 1654.40 2100.14 1270.97   77.51

  Variable Cost (`/t) 578.32 368.58 379.67 346.41 347.66 349.89 352.12 352.43 352.45 352.47 352.49 352.40 350.31 340.73 329.03 329.03 369.71 423.80 528.78 368.73   22.49

Total Sales (` in
  81076.67 74036.10 74036.10 95199.99 91643.85 89799.60 90758.12 90800.13 86879.68 88064.80 90755.24 92119.74 100171.80 102623.63 90175.35 90175.35 78903.43 67631.51 52721.10 1627572.20 1386.83  
Lakhs)
Total Cost (` in
  49973.73 70238.27 79822.41 106163.82 107123.46 107864.01 108607.68 108761.49 108844.51 108917.80 108994.40 109061.62 108996.14 108425.23 107713.97 107802.54 106910.73 105988.34 104131.36 1924341.51 1639.70  
Lakhs)
Total Profits (` in
  31102.94 3797.84 -5786.30 -10963.83 -15479.62 -18064.40 -17849.55 -17961.36 -21964.83 -20853.01 -18239.16 -16941.88 -8824.35 -5801.60 -17538.62 -17627.19 -28007.30 -38356.82 -51410.26 -296769.31 -252.87  
Lakhs)
ADD - ON SLIDES

Appendix - C.3
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Option - I (Total Coal & OB Departmental) - 8 Mtpa
Statement Showing Economics at Different Capacity Utilisation

Option - I (Integrated - 8 Mtpa)

Sl Capacity Utilisation
Particulars
No. 100% 90% 85% 80% 75%

1 Output (Mtpa) 8.00 7.20 6.80 6.40 6.00

2 Cost (`/t) 1449.05 1569.09 1639.70 1719.13 1809.16

3 Selling Price (`/t) 1386.83 1386.83 1386.83 1386.83 1386.83

4 Profit (`/t) -62.23 -182.26 -252.87 -332.31 -422.33

5 IRR (%) -1.00% -10.53% -ve -ve -ve

6 DSP to yield 12%IRR 1640.12 1780.43 1862.96 1955.81 2061.05


ADD - ON SLIDES

Appendix - C.4
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Option - I (Total Coal & OB Departmental) - 8 Mtpa
Statement showing Sensitivity of IRR

Option - I (Integrated - 8 Mtpa)


Capacity Utilisation
Sl No. Particulars
100% 90% 85% 80% 75%
A Base Case -1.00% -10.53% -ve -ve -ve
B Increase in Capital          
  1)5% -1.80% -11.05% -ve -ve -ve
  2)10% -2.53% -11.51% -ve -ve -ve
  3)15% -3.21% -11.91% -ve -ve -ve
C Increase in Op.Cost          
  1)5% -5.70% -ve -ve -ve -ve
  2)10% -14.62% -ve -ve -ve -ve
  3)15% -ve -ve -ve -ve -ve
D Decrease in Sales          
  1)5% -6.78% -ve -ve -ve -ve
  2)10% -ve -ve -ve -ve -ve
  3)15% -ve -ve -ve -ve -ve
E Increase in Cap.+Op.Cost          
  1)5% -6.40% -ve -ve -ve -ve
  2)10% -15.27% -ve -ve -ve -ve
  3)15% -ve -ve -ve -ve -ve
ADD - ON SLIDES

Appendix - D

RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)


Option - I (Total Coal & OB Departmental) - 8 Mtpa
Statement Showing Estimated Cash Flow Analysis
(Pre-Tax IRR on Total Capital)
At 100% capacity utilisation
Option - I (Integrated - 8 Mtpa)           (Amt. in ` Lakhs)

Sl.
Particulars Existing Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total
No.
1 Initial Capital 31326.68   182099.77 66374.19 105642.09                               385442.73

-
2 Replacement Capital     507.10 6267.15 6344.53 1858.92 384.15 4733.49 361.90 303.12 2457.13 9923.85 14427.16 14251.99 8930.06 812.85 3058.39 1763.74  
30009.08
46376.45

Less: GST credit on Capital


3     4355.06 4355.06 5600.00 5390.81 5282.33 5338.71 5341.18 5110.57 2567.64 1506.59 2172.75 2124.33 1357.91 122.68 444.39 246.02     51316.04
Goods
85429.7
4 Cash Operating Expenses   49427.93 58513.95 64235.99 84667.67 85639.19 86406.47 87176.46 87333.93 87403.74 87476.70 87552.96 87618.37 87527.83 86842.00 85990.33 86078.90
4
84748.72 83751.85 1553822.73

86947.4
5 Total Cash Outflow 31326.68 49427.93 236765.75 132522.26 191054.30 82107.30 81508.29 86571.23 82354.65 82596.30 87366.19 95970.23 99872.78 99655.50 94414.14 86680.50 88692.91
6
84748.72 53742.77 1934325.88

106823.6 102211.3 103605.6 106770.8 108376.1 117849.1 120733.6 106088.6 106088.6 92827.5
6 Inflow from Sales   95384.32 87101.30 87101.30 111999.99 107816.29 105646.59 106774.26
8 8 4 7 6 7 9 5 5 7
79566.49 62024.82 1914790.82

7 Net Cash Flow -31326.68 45956.39 -149664.45 -45420.96 -79054.32 25708.99 24138.31 20203.03 24469.04 19615.09 16239.45 10800.64 8503.38 18193.67 26319.54 19408.15 17395.74 5880.11 -5182.23 8282.05 -19535.06

Coal Production (Lakh


8   54.70 54.70 54.70 80.00 80.00 80.00 80.00 80.00 80.00 80.00 80.00 80.00 80.00 80.00 80.00 80.00 70.00 60.00 46.60 1380.70
Tonnes)
9 Pre Tax Internal rate of return       -1.00%                                  

Desired Selling Price to Yield


10       1640.12                                  
12% IRR (`/t)

11 Net Present Value (` Lakhs)       -111665.16                                  


ADD - ON SLIDES

Appendix - D.1

RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)


Option - I (Total Coal & OB Departmental) - 8 Mtpa
Statement Showing Estimated Cash Flow Analysis
(Pre-Tax IRR on Total Capital)
At 85% capacity utilisation
Option - I (Integrated - 8 Mtpa) (Amt. in ` Lakhs)

Sl.
Particulars Existing Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total
No.

1 Initial Capital 31326.68   182099.77 66374.19 105642.09                               385442.73

-
2 Replacement Capital     507.10 6267.15 6344.53 1858.92 384.15 4733.49 361.90 303.12 2457.13 9923.85 14427.16 14251.99 8930.06 812.85 3058.39 1763.74   46376.45
30009.08

3 Less: GST credit on Capital Goods     4355.06 4355.06 5600.00 5390.81 5282.33 5338.71 5341.18 5110.57 2567.64 1506.59 2172.75 2124.33 1357.91 122.68 444.39 246.02     51316.04

81547.8
4 Cash Operating Expenses   44682.81 55489.72 61120.81 80510.70 81467.22 82207.76 82951.02 83104.83 83174.39 83247.09 83323.09 83389.62 83324.14 82753.23 82041.96 82130.54 80934.49 80055.71 1477456.93
1

83065.5
5 Total Cash Outflow 31326.68 44682.81 233741.52 129407.08 186897.33 77935.32 77309.58 82345.79 78125.55 78366.94 83136.58 91740.36 95644.03 95451.81 90325.37 82732.13 84744.54 80934.49 50046.64 1857960.08
3

100171.8 102623.6 78903.4


6 Inflow from Sales   81076.67 74036.10 74036.10 95199.99 91643.85 89799.60 90758.12 90800.13 86879.68 88064.80 90755.24 92119.74 90175.35 90175.35 67631.51 52721.10 1627572.20
0 3 3

- - -
7 Net Cash Flow 36393.86 -55370.98 -91697.35 13708.52 12490.03 8412.33 12674.58 8512.74 4928.22 -985.11 -3524.29 4719.99 12298.26 7443.22 5430.81 -4162.10 2674.46 -230387.88
31326.68 159705.42 13302.98

8 Coal Production (Lakh Tonnes)   46.50 46.50 46.50 68.00 68.00 68.00 68.00 68.00 68.00 68.00 68.00 68.00 68.00 68.00 68.00 68.00 59.50 51.00 39.61 1173.60

9 Pre Tax Internal rate of return       -ve                                  

Desired Selling Price to Yield 12% IRR


10       1862.96                                  
(`/t)

-
11 Net Present Value (` Lakhs)                                        
193517.78
ADD - ON SLIDES

Appendix - A
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)

STATEMENT OF ESTIMATED CAPITAL INVESTMENT AND YEARWISE PHASING


Option - I (Total Coal & OB Departmental) - Incremental 4.5 Mtpa
Base Date: October, 2018
Option - I (Incremental- 4.5 Mtpa) (Amt. in ` Lakhs)
TOTAL PHASING OF CAPITAL
COMMITTE
SANCTION TOTAL EXISTING BALANCE
D
SL. ED PROVN AS ON INCREMENTA
PARTICULARS EXPENSES
NO. CAPITAL (4.5 31.03.18 L PROVISION Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7
FOR 3.5
(3.5 Mtpa) (3.5 Mtpa) (4.5 Mtpa)
Mtpa
Mtpa)
1 Land 858 19767     19767   988 18779        
2 Buildings                        
  Service 2279 9773     9773     1955 7818      
  Residential 1371 9779     9779     1956 7823      
3 Plant & Machinery                        
  a) HEMM 8298 244748     244748   177605 1170 65973      
  b) Others than HEMM 23201 18563     18563     5854 12709      
4 Furniture & Fittings 98 74     74     37 37      
5 Railway Siding 3600                      
6 Vehicles 308 711     711     240 471      
7 Prospecting & Boring 115                      
8 Development.                        
8.1 Capital Outlay in Mines 7125 37839     37839   1744 33730 2365      
8.2 Roads & Culverts 2417 3956     3956     791 3165      
Water Supply &
8.3 1842 5942     5942     1188 4753      
Sewerage
8.4 Scientific Research 50 80     80     80        
8.5 PR Preparation Cost 497 1762     1762   1762          
9.1 Revenue Exp.                      
Capitalised less 618
                       
Depreciation
10 Land Reclamation 831 1123     1123     595 527      
ADD - ON SLIDES

Appendix - C
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Option - I (Total Coal & OB Departmental) - Incremental 4.5 Mtpa

Statement Showing Average Cost of Production

Option - I (Incremental- 4.5 Mtpa)


Sl. Total Coal OB Common
Particulars
No. (`/t) (`/t) (`/m3) (`/t)
1 Salary & Wages 296.32 32.87 19.33 164.14
2 Stores 964.48 42.18 175.05 22.76
3 Power 118.45 3.36 11.76 54.66
4 Misc. Expenses 121.22 3.22 16.46 33.40
5 Adminstrative Cost (Cash) 3.62     3.62
6 Mine closure Cost 13.88     13.88
7 OB Outsourcing Cost 11.88   2.31  
8 COAL Outsourcing Cost        
9 Interest on Working capital 73.94 3.95 10.87 14.14
10 Total cash Cost 1603.78 85.57 235.78 306.61
11 Interest        
12 Adminstrative Cost (Notional) 30.91     30.91
13 Depreciation 442.62 22.81 55.91 132.52
  Total 2077.31 108.38 291.69 470.03
14 Common cost apportioned to coal & OB   53.35 81.09  
  Total   161.73 372.78  
15 OB Cost Charged to coal   1915.58    
  Total Cost   2077.31    
ADD - ON SLIDES

Appendix - C.1
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)

Statement Showing Estimated Year wise Operating Cost at 100% capacity utilisation
Option - I (Total Coal & OB Departmental) - Incremental 4.5 Mtpa
Option - I (Incremental- 4.5 Mtpa) (Amt. in ` Lakhs)
% of
Sl. Avg Cost
Particulars Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total Cost Total
No. (`/t)
Cost

1 Salary & Wages 6551.82 5760.27 9031.58 12708.07 12708.07 12708.07 12708.07 12708.07 12708.07 12708.07 12708.07 12708.07 12708.07 12708.07 12708.07 12708.07 12708.07 12708.07 12708.07 224672.73 296.32 14.26

2 Stores 799.68 28391.92 29199.25 42659.28 42659.28 42659.28 42659.28 42659.28 42659.28 42659.28 42659.28 42652.16 42492.81 41761.96 41064.05 41064.05 40933.27 40895.88 40738.45 731267.72 964.48 46.43

3 Power   2421.14 3152.40 4262.16 4527.98 5020.35 5512.71 5571.05 5574.27 5577.49 5580.71 5580.71 5580.71 5580.71 5580.71 5580.71 5252.43 4888.87 4560.58 89805.70 118.45 5.70

4 Misc. Expenses 421.13 3105.91 3319.53 4861.96 5357.49 5357.49 5357.49 5357.49 5357.49 5357.49 5357.49 5357.49 5357.49 5357.49 5357.49 5357.49 5318.11 5318.11 5271.65 91906.24 121.22 5.84

5 Adminstrative Cost (Cash) 71.31 71.31 71.31 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 144.79 144.79 123.43 2744.52 3.62 0.17

6 Mine Closure Cost 344.56 361.79 379.88 398.88 418.82 439.76 461.75 484.84 509.08 534.53 561.26 589.32 618.79 649.73 682.21 716.32 752.14 789.75 829.23 10522.62 13.88 0.67

7 OB Outsourcing 9003.68                                     9003.68 11.88 0.57

8 Coal Outsourcing                                            

Interest on Working
9 830.96 1938.76 2182.44 3144.24 3182.00 3206.81 3231.67 3235.61 3236.94 3238.32 3239.77 3240.78 3234.50 3200.67 3168.51 3170.16 3146.93 3129.36 3104.52 56062.96 73.94 3.56
capital
1215986.1
10 Total Cash Cost 18023.14 42051.11 47336.39 68197.48 69016.52 69554.64 70093.86 70179.22 70208.01 70238.07 70269.46 70291.42 70155.26 69421.52 68723.92 68759.68 68255.73 67874.83 67335.93 1603.78 77.20
8

11 Interest                                            

Adminstrative Cost
12 608.89 608.89 608.89 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1236.33 1236.33 1053.97 23434.59 30.91 1.49
(Notional)

13 Depreciation   9452.56 13396.69 19565.83 19565.83 19565.83 19565.83 19565.83 19565.83 19565.83 19565.83 19565.83 19565.83 19565.83 19565.83 19565.83 19565.83 19514.42 19307.92 335593.14 442.62 21.31

1575013.9
  Total 18632.03 52112.57 61341.97 89154.17 89973.22 90511.34 91050.55 91135.91 91164.70 91194.76 91226.16 91248.11 91111.95 90378.21 89680.62 89716.38 89057.88 88625.57 87697.81 2077.31 100.00
1

  Cost (`/t) 945.79 2645.31 3113.81 1981.20 1999.40 2011.36 2023.35 2025.24 2025.88 2026.55 2027.25 2027.74 2024.71 2008.40 1992.90 1993.70 2226.45 2215.64 2571.78 2077.31    

  Fixed Cost (`/t) 415.85 1880.18 2321.98 1461.69 1478.34 1487.43 1496.55 1498.11 1498.73 1499.38 1500.06 1500.71 1501.40 1502.12 1502.87 1503.67 1681.77 1674.33 1945.61 1537.80   74.03

  Variable Cost (Rs/t) 529.94 765.13 791.82 519.51 521.06 523.93 526.80 527.14 527.15 527.17 527.19 527.03 523.31 506.29 490.03 490.03 544.67 541.31 626.18 539.50   25.97

1051491.5
  Total Sales (` in Lakhs) 27320.47 27320.47 27320.47 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 55473.04 55473.04 47290.77 1386.83  
6
1575013.9
  Total Cost (` in Lakhs) 18632.03 52112.57 61341.97 89154.17 89973.22 90511.34 91050.55 91135.91 91164.70 91194.76 91226.16 91248.11 91111.95 90378.21 89680.62 89716.38 89057.88 88625.57 87697.81 2077.31  
1

  Total Profits (` in Lakhs) 8688.44 -24792.09 -34021.49 -26746.99 -27566.04 -28104.16 -28643.38 -28728.74 -28757.53 -28787.59 -28818.98 -28840.93 -28704.78 -27971.03 -27273.44 -27309.20 -33584.84 -33152.52 -40407.04 -523522.34 -690.48  
ADD - ON SLIDES

Appendix - C.2
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Statement Showing Estimated Year wise operating cost at 85% capacity utilisation
Option - I (Total Coal & OB Departmental) - Incremental 4.5 Mtpa
(Amount in Rs. Lakhs)
Option - I (Incremental- 4.5 Mtpa)
% of
Sl. Avg Cost
Particulars Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total Cost Total
No. (`/t)
Cost

1 Salary & Wages 6551.82 5760.27 9031.58 12708.07 12708.07 12708.07 12708.07 12708.07 12708.07 12708.07 12708.07 12708.07 12708.07 12708.07 12708.07 12708.07 12708.07 12708.07 12708.07 224672.73 348.62 14.84

2 Stores 679.73 26586.87 27351.11 39864.33 39864.33 39864.33 39864.33 39864.33 39864.33 39864.33 39864.33 39858.27 39722.83 39101.60 38508.38 38508.38 38397.21 38365.43 38231.62 684226.03 1061.69 45.20

3 Power   2330.35 3034.18 4102.33 4358.18 4832.08 5305.99 5362.14 5365.24 5368.34 5371.43 5371.43 5371.43 5371.43 5371.43 5371.43 5055.46 4705.53 4389.56 86437.98 134.12 5.71

4 Misc. Expenses 397.86 2845.04 3053.92 4471.71 4967.24 4967.24 4967.24 4967.24 4967.24 4967.24 4967.24 4967.24 4967.24 4967.24 4967.24 4967.24 4933.77 4933.77 4894.28 85137.24 132.10 5.62

5 Adminstrative Cost (Cash) 71.31 71.31 71.31 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 144.79 144.79 123.43 2744.52 4.26 0.18

6 Mine Closure Cost 344.56 361.79 379.88 398.88 418.82 439.76 461.75 484.84 509.08 534.53 561.26 589.32 618.79 649.73 682.21 716.32 752.14 789.75 829.23 10522.62 16.33 0.70

7 OB Outsourcing 7653.13                                     7653.13 11.88 0.51

8 Coal Outsourcing                                            

Interest on Working
9 758.76 1834.52 2074.56 2982.56 3019.84 3043.76 3067.73 3071.56 3072.88 3074.26 3075.70 3076.77 3071.64 3043.11 3016.01 3017.66 2996.25 2979.62 2956.85 53234.06 82.60 3.52
capital

10 Total Cash Cost 16457.17 39790.16 44996.55 64690.77 65499.36 66018.13 66537.98 66621.05 66649.72 66679.65 66710.92 66733.99 66622.89 66004.07 65416.23 65451.99 64987.69 64626.97 64133.04 1154628.32 1791.59 76.28

11 Interest                                            

Adminstrative Cost
12 608.89 608.89 608.89 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1236.33 1236.33 1053.97 23434.59 36.36 1.55
(Notional)

13 Depreciation   9452.56 13396.69 19565.83 19565.83 19565.83 19565.83 19565.83 19565.83 19565.83 19565.83 19565.83 19565.83 19565.83 19565.83 19565.83 19565.83 19514.42 19307.92 335593.14 520.73 22.17

1513656.0
  Total 17066.06 49851.61 59002.13 85647.46 86456.06 86974.82 87494.68 87577.75 87606.41 87636.34 87667.61 87690.68 87579.58 86960.77 86372.92 86408.68 85789.85 85377.71 84494.92 2348.68 100.00
5

  Cost (`/t) 1019.17 2977.10 3523.57 2239.15 2260.29 2273.85 2287.44 2289.61 2290.36 2291.15 2291.96 2292.57 2289.66 2273.48 2258.12 2259.05 2523.23 2511.11 2915.13 2348.68    

  Fixed Cost (`/t) 489.23 2211.98 2731.74 1719.64 1739.23 1749.92 1760.65 1762.48 1763.21 1763.97 1764.77 1765.54 1766.35 1767.20 1768.09 1769.02 1978.56 1969.80 2288.95 1809.18   77.03

  Variable Cost (Rs/t) 529.94 765.13 791.82 519.51 521.06 523.93 526.80 527.14 527.15 527.17 527.19 527.03 523.31 506.29 490.03 490.03 544.67 541.31 626.18 539.50   22.97

  Total Sales (` in Lakhs) 23222.40 23222.40 23222.40 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 47152.09 47152.09 40197.16 893767.83 1386.83  

1513656.0
  Total Cost (` in Lakhs) 17066.06 49851.61 59002.13 85647.46 86456.06 86974.82 87494.68 87577.75 87606.41 87636.34 87667.61 87690.68 87579.58 86960.77 86372.92 86408.68 85789.85 85377.71 84494.92 2348.68  
5

  Total Profits (` in Lakhs) 6156.34 -26629.21 -35779.73 -32601.36 -33409.96 -33928.72 -34448.58 -34531.65 -34560.31 -34590.24 -34621.51 -34644.58 -34533.48 -33914.67 -33326.82 -33362.58 -38637.76 -38225.62 -44297.77 -619888.22 -961.86  
ADD - ON SLIDES

Appendix - C.3
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Option - I (Total Coal & OB Departmental) - Incremental 4.5 Mtpa
Statement Showing Economics at Different Capacity Utilisation

Option - I (Incremental- 4.5 Mtpa)


Sl Capacity Utilisation
Particulars
No. 100% 90% 85% 80% 75%
1 Output (Mtpa) 4.50 4.05 3.83 3.60 3.38
2 Cost/Te (`/t) 2077.31 2248.17 2348.68 2461.76 2589.91
3 Selling Price (`/t) 1386.83 1386.83 1386.83 1386.83 1386.83
4 Profit (`/t) -690.48 -861.35 -961.86 -1074.93 -1203.08
5 IRR (%) -ve -ve -ve -ve -ve
6 DSP to yield 12%IRR 2532.72 2752.74 2882.16 3027.77 3192.78
ADD - ON SLIDES

Appendix - C.4
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Option - I (Total Coal & OB Departmental) - Incremental 4.5 Mtpa
Statement showing Sensitivity of IRR

Option - I (Incremental- 4.5 Mtpa)


Capacity Utilisation
Sl No. Particulars
100% 90% 85% 80% 75%
A Base Case -ve -ve -ve -ve -ve
B Increase in Capital          
  1)5% -ve -ve -ve -ve -ve
  2)10% -ve -ve -ve -ve -ve
  3)15% -ve -ve -ve -ve -ve
C Increase in Op.Cost          
  1)5% -ve -ve -ve -ve -ve
  2)10% -ve -ve -ve -ve -ve
  3)15% -ve -ve -ve -ve -ve
D Decrease in Sales          
  1)5% -ve -ve -ve -ve -ve
  2)10% -ve -ve -ve -ve -ve
  3)15% -ve -ve -ve -ve -ve
E Increase in Cap.+Op.Cost          
  1)5% -ve -ve -ve -ve -ve
  2)10% -ve -ve -ve -ve -ve
  3)15% -ve -ve -ve -ve -ve
ADD - ON SLIDES

Appendix - D

RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)

Option - I (Total Coal & OB Departmental) - Incremental 4.5 Mtpa

Statement Showing Estimated Cash Flow Analysis

(Pre-Tax IRR on Total Capital)

At 100% capacity utilisation

Option - I (Incremental- 4.5 Mtpa)             (Amt. in ` Lakhs)

Sl.
Particulars Existing Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total
No.

1 Initial Capital     182099.77 66374.19 105642.09                               354116.05

2 Replacement Capital             182.00 731.00   182.00 731.00 9417.62 9084.36 8657.06 5611.47 182.00 876.20 145.60   -9125.69 26674.61

3 Less: GST credit on Capital Goods     1366.02 1366.02 3120.36 3120.36 3120.36 3120.36 3120.36 3120.36 3120.36 3120.36 3120.36 3120.36 3120.36 3120.36 3120.36 1900.81     45197.53

4 Cash Operating Expenses   18023.14 42051.11 47336.39 68197.48 69016.52 69554.64 70093.86 70179.22 70208.01 70238.07 70269.46 70291.42 70155.26 69421.52 68723.92 68759.68 68255.73 67874.83 67335.93 1215986.18

5 Total Cash Outflow   18023.14 222784.86 112344.55 170719.21 65896.16 66616.28 67704.50 67058.86 67269.65 67848.71 76566.72 76255.41 75691.96 71912.63 65785.57 66515.52 66500.51 67874.83 58210.24 1551579.31

6 Inflow from Sales   27320.47 27320.47 27320.47 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 55473.04 55473.04 47290.77 1051491.56

- -
7 Net Cash Flow   9297.33 -85024.07 -3488.99 -4209.11 -5297.32 -4651.69 -4862.47 -5441.53 -14159.54-13848.24-13284.79 -9505.45 -3378.39 -4108.35 -11027.47 -12401.78 -10919.47 -500087.75
195464.38 108312.04

8 Coal Production (Lakh Tonnes)   19.70 19.70 19.70 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 40.00 40.00 34.10 758.20

9 Pre Tax Internal rate of return       -ve                                  

Desired Selling Price to Yield 12% IRR


10       2532.72                                  
(`/t)

-
11 Net Present Value (` Lakhs)                                        
307155.78
ADD - ON SLIDES

Appendix - D.1

RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)

Option - I (Total Coal & OB Departmental) - Incremental 4.5 Mtpa

Statement Showing Estimated Cash Flow Analysis

(Pre-Tax IRR on Total Capital)

At 85% capacity utilisation

Option - I (Incremental- 4.5 Mtpa) (Amount in Rs. Lakhs)

Sl.
Particulars Existing Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total
No.

1 Initial Capital     182099.77 66374.19 105642.09                               354116.05

2 Replacement Capital             182.00 731.00   182.00 731.00 9417.62 9084.36 8657.06 5611.47 182.00 876.20 145.60   -9125.69 26674.61

3 Less: GST credit on Capital Goods     1366.02 1366.02 3120.36 3120.36 3120.36 3120.36 3120.36 3120.36 3120.36 3120.36 3120.36 3120.36 3120.36 3120.36 3120.36 1900.81     45197.53

4 Cash Operating Expenses   16457.17 39790.16 44996.55 64690.77 65499.36 66018.13 66537.98 66621.05 66649.72 66679.65 66710.92 66733.99 66622.89 66004.07 65416.23 65451.99 64987.69 64626.97 64133.04 1154628.32

5 Total Cash Outflow   16457.17 220523.90 110004.71 167212.50 62379.00 63079.77 64148.63 63500.70 63711.36 64290.29 73008.17 72697.99 72159.59 68495.18 62477.87 63207.83 63232.48 64626.97 55007.35 1490221.45

6 Inflow from Sales   23222.40 23222.40 23222.40 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 47152.09 47152.09 40197.16 893767.83

- -
7 Net Cash Flow   6765.24 -86782.31 -9332.91 -10033.67 -11102.53-10454.60-10665.26-11244.19-19962.07-19651.89-19113.49-15449.08 -9431.77 -10161.73 -16080.39 -17474.88 -14810.19 -596453.62
197301.50 114166.40

8 Coal Production (Lakh Tonnes)   16.75 16.75 16.75 38.25 38.25 38.25 38.25 38.25 38.25 38.25 38.25 38.25 38.25 38.25 38.25 38.25 34.00 34.00 28.99 644.47

9 Pre Tax Internal rate of return       -ve                                  

Desired Selling Price to Yield 12% IRR


10       2882.16                                  
(`/t)

-
11 Net Present Value (` Lakhs)                                        
340701.03
ADD - ON SLIDES

Appendix - A
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)

STATEMENT OF ESTIMATED CAPITAL INVESTMENT AND YEARWISE PHASING


Option - II (Total Coal Departmentaln & Total OB Outsourced) - 8 Mtpa
Base Date: October, 2018
Option - II (Integrated - 8 Mtpa) (Amt. in ` Lakhs)
PHASING OF CAPITAL
TOTAL TOTAL EXISTING BALANCE
COMMITTED
SL SANCTIONED PROVN AS ON INCREMENTAL
PARTICULARS EXPENSES
NO CAPITAL (8 31.03.18 PROVISION Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7
FOR 3.5 Mtpa
(3.5 Mtpa) Mtpa) (3.5 Mtpa) (4.5 Mtpa)

1 Land 858 25522 5755   19767   988 18779        


2 Buildings                        
  Service 2279 5846 296   5550     1110 4440      
  Residential 1371 5158 1755   3402     680 2722      
3 Plant & Machinery                        
  a) HEMM 8298 13826 8060   5766     257 5509      
  b) Others than HEMM 23201 39454 24374   15080     4428 10652      
4 Furniture & Fittings 98 277 218   58     29 29      
5 Railway Siding 3600 8516 4889 3627                
6 Vehicles 308 939 228   711     240 471      
7 Prospecting & Boring 115 44 44                  
8 Development.                        
8.1 Capital Outlay in Mines 7125 40695 2652 204 37839   1725 33450 2664      
8.2 Roads & Culverts 2417 3712 460 106 3146     629 2517      
8.3 Water Supply & Sewerage 1842 6617 1031   5586     1117 4469      
8.4 Scientific Research 50 80     80     80        
8.5 PR Preparation Cost 497 1762     1762   1762          
9.1 Revenue Exp. Capitalised                      
618
  less Depreciation                      
10 Land Reclamation 831 2456 1333   1123     595 527      
  INITIAL CAPITAL 53510 154903 51096 3936 99871   4476 61394 34002      
ADD - ON SLIDES

Appendix - C
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Option - II (Total Coal Departmentaln & Total OB Outsourced) - 8 Mtpa

Statement Showing Average Cost of Production

Option - II (Integrated - 8 Mtpa)

Sl. Total Coal OB Common


Particulars
No.
(`/t) (`/t) (`/m3) (`/t)
1 Salary & Wages 146.49 39.48 1.31 101.32
2 Stores 156.14 84.12 8.90 33.50
3 Power 34.83 7.01   27.81
4 Misc. Expenses 36.07 5.96 0.03 29.96
5 Adminstrative Cost (Cash) 3.62     3.62
6 Mine closure Cost 18.88     18.88
7 OB Outsourcing Cost 479.78   110.88  
8 COAL Outsourcing Cost        
9 Interest on Working capital 42.33 6.60 5.85 10.40
10 Total cash Cost 918.14 143.18 126.99 225.49
11 Interest        
12 Adminstrative Cost (Notional) 30.91     30.91
13 Depreciation 124.51 43.34   81.18
  Total 1073.56 186.52 126.99 337.57
14 Common cost apportioned to coal & OB   44.55 67.72  
  Total   231.07 194.71  
15 OB Cost Charged to coal   842.49    
  Total Cost   1073.56    
ADD - ON SLIDES

Appendix - C.1
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)

Statement Showing Estimated Year wise Operating Cost at 100% capacity utilisation
Option - II (Total Coal Departmentaln & Total OB Outsourced) - 8 Mtpa
Option - II (Integrated - 8 Mtpa) (Amt. in ` Lakhs)
Avg % of
Sl.
Particulars Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total Cost Cost Total
No.
(`/t) Cost

1 Salary & Wages 6872.42 6995.38 9153.36 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 202262.44 146.49 13.65

2 Stores 8103.21 9014.77 9418.19 12558.35 12558.35 12558.35 12558.35 12558.35 12558.35 12558.35 12558.35 12551.23 12391.89 11661.03 10768.16 10768.16 10507.50 10247.73 9685.38 215584.07 156.14 14.54

3 Power   333.85 946.06 1894.72 2147.96 2567.13 2986.29 3083.48 3090.32 3097.16 3104.00 3104.00 3104.00 3104.00 3104.00 3104.00 3104.00 3104.00 3104.00 48082.92 34.83 3.24

4 Misc. Expenses 1554.24 1700.09 1942.63 2540.12 2837.84 2837.84 2837.84 2837.84 2837.84 2837.84 2837.84 2837.84 2837.84 2837.84 2837.84 2837.84 2759.09 2680.34 2574.82 49805.45 36.07 3.36

Adminstrative Cost
5 198.00 198.00 198.00 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 253.39 217.19 168.68 4997.84 3.62 0.34
(Cash)
6 Mine Closure Cost 853.47 896.14 940.95 987.99 1037.39 1089.26 1143.73 1200.91 1260.96 1324.01 1390.21 1459.72 1532.70 1609.34 1689.81 1774.30 1863.01 1956.16 2053.97 26064.03 18.88 1.76

7 OB Outsourcing 25015.16 36369.56 36369.56 44353.12 44353.12 44353.12 44353.12 44353.12 44353.12 44353.12 44353.12 44264.42 42279.61 33176.14 22054.59 22054.59 19293.61 16543.71 10190.13 662436.05 479.78 44.69

8 Coal Outsourcing                                            

Interest on Working
9 2058.83 2682.88 2850.16 3568.28 3597.30 3620.06 3642.96 3650.42 3653.65 3657.03 3660.56 3659.29 3559.18 3087.56 2510.75 2514.83 2367.52 2221.00 1884.01 58446.25 42.33 3.94
capital

10 Total Cash Cost 44655.33 58190.67 61818.90 77394.75 78024.13 78517.93 79014.46 79176.29 79246.41 79319.67 79396.24 79368.65 77197.38 66968.07 54457.31 54545.89 51350.69 48172.71 40863.56 1267679.06 918.14 85.52

11 Interest                                            

Adminstrative Cost
12 1690.68 1690.68 1690.68 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2163.57 1854.49 1440.32 42674.94 30.91 2.88
(Notional)

13 Depreciation 3600.24 3853.96 7505.26 9831.40 9834.54 9834.54 9834.95 9834.95 9848.40 9849.00 9849.60 9850.29 9850.29 9850.29 9850.29 9850.29 9850.29 9850.29 9286.09 171914.95 124.51 11.60

  Total 49946.25 63735.31 71014.84 89698.81 90331.32 90825.13 91322.06 91483.89 91567.47 91641.33 91718.49 91691.60 89520.33 79291.01 66780.26 66868.83 63364.56 59877.49 51589.97 1482268.95 1073.56 100.00

  Cost (`/t) 913.09 1165.18 1298.26 1121.24 1129.14 1135.31 1141.53 1143.55 1144.59 1145.52 1146.48 1146.14 1119.00 991.14 834.75 835.86 905.21 997.96 1107.08 1073.56    

  Fixed Cost (`/t) 334.77 350.18 477.53 427.05 434.13 438.93 443.77 445.47 446.49 447.40 448.34 449.26 450.21 451.22 452.27 453.38 514.52 596.12 747.64 458.64   42.72

  Variable Cost (`/t) 578.32 815.00 820.73 694.18 695.01 696.39 697.76 698.08 698.10 698.12 698.14 696.89 668.79 539.92 382.48 382.48 390.69 401.84 359.44 614.92   57.28

106823.6 102211.3 103605.6 106770.8 108376.1 117849.1 120733.6 106088.6 106088.6


  Total Sales (` in Lakhs) 95384.32 87101.30 87101.30 111999.99 107816.29105646.59106774.26
8 8 4 7 6 7 9 5 5
92827.57 79566.49 62024.82 1914790.82 1386.83  

  Total Cost (` in Lakhs) 49946.25 63735.31 71014.84 89698.81 90331.32 90825.13 91322.06 91483.89 91567.47 91641.33 91718.49 91691.60 89520.33 79291.01 66780.26 66868.83 63364.56 59877.49 51589.97 1482268.95 1073.56  

  Total Profits (` in Lakhs) 45438.07 23365.99 16086.46 22301.17 17484.97 14821.47 15452.20 15339.79 10643.92 11964.31 15052.38 16684.56 28328.84 41442.67 39308.39 39219.82 29463.01 19689.00 10434.85 432521.87 313.26  
ADD - ON SLIDES

Appendix - C.2
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Statement Showing Estimated Year wise operating cost at 85% capacity utilisation
Option - II (Total Coal Departmentaln & Total OB Outsourced) - 8 Mtpa
(Amt. in ` Lakhs)
Option - II (Integrated - 8 Mtpa)
Avg % of
Sl.
Particulars Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total Cost Cost Total
No.
(`/t) Cost

1 Salary & Wages 6872.42 6995.38 9153.36 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 202262.44 172.34 14.93

2 Stores 7423.80 8198.63 8583.19 11476.57 11476.57 11476.57 11476.57 11476.57 11476.57 11476.57 11476.57 11470.51 11335.07 10713.85 9954.91 9954.91 9733.34 9512.53 9034.54 197727.81 168.48 14.59

3 Power   321.33 910.58 1823.67 2067.41 2470.86 2874.31 2967.85 2974.43 2981.01 2987.60 2987.60 2987.60 2987.60 2987.60 2987.60 2987.60 2987.60 2987.60 46279.81 39.43 3.42

4 Misc. Expenses 1459.58 1605.43 1844.95 2399.80 2697.52 2697.52 2697.52 2697.52 2697.52 2697.52 2697.52 2697.52 2697.52 2697.52 2697.52 2697.52 2630.59 2563.65 2473.95 47348.25 40.34 3.49

Adminstrative Cost
5 198.00 198.00 198.00 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 253.39 217.19 168.68 4997.84 4.26 0.37
(Cash)
6 Mine Closure Cost 853.47 896.14 940.95 987.99 1037.39 1089.26 1143.73 1200.91 1260.96 1324.01 1390.21 1459.72 1532.70 1609.34 1689.81 1774.30 1863.01 1956.16 2053.97 26064.03 22.21 1.92

7 OB Outsourcing 21262.89 30914.13 30914.13 37700.15 37700.15 37700.15 37700.15 37700.15 37700.15 37700.15 37700.15 37624.75 35937.67 28199.71 18746.40 18746.40 16399.57 14062.16 8661.61 563070.65 479.78 41.56

8 Coal Outsourcing                                            

Interest on Working
9 1840.06 2374.57 2539.68 3184.22 3212.78 3234.78 3256.91 3264.20 3267.42 3270.79 3274.30 3273.73 3189.17 2788.84 2299.14 2303.22 2178.39 2054.26 1768.17 52574.62 44.80 3.88
capital

10 Total Cash Cost 39910.21 51503.60 55084.84 69064.57 69683.99 70161.31 70641.36 70799.37 70869.22 70942.22 71018.52 71006.00 69171.89 60489.03 49867.54 49956.11 47248.46 44556.12 38351.10 1140325.45 971.65 84.16

11 Interest                                            

Adminstrative Cost
12 1690.68 1690.68 1690.68 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2163.57 1854.49 1440.32 42674.94 36.36 3.15
(Notional )

13 Depreciation 3600.24 3853.96 7505.26 9831.40 9834.54 9834.54 9834.95 9834.95 9848.40 9849.00 9849.60 9850.29 9850.29 9850.29 9850.29 9850.29 9850.29 9850.29 9286.09 171914.95 146.49 12.69

  Total 45201.13 57048.24 64280.78 81368.62 81991.18 82468.50 82948.96 83106.97 83190.28 83263.87 83340.77 83328.94 81494.84 72811.97 62190.48 62279.06 59262.32 56260.91 49077.51 1354915.34 1154.50 100.00

  Cost (`/t) 972.17 1226.98 1382.53 1196.60 1205.75 1212.77 1219.84 1222.16 1223.39 1224.47 1225.60 1225.43 1198.45 1070.76 914.57 915.87 996.01 1103.16 1239.02 1154.50    

  Fixed Cost (`/t) 393.85 411.98 561.80 502.42 510.74 516.39 522.08 524.08 525.29 526.35 527.46 528.54 529.66 530.84 532.08 533.39 605.32 701.31 879.58 539.58   46.74

  Variable Cost (`/t) 578.32 815.00 820.73 694.18 695.01 696.39 697.76 698.08 698.10 698.12 698.14 696.89 668.79 539.92 382.48 382.48 390.69 401.84 359.44 614.92   53.26

100171.8 102623.6
  Total Sales (` in Lakhs) 81076.67 74036.10 74036.10 95199.99 91643.85 89799.60 90758.12 90800.13 86879.68 88064.80 90755.24 92119.74
0 3
90175.35 90175.35 78903.43 67631.51 52721.10 1627572.20 1386.83  

  Total Cost (` in Lakhs) 45201.13 57048.24 64280.78 81368.62 81991.18 82468.50 82948.96 83106.97 83190.28 83263.87 83340.77 83328.94 81494.84 72811.97 62190.48 62279.06 59262.32 56260.91 49077.51 1354915.34 1154.50  

  Total Profits (` in Lakhs) 35875.54 16987.86 9755.33 13831.36 9652.67 7331.10 7809.16 7693.16 3689.40 4800.92 7414.47 8790.80 18676.96 29811.66 27984.87 27896.29 19641.11 11370.61 3643.58 272656.86 232.33  
ADD - ON SLIDES

Appendix - C.3
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Option - II (Total Coal Departmentaln & Total OB Outsourced) - 8 Mtpa
Statement Showing Economics at Different Capacity Utilisation

Option - II (Integrated - 8 Mtpa)

Capacity Utilisation
Sl No. Particulars
100% 90% 85% 80% 75%

1 Output (Mtpa) 8.00 7.20 6.80 6.40 6.00

2 Cost/t (`) 1073.56 1124.52 1154.50 1188.22 1226.44

3 Selling Price (`/t) 1386.83 1386.83 1386.83 1386.83 1386.83

4 Profit (`/t) 313.26 262.30 232.33 198.60 160.38

5 IRR (%) 81.02% 51.63% 39.21% 29.44% 21.88%


ADD - ON SLIDES

Appendix - C.4
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Option - II (Total Coal Departmentaln & Total OB Outsourced) - 8 Mtpa
Statement showing Sensitivity of IRR
Option - II (Integrated - 8 Mtpa)
Capacity Utilisation
Sl No. Particulars
100% 90% 85% 80% 75%
A Base Case 81.02% 51.63% 39.21% 29.44% 21.88%
B Increase in Capital          
  1)5% 77.27% 47.86% 36.17% 27.20% 20.26%
  2)10% 73.35% 44.24% 33.39% 25.19% 18.80%
  3)15% 69.26% 40.84% 30.88% 23.38% 17.47%
C Increase in Op.Cost          
  1)5% 64.73% 38.07% 28.61% 21.38% 15.60%
  2)10% 47.67% 27.00% 20.27% 14.89% 10.31%
  3)15% 32.65% 18.62% 13.73% 9.53% 5.72%
D Decrease in Sales          
  1)5% 54.20% 32.23% 24.64% 18.62% 13.60%
  2)10% 31.64% 19.26% 14.67% 10.66% 7.01%
  3)15% 17.64% 10.37% 7.22% 4.22% 1.29%
E Increase in Cap.+Op.Cost          
  1)5% 60.52% 34.99% 26.38% 19.77% 14.41%
  2)10% 39.95% 22.97% 17.36% 12.71% 8.63%
  3)15% 25.22% 14.79% 10.82% 7.25% 3.92%
ADD - ON SLIDES

Appendix - D

RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)


Option - II (Total Coal Departmentaln & Total OB Outsourced) - 8 Mtpa
Statement Showing Estimated Cash Flow Analysis
(Pre-Tax IRR on Total Capital)
At 100% capacity utilisation
Option - II (Integrated - 8 Mtpa)                             (Amt. in ` Lakhs)

Sl.
Particulars Existing Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total
No.

1 Initial Capital 31326.68   4475.79 61393.56 34001.84                               131197.87

-
2 Replacement Capital     507.10 6267.15 6344.53 1858.92 384.15 4733.49 361.90 303.12 2457.13 506.24 6162.03 11133.69 5198.35 812.85 3058.39 1763.74   24254.5 27598.17
9

Less: GST credit on


3     70.00 1650.52 3118.98 279.26 58.60 721.24 55.20 27.76 373.63 70.00 911.97 1648.65 788.67 122.68 444.39 246.02     10587.58
Capital Goods

Cash Operating 78024.1 78517.9 79014.4 79176.2 79246.4 79319.6 79396.2 79368.6 66968.0 54457.3 54545.8 48172.7 40863.5 1267679.0
4   44655.33 58190.67 61818.90 77394.75 77197.38 51350.69
Expenses 3 3 6 9 1 7 4 5 7 1 9 1 6 6

79603.7 78843.4 83026.7 79482.9 79521.7 81403.1 79832.4 84618.7 71377.7 55147.4 57159.8 48172.7 16608.9 1415887.5
5 Total Cash Outflow 31326.68 44655.33 63103.56 127829.09 114622.15 86682.42 52868.42
9 9 0 8 7 7 8 2 5 8 9 1 7 2

107816. 105646. 106774. 106823. 102211. 103605. 106770. 108376. 120733. 106088. 106088. 79566.4 62024.8 1914790.8
6 Inflow from Sales   95384.32 87101.30 87101.30 111999.99 117849.17 92827.57
29 59 26 68 38 64 87 16 69 65 65 9 2 2

28212.5 26803.1 23747.5 27340.7 22689.6 22202.4 26938.4 23757.4 49355.9 50941.1 48928.7 31393.7 45415.8
7 Net Cash Flow -31326.68 50728.99 23997.74 -40727.79 -2622.16 31166.75 39959.15 498903.30
0 1 6 0 2 8 0 4 4 7 5 8 5

Coal Production (Lakh


8   54.70 54.70 54.70 80.00 80.00 80.00 80.00 80.00 80.00 80.00 80.00 80.00 80.00 80.00 80.00 80.00 70.00 60.00 46.60 1380.70
Tonnes)
Pre Tax Internal rate of
9       81.02%                                  
return
Desired Selling Price
10       1170.71                                  
to Yield 12% IRR (`/t)

Net Present Value (`


11       132692.77                                  
Lakhs)
ADD - ON SLIDES

Appendix - D.1
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Option - II (Total Coal Departmentaln & Total OB Outsourced) - 8 Mtpa
Statement Showing Estimated Cash Flow Analysis
(Pre-Tax IRR on Total Capital)
At 85% capacity utilisation
Option - II (Integrated - 8 Mtpa) (Amt. in ` Lakhs)

Sl.
Particulars Existing Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total
No.

1 Initial Capital 31326.68   4475.79 61393.56 34001.84                               131197.87

-
2 Replacement Capital     507.10 6267.15 6344.53 1858.92 384.15 4733.49 361.90 303.12 2457.13 506.24 6162.03 11133.69 5198.35 812.85 3058.39 1763.74  
24254.59
27598.17

Less: GST credit on


3     70.00 1650.52 3118.98 279.26 58.60 721.24 55.20 27.76 373.63 70.00 911.97 1648.65 788.67 122.68 444.39 246.02     10587.58
Capital Goods
47248.4
4 Cash Operating Expenses   39910.21 51503.60 55084.84 69064.57 69683.99 70161.31 70641.36 70799.37 70869.22 70942.22 71018.52 71006.00 69171.89 60489.03 49867.54 49956.11
6
44556.12 38351.10 1140325.45

48766.1
5 Total Cash Outflow 31326.68 39910.21 56416.49 121095.03 106291.96 71263.65 70486.86 74653.60 71106.06 71144.58 73025.71 71454.75 76256.06 78656.93 64898.70 50557.70 52570.12
8
44556.12 14096.51 1288533.91

100171.8 102623.6 78903.4


6 Inflow from Sales   81076.67 74036.10 74036.10 95199.99 91643.85 89799.60 90758.12 90800.13 86879.68 88064.80 90755.24 92119.74
0 3
90175.35 90175.35
3
67631.51 52721.10 1627572.20

30137.2
7 Net Cash Flow -31326.68 41166.46 17619.61 -47058.92 -11091.97 20380.20 19312.74 16104.52 19694.07 15735.10 15039.09 19300.49 15863.68 21514.87 37724.93 39617.65 37605.23
5
23075.39 38624.59 339038.28

Coal Production
8   46.50 46.50 46.50 68.00 68.00 68.00 68.00 68.00 68.00 68.00 68.00 68.00 68.00 68.00 68.00 68.00 59.50 51.00 39.61 1173.60
(Lakh Tonnes)
9 Pre Tax Internal rate of return       39.21%                                  

Desired Selling Price to


10       1259.39                                  
Yield 12% IRR (`/t)

11 Net Present Value (` Lakhs)       73551.67                                  


ADD - ON SLIDES

Appendix - A
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)

STATEMENT OF ESTIMATED CAPITAL INVESTMENT AND YEARWISE PHASING


Option - II (Total Coal Departmental & Total OB Outsourced) - Incremental 4.5 Mtpa
Base Date: October, 2018
Option - II (Incremental - 4.5 Mtpa) (Amt. in ` Lakhs)
PHASING OF CAPITAL
TOTAL BALANCE
TOTAL EXISTING AS COMMITTED
SL SANCTIONED INCREMENTA
PARTICULARS PROVN ON 31.03.18 EXPENSES
NO CAPITAL L PROVISION Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7
(8 Mtpa) (3.5 Mtpa) FOR 3.5Mtpa
(3.5 Mtpa) (4.5 Mtpa)

1 Land 858 19767     19767   988 18779        


2 Buildings                        
  Service 2279 5550     5550     1110 4440      
  Residential 1371 3402     3402     680 2722      
3 Plant & Machinery                        
  a) HEMM 8298 5766     5766     257 5509      
  b) Others than HEMM 23201 15080     15080     4428 10652      
4 Furniture & Fittings 98 58     58     29 29      
5 Railway Siding 3600                      
6 Vehicles 308 711     711     240 471      
7 Prospecting & Boring 115                      
8 Development.                        
8.1 Capital Outlay in Mines 7125 37839     37839   1725 33450 2664      
8.2 Roads & Culverts 2417 3146     3146     629 2517      

8.3 Water Supply & Sewerage 1842 5586     5586     1117 4469      

8.4 Scientific Research 50 80     80     80        


8.5 P.R. Prep. Cost 497 1762     1762   1762          
9.1                      
Revenue Exp. Capitalised less
618
  Depreciation                      

10 Land Reclamation 831 1123     1123     595 527      

  INITIAL CAPITAL 53510 99871     99871   4476 61394 34002      


ADD - ON SLIDES

Appendix - C
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)

Option - II (Total Coal Departmental & Total OB Outsourced) - Incremental 4.5 Mtpa

Statement Showing Average Cost of Production

Option - II (Incremental - 4.5 Mtpa)

Sl. Total Coal OB Common


Particulars
No.
(`/t) (`/t) (`/m3) (`/t)
1 Salary & Wages 129.09 32.84 1.43 88.89
2 Stores 109.35 42.18 8.90 21.42
3 Power 32.15 3.55   28.60
4 Misc. Expenses 29.54 3.21 0.04 26.13
5 Adminstrative Cost (Cash) 3.62     3.62
6 Mine closure Cost 13.88     13.88
7 OB Outsourcing Cost 569.78   110.88  
8 COAL Outsourcing Cost        
9 Interest on Working capital 42.89 3.95 5.86 8.82
10 Total cash Cost 930.30 85.73 127.12 191.36
11 Interest        
12 Adminstrative Cost (Notional) 30.91     30.91
13 Depreciation 136.24 22.81   113.44
  Total 1097.45 108.54 127.12 335.71

14 Common cost apportioned to coal & OB   38.10 57.92  

  Total   146.64 185.03  


15 OB Cost Charged to coal   950.81    
  Total Cost   1097.45    
ADD - ON SLIDES

Appendix - C.1
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)

Statement Showing Estimated Year wise Operating Cost at 100% capacity utilisation
Option - II (Total Coal Departmental & Total OB Outsourced) - Incremental 4.5 Mtpa
Option - II (Incremental - 4.5 Mtpa) (Amt. in ` Lakhs)

% of
Sl. Avg Cost
Particulars Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total Cost Total
No. (`/t)
Cost

1 Salary & Wages 2214.27 1478.46 3615.04 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 97874.91 129.09 11.76

2 Stores 799.68 1128.16 1531.58 5569.95 5569.95 5569.95 5569.95 5569.95 5569.95 5569.95 5569.95 5562.83 5403.49 4672.63 3974.72 3974.72 3843.94 3806.55 3649.12 82907.07 109.35 9.96

3 Power   92.81 393.25 929.00 1063.20 1292.93 1522.65 1583.17 1586.00 1588.84 1591.68 1591.68 1591.68 1591.68 1591.68 1591.68 1591.68 1591.68 1591.68 24376.97 32.15 2.93

4 Misc. Expenses 307.27 353.50 518.24 1057.18 1354.91 1354.91 1354.91 1354.91 1354.91 1354.91 1354.91 1354.91 1354.91 1354.91 1354.91 1354.91 1315.53 1315.53 1269.07 22395.22 29.54 2.69

5 Adminstrative Cost (Cash) 71.31 71.31 71.31 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 144.79 144.79 123.43 2744.52 3.62 0.33

6 Mine Closure Cost 344.56 361.79 379.88 398.88 418.82 439.76 461.75 484.84 509.08 534.53 561.26 589.32 618.79 649.73 682.21 716.32 752.14 789.75 829.23 10522.62 13.88 1.26

7 OB Outsourcing 9003.68 13095.26 13095.26 32266.90 32266.90 32266.90 32266.90 32266.90 32266.90 32266.90 32266.90 32178.19 30193.39 21089.91 12396.70 12396.70 11010.66 10544.95 8870.62 432010.50 569.78 51.92

8 Coal Outsourcing                                            

Interest on Working
9 615.80 801.43 947.55 2225.52 2247.36 2259.48 2271.64 2275.68 2276.99 2278.36 2279.79 2276.51 2174.30 1700.47 1248.14 1249.79 1175.43 1152.93 1063.02 32520.20 42.89 3.91
capital

10 Total Cash Cost 13356.58 17382.72 20552.11 48270.77 48744.48 49007.26 49271.14 49358.78 49387.17 49416.83 49447.82 49376.78 47159.89 36882.67 27071.69 27107.45 25494.62 25006.63 23056.63 705352.01 930.30 84.77

11 Interest                                            

Adminstrative Cost
12 608.89 608.89 608.89 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1236.33 1236.33 1053.97 23434.59 30.91 2.82
(Notional)

13 Depreciation   248.66 3891.03 6216.77 6216.77 6216.77 6216.77 6216.77 6216.77 6216.77 6216.77 6216.77 6216.77 6216.77 6216.77 6216.77 6216.77 6165.36 5958.86 103298.63 136.24 12.41

  Total 13965.47 18240.27 25052.04 55878.40 56352.11 56614.89 56878.77 56966.41 56994.80 57024.46 57055.46 56984.42 54767.53 44490.30 34679.33 34715.09 32947.72 32408.32 30069.46 832085.24 1097.45 100.00

  Cost (`/t.) 708.91 925.90 1271.68 1241.74 1252.27 1258.11 1263.97 1265.92 1266.55 1267.21 1267.90 1266.32 1217.06 988.67 770.65 771.45 823.69 810.21 881.80 1097.45    

  Fixed Cost (`/t) 178.97 159.51 493.53 385.46 395.21 399.71 404.24 405.83 406.45 407.09 407.76 408.42 409.10 409.82 410.58 411.37 459.40 459.10 527.68 406.06   37.00

  Variable Cost (`/t) 529.94 766.39 778.14 856.28 857.06 858.40 859.74 860.09 860.10 860.12 860.14 857.91 807.95 578.85 360.07 360.07 364.30 351.11 354.12 691.39   63.00

1051491.5
  Total Sales (` in Lakhs) 27320.47 27320.47 27320.47 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 55473.04 55473.04 47290.77 1386.83  
6

  Total Cost (` in Lakhs) 13965.47 18240.27 25052.04 55878.40 56352.11 56614.89 56878.77 56966.41 56994.80 57024.46 57055.46 56984.42 54767.53 44490.30 34679.33 34715.09 32947.72 32408.32 30069.46 832085.24 1097.45  

  Total Profits (` in Lakhs) 13355.00 9080.21 2268.44 6528.77 6055.06 5792.28 5528.40 5440.76 5412.37 5382.71 5351.72 5422.76 7639.65 17916.87 27727.85 27692.09 22525.33 23064.73 17221.31 219406.32 289.38  
ADD - ON SLIDES

Appendix - C.2
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Statement Showing Estimated Year wise operating cost at 85% capacity utilisation
Option - II (Total Coal Departmental & Total OB Outsourced) - Incremental 4.5 Mtpa
(Amount in Rs. Lakhs)
Option - II (Incremental - 4.5 Mtpa)
% of
Sl. Avg Cost
Particulars Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total Cost Total
No. (`/t)
Cost

1 Salary & Wages 2214.27 1478.46 3615.04 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 97874.91 151.87 12.99

2 Stores 679.73 958.94 1343.50 5000.36 5000.36 5000.36 5000.36 5000.36 5000.36 5000.36 5000.36 4994.30 4858.86 4237.64 3644.41 3644.41 3533.25 3501.47 3367.65 74767.01 116.01 9.92

3 Power   89.33 378.50 894.16 1023.33 1244.44 1465.55 1523.80 1526.53 1529.26 1531.99 1531.99 1531.99 1531.99 1531.99 1531.99 1531.99 1531.99 1531.99 23462.84 36.41 3.11

4 Misc. Expenses 284.00 330.23 491.95 988.26 1285.98 1285.98 1285.98 1285.98 1285.98 1285.98 1285.98 1285.98 1285.98 1285.98 1285.98 1285.98 1252.51 1252.51 1213.02 21244.23 32.96 2.82

5 Adminstrative Cost (Cash) 71.31 71.31 71.31 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 144.79 144.79 123.43 2744.52 4.26 0.36

6 Mine Closure Cost 344.56 361.79 379.88 398.88 418.82 439.76 461.75 484.84 509.08 534.53 561.26 589.32 618.79 649.73 682.21 716.32 752.14 789.75 829.23 10522.62 16.33 1.40

7 OB Outsourcing 7653.13 11130.97 11130.97 27426.86 27426.86 27426.86 27426.86 27426.86 27426.86 27426.86 27426.86 27351.46 25664.38 17926.42 10537.19 10537.19 9359.06 8963.21 7540.03 367208.92 569.78 48.74

8 Coal Outsourcing                                            

Interest on Working
9 543.61 697.02 841.54 1959.04 1980.64 1992.34 2004.09 2008.02 2009.32 2010.68 2012.11 2009.53 1922.86 1520.33 1136.08 1137.73 1074.65 1055.80 979.51 28894.88 44.84 3.83
capital

10 Total Cash Cost 11790.61 15118.04 18252.69 42490.89 42959.32 43213.07 43467.92 43553.18 43581.46 43611.01 43641.89 43585.92 41706.20 32975.42 24641.20 24676.96 23308.84 22899.97 21245.32 626719.93 972.46 83.18

11 Interest                                            

Adminstrative Cost
12 608.89 608.89 608.89 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1236.33 1236.33 1053.97 23434.59 36.36 3.11
(Notional )

13 Depreciation   248.66 3891.03 6216.77 6216.77 6216.77 6216.77 6216.77 6216.77 6216.77 6216.77 6216.77 6216.77 6216.77 6216.77 6216.77 6216.77 6165.36 5958.86 103298.63 160.28 13.71

  Total 12399.50 15975.59 22752.62 50098.52 50566.96 50820.71 51075.56 51160.82 51189.10 51218.65 51249.53 51193.56 49313.83 40583.06 32248.84 32284.60 30761.94 30301.65 28258.14 753453.16 1169.11 100.00

  Cost (`/t.) 740.49 954.05 1358.77 1309.77 1322.01 1328.65 1335.31 1337.54 1338.28 1339.05 1339.86 1338.39 1289.25 1060.99 843.11 844.04 904.76 891.23 974.92 1169.11    

  Fixed Cost (`/t) 210.55 187.66 580.63 453.49 464.95 470.25 475.57 477.45 478.17 478.93 479.72 480.49 481.30 482.14 483.03 483.97 540.47 540.11 620.80 477.71   40.86

  Variable Cost (`/t) 529.94 766.39 778.14 856.28 857.06 858.40 859.74 860.09 860.10 860.12 860.14 857.91 807.95 578.85 360.07 360.07 364.30 351.11 354.12 691.39   59.14

  Total Sales (` in Lakhs) 23222.40 23222.40 23222.40 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 47152.09 47152.09 40197.16 893767.83 1386.83  

  Total Cost (` in Lakhs) 12399.50 15975.59 22752.62 50098.52 50566.96 50820.71 51075.56 51160.82 51189.10 51218.65 51249.53 51193.56 49313.83 40583.06 32248.84 32284.60 30761.94 30301.65 28258.14 753453.16 1169.11  

  Total Profits (` in Lakhs) 10822.90 7246.81 469.78 2947.57 2479.14 2225.39 1970.54 1885.28 1857.00 1827.45 1796.57 1852.54 3732.27 12463.04 20797.26 20761.50 16390.15 16850.44 11939.01 140314.67 217.72  
ADD - ON SLIDES

Appendix - C.3
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)

Option - II (Total Coal Departmental & Total OB Outsourced) - Incremental 4.5 Mtpa

Statement Showing Economics at Different Capacity Utilisation

Option - II (Incremental - 4.5 Mtpa)


Capacity Utilisation
Sl No. Particulars
100% 90% 85% 80% 75%

1 Output (Mtpa) 4.50 4.05 3.83 3.60 3.38

2 Cost (`/t) 1097.45 1142.57 1169.11 1198.96 1232.80

3 Selling Price (`/t) 1386.83 1386.83 1386.83 1386.83 1386.83

4 Profit (`/t) 289.38 244.26 217.72 187.86 154.03

5 IRR (%) 29.15% 20.06% 16.72% 13.75% 11.00%


ADD - ON SLIDES

Appendix - C.4
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Option - II (Total Coal Departmental & Total OB Outsourced) - Incremental 4.5 Mtpa
Statement showing Sensitivity of IRR

Option - II (Incremental - 4.5 Mtpa)


Capacity Utilisation
Sl No. Particulars
100% 90% 85% 80% 75%
A Base Case 29.15% 20.06% 16.72% 13.75% 11.00%
B Increase in Capital          
  1)5% 25.77% 18.27% 15.30% 12.58% 10.02%
  2)10% 23.24% 16.77% 14.05% 11.53% 9.13%
  3)15% 21.22% 15.46% 12.96% 10.60% 8.32%
C Increase in Op.Cost          
  1)5% 21.45% 15.28% 12.65% 10.19% 7.82%
  2)10% 16.08% 11.33% 9.15% 7.03% 4.92%
  3)15% 11.82% 7.93% 6.04% 4.14% 2.22%
D Decrease in Sales          
  1)5% 19.13% 13.74% 11.35% 9.07% 6.85%
  2)10% 12.55% 8.66% 6.78% 4.91% 3.01%
  3)15% 7.30% 4.21% 2.64% 1.02% -0.68%
E Increase in Cap.+Op.Cost          
  1)5% 19.50% 14.00% 11.58% 9.28% 7.03%
  2)10% 13.62% 9.52% 7.57% 5.64% 3.69%
  3)15% 9.25% 5.90% 4.22% 2.52% 0.76%
ADD - ON SLIDES

Appendix - D

RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)


Option - II (Total Coal Departmental & Total OB Outsourced) - Incremental 4.5 Mtpa
Statement Showing Estimated Cash Flow Analysis
(Pre-Tax IRR on Total Capital)
At 100% capacity utilisation

Option - II (Incremental - 4.5 Mtpa)           (Amt. in ` Lakhs)

Sl.
Particulars Existing Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total
No.

1 Initial Capital     4475.79 61393.56 34001.84                               99871.19

2 Replacement Capital             182.00 731.00   182.00 731.00   819.23 5538.75 1879.76 182.00 876.20 145.60   -3371.03 7896.51

3 Less: GST credit on Capital Goods       706.76 2151.99   27.76 111.51   27.76 111.51   110.58 795.19 286.74 27.76 111.51       4469.07

4 Cash Operating Expenses   13356.58 17382.72 20552.11 48270.77 48744.48 49007.26 49271.14 49358.78 49387.17 49416.83 49447.82 49376.78 47159.89 36882.67 27071.69 27107.45 25494.62 25006.63 23056.63 705352.01

5 Total Cash Outflow   13356.58 21858.51 81238.91 80120.62 48744.48 49161.49 49890.63 49358.78 49541.40 50036.32 49447.82 50085.43 51903.46 38475.68 27225.93 27872.14 25640.22 25006.63 19685.61 808650.65

6 Inflow from Sales   27320.47 27320.47 27320.47 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 55473.04 55473.04 47290.77 1051491.56

7 Net Cash Flow   13963.89 5461.96 -53918.44 -17713.44 13662.70 13245.68 12516.55 13048.40 12865.77 12370.86 12959.35 12321.75 10503.72 23931.49 35181.25 34535.03 29832.82 30466.41 27605.16 242840.92

8 Coal Production (Lakh Tonnes)   19.70 19.70 19.70 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 40.00 40.00 34.10 758.20

9 Pre Tax Internal rate of return       29.15%                                  

Desired Selling Price to Yield 12%


10       1241.44                                  
IRR (`/t)

11 Net Present Value (` Lakhs)       38969.55                                  


ADD - ON SLIDES

Appendix - D.1

RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)

Option - II (Total Coal Departmental & Total OB Outsourced) - Incremental 4.5 Mtpa

Statement Showing Estimated Cash Flow Analysis

(Pre-Tax IRR on Total Capital)

At 85% capacity utilisation

Option - II (Incremental - 4.5 Mtpa) (Amt. in ` Lakhs)

Sl.
Particulars Existing Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total
No.

1 Initial Capital     4475.79 61393.56 34001.84                               99871.19

2 Replacement Capital             182.00 731.00   182.00 731.00   819.23 5538.75 1879.76 182.00 876.20 145.60   -3371.03 7896.51

3 Less: GST credit on Capital Goods       706.76 2151.99   27.76 111.51   27.76 111.51   110.58 795.19 286.74 27.76 111.51       4469.07

4 Cash Operating Expenses   11790.61 15118.04 18252.69 42490.89 42959.32 43213.07 43467.92 43553.18 43581.46 43611.01 43641.89 43585.92 41706.20 32975.42 24641.20 24676.96 23308.84 22899.97 21245.32 626719.93

5 Total Cash Outflow   11790.61 19593.84 78939.50 74340.74 42959.32 43367.31 44087.41 43553.18 43735.70 44230.50 43641.89 44294.57 46449.76 34568.44 24795.44 25441.65 23454.44 22899.97 17874.29 730018.56

6 Inflow from Sales   23222.40 23222.40 23222.40 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 47152.09 47152.09 40197.16 893767.83

7 Net Cash Flow   11431.80 3628.57 -55717.09 -21294.64 10086.78 9678.79 8958.69 9492.92 9310.40 8815.60 9404.21 8751.53 6596.34 18477.66 28250.66 27604.45 23697.64 24252.12 22322.87 163749.27

8 Coal Production (Lakh Tonnes)   16.75 16.75 16.75 38.25 38.25 38.25 38.25 38.25 38.25 38.25 38.25 38.25 38.25 38.25 38.25 38.25 34.00 34.00 28.99 644.47

9 Pre Tax Internal rate of return       16.72%                                  

Desired Selling Price to Yield 12% IRR


10       1326.60                                  
(`/t)

11 Net Present Value (` Lakhs)       13721.12                                  


ADD - ON SLIDES

Appendix - A
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)

STATEMENT OF ESTIMATED CAPITAL INVESTMENT AND YEARWISE PHASING


Option - III (a) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines for Dumping) - 8 Mtpa
Base Date: October, 2018
Option - III (a) (Integrated - 8 Mtpa) (Amt. in ` Lakhs)
PHASING OF CAPITAL
TOTAL EXISTING BALANCE
TOTAL COMMITTED
SL. SANCTIONED AS ON INCREMENTAL
PARTICULARS PROVN EXPENSES
NO. CAPITAL 31.03.18 (3.5 PROVISION Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7
(8 Mtpa) FOR 3.5 Mtpa
(3.5 Mtpa) Mtpa) (4.5 Mtpa)

1 Land 858 25522 5755   19767   988 18779        


2 Buildings                        
  Service 2279 5846 296   5550     1110 4440      
  Residential 1371 5158 1755   3402     680 2722      
3 Plant & Machinery                        
  a) HEMM 8298 13826 8060   5766     257 5509      
  b) Others than HEMM 23201 39454 24374   15080     4428 10652      
4 Furniture & Fittings 98 277 218   58     29 29      
5 Railway Siding 3600 8516 4889 3627                
6 Vehicles 308 939 228   711     240 471      
7 Prospecting & Boring 115 44 44                  
8 Development.                        
8.1 Capital Outlay in Mines 7125 40695 2652 204 37839   1725 33450 2664      
8.2 Roads & Culverts 2417 11560 460 106 10994     2199 8795      
Water Supply &
8.3 1842 6617 1031   5586     1117 4469      
Sewerage
8.4 Scientific Research 50 80     80     80        
8.5 P.R. Prep. Cost 497 1762     1762   1762          
9.1 Revenue Exp.                      
Capitalised less 618
  Depreciation                      
10 Land Reclamation 831 2456 1333   1123     595 527      
  INITIAL CAPITAL 53510 162751 51096 3936 107719   4476 62963 40280      
ADD - ON SLIDES

Appendix - C
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)

Option - III (a) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines
for Dumping) - 8 Mtpa

Statement Showing Average Cost of Production

Option - III (a) (Integrated - 8 Mtpa)


Sl. Total Coal OB Common
Particulars
No.
(`/t) (`/t) (`/m3) (`/t)
1 Salary & Wages 146.49 39.48 1.31 101.32
2 Stores 156.14 84.12 8.90 33.50
3 Power 34.83 7.01   27.81
4 Misc. Expenses 37.89 5.96 0.03 31.77
5 Adminstrative Cost (Cash) 3.62     3.62
6 Mine closure Cost 18.88     18.88
7 OB Outsourcing Cost 508.64   117.55  
8 COAL Outsourcing Cost        
9 Interest on Working capital 43.81 6.60 6.18 10.48
10 Total cash Cost 950.29 143.18 133.98 227.39
11 Interest        
12 Adminstrative Cost (Notional) 30.91     30.91
13 Depreciation 130.20 43.34   86.86
  Total 1111.40 186.52 133.98 345.16

14 Common cost apportioned to coal & OB   45.55 69.24  


  Total   232.07 203.22  
15 OB Cost Charged to coal   879.32    
  Total Cost   1111.40    
ADD - ON SLIDES

Appendix - C.1
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)

Statement Showing Estimated Year wise Operating Cost at 100% capacity utilisation
Option - III (a) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines for Dumping) - 8 Mtpa
Option - III (a) (Integrated - 8 Mtpa) (Amt. in ` Lakhs)

Sl. Avg Cost % of Total


Particulars Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total Cost
No. (`/t) Cost

1 Salary & Wages 6872.42 6995.38 9153.36 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 202262.44 146.49 13.18

2 Stores 8103.21 9014.77 9418.19 12558.35 12558.35 12558.35 12558.35 12558.35 12558.35 12558.35 12558.35 12551.23 12391.89 11661.03 10768.16 10768.16 10507.50 10247.73 9685.38 215584.07 156.14 14.05

3 Power   333.85 946.06 1894.72 2147.96 2567.13 2986.29 3083.48 3090.32 3097.16 3104.00 3104.00 3104.00 3104.00 3104.00 3104.00 3104.00 3104.00 3104.00 48082.92 34.83 3.13

4 Misc. Expenses 1554.24 1700.09 1942.63 2573.08 3002.64 3002.64 3002.64 3002.64 3002.64 3002.64 3002.64 3002.64 3002.64 3002.64 3002.64 3002.64 2923.89 2845.14 2739.62 52310.41 37.89 3.41

5 Adminstrative Cost (Cash) 198.00 198.00 198.00 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 253.39 217.19 168.68 4997.84 3.62 0.33

6 Mine Closure Cost 853.47 896.14 940.95 987.99 1037.39 1089.26 1143.73 1200.91 1260.96 1324.01 1390.21 1459.72 1532.70 1609.34 1689.81 1774.30 1863.01 1956.16 2053.97 26064.03 18.88 1.70

7 OB Outsourcing 25015.16 36369.56 38725.20 46708.76 46708.76 46708.76 46708.76 46708.76 46708.76 46708.76 46708.76 46620.05 44635.25 35531.77 24410.23 24410.23 21649.25 18832.84 12407.20 702276.81 508.64 45.77

8 Coal Outsourcing                                            

Interest on Working
9 2058.83 2682.88 2964.01 3683.73 3719.12 3741.88 3764.78 3772.24 3775.47 3778.85 3782.38 3781.11 3681.00 3209.38 2632.57 2636.66 2489.34 2339.61 1999.14 60492.96 43.81 3.94
capital
1312071.4
10 Total Cash Cost 44655.33 58190.67 64288.39 79898.80 80666.39 81160.19 81656.72 81818.55 81888.67 81961.93 82038.50 82010.91 79839.64 69610.33 57099.57 57188.15 53992.95 50745.24 43360.56 950.29 85.50
9

11 Interest                                            

Adminstrative Cost
12 1690.68 1690.68 1690.68 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2163.57 1854.49 1440.32 42674.94 30.91 2.78
(Notional)

13 Depreciation 3600.24 3853.96 7597.58 10316.11 10319.24 10319.24 10319.65 10319.65 10333.11 10333.71 10334.30 10335.00 10335.00 10335.00 10335.00 10335.00 10335.00 10335.00 9770.79 179762.59 130.20 11.71

1534509.0
  Total 49946.25 63735.31 73576.66 92687.56 93458.29 93952.09 94449.02 94610.86 94694.44 94768.30 94845.46 94818.56 92647.30 82417.98 69907.22 69995.80 66491.52 62934.73 54571.67 1111.40 100.00
3

  Cost (`/t) 913.09 1165.18 1345.09 1158.59 1168.23 1174.40 1180.61 1182.64 1183.68 1184.60 1185.57 1185.23 1158.09 1030.22 873.84 874.95 949.88 1048.91 1171.07 1111.40    

  Fixed Cost (`/t) 334.77 350.18 479.22 433.54 442.35 447.15 451.99 453.69 454.71 455.61 456.56 457.48 458.43 459.44 460.49 461.60 523.91 607.07 761.75 466.23   41.95

  Variable Cost (`/t) 578.32 815.00 865.87 725.05 725.88 727.25 728.63 728.95 728.97 728.99 729.01 727.76 699.66 570.79 413.35 413.35 425.97 441.84 409.31 645.17   58.05

1914790.8
  Total Sales (` in Lakhs) 95384.32 87101.30 87101.30 111999.99 107816.29 105646.59 106774.26106823.68102211.38103605.64106770.87108376.16117849.17120733.69106088.65106088.65 92827.57 79566.49 62024.82 1386.83  
2
1534509.0
  Total Cost (` in Lakhs) 49946.25 63735.31 73576.66 92687.56 93458.29 93952.09 94449.02 94610.86 94694.44 94768.30 94845.46 94818.56 92647.30 82417.98 69907.22 69995.80 66491.52 62934.73 54571.67 1111.40  
3

  Total Profits (` in Lakhs) 45438.07 23365.99 13524.64 19312.42 14358.00 11694.50 12325.24 12212.82 7516.95 8837.35 11925.41 13557.60 25201.88 38315.71 36181.42 36092.85 26336.04 16631.76 7453.15 380281.80 275.43  
ADD - ON SLIDES

Appendix - C.2
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Statement Showing Estimated Year wise operating cost at 85% capacity utilisation
Option - III (a) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines for Dumping) - 8 Mtpa
(Amt. in ` Lakhs)
Option - III (a) (Integrated - 8 Mtpa)

Sl. Avg Cost % of Total


Particulars Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total Cost
No. (`/t) Cost

1 Salary & Wages 6872.42 6995.38 9153.36 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 202262.44 172.34 14.44

2 Stores 7423.80 8198.63 8583.19 11476.57 11476.57 11476.57 11476.57 11476.57 11476.57 11476.57 11476.57 11470.51 11335.07 10713.85 9954.91 9954.91 9733.34 9512.53 9034.54 197727.81 168.48 14.11

3 Power   321.33 910.58 1823.67 2067.41 2470.86 2874.31 2967.85 2974.43 2981.01 2987.60 2987.60 2987.60 2987.60 2987.60 2987.60 2987.60 2987.60 2987.60 46279.81 39.43 3.30

4 Misc. Expenses 1459.58 1605.43 1844.95 2432.76 2862.33 2862.33 2862.33 2862.33 2862.33 2862.33 2862.33 2862.33 2862.33 2862.33 2862.33 2862.33 2795.39 2728.45 2638.75 49853.21 42.48 3.56

5 Adminstrative Cost (Cash) 198.00 198.00 198.00 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 253.39 217.19 168.68 4997.84 4.26 0.36

6 Mine Closure Cost 853.47 896.14 940.95 987.99 1037.39 1089.26 1143.73 1200.91 1260.96 1324.01 1390.21 1459.72 1532.70 1609.34 1689.81 1774.30 1863.01 1956.16 2053.97 26064.03 22.21 1.86

7 OB Outsourcing 21262.89 30914.13 32916.42 39702.45 39702.45 39702.45 39702.45 39702.45 39702.45 39702.45 39702.45 39627.05 37939.96 30202.01 20748.69 20748.69 18401.86 16007.91 10546.12 596935.29 508.64 42.61

8 Coal Outsourcing                                            

Interest on Working
9 1840.06 2374.57 2636.46 3282.59 3317.52 3339.53 3361.66 3368.94 3372.16 3375.53 3379.05 3378.47 3293.91 2893.58 2403.88 2407.97 2283.13 2156.27 1867.22 54332.49 46.30 3.88
capital
1178452.9
10 Total Cash Cost 39910.21 51503.60 57183.91 71198.19 71955.82 72433.15 72913.19 73071.21 73141.06 73214.05 73290.35 73277.83 71443.73 62760.86 52139.37 52227.95 49520.29 46768.69 40499.46 1004.14 84.12
2

11 Interest                                            

Adminstrative Cost
12 1690.68 1690.68 1690.68 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2163.57 1854.49 1440.32 42674.94 36.36 3.05
(Notional )

13 Depreciation 3600.24 3853.96 7597.58 10316.11 10319.24 10319.24 10319.65 10319.65 10333.11 10333.71 10334.30 10335.00 10335.00 10335.00 10335.00 10335.00 10335.00 10335.00 9770.79 179762.59 153.17 12.83

1400890.4
  Total 45201.13 57048.24 66472.17 83986.95 84747.72 85225.05 85705.50 85863.52 85946.82 86020.41 86097.31 86085.48 84251.38 75568.51 64947.02 65035.60 62018.86 58958.18 51710.58 1193.67 100.00
6

  Cost (`/t) 972.17 1226.98 1429.66 1235.10 1246.29 1253.31 1260.38 1262.70 1263.92 1265.01 1266.14 1265.96 1238.99 1111.30 955.10 956.41 1042.33 1156.04 1305.49 1193.67    

  Fixed Cost (`/t) 393.85 411.98 563.79 510.05 520.41 526.06 531.75 533.75 534.96 536.02 537.12 538.21 539.33 540.51 541.75 543.06 616.37 714.20 896.18 548.50   45.95

  Variable Cost (`/t) 578.32 815.00 865.87 725.05 725.88 727.25 728.63 728.95 728.97 728.99 729.01 727.76 699.66 570.79 413.35 413.35 425.97 441.84 409.31 645.17   54.05

1627572.2
  Total Sales (` in Lakhs) 81076.67 74036.10 74036.10 95199.99 91643.85 89799.60 90758.12 90800.13 86879.68 88064.80 90755.24 92119.74 100171.80102623.63 90175.35 90175.35 78903.43 67631.51 52721.10 1386.83  
0
1400890.4
  Total Cost (` in Lakhs) 45201.13 57048.24 66472.17 83986.95 84747.72 85225.05 85705.50 85863.52 85946.82 86020.41 86097.31 86085.48 84251.38 75568.51 64947.02 65035.60 62018.86 58958.18 51710.58 1193.67  
6

  Total Profits (` in Lakhs) 35875.54 16987.86 7563.93 11213.03 6896.12 4574.56 5052.62 4936.61 932.85 2044.38 4657.93 6034.26 15920.41 27055.12 25228.33 25139.75 16884.57 8673.33 1010.52 226681.74 193.15  
ADD - ON SLIDES

Appendix - C.3
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Option - III (a) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines for Dumping) - 8 Mtpa

Statement Showing Economics at Different Capacity Utilisation

Option - III (a) (Integrated - 8 Mtpa)

Sl Capacity Utilisation
Particulars
No. 100% 90% 85% 80% 75%
1 Output (Mtpa) 8.00 7.20 6.80 6.40 6.00

2 Cost (`/t) 1111.40 1163.20 1193.67 1227.96 1266.81

3 Selling Price (`/t) 1386.83 1386.83 1386.83 1386.83 1386.83

4 Profit (`/t) 275.43 223.62 193.15 158.87 120.02


5 IRR (%) 72.07% 41.79% 30.95% 22.96% 16.79%
ADD - ON SLIDES

Appendix - C.4
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)

Option - III (a) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines for Dumping) - 8 Mtpa

Statement showing Sensitivity of IRR

Option - III (a) (Integrated - 8 Mtpa)


Capacity Utilisation
Sl No. Particulars
100% 90% 85% 80% 75%
A Base Case 72.07% 41.79% 30.95% 22.96% 16.79%
B Increase in Capital          
  1)5% 67.45% 38.07% 28.31% 21.10% 15.44%
  2)10% 62.63% 34.72% 25.99% 19.46% 14.23%
  3)15% 57.70% 31.76% 23.93% 17.99% 13.13%
C Increase in Op.Cost          
  1)5% 53.35% 29.15% 21.70% 15.95% 11.18%
  2)10% 35.76% 19.83% 14.62% 10.25% 6.35%
  3)15% 23.18% 12.87% 8.95% 5.40% 2.03%
D Decrease in Sales          
  1)5% 43.23% 24.72% 18.71% 13.81% 9.58%
  2)10% 23.65% 14.03% 10.25% 6.83% 3.59%
  3)15% 12.37% 6.34% 3.59% 0.89% -1.84%
E Increase in Cap.+Op.Cost          
  1)5% 48.51% 26.61% 19.92% 14.65% 10.20%
  2)10% 29.26% 16.74% 12.33% 8.49% 4.98%
  3)15% 17.86% 9.93% 6.65% 3.57% 0.57%
ADD - ON SLIDES

Appendix - D

RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)

Option - III (a) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines for Dumping) - 8 Mtpa

Statement Showing Estimated Cash Flow Analysis

(Pre-Tax IRR on Total Capital)

At 100% capacity utilisation

Option - III (a) (Integrated - 8 Mtpa)                             (Amt. in ` Lakhs)

Sl.
Particulars Existing Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total
No.

1 Initial Capital 31326.68   4475.79 62963.09 40279.95                               139045.51

2 Replacement Capital     507.10 6267.15 6344.53 1858.92 384.15 4733.49 361.90 303.12 2457.13 506.24 6162.03 11133.69 5198.35 812.85 3058.39 1763.74   -24254.59 27598.17

3 Less: GST credit on Capital Goods     70.00 1650.52 3118.98 279.26 58.60 721.24 55.20 27.76 373.63 70.00 911.97 1648.65 788.67 122.68 444.39 246.02     10587.58

53992.9
4 Cash Operating Expenses   44655.33 58190.67 64288.39 79898.80 80666.39 81160.19 81656.72 81818.55 81888.67 81961.93 82038.50 82010.91 79839.64 69610.33 57099.57 57188.15 50745.24 43360.56 1312071.49
5

55510.6
5 Total Cash Outflow 31326.68 44655.33 63103.56 131868.11 123404.30 82246.05 81485.74 85668.96 82125.24 82164.03 84045.43 82474.73 87260.98 89324.68 74020.01 57789.74 59802.15 50745.24 19105.96 1468127.60
8

106774.2 106823.6 102211.3 103605.6 106770.8 108376.1 117849.1 120733.6 106088.6 106088.6 92827.5
6 Inflow from Sales   95384.32 87101.30 87101.30 111999.99 107816.29 105646.59 79566.49 62024.82 1914790.82
6 8 8 4 7 6 7 9 5 5 7

37316.8
7 Net Cash Flow -31326.68 50728.99 23997.74 -44766.81 -11404.32 25570.24 24160.85 21105.30 24698.44 20047.36 19560.22 24296.14 21115.18 28524.49 46713.68 48298.91 46286.50 28821.25 42918.86 446663.22
9

8 Coal Production (Lakh Tonnes)   54.70 54.70 54.70 80.00 80.00 80.00 80.00 80.00 80.00 80.00 80.00 80.00 80.00 80.00 80.00 80.00 70.00 60.00 46.60 1380.70

9 Pre Tax Internal rate of return       72.07%                                  

Desired Selling Price to Yield 12% IRR


10       1208.87                                  
(`/t)

11 Net Present Value (` Lakhs)       112825.76                                  


ADD - ON SLIDES

Appendix - D.1

RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)

Option - III (a) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines for Dumping) - 8 Mtpa

Statement Showing Estimated Cash Flow Analysis

(Pre-Tax IRR on Total Capital)

At 85% capacity utilisation

Option - III (a) (Integrated - 8 Mtpa) (Amt. in ` Lakhs)

Sl.
Particulars Existing Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total
No.

1 Initial Capital 31326.68   4475.79 62963.09 40279.95                               139045.51

2 Replacement Capital     507.10 6267.15 6344.53 1858.92 384.15 4733.49 361.90 303.12 2457.13 506.24 6162.03 11133.69 5198.35 812.85 3058.39 1763.74   -24254.59 27598.17

3 Less: GST credit on Capital Goods     70.00 1650.52 3118.98 279.26 58.60 721.24 55.20 27.76 373.63 70.00 911.97 1648.65 788.67 122.68 444.39 246.02     10587.58

49520.2
4 Cash Operating Expenses   39910.21 51503.60 57183.91 71198.19 71955.82 72433.15 72913.19 73071.21 73141.06 73214.05 73290.35 73277.83 71443.73 62760.86 52139.37 52227.95 46768.69 40499.46 1178452.92
9

51038.0
5 Total Cash Outflow 31326.68 39910.21 56416.49 124763.63 114703.69 73535.48 72758.70 76925.44 73377.90 73416.41 75297.54 73726.58 78527.90 80928.76 67170.54 52829.54 54841.95 46768.69 16244.87 1334509.03
1

100171.8 102623.6 78903.4


6 Inflow from Sales   81076.67 74036.10 74036.10 95199.99 91643.85 89799.60 90758.12 90800.13 86879.68 88064.80 90755.24 92119.74 90175.35 90175.35 67631.51 52721.10 1627572.20
0 3 3

27865.4
7 Net Cash Flow -31326.68 41166.46 17619.61 -50727.52 -19503.71 18108.36 17040.91 13832.69 17422.23 13463.26 12767.25 17028.66 13591.84 19243.03 35453.09 37345.81 35333.40 20862.82 36476.23 293063.17
2

8 Coal Production (Lakh Tonnes)   46.50 46.50 46.50 68.00 68.00 68.00 68.00 68.00 68.00 68.00 68.00 68.00 68.00 68.00 68.00 68.00 59.50 51.00 39.61 1173.60

9 Pre Tax Internal rate of return       30.95%                                  

Desired Selling Price to Yield 12% IRR


10       1299.54                                  
(`/t)

11 Net Present Value (` Lakhs)       55783.19                                  


ADD - ON SLIDES

Appendix - A
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
STATEMENT OF ESTIMATED CAPITAL INVESTMENT AND YEARWISE PHASING
Option - III (a) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines for Dumping) - Incremental 4.5 Mtpa
Base Date: October, 2018
Option - III (a) (Incremental - 4.5 Mtpa) (Amt. in ` Lakhs)
PHASING OF CAPITAL
TOTAL
EXISTING BALANCE
SANCTIONE TOTAL COMMITTED
SL AS ON INCREMENTA
PARTICULARS D CAPITAL PROVN EXPENSES
NO 31.03.18 L PROVISION Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7
(3.5 (4.5 Mtpa) FOR 3.5 Mtpa
(3.5 Mtpa) (4.5 Mtpa)
Mtpa)
1 Land 858 19767     19767   988 18779        
2 Buildings                        
  Service 2279 5550     5550     1110 4440      
  Residential 1371 3402     3402     680 2722      
3 Plant & Machinery                        
  a) HEMM 8298 5766     5766     257 5509      
  b) Others than HEMM 23201 15080     15080     4428 10652      
4 Furniture & Fittings 98 58     58     29 29      
5 Railway Siding 3600                      
6 Vehicles 308 711     711     240 471      
7 Prospecting & Boring 115                      
8 Development.                        
8.1 Capital Outlay in Mines 7125 37839     37839   1725 33450 2664      
8.2 Roads & Culverts 2417 10994     10994     2199 8795      
8.3 Water Supply & Sewerage 1842 5586     5586     1117 4469      
8.4 Scientific Research 50 80     80     80        
8.5 P.R. Prep. Cost 497 1762     1762   1762          
9.1 Revenue Exp. Capitalised                      
618
  less Depreciation                      
10 Land Reclamation 831 1123     1123     595 527      

  INITIAL CAPITAL 53510 107719     107719   4476 62963 40280      


ADD - ON SLIDES

Appendix - C
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Option - III (a) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines for Dumping) -
Incremental 4.5 Mtpa

Statement Showing Average Cost of Production

Option - III (a) (Incremental - 4.5 Mtpa)


Total Coal OB Common
Sl. No. Particulars
(`/t) (`/t) (`/m3) (`/t)
1 Salary & Wages 129.09 32.84 1.43 88.89
2 Stores 109.35 42.18 8.90 21.42
3 Power 32.15 3.55   28.60
4 Misc. Expenses 32.84 3.21 0.04 29.43
5 Adminstrative Cost (Cash) 3.62     3.62
6 Mine closure Cost 13.88     13.88
7 OB Outsourcing Cost 622.33   121.11  
8 COAL Outsourcing Cost        
9 Interest on Working capital 45.59 3.95 6.35 8.98
10 Total cash Cost 988.85 85.73 137.84 194.83
11 Interest        
12 Adminstrative Cost (Notional) 30.91     30.91
13 Depreciation 146.59 22.81   123.79
  Total 1166.35 108.54 137.84 349.52
14 Common cost apportioned to coal & OB   39.67 60.30  
  Total   148.21 198.13  
15 OB Cost Charged to coal   1018.14    
  Total Cost   1166.35    
ADD - ON SLIDES

Appendix - C.1
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)

Statement Showing Estimated Year wise Operating Cost at 100% capacity utilisation
Option - III (a) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines for Dumping) - Incremental 4.5 Mtpa
Option - III (a) (Incremental - 4.5 Mtpa) (Amt in ` Lakhs

Sl. Avg Cost % of Total


Particulars Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total Cost
No. (`/t) Cost

1 Salary & Wages 2214.27 1478.46 3615.04 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 97874.91 129.09 11.07

2 Stores 799.68 1128.16 1531.58 5569.95 5569.95 5569.95 5569.95 5569.95 5569.95 5569.95 5569.95 5562.83 5403.49 4672.63 3974.72 3974.72 3843.94 3806.55 3649.12 82907.07 109.35 9.38

3 Power   92.81 393.25 929.00 1063.20 1292.93 1522.65 1583.17 1586.00 1588.84 1591.68 1591.68 1591.68 1591.68 1591.68 1591.68 1591.68 1591.68 1591.68 24376.97 32.15 2.76

4 Misc. Expenses 307.27 353.50 518.24 1090.14 1519.71 1519.71 1519.71 1519.71 1519.71 1519.71 1519.71 1519.71 1519.71 1519.71 1519.71 1519.71 1480.33 1480.33 1433.87 24900.19 32.84 2.82

5 Adminstrative Cost (Cash) 71.31 71.31 71.31 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 144.79 144.79 123.43 2744.52 3.62 0.31

6 Mine Closure Cost 344.56 361.79 379.88 398.88 418.82 439.76 461.75 484.84 509.08 534.53 561.26 589.32 618.79 649.73 682.21 716.32 752.14 789.75 829.23 10522.62 13.88 1.19

7 OB Outsourcing 9003.68 13095.26 15450.90 34622.53 34622.53 34622.53 34622.53 34622.53 34622.53 34622.53 34622.53 34533.83 32549.03 23445.55 14752.33 14752.33 13366.30 12834.08 11087.69 471851.25 622.33 53.36

8 Coal Outsourcing                                            

Interest on Working
9 615.80 801.43 1061.41 2340.97 2369.18 2381.30 2393.46 2397.50 2398.81 2400.18 2401.61 2398.33 2296.12 1822.29 1369.96 1371.61 1297.25 1271.54 1178.15 34566.91 45.59 3.91
capital

10 Total Cash Cost 13356.58 17382.72 23021.60 50774.81 51386.73 51649.52 51913.39 52001.04 52029.43 52059.09 52090.08 52019.04 49802.15 39524.93 29713.95 29749.71 28136.88 27579.17 25553.63 749744.44 988.85 84.78

11 Interest                                            

Adminstrative Cost
12 608.89 608.89 608.89 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1236.33 1236.33 1053.97 23434.59 30.91 2.65
(Notional)

13 Depreciation   248.66 3983.36 6701.47 6701.47 6701.47 6701.47 6701.47 6701.47 6701.47 6701.47 6701.47 6701.47 6701.47 6701.47 6701.47 6701.47 6650.06 6443.56 111146.27 146.59 12.57

  Total 13965.47 18240.27 27613.85 58867.16 59479.08 59741.86 60005.74 60093.38 60121.77 60151.43 60182.42 60111.38 57894.49 47617.27 37806.29 37842.05 36074.68 35465.56 33051.16 884325.31 1166.35 100.00

  Cost/t (`) 708.91 925.90 1401.72 1308.16 1321.76 1327.60 1333.46 1335.41 1336.04 1336.70 1337.39 1335.81 1286.54 1058.16 840.14 840.93 901.87 886.64 969.24 1166.35    

  Fixed Cost (`/t) 178.97 159.51 498.22 397.00 409.82 414.32 418.85 420.44 421.06 421.70 422.37 423.03 423.71 424.43 425.19 425.98 475.83 475.53 546.96 419.87   36.00

  Variable Cost (`/t) 529.94 766.39 903.50 911.16 911.94 913.28 914.61 914.97 914.98 915.00 915.02 912.78 862.83 633.73 414.95 414.95 426.03 411.11 422.28 746.48   64.00

1051491.5
  Total Sales (` in Lakhs) 27320.47 27320.47 27320.47 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 55473.04 55473.04 47290.77 1386.83  
6

  Total Cost (` in Lakhs) 13965.47 18240.27 27613.85 58867.16 59479.08 59741.86 60005.74 60093.38 60121.77 60151.43 60182.42 60111.38 57894.49 47617.27 37806.29 37842.05 36074.68 35465.56 33051.16 884325.31 1166.35  

  Total Profits (` in Lakhs) 13355.00 9080.21 -293.38 3540.02 2928.10 2665.32 2401.44 2313.80 2285.41 2255.75 2224.75 2295.79 4512.68 14789.91 24600.88 24565.12 19398.36 20007.49 14239.61 167166.25 220.48  
ADD - ON SLIDES

Appendix - C.2
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Statement Showing Estimated Year wise operating cost at 85% capacity utilisation
Option - III (a) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines for Dumping) - Incremental 4.5 Mtpa
(Amount in Rs. Lakhs)
Option - III (a) (Incremental - 4.5 Mtpa)

Sl. Avg Cost % of Total


Particulars Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total Cost
No. (`/t) Cost

1 Salary & Wages 2214.27 1478.46 3615.04 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 97874.91 151.87 12.24

2 Stores 679.73 958.94 1343.50 5000.36 5000.36 5000.36 5000.36 5000.36 5000.36 5000.36 5000.36 4994.30 4858.86 4237.64 3644.41 3644.41 3533.25 3501.47 3367.65 74767.01 116.01 9.35

3 Power   89.33 378.50 894.16 1023.33 1244.44 1465.55 1523.80 1526.53 1529.26 1531.99 1531.99 1531.99 1531.99 1531.99 1531.99 1531.99 1531.99 1531.99 23462.84 36.41 2.93

4 Misc. Expenses 284.00 330.23 491.95 1021.22 1450.78 1450.78 1450.78 1450.78 1450.78 1450.78 1450.78 1450.78 1450.78 1450.78 1450.78 1450.78 1417.31 1417.31 1377.82 23749.20 36.85 2.97

5 Adminstrative Cost (Cash) 71.31 71.31 71.31 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 144.79 144.79 123.43 2744.52 4.26 0.34

6 Mine Closure Cost 344.56 361.79 379.88 398.88 418.82 439.76 461.75 484.84 509.08 534.53 561.26 589.32 618.79 649.73 682.21 716.32 752.14 789.75 829.23 10522.62 16.33 1.32

7 OB Outsourcing 7653.13 11130.97 13133.26 29429.15 29429.15 29429.15 29429.15 29429.15 29429.15 29429.15 29429.15 29353.75 27666.67 19928.71 12539.48 12539.48 11361.35 10908.97 9424.54 401073.56 622.33 50.17

8 COAL Outsourcing                                            

Interest on Working
9 543.61 697.02 938.32 2057.41 2085.38 2097.08 2108.83 2112.76 2114.06 2115.43 2116.85 2114.27 2027.60 1625.07 1240.82 1242.47 1179.40 1157.81 1078.56 30652.74 47.56 3.83
capital

10 Total Cash Cost 11790.61 15118.04 20351.76 44624.51 45231.16 45484.91 45739.76 45825.02 45853.30 45882.84 45913.73 45857.76 43978.03 35247.26 26913.04 26948.80 25580.68 25112.53 23393.68 664847.40 1031.62 83.17

11 Interest                                            

Adminstrative Cost
12 608.89 608.89 608.89 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1236.33 1236.33 1053.97 23434.59 36.36 2.93
(Notional )

13 Depreciation   248.66 3983.36 6701.47 6701.47 6701.47 6701.47 6701.47 6701.47 6701.47 6701.47 6701.47 6701.47 6701.47 6701.47 6701.47 6701.47 6650.06 6443.56 111146.27 172.46 13.90

  Total 12399.50 15975.59 24944.01 52716.85 53323.50 53577.25 53832.10 53917.36 53945.64 53975.19 54006.07 53950.10 52070.37 43339.60 35005.38 35041.14 33518.48 32998.93 30891.21 799428.27 1240.44 100.00

  Cost/t (`) 740.49 954.05 1489.64 1378.22 1394.08 1400.71 1407.38 1409.60 1410.34 1411.12 1411.92 1410.46 1361.32 1133.06 915.17 916.11 985.84 970.56 1065.77 1240.44    

  Fixed Cost (`/t) 210.55 187.66 586.14 467.06 482.14 487.44 492.76 494.64 495.36 496.12 496.91 497.68 498.48 499.33 500.22 501.16 559.80 559.45 643.49 493.96   39.82

  Variable Cost (`/t) 529.94 766.39 903.50 911.16 911.94 913.28 914.61 914.97 914.98 915.00 915.02 912.78 862.83 633.73 414.95 414.95 426.03 411.11 422.28 746.48   60.18

  Total Sales (` in Lakhs) 23222.40 23222.40 23222.40 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 47152.09 47152.09 40197.16 893767.83 1386.83  

  Total Cost (` in Lakhs) 12399.50 15975.59 24944.01 52716.85 53323.50 53577.25 53832.10 53917.36 53945.64 53975.19 54006.07 53950.10 52070.37 43339.60 35005.38 35041.14 33518.48 32998.93 30891.21 799428.27 1240.44  

  Total Profits (` in Lakhs) 10822.90 7246.81 -1721.61 329.25 -277.40 -531.15 -786.00 -871.26 -899.54 -929.09 -959.97 -904.00 975.72 9706.50 18040.72 18004.96 13633.61 14153.16 9305.94 94339.56 146.38  
ADD - ON SLIDES

Appendix - C.3
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Option - III (a) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines for Dumping) - Incremental 4.5 Mtpa

Statement Showing Economics at Different Capacity Utilisation

Option - III (a) (Incremental - 4.5 Mtpa)


Capacity Utilisation
Sl No. Particulars
100% 90% 85% 80% 75%
1 Output (Mtpa) 4.50 4.05 3.83 3.60 3.38

2 Cost/t (`) 1166.35 1213.00 1240.44 1271.32 1306.30

3 Selling Price (`/t) 1386.83 1386.83 1386.83 1386.83 1386.83

4 Profit (`/t) 220.48 173.83 146.38 115.51 80.52


5 IRR (%) 18.40% 13.13% 10.79% 8.55% 6.36%

6 DSP to yield 12% IRR 1315.56 1371.62 1404.59 1441.69 1483.73


ADD - ON SLIDES

Appendix - C.4
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Option - III (a) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines for Dumping) - Incremental 4.5
Mtpa
Statement showing Sensitivity of IRR

Option - III (a) (Incremental - 4.5 Mtpa)


Capacity Utilisation
Sl No. Particulars
100% 90% 85% 80% 75%
A Base Case 18.40% 13.13% 10.79% 8.55% 6.36%
B Increase in Capital          
  1)5% 16.77% 11.99% 9.81% 7.70% 5.62%
  2)10% 15.38% 10.98% 8.93% 6.93% 4.93%
  3)15% 14.17% 10.07% 8.13% 6.22% 4.31%
C Increase in Op.Cost          
  1)5% 13.56% 9.37% 7.39% 5.43% 3.47%
  2)10% 9.58% 6.06% 4.32% 2.55% 0.73%
  3)15% 6.13% 3.05% 1.47% -0.17% -1.89%
D Decrease in Sales          
  1)5% 12.15% 8.29% 6.43% 4.57% 2.69%
  2)10% 7.10% 4.01% 2.44% 0.82% -0.87%
  3)15% 2.64% 0.01% -1.39% -2.86% -4.44%

E Increase in Cap.+Op.Cost          

  1)5% 12.42% 8.51% 6.63% 4.75% 2.86%


  2)10% 7.97% 4.76% 3.15% 1.49% -0.22%
  3)15% 4.34% 1.56% 0.10% -1.42% -3.03%
ADD - ON SLIDES

Appendix - D

RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)

Option - III (a) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines for Dumping) - Incremental 4.5 Mtpa

Statement Showing Estimated Cash Flow Analysis

(Pre-Tax IRR on Total Capital)

At 100% capacity utilisation

Option - III (a) (Incremental - 4.5 Mtpa)                     (Amt. in ` Lakhs)

Sl.
Particulars Existing Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total
No.

1 Initial Capital     4475.79 62963.09 40279.95                               107718.83

2 Replacement Capital             182.00 731.00   182.00 731.00   819.23 5538.75 1879.76 182.00 876.20 145.60   -3371.03 7896.51

3 Less: GST credit on Capital Goods       706.76 2151.99   27.76 111.51   27.76 111.51   110.58 795.19 286.74 27.76 111.51       4469.07

4 Cash Operating Expenses   13356.58 17382.72 23021.60 50774.81 51386.73 51649.52 51913.39 52001.04 52029.43 52059.09 52090.08 52019.04 49802.15 39524.93 29713.95 29749.71 28136.88 27579.17 25553.63 749744.44

5 Total Cash Outflow   13356.58 21858.51 85277.93 88902.78 51386.73 51803.75 52532.89 52001.04 52183.66 52678.58 52090.08 52727.69 54545.72 41117.94 29868.19 30514.40 28282.48 27579.17 22182.60 860890.72

6 Inflow from Sales   27320.47 27320.47 27320.47 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 55473.04 55473.04 47290.77 1051491.56

7 Net Cash Flow   13963.89 5461.96 -57957.46 -26495.60 11020.44 10603.42 9874.29 10406.14 10223.51 9728.60 10317.09 9679.49 7861.46 21289.23 32538.99 31892.77 27190.56 27893.88 25108.17 190600.84

8 Coal Production (Lakh Tonnes)   19.70 19.70 19.70 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 40.00 40.00 34.10 758.20

9 Pre Tax Internal rate of return       18.40%                                  

Desired Selling Price to Yield 12% IRR


10       1315.56                                  
(`/t)

11 Net Present Value (` Lakhs)       19102.54                                  


ADD - ON SLIDES

Appendix - D.1

RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)

Option - III (a) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines for Dumping) - Incremental 4.5 Mtpa

Statement Showing Estimated Cash Flow Analysis

(Pre-Tax IRR on Total Capital)

At 85% capacity utilisation

Option - III (a) (Incremental - 4.5 Mtpa) (Amt. in ` Lakhs)

Sl.
Particulars Existing Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total
No.

1 Initial Capital     4475.79 62963.09 40279.95                               107718.83

2 Replacement Capital             182.00 731.00   182.00 731.00   819.23 5538.75 1879.76 182.00 876.20 145.60   -3371.03 7896.51

3 Less: GST credit on Capital Goods       706.76 2151.99   27.76 111.51   27.76 111.51   110.58 795.19 286.74 27.76 111.51       4469.07

4 Cash Operating Expenses   11790.61 15118.04 20351.76 44624.51 45231.16 45484.91 45739.76 45825.02 45853.30 45882.84 45913.73 45857.76 43978.03 35247.26 26913.04 26948.80 25580.68 25112.53 23393.68 664847.40

5 Total Cash Outflow   11790.61 19593.84 82608.09 82752.48 45231.16 45639.14 46359.25 45825.02 46007.53 46502.34 45913.73 46566.40 48721.60 36840.27 27067.27 27713.49 25726.28 25112.53 20022.65 775993.68

6 Inflow from Sales   23222.40 23222.40 23222.40 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 47152.09 47152.09 40197.16 893767.83

7 Net Cash Flow   11431.80 3628.57 -59385.69 -29706.38 7814.94 7406.95 6686.85 7221.08 7038.57 6543.76 7132.37 6479.70 4324.50 16205.83 25978.82 25332.61 21425.81 22039.55 20174.51 117774.15

8 Coal Production (Lakh Tonnes)   16.75 16.75 16.75 38.25 38.25 38.25 38.25 38.25 38.25 38.25 38.25 38.25 38.25 38.25 38.25 38.25 34.00 34.00 28.99 644.47

9 Pre Tax Internal rate of return       10.79%                                  

Desired Selling Price to Yield 12% IRR


10       1404.59                                  
(`/t)

11 Net Present Value (` Lakhs)       -4047.36                                  


ADD - ON SLIDES

Appendix - A
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)

STATEMENT OF ESTIMATED CAPITAL INVESTMENT AND YEARWISE PHASING


Option - III (b) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines for Dumping) - 8 Mtpa
Base Date: October, 2018
Option - III (b) (Integrated - 8 Mtpa) (Amt. in ` Lakhs)
TOTAL EXISTING COMMITTED BALANCE PHASING OF CAPITAL
TOTAL
SL. SANCTIONED AS ON EXPENSES INCREMENTAL
PARTICULARS PROVN
NO. CAPITAL 31.03.18 FOR 3.5 PROVISION YR-1 YR-2 YR-3 YR-4 YR-5 YR-6 YR-7
(8 Mtpa)
(3.5 Mtpa) (3.5 Mtpa) Mtpa (4.5 Mtpa)
1 Land 858 25522 5755   19767   988 18779        
2 Buildings                        
  Service 2279 5846 296   5550     1110 4440      
  Residential 1371 5158 1755   3402     680 2722      
3 Plant & Machinery                        
  a) HEMM 8298 13826 8060   5766     257 5509      
  b) Others than HEMM 23201 39473 24374   15099     4429 10670      
4 Furniture & Fittings 98 277 218   58     29 29      
5 Railway Siding 3600 8516 4889 3627                
6 Vehicles 308 939 228   711     240 471      
7 Prospecting & Boring 115 44 44                  
8 Development.                        
8.1 Capital Outlay in Mines 7125 40695 2652 204 37839   1725 33450 2664      
8.2 Roads & Culverts 2417 3712 460 106 3146     629 2517      
Water Supply &
8.3 1842 6617 1031   5586     1117 4469      
Sewerage
8.4 Scientific Research 50 80     80     80        
8.5 PR Preparation Cost 497 1762     1762   1762          
9.1 Revenue Exp.                      
Capitalised less 618
                       
Depreciation
10 Land Reclamation 831 2456 1333   1123     595 527      
  INITIAL CAPITAL 53510 154922 51096 3936 99890   4476 61395 34020      
ADD - ON SLIDES

Appendix - C
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Option - III (b) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines for Dumping) - 8 Mtpa
Statement Showing Average Cost of Production
Option - III (b) (Integrated - 8 Mtpa)
Total Coal OB Common
Sl. No. Particulars
(`/t) (`/t) (`/m3) (`/t)
1 Salary & Wages 146.49 39.48 1.31 101.32
2 Stores 156.15 84.12 8.90 33.50
3 Power 52.19 7.05 3.93 28.13
4 Misc. Expenses 36.07 5.96 0.03 29.96
5 Adminstrative Cost (Cash) 3.62     3.62
6 Mine closure Cost 18.88     18.88
7 OB Outsourcing Cost 364.33   84.20  
8 OB Crushing & Conveying Cost 182.71   42.23  
9 COAL Outsourcing Cost        
10 Interest on Working capital 46.42 6.60 6.80 10.41
11 Total cash Cost 1006.87 143.22 147.41 225.82
12 Interest        
13 Adminstrative Cost (Notional) 30.91     30.91
14 Depreciation 124.52 43.34   81.19
  Total 1162.30 186.56 147.41 337.92
15 Common cost apportioned to coal & OB   44.60 67.79  
  Total   231.16 215.20  
16 OB Cost Charged to coal   931.14    
  Total Cost   1162.30    
ADD - ON SLIDES

Appendix - C.1
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)

Statement Showing Estimated Year wise Operating Cost at 100% capacity utilisation
Option - III (b) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines for Dumping) - 8 Mtpa
Option - III (b) (Integrated - 8 Mtpa) (Amt. in ` Lakhs)
% of
Sl. Avg Cost
Particulars Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total Cost Total
No. (`/t)
Cost

1 Salary & Wages 6872.42 6995.38 9153.36 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 202262.44 146.49 12.60

2 Stores 8103.21 9014.77 9418.21 12558.69 12558.69 12558.69 12558.69 12558.69 12558.69 12558.69 12558.69 12551.57 12392.23 11661.37 10768.50 10768.50 10507.84 10248.07 9685.72 215589.54 156.15 13.43

3 Power   1145.80 2031.25 3257.98 3516.54 3940.24 4363.94 4463.90 4471.90 4479.91 4487.91 4487.91 4487.91 4487.91 4487.91 4487.91 4487.91 4487.91 4487.91 72062.66 52.19 4.49

4 Misc. Expenses 1554.24 1700.09 1942.63 2540.20 2837.93 2837.93 2837.93 2837.93 2837.93 2837.93 2837.93 2837.93 2837.93 2837.93 2837.93 2837.93 2759.18 2680.43 2574.90 49806.81 36.07 3.10

5 Adminstrative Cost (Cash) 198.00 198.00 198.00 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 253.39 217.19 168.68 4997.84 3.62 0.31

6 Mine Closure Cost 853.47 896.14 940.95 987.99 1037.39 1089.26 1143.73 1200.91 1260.96 1324.01 1390.21 1459.72 1532.70 1609.34 1689.81 1774.30 1863.01 1956.16 2053.97 26064.03 18.88 1.62

7 OB Outsourcing 25015.16 36369.56 26944.52 34928.08 34928.08 34928.08 34928.08 34928.08 34928.08 34928.08 34928.08 34839.38 32854.58 23751.10 12629.55 12629.55 9868.57 7384.79 1319.51 503030.93 364.33 31.35

OB Crushing & Conveying


8     14915.97 14915.97 14915.97 14915.97 14915.97 14915.97 14915.97 14915.97 14915.97 14915.97 14915.97 14915.97 14915.97 14915.97 14915.97 14494.81 14038.56 252272.90 182.71 15.72
Cost

9 Coal Outsourcing                                            

10 Interest on Working capital 2058.83 2722.12 3168.00 3899.59 3928.86 3951.85 3974.96 3982.55 3985.84 3989.28 3992.86 3991.59 3891.48 3419.86 2843.06 2847.14 2699.82 2545.81 2200.71 64094.21 46.42 3.99

1390181.3
11 Total Cash Cost 44655.33 59041.86 68712.90 84580.67 85215.63 85714.19 86215.46 86380.20 86451.54 86526.03 86603.82 86576.23 84404.96 74175.64 61664.89 61753.46 58558.27 55217.75 47732.53 1006.87 86.63
8

12 Interest                                            

Adminstrative Cost
13 1690.68 1690.68 1690.68 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2163.57 1854.49 1440.32 42674.94 30.91 2.66
(Notional)

14 Depreciation 3600.24 3853.96 7505.31 9832.30 9835.44 9835.44 9835.85 9835.85 9849.31 9849.90 9850.50 9851.19 9851.19 9851.19 9851.19 9851.19 9851.19 9851.19 9286.99 171929.41 124.52 10.71

1604785.7
  Total 49946.25 64586.50 77908.89 96885.63 97523.72 98022.28 98523.97 98688.70 98773.50 98848.58 98926.97 98900.08 96728.81 86499.49 73988.74 74077.31 70573.03 66923.44 58459.84 1162.30 100.00
4

  Cost (`/t) 913.09 1180.74 1424.29 1211.07 1219.05 1225.28 1231.55 1233.61 1234.67 1235.61 1236.59 1236.25 1209.11 1081.24 924.86 925.97 1008.19 1115.39 1254.50 1162.30    

  Fixed Cost (`/t) 334.77 361.85 493.13 440.47 447.59 452.44 457.32 459.05 460.09 461.00 461.95 462.87 463.83 464.83 465.89 466.99 530.08 614.27 771.02 472.31   40.64

  Variable Cost (`/t) 578.32 818.89 931.16 770.60 771.45 772.84 774.23 774.56 774.58 774.61 774.63 773.38 745.28 616.41 458.97 458.97 478.11 501.12 483.48 689.99   59.36

106823.6 103605.6 106770.8 108376.1 120733.6 106088.6 106088.6 1914790.8


  Total Sales (` in Lakhs) 95384.32 87101.30 87101.30 111999.99 107816.29105646.59 106774.26 102211.38 117849.17 92827.57 79566.49 62024.82 1386.83  
8 4 7 6 9 5 5 2
1604785.7
  Total Cost (` in Lakhs) 49946.25 64586.50 77908.89 96885.63 97523.72 98022.28 98523.97 98688.70 98773.50 98848.58 98926.97 98900.08 96728.81 86499.49 73988.74 74077.31 70573.03 66923.44 58459.84 1162.30  
4

  Total Profits (` in Lakhs) 45438.07 22514.80 9192.41 15114.35 10292.57 7624.31 8250.30 8134.98 3437.88 4757.06 7843.90 9476.09 21120.36 34234.20 32099.91 32011.34 22254.53 12643.05 3564.98 310005.09 224.53  
ADD - ON SLIDES

Appendix - C.2
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Statement Showing Estimated Year wise operating cost at 85% capacity utilisation
Option - III (b) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines for Dumping) - 8 Mtpa
(Amount in Rs. Lakhs)
Option - III (b) (Integrated - 8 Mtpa)
% of
Sl. Avg Cost
Particulars Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total Cost Total
No. (`/t)
Cost

1 Salary & Wages 6872.42 6995.38 9153.36 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 202262.44 172.34 13.84

2 Stores 7423.80 8198.63 8583.21 11476.89 11476.89 11476.89 11476.89 11476.89 11476.89 11476.89 11476.89 11470.83 11335.39 10714.17 9955.23 9955.23 9733.66 9512.85 9034.86 197732.95 168.48 13.53

3 Power   1102.83 1955.08 3135.81 3384.67 3792.48 4200.29 4296.50 4304.20 4311.91 4319.62 4319.62 4319.62 4319.62 4319.62 4319.62 4319.62 4319.62 4319.62 69360.31 59.10 4.74

4 Misc. Expenses 1459.58 1605.43 1844.95 2399.88 2697.60 2697.60 2697.60 2697.60 2697.60 2697.60 2697.60 2697.60 2697.60 2697.60 2697.60 2697.60 2630.66 2563.73 2474.03 47349.49 40.35 3.24

5 Adminstrative Cost (Cash) 198.00 198.00 198.00 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 253.39 217.19 168.68 4997.84 4.26 0.34

6 Mine Closure Cost 853.47 896.14 940.95 987.99 1037.39 1089.26 1143.73 1200.91 1260.96 1324.01 1390.21 1459.72 1532.70 1609.34 1689.81 1774.30 1863.01 1956.16 2053.97 26064.03 22.21 1.78

7 OB Outsourcing 21262.89 30914.13 22902.84 29688.87 29688.87 29688.87 29688.87 29688.87 29688.87 29688.87 29688.87 29613.47 27926.39 20188.43 10735.12 10735.12 8388.28 6277.08 1121.58 427576.29 364.33 29.25

OB Crushing & Conveying


8     12678.57 12678.57 12678.57 12678.57 12678.57 12678.57 12678.57 12678.57 12678.57 12678.57 12678.57 12678.57 12678.57 12678.57 12678.57 12320.59 11932.77 214431.96 182.71 14.67
Cost
9 Coal Outsourcing                                            

10 Interest on Working capital 1840.06 2412.34 2815.75 3473.24 3502.05 3524.27 3546.61 3554.02 3557.30 3560.72 3564.29 3563.71 3479.15 3078.83 2589.13 2593.21 2468.37 2337.87 2044.89 57505.81 49.00 3.93

1247281.1
11 Total Cash Cost 39910.21 52322.87 61072.73 75333.42 75958.21 76440.11 76924.73 77085.53 77156.56 77230.73 77308.21 77295.69 75461.59 66778.72 56157.23 56245.81 53538.15 50707.67 44352.98 1062.79 85.32
3
12 Interest                                            
Adminstrative Cost (Notional
13 1690.68 1690.68 1690.68 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2163.57 1854.49 1440.32 42674.94 36.36 2.92
)

14 Depreciation 3600.24 3853.96 7505.31 9832.30 9835.44 9835.44 9835.85 9835.85 9849.31 9849.90 9850.50 9851.19 9851.19 9851.19 9851.19 9851.19 9851.19 9851.19 9286.99 171929.41 146.50 11.76

1461885.4
  Total 45201.13 57867.51 70268.72 87638.37 88266.30 88748.20 89233.23 89394.04 89478.52 89553.29 89631.36 89619.54 87785.43 79102.57 68481.08 68569.65 65552.91 62413.35 55080.29 1245.65 100.00
9
  Cost (`/t) 972.17 1244.60 1511.32 1288.80 1298.03 1305.12 1312.25 1314.62 1315.86 1316.96 1318.11 1317.93 1290.96 1163.27 1007.07 1008.38 1101.73 1223.79 1390.57 1245.65    

  Fixed Cost (`/t) 393.85 425.71 580.16 518.19 526.58 532.28 538.03 540.06 541.28 542.35 543.47 544.56 545.68 546.86 548.10 549.41 623.62 722.67 907.08 555.66   44.61

  Variable Cost (`/t) 578.32 818.89 931.16 770.60 771.45 772.84 774.23 774.56 774.58 774.61 774.63 773.38 745.28 616.41 458.97 458.97 478.11 501.12 483.48 689.99   55.39
100171.8 102623.6 1627572.2
  Total Sales (` in Lakhs) 81076.67 74036.10 74036.10 95199.99 91643.85 89799.60 90758.12 90800.13 86879.68 88064.80 90755.24 92119.74 90175.35 90175.35 78903.43 67631.51 52721.10 1386.83  
0 3 0
1461885.4
  Total Cost (` in Lakhs) 45201.13 57867.51 70268.72 87638.37 88266.30 88748.20 89233.23 89394.04 89478.52 89553.29 89631.36 89619.54 87785.43 79102.57 68481.08 68569.65 65552.91 62413.35 55080.29 1245.65  
9

  Total Profits (` in Lakhs) 35875.54 16168.59 3767.39 7561.61 3377.54 1051.40 1524.89 1406.09 -2598.84 -1488.49 1123.88 2500.20 12386.36 23521.07 21694.27 21605.70 13350.52 5218.17 -2359.19 165686.71 141.18  
ADD - ON SLIDES

Appendix - C.3
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Option - III (b) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines for Dumping) - 8 Mtpa

Statement Showing Economics at Different Capacity Utilisation

Option - III (b) (Integrated - 8 Mtpa)

Sl Capacity Utilisation
Particulars
No. 100% 90% 85% 80% 75%
1 Output (Mtpa) 8.00 7.20 6.80 6.40 6.00

2 Cost (`/t) 1162.30 1214.78 1245.65 1280.38 1319.74

3 Selling Price (`/t) 1386.83 1386.83 1386.83 1386.83 1386.83

4 Profit (`/t) 224.53 172.05 141.18 106.45 67.09


5 IRR (%) 65.28% 34.71% 25.00% 17.96% 12.43%
ADD - ON SLIDES

Appendix - C.4
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Option - III (b) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines for Dumping) - 8 Mtpa
Statement showing Sensitivity of IRR

Option - III (b) (Integrated - 8 Mtpa)


Capacity Utilisation
Sl No. Particulars
100% 90% 85% 80% 75%
A Base Case 65.28% 34.71% 25.00% 17.96% 12.43%
B Increase in Capital          
  1)5% 60.31% 31.43% 22.82% 16.46% 11.34%
  2)10% 55.20% 28.57% 20.91% 15.11% 10.35%
  3)15% 50.10% 26.09% 19.23% 13.91% 9.45%
C Increase in Op.Cost          
  1)5% 43.72% 22.28% 16.02% 11.02% 6.71%
  2)10% 26.11% 13.57% 9.18% 5.31% 1.69%
  3)15% 15.20% 7.01% 3.58% 0.32% -2.94%
D Decrease in Sales          
  1)5% 34.74% 18.87% 13.68% 9.32% 5.42%
  2)10% 17.19% 9.06% 5.68% 2.49% -0.63%
  3)15% 7.09% 1.68% -0.94% -3.60% -6.38%
E Increase in Cap.+Op.Cost          
  1)5% 39.09% 20.31% 14.65% 10.02% 5.95%
  2)10% 21.40% 11.32% 7.49% 4.00% 0.68%
  3)15% 11.62% 4.94% 1.95% -0.96% -3.92%
ADD - ON SLIDES

Appendix - D

RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)

Option - III (b) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines for Dumping) - 8 Mtpa

Statement Showing Estimated Cash Flow Analysis

(Pre-Tax IRR on Total Capital)

At 100% capacity utilisation

Option - III (b) (Integrated - 8 Mtpa)                         (Amt. in ` Lakhs)

Sl.
Particulars Existing Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total
No.

1 Initial Capital 31326.68   4475.79 61394.68 34019.84                               131217.00

2 Replacement Capital     507.10 6267.15 6344.53 1858.92 384.15 4733.49 361.90 303.12 2457.13 506.24 6162.03 11133.69 5198.35 812.85 3058.39 1763.74   -24256.34 27596.42

3 Less: GST credit on Capital Goods     70.00 1650.69 3121.73 279.26 58.60 721.24 55.20 27.76 373.63 70.00 911.97 1648.65 788.67 122.68 444.39 246.02     10590.49

4 Cash Operating Expenses   44655.33 59041.86 68712.90 84580.67 85215.63 85714.19 86215.46 86380.20 86451.54 86526.03 86603.82 86576.23 84404.96 74175.64 61664.89 61753.46 58558.27 55217.75 47732.53 1390181.38

5 Total Cash Outflow 31326.68 44655.33 63954.75 134724.04 121823.33 86795.29 86039.74 90227.71 86686.89 86726.90 88609.52 87040.05 91826.30 93890.00 78585.32 62355.06 64367.47 60076.00 55217.75 23476.19 1538404.31

106774.2 106823.6 102211.3 103605.6 106770.8 108376.1 117849.1 120733.6 106088.6 106088.6
6 Inflow from Sales   95384.32 87101.30 87101.30 111999.99 107816.29 105646.59 92827.57 79566.49 62024.82 1914790.82
6 8 8 4 7 6 7 9 5 5

-
7 Net Cash Flow 50728.99 23146.55 -47622.74 -9823.34 21021.00 19606.86 16546.56 20136.79 15484.49 14996.12 19730.82 16549.86 23959.18 42148.36 43733.59 41721.18 32751.57 24348.73 38548.63 376386.51
31326.68

8 Coal Production (Lakh Tonnes)   54.70 54.70 54.70 80.00 80.00 80.00 80.00 80.00 80.00 80.00 80.00 80.00 80.00 80.00 80.00 80.00 70.00 60.00 46.60 1380.70

9 Pre Tax Internal rate of return       65.28%                                  

Desired Selling Price to


10       1250.01                                  
Yield 12% IRR (`/t)

11 Net Present Value (` Lakhs)       91413.80                                  


ADD - ON SLIDES

Appendix - D.1
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Option - III (b) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines for Dumping) - 8 Mtpa

Statement Showing Estimated Cash Flow Analysis


(Pre-Tax IRR on Total Capital)
At 85% capacity utilisation

Option - III (b) (Integrated - 8 Mtpa) (Amt. in ` Lakhs)

Sl.
Particulars Existing Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total
No.

1 Initial Capital 31326.68   4475.79 61394.68 34019.84                               131217.00

2 Replacement Capital     507.10 6267.15 6344.53 1858.92 384.15 4733.49 361.90 303.12 2457.13 506.24 6162.03 11133.69 5198.35 812.85 3058.39 1763.74   -24256.34 27596.42

3 Less: GST credit on Capital Goods     70.00 1650.69 3121.73 279.26 58.60 721.24 55.20 27.76 373.63 70.00 911.97 1648.65 788.67 122.68 444.39 246.02     10590.49

4 Cash Operating Expenses   39910.21 52322.87 61072.73 75333.42 75958.21 76440.11 76924.73 77085.53 77156.56 77230.73 77308.21 77295.69 75461.59 66778.72 56157.23 56245.81 53538.15 50707.67 44352.98 1247281.13

5 Total Cash Outflow 31326.68 39910.21 57235.76 127083.87 112576.07 77537.87 76765.66 80936.97 77392.23 77431.92 79314.23 77744.44 82545.76 84946.62 71188.40 56847.40 58859.81 55055.87 50707.67 20096.64 1395504.06

100171.8 102623.6
6 Inflow from Sales   81076.67 74036.10 74036.10 95199.99 91643.85 89799.60 90758.12 90800.13 86879.68 88064.80 90755.24 92119.74 90175.35 90175.35 78903.43 67631.51 52721.10 1627572.20
0 3

-
7 Net Cash Flow 41166.46 16800.34 -53047.76 -17376.08 14105.98 13033.95 9821.15 13407.90 9447.76 8750.57 13010.80 9573.98 15225.17 31435.23 33327.95 31315.54 23847.56 16923.85 32624.46 232068.13
31326.68

8 Coal Production (Lakh Tonnes)   46.50 46.50 46.50 68.00 68.00 68.00 68.00 68.00 68.00 68.00 68.00 68.00 68.00 68.00 68.00 68.00 59.50 51.00 39.61 1173.60

9 Pre Tax Internal rate of return       25.00%                                  

Desired Selling Price to Yield 12% IRR


10       1340.89                                  
(`/t)

11 Net Present Value (` Lakhs)       37489.07                                  


ADD - ON SLIDES

Appendix - A
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)

STATEMENT OF ESTIMATED CAPITAL INVESTMENT AND YEARWISE PHASING


Option - III (b) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines for Dumping) - Incremental 4.5 Mtpa
Base Date: October, 2018
Option - III (b) (Incremental - 4.5 Mtpa) (Amt. in ` Lakhs)
PHASING OF CAPITAL
TOTAL EXISTING BALANCE
TOTAL COMMITTED
SL. SANCTIONED AS ON INCREMENTAL
PARTICULARS PROVN EXPENSES
NO. CAPITAL 31.03.18 (3.5 PROVISION YR-1 YR-2 YR-3 YR-4 YR-5 YR-6 YR-7
(4.5 Mtpa) FOR 3.5 Mtpa
(3.5 Mtpa) Mtpa) (4.5 Mtpa)

1 Land 858 19767     19767   988 18779        


2 Buildings                        
  Service 2279 5550     5550     1110 4440      
  Residential 1371 3402     3402     680 2722      
3 Plant & Machinery                        
  a) HEMM 8298 5766     5766     257 5509      
  b) Others than HEMM 23201 15099     15099     4429 10670      
4 Furniture & Fittings 98 58     58     29 29      
5 Railway Siding 3600                      
6 Vehicles 308 711     711     240 471      
7 Prospecting & Boring 115                      
8 Development.                        
8.1 Capital Outlay in Mines 7125 37839     37839   1725 33450 2664      
8.2 Roads & Culverts 2417 3146     3146     629 2517      
8.3 Water Supply & Sewerage 1842 5586     5586     1117 4469      
8.4 Scientific Research 50 80     80     80        
8.5 PR Preparation Cost 497 1762     1762   1762          
9.1 Revenue Exp. Capitalised                      
618
less Depreciation                      
10 Land Reclamation 831 1123     1123     595 527      
  INITIAL CAPITAL 53510 99890     99890   4476 61395 34020      
ADD - ON SLIDES

Appendix - C
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Option - III (b) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines for Dumping) - Incremental 4.5 Mtpa

Statement Showing Average Cost of Production

Option - III (b) (Incremental - 4.5 Mtpa)


Sl. Total Coal OB Common
Particulars
No. (`/t) (`/t) (`/m3) (`/t)
1 Salary & Wages 129.09 32.84 1.43 88.89
2 Stores 109.35 42.18 8.90 21.43
3 Power 65.23 3.68 6.21 29.64
4 Misc. Expenses 29.54 3.21 0.04 26.13
5 Adminstrative Cost (Cash) 3.62     3.62
6 Mine closure Cost 13.88     13.88
7 OB Outsourcing Cost 359.54   69.97  
8 OB Crushing & Conveying Cost 332.73   64.75  
9 COAL Outsourcing Cost        
10 Interest on Working capital 50.41 3.96 7.31 8.87
11 Total cash Cost 1093.39 85.87 158.61 192.46
12 Interest        
13 Adminstrative Cost (Notional) 30.91     30.91
14 Depreciation 136.26 22.81   113.45
  Total 1260.56 108.68 158.61 336.82
15 Common cost apportioned to coal & OB   38.23 58.11  
  Total   146.90 216.72  
16 OB Cost Charged to coal   1113.65    
  Total Cost   1260.56    
ADD - ON SLIDES

Appendix - C.1
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)

Statement Showing Estimated Year wise Operating Cost at 100% capacity utilisation
Option - III (b) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines for Dumping) - Incremental 4.5 Mtpa
Option - III (b) (Incremental - 4.5 Mtpa) (Amt. in ` Lakhs)
% of
Sl. Avg Cost
Particulars Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total Cost Total
No. (`/t)
Cost

1 Salary & Wages 2214.27 1478.46 3615.04 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 97874.91 129.09 10.24

2 Stores 799.68 1128.16 1531.60 5570.29 5570.29 5570.29 5570.29 5570.29 5570.29 5570.29 5570.29 5563.17 5403.83 4672.97 3975.06 3975.06 3844.28 3806.89 3649.46 82912.53 109.35 8.68

3 Power   930.44 1519.90 2353.22 2492.30 2730.38 2968.45 3031.17 3034.11 3037.05 3040.00 3040.00 3040.00 3040.00 3040.00 3040.00 3040.00 3040.00 3040.00 49456.98 65.23 5.17

4 Misc. Expenses 307.27 353.50 518.24 1057.27 1354.99 1354.99 1354.99 1354.99 1354.99 1354.99 1354.99 1354.99 1354.99 1354.99 1354.99 1354.99 1315.62 1315.62 1269.16 22396.59 29.54 2.34

5 Adminstrative Cost (Cash) 71.31 71.31 71.31 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 144.79 144.79 123.43 2744.52 3.62 0.29

6 Mine Closure Cost 344.56 361.79 379.88 398.88 418.82 439.76 461.75 484.84 509.08 534.53 561.26 589.32 618.79 649.73 682.21 716.32 752.14 789.75 829.23 10522.62 13.88 1.10

7 OB Outsourcing 9003.68 13095.26 3670.22 22841.86 22841.86 22841.86 22841.86 22841.86 22841.86 22841.86 22841.86 22753.15 20768.35 11664.87 2971.66 2971.66 1585.62 1386.04   272605.38 359.54 28.52

OB Crushing & Conveying


8     14915.97 14915.97 14915.97 14915.97 14915.97 14915.97 14915.97 14915.97 14915.97 14915.97 14915.97 14915.97 14915.97 14915.97 14915.97 14494.81 14038.56 252272.90 332.73 26.40
Cost

9 Coal Outsourcing                                            

10 Interest on Working capital 615.80 841.91 1267.40 2559.77 2581.85 2594.37 2606.94 2611.09 2612.40 2613.77 2615.21 2611.93 2509.72 2035.89 1583.56 1585.20 1510.85 1480.85 1382.83 38221.34 50.41 4.00

11 Total Cash Cost 13356.58 18260.84 27489.56 55520.59 55999.42 56270.96 56543.59 56633.54 56662.04 56691.81 56722.91 56651.87 54434.98 44157.76 34346.78 34382.54 32769.71 32119.19 29993.11 829007.77 1093.39 86.74

12 Interest                                            

13 Adminstrative Cost (Notional) 608.89 608.89 608.89 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1236.33 1236.33 1053.97 23434.59 30.91 2.45

14 Depreciation   248.66 3891.09 6217.67 6217.67 6217.67 6217.67 6217.67 6217.67 6217.67 6217.67 6217.67 6217.67 6217.67 6217.67 6217.67 6217.67 6166.26 5959.76 103313.10 136.26 10.81

  Total 13965.47 19118.39 31989.54 63129.13 63607.95 63879.49 64152.13 64242.08 64270.57 64300.34 64331.44 64260.40 62043.51 51766.29 41955.32 41991.08 40223.70 39521.78 37006.84 955755.46 1260.56 100.00

  Cost (`/t) 708.91 970.48 1623.83 1402.87 1413.51 1419.54 1425.60 1427.60 1428.23 1428.90 1429.59 1428.01 1378.74 1150.36 932.34 933.14 1005.59 988.04 1085.24 1260.56    

  Fixed Cost (`/t) 178.97 192.94 538.50 410.37 420.20 424.85 429.52 431.16 431.77 432.42 433.09 433.75 434.43 435.15 435.91 436.70 487.89 487.59 561.11 432.09   34.28

  Variable Cost (`/t) 529.94 777.53 1085.33 992.50 993.31 994.69 996.08 996.44 996.46 996.48 996.50 994.26 944.31 715.21 496.43 496.43 517.70 500.45 524.13 828.47   65.72

1051491.5
  Total Sales (` in Lakhs) 27320.47 27320.47 27320.47 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 55473.04 55473.04 47290.77 1386.83  
6

  Total Cost (` in Lakhs) 13965.47 19118.39 31989.54 63129.13 63607.95 63879.49 64152.13 64242.08 64270.57 64300.34 64331.44 64260.40 62043.51 51766.29 41955.32 41991.08 40223.70 39521.78 37006.84 955755.46 1260.56  

  Total Profits (` in Lakhs) 13355.00 8202.09 -4669.07 -721.95 -1200.78 -1472.32 -1744.95 -1834.90 -1863.40 -1893.17 -1924.27 -1853.23 363.66 10640.88 20451.86 20416.10 15249.34 15951.27 10283.93 95736.10 126.27  
ADD - ON SLIDES

Appendix - C.2
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Statement Showing Estimated Year wise operating cost at 85% capacity utilisation
Option - III (b) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines for Dumping) - Incremental 4.5 Mtpa
(Amount in Rs. Lakhs)
Option - III (b) (Incremental - 4.5 Mtpa)
Sl. Avg Cost
Particulars Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total Cost
No. (`/t)

1 Salary & Wages 2214.27 1478.46 3615.04 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 97874.91 151.87

2 Stores 679.73 958.94 1343.52 5000.68 5000.68 5000.68 5000.68 5000.68 5000.68 5000.68 5000.68 4994.62 4859.18 4237.96 3644.73 3644.73 3533.57 3501.79 3367.97 74772.15 116.02

3 Power   895.55 1462.90 2264.97 2398.84 2627.99 2857.14 2917.50 2920.33 2923.16 2926.00 2926.00 2926.00 2926.00 2926.00 2926.00 2926.00 2926.00 2926.00 47602.34 73.86

4 Misc. Expenses 284.00 330.23 491.95 988.33 1286.06 1286.06 1286.06 1286.06 1286.06 1286.06 1286.06 1286.06 1286.06 1286.06 1286.06 1286.06 1252.59 1252.59 1213.10 21245.47 32.97

5 Adminstrative Cost (Cash) 71.31 71.31 71.31 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 144.79 144.79 123.43 2744.52 4.26

6 Mine Closure Cost 344.56 361.79 379.88 398.88 418.82 439.76 461.75 484.84 509.08 534.53 561.26 589.32 618.79 649.73 682.21 716.32 752.14 789.75 829.23 10522.62 16.33

7 OB Outsourcing 7653.13 11130.97 3119.69 19415.58 19415.58 19415.58 19415.58 19415.58 19415.58 19415.58 19415.58 19340.18 17653.10 9915.14 2525.91 2525.91 1347.78 1178.13   231714.57 359.54

OB Crushing & Conveying


8     12678.57 12678.57 12678.57 12678.57 12678.57 12678.57 12678.57 12678.57 12678.57 12678.57 12678.57 12678.57 12678.57 12678.57 12678.57 12320.59 11932.77 214431.96 332.73
Cost

9 Coal Outsourcing                                          

10 Interest on Working capital 543.61 735.98 1119.54 2250.90 2272.72 2284.81 2296.95 2300.98 2302.29 2303.66 2305.09 2302.51 2215.84 1813.31 1429.06 1430.71 1367.63 1342.41 1259.23 33877.25 52.57

11 Total Cash Cost 11790.61 15963.23 24282.41 48821.25 49294.60 49556.78 49820.06 49907.54 49935.93 49965.58 49996.56 49940.59 48060.87 39330.10 30995.88 31031.63 29663.52 29116.49 27312.17 734785.80 1140.14

12 Interest                                          

13 Adminstrative Cost (Notional ) 608.89 608.89 608.89 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1236.33 1236.33 1053.97 23434.59 36.36

14 Depreciation   248.66 3891.09 6217.67 6217.67 6217.67 6217.67 6217.67 6217.67 6217.67 6217.67 6217.67 6217.67 6217.67 6217.67 6217.67 6217.67 6166.26 5959.76 103313.10 160.31

  Total 12399.50 16820.78 28782.39 56429.78 56903.14 57165.32 57428.60 57516.08 57544.46 57574.11 57605.10 57549.13 55669.41 46938.63 38604.41 38640.17 37117.51 36519.07 34325.90 861533.49 1336.81

  Cost (`/t) 740.49 1004.53 1718.86 1475.29 1487.66 1494.52 1501.40 1503.69 1504.43 1505.21 1506.02 1504.55 1455.41 1227.15 1009.27 1010.20 1091.69 1074.09 1184.26 1336.81  

  Fixed Cost (`/t) 210.55 226.99 633.53 482.79 494.36 499.83 505.32 507.24 507.97 508.73 509.52 510.29 511.10 511.94 512.84 513.77 573.99 573.64 660.13 508.34  

  Variable Cost (`/t) 529.94 777.53 1085.33 992.50 993.31 994.69 996.08 996.44 996.46 996.48 996.50 994.26 944.31 715.21 496.43 496.43 517.70 500.45 524.13 828.47  

  Total Sales (` in Lakhs) 23222.40 23222.40 23222.40 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 47152.09 47152.09 40197.16 893767.83 1386.83

  Total Cost (` in Lakhs) 12399.50 16820.78 28782.39 56429.78 56903.14 57165.32 57428.60 57516.08 57544.46 57574.11 57605.10 57549.13 55669.41 46938.63 38604.41 38640.17 37117.51 36519.07 34325.90 861533.49 1336.81

  Total Profits (` in Lakhs) 10822.90 6401.62 -5559.98 -3383.68 -3857.04 -4119.22 -4382.50 -4469.98 -4498.36 -4528.02 -4559.00 -4503.03 -2623.31 6107.47 14441.69 14405.93 10034.58 10633.01 5871.25 32234.34 50.02
ADD - ON SLIDES

Appendix - C.3
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Option - III (b) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines for Dumping) -
Incremental 4.5 Mtpa
Statement Showing Economics at Different Capacity Utilisation

Option - III (b) (Incremental - 4.5 Mtpa)


Capacity Utilisation
Sl
Particulars
No.
100% 90% 85% 80% 75%

1 Output (Mtpa) 4.50 4.05 3.83 3.60 3.38

2 Cost (`/t) 1260.56 1308.57 1336.81 1368.58 1404.59

3 Selling Price (``/t) 1386.83 1386.83 1386.83 1386.83 1386.83

4 Profit (`/t) 126.27 78.26 50.02 18.25 -17.76

5 IRR (%) 11.15% 7.14% 5.20% 3.26% 1.28%

6 DSP to yield 12% IRR 1396.89 1453.32 1486.52 1523.87 1566.19


ADD - ON SLIDES

Appendix - C.4
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Option - III (b) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines for Dumping) - Incremental 4.5 Mtpa
Statement showing Sensitivity of IRR

Option - III (b) (Incremental - 4.5 Mtpa)


Capacity Utilisation
Sl No. Particulars
100% 90% 85% 80% 75%
A Base Case 11.15% 7.14% 5.20% 3.26% 1.28%
B Increase in Capital          
  1)5% 10.17% 6.39% 4.54% 2.67% 0.76%
  2)10% 9.29% 5.71% 3.93% 2.13% 0.27%
  3)15% 8.50% 5.08% 3.36% 1.62% -0.19%
C Increase in Op.Cost          
  1)5% 6.79% 3.42% 1.71% -0.06% -1.91%
  2)10% 3.01% 0.02% -1.56% -3.23% -5.02%
  3)15% -0.41% -3.18% -4.69% -6.32% -8.12%
D Decrease in Sales          
  1)5% 5.86% 2.65% 1.00% -0.71% -2.51%
  2)10% 1.19% -1.58% -3.06% -4.65% -6.37%
  3)15% -3.24% -5.78% -7.20% -8.76% -ve
E Increase in Cap.+Op.Cost          
  1)5% 6.10% 2.86% 1.20% -0.52% -2.32%
  2)10% 2.01% -0.81% -2.32% -3.92% -5.65%
  3)15% -1.51% -4.12% -5.56% -7.12% -8.84%
ADD - ON SLIDES

Appendix - D

RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)

Option - III (b) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines for Dumping) - Incremental 4.5 Mtpa

Statement Showing Estimated Cash Flow Analysis

(Pre-Tax IRR on Total Capital)

At 100% capacity utilisation

Option - III (b) (Incremental - 4.5 Mtpa)           (Amt. in ` Lakhs)

Sl.
Particulars Existing Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total
No.

1 Initial Capital     4475.79 61394.68 34019.84                               99890.32

2 Replacement Capital             182.00 731.00   182.00 731.00   819.23 5538.75 1879.76 182.00 876.20 145.60   -3372.78 7894.76

3 Less: GST credit on Capital Goods       706.93 2154.73   27.76 111.51   27.76 111.51   110.58 795.19 286.74 27.76 111.51       4471.98

4 Cash Operating Expenses   13356.58 18260.84 27489.56 55520.59 55999.42 56270.96 56543.59 56633.54 56662.04 56691.81 56722.91 56651.87 54434.98 44157.76 34346.78 34382.54 32769.71 32119.19 29993.11 829007.77

5 Total Cash Outflow   13356.58 22736.63 88177.32 87385.70 55999.42 56425.19 57163.08 56633.54 56816.28 57311.30 56722.91 57360.52 59178.54 45750.77 34501.02 35147.23 32915.31 32119.19 26620.34 932320.87

6 Inflow from Sales   27320.47 27320.47 27320.47 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 55473.04 55473.04 47290.77 1051491.56

7 Net Cash Flow   13963.89 4583.84 -60856.84 -24978.53 6407.76 5981.98 5244.09 5773.63 5590.90 5095.88 5684.27 5046.66 3228.63 16656.41 27906.16 27259.94 22557.74 23353.85 20670.43 119170.69

8 Coal Production (Lakh Tonnes)   19.70 19.70 19.70 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 40.00 40.00 34.10 758.20

9 Pre Tax Internal rate of return       11.15%                                  

Desired Selling Price to Yield 12% IRR


10       1396.89                                  
(`/t)

11 Net Present Value (` Lakhs)       -2696.60                                  


ADD - ON SLIDES

Appendix - D.1

RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)

Option - III (b) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines for Dumping) - Incremental 4.5 Mtpa

Statement Showing Estimated Cash Flow Analysis

(Pre-Tax IRR on Total Capital)

At 85% capacity utilisation

Option - III (b) (Incremental - 4.5 Mtpa) (Amt. in ` Lakhs)

Sl.
Particulars Existing Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total
No.

1 Initial Capital     4475.79 61394.68 34019.84                               99890.32

2 Replacement Capital             182.00 731.00   182.00 731.00   819.23 5538.75 1879.76 182.00 876.20 145.60   -3372.78 7894.76

3 Less: GST credit on Capital Goods       706.93 2154.73   27.76 111.51   27.76 111.51   110.58 795.19 286.74 27.76 111.51       4471.98

4 Cash Operating Expenses   11790.61 15963.23 24282.41 48821.25 49294.60 49556.78 49820.06 49907.54 49935.93 49965.58 49996.56 49940.59 48060.87 39330.10 30995.88 31031.63 29663.52 29116.49 27312.17 734785.80

5 Total Cash Outflow   11790.61 20439.03 84970.16 80686.36 49294.60 49711.02 50439.55 49907.54 50090.16 50585.07 49996.56 50649.24 52804.44 40923.11 31150.11 31796.33 29809.12 29116.49 23939.40 838098.90

6 Inflow from Sales   23222.40 23222.40 23222.40 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 47152.09 47152.09 40197.16 893767.83

7 Net Cash Flow   11431.80 2783.38 -61747.76 -27640.26 3751.50 3335.08 2606.55 3138.56 2955.94 2461.03 3049.53 2396.86 241.66 12122.99 21895.99 21249.77 17342.97 18035.60 16257.76 55668.93

8 Coal Production (Lakh Tonnes)   16.75 16.75 16.75 38.25 38.25 38.25 38.25 38.25 38.25 38.25 38.25 38.25 38.25 38.25 38.25 38.25 34.00 34.00 28.99 644.47

9 Pre Tax Internal rate of return       5.20%                                  

Desired Selling Price to Yield 12% IRR


10       1486.52                                  
(`/t)

11 Net Present Value (` Lakhs)       -22714.14                                  


ADD - ON SLIDES
Option-I
                                       
As per Existing as As per
  SIZE/ Balance
HEMM sanctioned on completion
CAP. Provision Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total
3.5 Mtpa 31.03.2018 report

A. OBR                                                  
1 Electric Rope Shovel 20m3 8 6 6 8 8 8 8 8 8 8 8 8 8 8 8 8 7 6 5 8
OUTSOURCING

OUTSOURCING
OUTSOURCING

OUTSOURCING
2 Diesel Hyd. Backhoe 10-12m3 2 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1 2
3 Rear Dumper 190-210T 64 48 48 64 64 64 64 64 64 64 64 64 64 64 64 64 56 48 40 64
4 Rear Dumper 100T 20 14 16 20 20 20 20 20 20 20 20 20 20 20 20 20 20 10 10 20
5 RBH Drill (Electric) 250mm 10 7 7 10 10 10 10 10 10 10 10 10 10 10 10 10 9 7 6 10
6 Dozer 850 HP 8 6 6 8 8 8 8 8 8 8 8 8 8 8 8 8 7 6 5 8
7 Dozer 410 HP 2 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1 2
B. Coal Winning                                                  
1 Diesel Hyd. Shovel 10-12m3 1 - 1* 1 1 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1 2
2 Diesel Hyd. Backhoe 10-12m 3
1 1 1 - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
3 Rear Dumper 85T - 1   - 1                                      
4 Rear Dumper 100T 10 14 15 5 14 15 15 20 20 20 20 20 20 20 20 20 20 20 20 20 20 16 16 20
5 RBH Drill (Diesel) 160mm 3 4 5 1 5 5 5 6 6 6 6 6 6 6 6 6 6 6 6 6 6 5 4 6
6 Dozer 410 HP 2 2 2 1 2 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 2 2 3
C. Common                                                  
1 FE Loader* 5.74/6.4m3 1 1 1 - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
2 FE Loader* 10-12m3       1       1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
3 Motor Grader 280 HP 2 2 2 2 2 2 3 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
4 Hyd. Backhoe 2.8/3.5 m3 2 1 2## - 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
5 Mobile Crane 30-50T 2 2 2 - 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
6 Mobile Crane 8-10T 2 2 2 3 2 2 4 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
7 Wheel Dozer/Dozer 410 HP 1 1 1 - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
D Reclamation                                                  
1 Dozer 410 HP 2 4 4 1 4 4 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
2 Motor Grader 280 HP 1 2 - 1 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
3 Water Sprinkler 28 KL 3 3 4** - 4 4 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
2(1+
4 Water Sprinkler 70KL - - - 2     - 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
1**)
Road Sweeping
5
Machine
- - 1 - - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
6 Mist SprayGun   - - - 2     1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
 * 1 No. 10-12m3 Hyd. Shovel transferred to other project in Completion Report.                                        

 ** 2 No. 28 KL Water Sprinkler to be upgraded to 1 No. 70 KL Water Sprinkler.                                        

 ## 1 No. 2.8 m3 Hyd. Shovel transferred to other project in Completion Report.                                        
ADD - ON SLIDES
Option-II
                                       
As per As per
  Existing as on Balance
HEMM SIZE/ CAP. sanctioned completion
31.03.2018 Provision
3.5 Mtpa report Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total

A. OBR                                                  

1 Electric Rope Shovel 20m3

2 Diesel Hyd. Backhoe 10-12m3


OUTSOURCING

OUTSOURCING

OUTSOURCING

OUTSOURCING

OUTSOURCING
3 Rear Dumper 190-210T

4 Rear Dumper 100T OUTSOURCING


5 RBH Drill (Electric) 250mm

6 Dozer 850 HP

7 Dozer 410 HP

B. Coal Winning                                                  
1 Diesel Hyd. Shovel 10-12m 3
1 - 1* 1 1 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1 2
2 Diesel Hyd. Backhoe 10-12m3 1 1 1 - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
3 Rear Dumper 85T - 1   - 1                                      
4 Rear Dumper 100T 10 14 15 5 14 15 15 20 20 20 20 20 20 20 20 20 20 20 20 20 20 16 16 20
5 RBH Drill (Diesel) 160mm 3 4 5 1 5 5 5 6 6 6 6 6 6 6 6 6 6 6 6 6 6 5 4 6
6 Dozer 410 HP 2 2 2 1 2 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 2 2 3
C. Common                                                  
1 FE Loader* 5.74/6.4m3 1 1 1 - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
2 FE Loader* 10-12m 3
- - - 1       1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
3 Motor Grader 280 HP 2 2 2 2 2 2 3 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
4 Hyd. Backhoe 2.8/3.5 m 3
2 1 2##
- 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
5 Mobile Crane 30-50T 2 2 2 - 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
6 Mobile Crane 8-10T 2 2 2 3 2 2 4 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
7 Wheel Dozer/Dozer 410 HP 1 1 1 - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
D Reclamation                                                  
1 Dozer 410 HP 2 4 4 1 4 4 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
2 Motor Grader 280 HP 1 2 - 1 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
3 Water Sprinkler 28 KL 3 3 4** - 4 4 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
2(1+1
4 Water Sprinkler 70KL - - - 2     - 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
**)
5 Road Sweeping Machine - - 1 - - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
6 Mist SprayGun   - - - 2     1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
 * 1 No. 10-12m3 Hyd. Shovel transferred to other project in Completion Report.                                          
** 2 No. 28 KL Water Sprinkler to be upgraded to 1 No. 70 KL Water Sprinkler.                                        
ADD - ON SLIDES
Option III(a) & III(b)
                                       
As per As per
  Existing as on Balance
HEMM SIZE/ CAP. sanctioned completion
31.03.2018 Provision
3.5 Mtpa report Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total

A. OBR                                                  

1 Electric Rope Shovel 20m3

2 Diesel Hyd. Backhoe 10-12m3


OUTSOURCING

OUTSOURCING

OUTSOURCING

OUTSOURCING

OUTSOURCING
3 Rear Dumper 190-210T

4 Rear Dumper 100T OUTSOURCING


5 RBH Drill (Electric) 250mm

6 Dozer 850 HP

7 Dozer 410 HP

B. Coal Winning                                                  
1 Diesel Hyd. Shovel 10-12m 3
1 - 1* 1 1 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1 2
2 Diesel Hyd. Backhoe 10-12m3 1 1 1 - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
3 Rear Dumper 85T - 1   - 1                                      
4 Rear Dumper 100T 10 14 15 5 14 15 15 20 20 20 20 20 20 20 20 20 20 20 20 20 20 16 16 20
5 RBH Drill (Diesel) 160mm 3 4 5 1 5 5 5 6 6 6 6 6 6 6 6 6 6 6 6 6 6 5 4 6
6 Dozer 410 HP 2 2 2 1 2 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 2 2 3
C. Common                                                  
1 FE Loader* 5.74/6.4m3 1 1 1 - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
2 FE Loader* 10-12m3 - - - 1       1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
3 Motor Grader 280 HP 2 2 2 2 2 2 3 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
4 Hyd. Backhoe 2.8/3.5 m3 2 1 2## - 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
5 Mobile Crane 30-50T 2 2 2 - 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
6 Mobile Crane 8-10T 2 2 2 3 2 2 4 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
7 Wheel Dozer/Dozer 410 HP 1 1 1 - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
D Reclamation                                                  
1 Dozer 410 HP 2 4 4 1 4 4 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
2 Motor Grader 280 HP 1 2 - 1 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
3 Water Sprinkler 28 KL 3 3 4** - 4 4 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
2(1+
4 Water Sprinkler 70KL - - - 2     - 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
1**)
5 Road Sweeping Machine - - 1 - - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
6 Mist SprayGun   - - - 2     1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
 * 1 No. 10-12m3 Hyd. Shovel transferred to other project in Completion Report.                                          
ADD - ON SLIDES

Appendix-F

Recast EPR for Block-B Opencast Project (8 Mtpa)


STATEMENT OF ESTIMATED CAPITAL INVESTMENT ON ENVIRONMENTAL MANAGEMENT

Base Date: Oct, 2018


Option-I (Total Coal & Total OB Departmental ) (Amt. in ` Lakhs)
Existing Total Provn. Reference
SI. NO. PARTICULARS Balance Provision
(3.5 Mtpa) (8 Mtpa) Appendices
           
1 Arboriculture/Plantation   122.29 122.29 A.8.1
           
2 Compesatory Afforestation   12465.00 12465.00 A.8.1
         
3 Technical Reclamation 1332.99 1122.66 2455.65 E
           
4 Pollution Abatement Cost (Mine Area)        
           
  a) Water Sprinkler 307.10 450.64 757.74 E
           
  c) Dust Suppression/Extraction in CHP   40.00 40.00 A.3.5.2
           
5 Pollution Abatement Cost (Residential Area)        
           
  a) Colony Sewerage 481 296.12 777.35 A.8.3
           
  b) Green Belt Development   60.00 60.00 A.8.1
           
6 Anti-pollution Measures (Industrial Area)        
           
  a) Industrial Sewerage 482 1274.74 1756.49 A.8.3
           
b) Community Development   196.15 196.15 A.8.1
           
c) Open Lungs   16.04 16.04 A.8.1
       
7 Rain Water Harvesting   250.00 250.00 A.8.1
  INITIAL CAPITAL 2295.96 15843.00 18138.96  
ADD - ON SLIDES

Appendix-F

Recast EPR for Block-B Opencast Project (8 Mtpa)


STATEMENT OF ESTIMATED CAPITAL INVESTMENT ON ENVIRONMENTAL MANAGEMENT

Base Date: Oct, 2018


Option-II (Amt. in ` Lakhs)
Existing Total Provn. Reference
SI. NO. PARTICULARS Balance Provision
(3.5 Mtpa) (8 Mtpa) Appendices
           
1 Arboriculture/Plantation   122.29 122.29 A.8.1
           
2 Compesatory Afforestation   12465.00 12465.00 A.8.1
         
3 Technical Reclamation 1332.99 1122.66 2455.65 E
           
4 Pollution Abatement Cost (Mine Area)        
           
  a) Water Sprinkler 307.10 450.64 757.74 E
           
  c) Dust Suppression/Extraction in CHP   40.00 40.00 A.3.5.2
           
5 Pollution Abatement Cost (Residential Area)        
           
  a) Colony Sewerage 481 136.69 617.92 A.8.3
           
  b) Green Belt Development   60.00 60.00 A.8.1
           
6 Anti-pollution Measures (Industrial Area)        
           
  a) Industrial Sewerage 482 1156.76 1638.51 A.8.3
           
b) Community Development   196.15 196.15 A.8.1
           
c) Open Lungs   16.04 16.04 A.8.1
       
           
7 Rain Water Harvesting   250.00 250.00 A.8.1
  INITIAL CAPITAL 2295.96 15565.59 17861.55  
ADD - ON SLIDES

Appendix-F

Recast EPR for Block-B Opencast Project (8 Mtpa)


STATEMENT OF ESTIMATED CAPITAL INVESTMENT ON ENVIRONMENTAL MANAGEMENT

Base Date: Oct, 2018


Option-III(a) & III(b) (Amt. in ` Lakhs)
Existing Total Provn. Reference
SI. NO. PARTICULARS Balance Provision
(3.5 Mtpa) (8 Mtpa) Appendices
           
1 Arboriculture/Plantation   122.29 122.29 A.8.1
           
2 Compesatory Afforestation   12465.00 12465.00 A.8.1
         
3 Technical Reclamation 1332.99 1122.66 2455.65 E
           
4 Pollution Abatement Cost (Mine Area)        
           
  a) Water Sprinkler 307.10 450.64 757.74 E
           
  c) Dust Suppression/Extraction in CHP   40.00 40.00 A.3.5.2
           
5 Pollution Abatement Cost (Residential Area)        
           
  a) Colony Sewerage 481 136.69 617.92 A.8.3
           
  b) Green Belt Development   60.00 60.00 A.8.1
           
6 Anti-pollution Measures (Industrial Area)        
           
  a) Industrial Sewerage 482 1156.76 1638.51 A.8.3
           
b) Community Development   196.15 196.15 A.8.1
           
c) Open Lungs   16.04 16.04 A.8.1
       
           
7 Rain Water Harvesting   250.00 250.00 A.8.1
  INITIAL CAPITAL 2295.96 15565.59 17861.55  
ADD - ON SLIDES

Appendix-A.1
Recast EPR for Block-B Opencast Project (8 Mtpa)
Statement of Estimated Capital Investment on Land
Base Date: October, 2018
Option-II (Coal Departmental & OB Outsourcing)         (Amt. in ` Lakhs)
Sanctioned Report Total Provision Existing as on Balance Provision Phasing of Balance
(3.5 Mtpa) (8 Mtpa) 31.3.18 (3.5 Mtpa) ( 4.5 Mtpa) Provision

Sl.
Particulars Rate
No. Qty. Existing Qty.
Qty.(Ha) Amt. Qty.(Ha) Amt. Amt. (`Lakh Amt. Yr-1 Yr-2 Yr-3 Yr-4
(Ha) Amt. (Ha)
/Ha)

  PHASE -I                            

Leased Leased
Leased
land, land
land, Leased
amount Amount
amount land on
1 Forest Land 447 1070.25 447   shown 623.25   shown        
shown Mine Dev.
in Mine on Mine
in Mine Fund
Dev. Dev.
Dev. Fund
Fund Fund

                             
Non -Forest
2 Land (Total) 892 858.0 1186.92 858.0 1065.81   858 121.11        
  a) Govt. Land 429           51.78          
b) Tenancy
  Land 463     19767.0       69.33 285.11 19766.95      
Total 1339.00 858.0 2257.17 25522 1512.81 5755 858 744.36   19766.95 988.35 18778.60  
   
ADD - ON SLIDES

Appendix-A.8.1
Recast EPR of Block-B Opencast Project (8 Mtpa)
Statement showing the Capital Expenditure on Capital Outlay
(SUMMARY)
Base Date: October, 2018
Option-II (Coal Departmental & OB Outsourcing) (Amt. in ` '00000)
Total Provision (8 Yearwise Phasing of Balance
Sl. Existing as on 31.3.18 (3.5 Mtpa) Balance Provision (4.5 Mtpa)
Mtpa) Provision
Item Description Unit
Committed Existing Rate in Rs.
No. Qty. Amt. Qty. Qty. Amt. Yr-1 Yr-2 Yr-3 Yr-4
Amt. Amt. Lakh
                         
1 Earth work in filling and banking                    
  a)Colony/ Aproach Road     282.75         282.75      
b) Workshop     259.81         259.81        
  Total (a+b) including 18% GST     640.22           640.22     128.0 512.18
2 Open Lungs     16.04           16.04     3.2 12.83
3 a) Development of land for residential     131.28         131.28     26.3 105.02
  and other buildings                        
b) Renovation of existing buildings     209.51         209.51     41.9 167.61
  in the colony                        
4 Community Development     196.15           196.15   9.8 186.34  
5 Arboriculture     122.29           122.29   6.1 116.18  
Rehabilitation work and house compensation of PAP 15192.0
6 nos. 207 15991.58       207   15991.58   799.6  
( 207 Nos.) 0
7 One time cash grant compensation against R&R                 0.00        
2140.5 1246.5 11841.7
8 Compensatory Afforestation (Balance Land 2x623.25 Ha) Ha 12465.00 894.00     10.000 12465.00   623.3  
0 0 5
1070.2
9 Net Present Value of Forest Land ha 5733.90 447     623.25 9.2 5733.90   286.7 5447.21  
5
10 Retaining wall/ Garland drain     160.85           160.85     32.2 128.68
11 Diversion of Nalla/ rain water etc.     210.34           210.34     42.1 168.27
12 Chain linked fencing around colony and quarry     278.06           278.06     55.6 222.45
13 Water Recharge & Harvesting Arrangement     250.00           250.00     50.0 200.00
14 Green belt Development of mine     60.00           60.00     12.0 48.00
Diversion of rail line or Provision of OB haul road bridge
15     1000.00         LS 1000.00     200.0 800.00
over rail line
16 Development - Others/spent     0.00                    
17 Tree feeling cost for Block-B           623.25 600.3212 374.15     74.8 299.32

  Total     40694.94   204.00 2651.6     37839.37   1725.4 33449.6 2664.36

*Rehabilitation/House compensation rate as per Jayant


OCP report
ADD - ON SLIDES

The Financial analysis summary based on actual average sales price of last three years
has been done and findings are given below

Option-I Option-II Option-III (a) Option-IIII (b)


Sl.
Particulars (Incremental (Incremental (Incremental 4.5 (Incremental 4.5
No.
4.5 Mtpa) 4.5 Mtpa) Mtpa) Mtpa)

1 Output (Mtpa) 4.50 4.50 4.50 4.50


Cost (`/t) - at
2077.31 1097.45 1166.35 1260.56
2 100%
- at 85% 2348.68 1169.11 1240.44 1336.81
3 Selling Price (`/t) 1523.09 1523.09 1523.09 1523.09
Profit (`/t) - at
-554.22 425.64 356.74 262.53
4 100%
- at 85% -825.59 353.98 282.65 186.28
FIN IRR (%) - at 100% -ve +ve +ve 27.83%
5
- at 85% -ve 34.99% 22.03% 14.94%

NPV (` Lakhs) - at 100% -270630.30 75495.04 55628.03 33828.89


6
- at 85% -309654.37 44767.78 26999.31 8332.52
ADD - ON SLIDES
ADD - ON SLIDES
ADD - ON SLIDES

COMPARISON

Balance Land UCE may


Type of Land Balance Land recast EPR nov.2018
2017
diff

Forest Land 623.25 393.62 229.63

Non-Forest Land 121.11 997.94 -876.83

Total 744.36 1391.56 -647.2

RS. CRS

Particulars diff.
Land Cost recast EPR Nov-18 Land Cost UCE May-17
Tenancy Land 197.67 319 -121.33
NPV 124.65 9.3238 115.3262
CA 57.339 24.6406 32.6984
Total 379.66 352.96 26.6946

  PAPS TOTAL COST  

RECAST EPR NOV. 18   207 15991.58 lakhs


R&R

UCE May 2017   1500 10440 lakhs

difference 5551.58 lakhs


comparison between Recast EPR 2018 and UCE May 2017
    (Amt. in ` Lakh)
Option -II Recast EPR 2018 Option II UCE May 2017 Difference in cost
Integrated Incremental (4.5 Integrated (8 Incremental (4.5
SL NO PARTICULARS (8 Mtpa) Mtpa) Mtpa) Mtpa) Integrated Incremental
TOTAL TOTAL PROVN TOTAL PROVN (8 Mtpa) (4.5 Mtpa)
TOTAL PROVN
PROVN (8 (4.5
(4.5 Mtpa)
(8 Mtpa) Mtpa) Mtpa)
1 Land 25522 19767 32758 31900 -7236 -12133
2 Buildings    
  a) Service 5846 5550 6773 4837 -926 713
  b) Residential 5158 3402 6451 4030 -1293 -628
  Sub Total 11004 8953 13223 8867 -2219 86
3 Plant & Machinery
  a) H. E. M. M. 13826 5766 16152 9198 -2326 -3433
  b) CHP 33584 10182 30403 6519 3181 3663
  c) Pumping 781 621 2572 2222 -1791 -1602
  d) Electrical 2996 2493 3192 2597 -196 -104
  e) Workshop 1966 1722 1705 1576 260 146
  f) Other P&M 127 62 134 62 -6 0
  Sub Total 53280 20846 54158 22174 -879 -1329
4 Furniture & Fittings 277 58 242 57 35 1
5 Railway Siding 8516 0 8261 0 255 0
6 Vehicles 939 711 901 730 38 -19
7 Prospecting & Boring 44 0 44 0 0 0
8 Development
8.1 Capital Outlay in Mines 40695 37839 23405 16898 17290 20941
8.2 Roads & Culverts 3712 3146 3500 3064 212 82
8.3 Water Supply & Sewerage 6617 5586 5929 4769 688 817
8.4 Scientific Research 80 80 80 80 0 0
8.5 P.R. Prep. Cost 1762 1762 1992 1992 -230 -230
  Sub Total 52867 48414 34907 26803 17960 21611
9.1 Revenue Exp. Capitalised less Depreciation 0 0 0 0 0 0
10 Land Reclamation 2456 1123 1760 692 695 431
  TOTAL CAPITAL 154903 99871 146255 91223 8648 8648
  IRR
  at 100% 81.02% 29.15% 32.92% 20.82%    
  at 85% 39.21% 16.72% 21.09% 13.51%    
LINE DAIGRAM OF PROJECT BOUNDARY
ADD - ON SLIDES

Mineable Reserves (Mt)

Sanctioned PR Balance Incremental Total


Expansion
(3.5 Mtpa) As on 01.04.16 (4.50 Mtpa) (8 Mtpa)
Seam

Coal OBR Coal OBR Coal OBR Coal OBR

Purewa 20.97
Merged 28.51   57.70 78.67
     
656.39
290.14 177.13 479.26
Turra 59.16 33.29 36.81 70.10
Total 87.67 290.14 54.26 177.13 94.51 479.26 148.77 656.39

Stripping
3.31 3.26 5.07 4.41
Ratio
LAND REQUIREMENT PLAN

1) Land Requirement Plan Op-I &II Pdf


2) Land Requirement Plan Op-III
LAND REQUIREMENT PLAN

1) Land Requirement Plan Op-I &II Pdf


2) Land Requirement Plan Op-III
MASTER PLAN

Master Plan pdf


DUMP PLAN OPTION-I & II

Dump plan Option-I & II Pdf


DUMP PLAN OPTION-III

Dump plan Option-III Pdf


CROSS-SECTION

CROSS SECTION PDF


MAIN INFRASTRUCTURE
Coal Flow Diagram

PDF Plan
Option –III (b)
(Crushing and conveying of part OB to Old Gorbi Mine with spreader system)

Tentative estimation for Crushing and conveying of part OB to Old Gorbi Mine with
following considerations:
• Semi mobile crushing plant with double roll sizers; each capacity 3000 Tph ,
ROM OB from -1500 mm to -250/-300 mm size.
• 2 nos. rock breaker for breaking the above ROM -1500 mm OB
• Spreader with tipper car 6000 Tph.
• Transport Crawler, 400t.
• Associated conveyors.
Operating Cost
Sl. No. Particulars Amt (` Lakhs) Sl. No. Particulars Amt.(Rs. Lakhs)
1 Depreciation on P&M 2838.61
2 Depreciation on Belting 376.56
1 Conveyor 5566
3 Salary Wages 102.26
2 Equipment 18746
4 Power 4144.73
3 Electrical Equipment 4155
4 Civil Structure 9640 5 Stores 1144.164
5 Errection & commissioning 3186 6 Misc. Exp. 288.73
6 Design & Engg. 1752 7 Interest on working capital 274.53
7 Over head construction cost 5519   Total Cost 9169.58
8 Insurance 335
9 Contigency 1559
10 Misc. Electrical &Mechanical items 637 OB Quantity per year : 8.5 Mm3
11 Belting (steel) 3389
  Total Capital 54484
Operating Cost : 107.88 Rs./Bm3
OB Crushing & Conveying System

PDF
POWER SUPPLY ARRANGEMENT

• The estimated peak power demand and annual energy consumption


for 8 Mtpa is given below:

Installed Peak Power Annual Energy


Name of Substation Capacity Source Demand Consumption
(MVA) (KVA) (MKWH)

Proposed Sub-station
40 Madhauli S/S 16784 96.14
Option-I

Proposed Sub-station
Option-II & III (a) 30 Madhauli S/S 8841 40.26

Proposed Sub-station APPENDIX A3.2 OPTION I OPTION II


40 Madhauli S/S 13047OPTION III OPTION IV 57.91
Option-III(b)
CAPITAL INVESTMENT OPTION- III (b) (INCREMENTAL 4.5 MTPA)
Option III (b)
Incremental (4.5 Mtpa)
SL. NO. PARTICULARS
Land Reclamation
Total Provn. (8 Mtpa) (Rs. %age of Total 1.12%
Lakhs) Capital
1 Land 19767 19.79
2 Buildings
  a) Service 5550 5.56
  b) Residential 3402 3.41
  Sub Total 8953 8.96 Land
3 Plant & Machinery 19.79%
  a) H. E. M. M. 5766 5.77
  b) CHP 10182 10.19
  c) Pumping 621 0.62
Buildings
  d) Electrical 2512 2.52 Development. 8.96%
  e) Workshop 1722 1.72 48.47%
  f) Other P&M 62 0.06
  Sub Total 20865 20.89
4 Furniture & Fittings 58 0.06
Plant & Machinery
5 Railway Siding 0 0.00 20.89%
6 Vehicles 711 0.71
7 Prospecting & Boring 0  
8 Development.
8.1 Capital Outlay in Mines 37839 37.88
8.2 Roads & Culverts 3146 3.15 Others
0.77%
8.3 Water Supply & Sewerage 5586 5.59
8.4 Scientific Research 80 0.08
8.5 P.R. Prep. Cost 1762 1.76
  Sub Total 48414 48.47 Appendix A: Option-III(b) (Incremental)
Revenue Exp. Capitalised less  
9.1  
Depreciation
10 Land Reclamation 1123 1.12
  INITIAL CAPITAL 99890 100.00
COST OF PRODUCTION (`\t) Option – I (Integrated)

    Option-I (Integrated)
At 85% Capacity
At 100% At 85%
Sl. No. Particulars Capacity Capacity
Salary & Wages
10%
1 Salary & Wages 238.47 280.55 Adminstrative
Cost (Notional)
1% Depreciation
2 Stores 625.73 687.79 12%

3 Power 82.27 93.16


4 Misc. Expenses 86.42 94.79
Stores
24%
5 Adminstrative Cost (Cash) 3.62 4.26
6 Mine Closure Cost 18.88 22.21
7 OB Outsourcing 18.12 18.12 Total Cash Cost
43%
8 COAL Outsourcing 0.00 0.00 Misc. Expenses
3%
Power
9 Interest on Working capital 51.89 58.04 Adminstrative
3% (Cash)
Cost
0%
10 Total Cash Cost 1125.39 1258.92 Interest on Work-
Mine Closure Cost
1%
ing capital
11 Interest 0.00 0.00 2% OB Outsourcing
1%

12 Adminstrative Cost 30.91 36.36 Appendix C


(Notional) Appendix D
Appendix C1
13 Depreciation 292.76 344.42 Appendix C2 Appendix D1

  Total 1449.05 1639.70


COST OF PRODUCTION (`\t) Option – I (Incremental)

    Option-I (Incremental)
Sl. At 100% At 85% At 85% Capacity
Particulars Capacity Capacity
No.
1 Salary & Wages 296.32 348.62
2 Stores 964.48 1061.69
Salary & Wages
3 Power 118.45 134.12 Adminstrative Depreciation 15%
Cost (No- 22%
4 Misc. Expenses 121.22 132.10
tional)
2%
Interest on
5 Adminstrative Cost (Cash) 3.62 4.26
Working capi-
tal
4%
6 Mine Closure Cost 13.88 16.33 OB Outsourc-
ing
1%
7 OB Outsourcing 11.88 11.88 Mine Closure
Cost
1%
8 COAL Outsourcing 0.00 0.00 Adminstrative
Cost (Cash) Power Stores
9 Interest on Working capital 73.94 82.60 0% 6% 45%

Misc.
10 Total Cash Cost 1603.78 1791.59
Ex-
penses
6%
11 Interest 0.00 0.00
12 Adminstrative Cost
(Notional) 30.91 36.36
Appendix C Appendix D
13 Depreciation 442.62 520.73
Appendix C1
Appendix D1
  Total 2077.31 2348.68 Appendix C2
CAPITAL INVESTMENT OPTION- I (INTEGRATED 8 MTPA)
Option -I
Integrated (8 Mtpa)
SL. NO. PARTICULARS Total Provn.
%age of Total
(8 Mtpa) Capital
(Rs. Lakhs) Land Reclamation Buil
Rail ding
1 Land 25522 6.24 way 0.60%
s
Sid- 5.28
Buildings ing Land %
2 a) Service 10069 2.46 2.08 6.24%
%
  b) Residential 11534 2.82 Development.
  Sub Total 21603 5.28 13.21%
  Plant & Machinery
Oth
a) H. E. M. M. 252808 61.79 ers
3 b) CHP 33584 8.21 0.31
  %
  c) Pumping 781 0.19
  d) Electrical 4909 1.20
  e) Workshop 3535 0.86
  f) Other P&M 127 0.03
 
  Sub Total 295745 72.28
Furniture & Fittings 293 0.07
4 Railway Siding 8516 2.08
5 Vehicles 939 0.23
6 Prospecting & Boring 44 0.01
7 Development.
8 Capital Outlay in Mines 40695 9.95
8.1 Roads & Culverts 4523 1
Water Supply &
8.2 6972 1.70
Sewerage Plant & Machinery
72.28%
8.3 Scientific Research 80 0.02
8.4 P.R. Prep. Cost 1762 0.43
8.5 Sub Total 54032 13.21
  Revenue Exp. Appendix A: Option-I (Integrated)
Capitalised less    
9.1
Depreciation
10 Land Reclamation 2456 0.60
  INITIAL CAPITAL 409148 100.00
CAPITAL INVESTMENT OPTION- I (INCREMENTAL 4.5 MTPA)
Option -I
Incremental (4.5 Mtpa) Land Reclamation
SL. NO. PARTICULARS Total Provn. 0.32% Build-
%age of Total ings
(8 Mtpa) Capital
(Rs. Lakhs) Land 5.52%
5.58%
1 Land 19767 5.58
Buildings Development.
14.00%
2 a) Service 9773 2.76
  b) Residential 9779 2.76
  Sub Total 19551 5.52
  Plant & Machinery
3 a) H. E. M. M. 244748 69.12
  b) CHP 10182 2.88
  c) Pumping 621 0.18
  d) Electrical 4407 1.24
  e) Workshop 3291 0.93
  f) Other P&M 62 0.02
  Sub Total 263311 74.36
  Furniture & Fittings 74 0.02
4 Railway Siding 0 0.00
5 Vehicles 711 0.20
Others
6 Prospecting & Boring 0 0.00 0.22%
7 Development.
8 Capital Outlay in Mines 37839 10.69
8.1 Roads & Culverts 3956 1.12
Water Supply & Plant & Machinery
8.2 5942 1.68 74.36%
Sewerage
8.3 Scientific Research 80 0.02
8.4 P.R. Prep. Cost 1762 0.50
8.5 Sub Total 49579 14.00 Appendix A: Option-I (Incremental)
  Revenue Exp.
Capitalised less    
9.1
Depreciation
10 Land Reclamation 1123 0.32
  INITIAL CAPITAL 354116 100.00
CAPITAL INVESTMENT OPTION- II (INTEGRATED 8 MTPA)
Option -II
Integrated (8 Mtpa)
SL. Land Reclamation
NO. PARTICULARS Total Provn. 1.59%
%age of Total
(8 Mtpa)
Capital
(Rs. Lakhs)
1 Land 25522 16.48
Land
2 Buildings 16.48%
  a) Service 5846 3.77
  b) Residential 5158 3.33
  Sub Total 11004 7.10
3 Plant & Machinery
Development. Buildings
  a) H. E. M. M. 13826 8.93 34.13% 7.10%
  b) CHP 33584 21.68
  c) Pumping 781 0.50
  d) Electrical 2996 1.93
  e) Workshop 1966 1.27
  f) Other P&M 127 0.08
  Sub Total 53280 34.40
4 Furniture & Fittings 277 0.18
5.50 Plant & Machinery
5 Railway Siding 8516 34.40%
6 Vehicles 939 0.61
7 Prospecting & Boring 44 0.03 Railway Sid-
8 Development. ing
5.50%
8.1 Capital Outlay in Mines 40695 26.27 Others
2.40 0.81%
8.2 Roads & Culverts 3712
8.3 Water Supply & Sewerage 6617 4.27
8.4 Scientific Research 80 0.05
8.5 P.R. Prep. Cost 1762 1.14
  Sub Total 52867 34.13
Appendix A: Option-II (Integrated)
Revenue Exp. Capitalised less  
9.1  
Depreciation
10 Land Reclamation 2456 1.59
  INITIAL CAPITAL 154903 100.00
CAPITAL INVESTMENT OPTION- II (INCREMENTAL 4.5 MTPA)
Option -II
Incremental (4.5 Mtpa)
SL. Land Reclamation
PARTICULARS Total Provn. 1.12%
NO. %age of Total
(8 Mtpa) Capital
(Rs. Lakhs)
1 Land 19767 19.79
2 Buildings     Land
5.56 19.79%
  a) Service 5550
  b) Residential 3402 3.41
  Sub Total 8953 8.96
3 Plant & Machinery    
  a) H. E. M. M. 5766 5.77
  b) CHP 10182 10.20
  c) Pumping 621 0.62 Buildings
Development. 8.96%
  d) Electrical 2493 2.50 48.48%
  e) Workshop 1722 1.72
  f) Other P&M 62 0.06
  Sub Total 20846 20.87
4 Furniture & Fittings 58 0.06
5 Railway Siding 0 0.00 Plant & Machinery
20.87%
6 Vehicles 711 0.71
7 Prospecting & Boring 0 0.00
8 Development.    
8.1 Capital Outlay in Mines 37839 37.89
8.2 Roads & Culverts 3146 3.15 Others
8.3 Water Supply & Sewerage 5586 5.59 0.77%

8.4 Scientific Research 80 0.08


8.5 P.R. Prep. Cost 1762 1.76
  Sub Total 48414 48.48 Appendix A: Option-II (Incremental)
Revenue Exp. Capitalised less  
9.1  
Depreciation
10 Land Reclamation 1123 1.12
  INITIAL CAPITAL 99871 100.00
CAPITAL INVESTMENT OPTION- III (a) (INTEGRATED 8 MTPA)
Option III (a)
Land Reclamation
Integrated (8 Mtpa) 1.51%
SL. NO. PARTICULARS Total Provn. %age of Total
(8 Mtpa) Capital
(Rs. Lakhs)
1 Land 25522 15.68 Land
2 Buildings     15.68%
  a) Service 5846 3.59
  b) Residential 5158 3.17
  Sub Total 11004 6.76
3 Plant & Machinery    
  a) H. E. M. M. 13826 8.50 Buildings
  b) CHP 33584 20.64 6.76%
Development.
  c) Pumping 781 0.48 37.30%
  d) Electrical 2996 1.84
  e) Workshop 1966 1.21
  f) Other P&M 127 0.08
  Sub Total 53280 32.74
4 Furniture & Fittings 277 0.17
5 Railway Siding 8516 5.23
6 Vehicles 939 0.58 Plant & Machinery
7 Prospecting & Boring 44 0.03 32.74%
8 Development.    
8.1 Capital Outlay in Mines 40695 25.00
8.2 Roads & Culverts 11560 7.10 Rail
way
Water Supply & 4.07 Sid-
8.3 6617
Sewerage ing Others
8.4 Scientific Research 80 0.05 5.23 0.77%
%
8.5 P.R. Prep. Cost 1762 1.08
  Sub Total 60714 37.30
Revenue Exp.
Appendix A: Option-III(a) (Integrated)
9.1 Capitalised less    
Depreciation
10 Land Reclamation 2456 1.51
  INITIAL CAPITAL 162751 100.00
CAPITAL INVESTMENT OPTION- III (a) (INCREMENTAL 4.5 MTPA)
Land Reclamation
Option III (a) 1.04%
Incremental (4.5 Mtpa)
SL. NO. PARTICULARS
Total Provn. %age of Total
(8 Mtpa)
(Rs. Lakhs)
Capital
Land
1 Land 19767 18.35 18.35%
2 Buildings
  a) Service 5550 5.15
  b) Residential 3402 3.16
  Sub Total 8953 8.31
3 Plant & Machinery
Buildings
  a) H. E. M. M. 5766 5.35 8.31%
  b) CHP 10182 9.45
  c) Pumping 621 0.58 Development.
52.23%
  d) Electrical 2493 2.31
  e) Workshop 1722 1.60
  f) Other P&M 62 0.06 Plant & Machinery
  Sub Total 20846 19.35 19.35%
4 Furniture & Fittings 58 0.05
5 Railway Siding 0  
6 Vehicles 711 0.66
7 Prospecting & Boring 0  
8 Development.
8.1 Capital Outlay in Mines 37839 35.13
Others
8.2 Roads & Culverts 10994 10.21 0.71%
8.3 Water Supply & Sewerage 5586 5.19
8.4 Scientific Research 80 0.07
8.5 P.R. Prep. Cost 1762 1.64
  Sub Total 56261 52.23 Appendix A: Option-III (a) (Intcremental)
Revenue Exp. Capitalised  
9.1  
less Depreciation
10 Land Reclamation 1123 1.04
  INITIAL CAPITAL 107719 100.00
CAPITAL INVESTMENT OPTION- III (b) (INTEGRATED 8 MTPA)
Option III (b)
Integrated (8 Mtpa)
SL. NO. PARTICULARS Total Provn. %age of Total Land Reclamation
(8 Mtpa) Capital 1.59%
(Rs. Lakhs)
1 Land 25522 16.47
2 Buildings   Land
  a) Service 5846 3.77 16.47%
  b) Residential 5158 3.33
  Sub Total 11004 7.10
3 Plant & Machinery    
  a) H. E. M. M. 13826 8.92
Development. Buildings
  b) CHP 33584 21.68 34.12% 7.10%
  c) Pumping 781 0.50
  d) Electrical 3015 1.95
  e) Workshop 1966 1.27
  f) Other P&M 127 0.08
  Sub Total 53299 34.40
4 Furniture & Fittings 277 0.18
5 Railway Siding 8516 5.50
6 Vehicles 939 0.61
0.03 Plant & Machinery
7 Prospecting & Boring 44 34.40%
8 Development.    
8.1 Capital Outlay in Mines 40695 26.27 Railway Siding
8.2 Roads & Culverts 3712 2.40 5.50%
Others
8.3 Water Supply & Sewerage 6617 4.27 0.81%
8.4 Scientific Research 80 0.05
8.5 P.R. Prep. Cost 1762 1.14
  Sub Total 52867 34.12 Appendix A: Option-III (b) (Integrated)
Revenue Exp. Capitalised  
9.1  
less Depreciation
10 Land Reclamation 2456 1.59
  INITIAL CAPITAL 154922 100.00
PUMPING ARRANGEMENT

Maximum Rain Fall : 170 mm (in a day)


Catchment Area : m2
(Mine out- & Dump-1726650 m2 + Beyond Excv.-118631000m2)
Make of Water : 1327639 m /day 3

Pumping Capacity : 8382 m3/hr


Main Pump:

Sl.No. Items Qty.

1 Main Pump , 1100 m3/hr (305 lps), 250-300m head, 1500kw 2 Nos

2 Main Pump , 650 m3/hr (180 lps), 200-250m head, 450kw 4 Nos
3 Face pump 40m3/hr (11 lps), 30m head, 10 kW 2 N0s
4 Slurry pump 101m3/hr (28 lps), 28m head, 37kW 2 Nos
Diesel pump 289m3/hr (80 lps), 150m head complete with diesel
5 2 No.
engine and other accessories.
6 ERW Pipes LS
7 Pipe fittings, bends, armoured suction, delivery hoses etc. LS
8 Phantoons, moving trolleys etc. 2
COST OF PRODUCTION (`\t) Option – II (Integrated)

    Option-II (Integrated)
At 85% Capacity
Sl. At 100% At 85%
Particulars Capacity Capacity
No.
1 Salary & Wages 146.49 172.34 Depreciation Salary & Wages
13% 15%
2 Stores 156.14 168.48 Adminstrative Cost
(Notional)
3%
3 Power 34.83 39.43 Interest on Working
capital
4%
4 Misc. Expenses 36.07 40.34
Stores
5 Adminstrative Cost (Cash) 3.62 4.26 15%

6 Mine Closure Cost 18.88 22.21


Power
OB Outsourcing 3%
7 OB Outsourcing 479.78 479.78 42%
Misc. Expenses
3%
8 COAL Outsourcing 0.00 0.00 Adminstrative Cost
(Cash)
9 Interest on Working capital 42.33 44.80 0%
Mine Closure Cost
2%
10 Total Cash Cost 918.14 971.65
11 Interest 0.00 0.00

12 Adminstrative Cost 30.91 36.36


(Notional) Appendix C Appendix D
13 Depreciation 124.51 146.49 Appendix C1 Appendix D1
Appendix C2
  Total 1073.56 1154.50
COST OF PRODUCTION (`\t) Option – II (Incremental)
    Option-II (Incremental)

Sl. At 100% At 85%


Particulars Capacity Capacity At 85% Capacity
No.
1 Salary & Wages 129.09 151.87
Depreciation Salary & Wages
2 Stores 109.35 116.01 14% 13%
Adminstrative
3 Power 32.15 36.41 Cost (Notional)
3%
4 Misc. Expenses 29.54 32.96 Interest on
Working capital
4% Stores
10%
5 Adminstrative Cost (Cash) 3.62 4.26
Power
3%
Misc. Expenses
6 Mine Closure Cost 13.88 16.33 3%
Adminstrative
7 OB Outsourcing 569.78 569.78 OB Outsourcing
49%
Cost (Cash)
0%

8 COAL Outsourcing 0.00 0.00 Mine Closure


Cost
1%

9 Interest on Working 42.89 44.84


capital
10 Total Cash Cost 930.30 972.46
11 Interest 0.00 0.00

12 Adminstrative Cost
Appendix C
30.91 36.36
(Notional) Appendix C1
Appendix C2
13 Depreciation 136.24 160.28 Appendix D
  Total 1097.45 1169.11 Appendix D1
COST OF PRODUCTION (`\t) Option – III(a) (Integrated)

    Option-III (a) (Integrated)

Sl. At 100% At 85%


Particulars Capacity Capacity At 85% Capacity
No.
1 Salary & Wages 146.49 172.34
Adminstrative
2 Stores 156.14 168.48 Cost (No- Salary &
Wages
tional)
14%
3 Power 34.83 39.43 Interest on
3%

Working capi- Depreciation


4 Misc. Expenses 37.89 42.48 tal 13%
4%
5 Adminstrative Cost (Cash) 3.62 4.26
6 Mine Closure Cost 18.88 22.21 Stores
14%
7 OB Outsourcing 508.64 508.64
8 COAL Outsourcing 0.00 0.00 Power
3%
Interest on Working
9 43.81 46.30 OB Outsourcing Misc.
capital 43% Ex-
penses
4%
Adminstrative
10 Total Cash Cost 950.29 1004.14 Cost (Cash)
0%
Mine Closure
11 Interest 0.00 0.00 Cost
2%

12 Adminstrative Cost 30.91 36.36


Appendix C
Appendix C1
(Notional) Appendix C2
13 Depreciation 130.20 153.17 Appendix D
Appendix D1
  Total 1111.40 1193.67
COST OF PRODUCTION (`\t) Option – III(a) (Incremental)
  Option-III(a) (Incremental)
Sl. At 100% At 85% At 85% Capacity
Particulars Capacity Capacity
No.
1 Salary & Wages 129.09 151.87 Adminstrative
2 Stores 109.35 116.01 Interest on
Cost (Notional)
3% Salary & Wages
12%
3 Power 32.15 36.41 Working capital
4%

4 Misc. Expenses 32.84 36.85 Depreciation


14%
Adminstrative Cost
5 (Cash) 3.62 4.26 Stores
9%
Power
3%
6 Mine Closure Cost 13.88 16.33 Misc. Expenses
3%

7 OB Outsourcing 622.33 622.33 Adminstrative


Cost (Cash)
8 COAL Outsourcing 0.00 0.00 0%
Mine Closure
Cost

9 Interest on Working 45.59 47.56


OB Outsourcing
50%
1%

capital
10 Total Cash Cost 988.85 1031.62
11 Interest 0.00 0.00 Appendix C
12 Adminstrative Cost
Appendix C1
30.91 36.36 Appendix C2
(Notional) Appendix D
13 Depreciation 146.59 172.46 Appendix D1
  Total 1166.35 1240.44
COST OF PRODUCTION (`\t) Option – III(b) (Integrated)

 
  Option-III(b) (Integrated) Admin- At 85% Capacity
strative
At 100% At 85% Cost (No-
Sl. No. Particulars Capacity Capacity tional)
3%
Depreciation
Interest on 12% Salary & Wages
1 Salary & Wages 146.49 172.34 Working cap- 14%
ital
2 Stores 156.15 168.48
4%

3 Power 52.19 59.10


Stores
14%
4 Misc. Expenses 36.07 40.35 OB Crushing
& Conveying
5 Adminstrative Cost (Cash) 3.62 4.26
Cost
15%
Power
6 Mine Closure Cost 18.88 22.21
5%

7 OB Outsourcing 364.33 364.33 Misc.


Ex-
8 OB Crushing & Conveying penses
OB Outsourcing Admin-3%
Cost 182.71 182.71 29% strative
Cost (Cash)
9 COAL Outsourcing 0.00 0.00 0%
Mine Closure
10 Interest on Working capital 46.42 49.00 Cost
2%
11 Total Cash Cost 1006.87 1062.79
12 Interest 0.00 0.00 Appendix C
13 Adminstrative Cost Appendix C1
(Notional) 30.91 36.36 Appendix C2
Appendix D
14 Depreciation 124.52 146.50 Appendix D1
  Total 1162.30 1245.65
COST OF PRODUCTION (`\t) Option – III(b) (Incremental)

    Option-III(b) (Incremental)
Sl. At 100% At 85%
Particulars Capacity Capacity
No.
1 Salary & Wages At 85% Capacity
129.09 151.87
2 Stores 109.35 116.02
3 Power 65.23 73.86 Depreciation Salary & Wages
Adminstrative Cost 11%
4 Misc. Expenses 29.54 32.97 (Notional)
12%
3%
5 Adminstrative Cost (Cash) 3.62 4.26 Interest on Work-
ing capital
6 Mine Closure Cost 13.88 16.33 4% Stores
9%

7 OB Outsourcing 359.54 359.54 Power


6%
Misc. Expenses
8 OB Crushing & OB Crushing & 2%
Conveying Cost
Conveying Cost 332.73 332.73 25% Adminstrative Cos
(Cash)
0%
9 COAL Outsourcing 0.00 0.00 OB Outsourcing
Mine Closure Cost
27%
1%
10 Interest on Working capital 50.41 52.57
11 Total Cash Cost 1093.39 1140.14
12 Interest 0.00 0.00 Appendix C
13 Adminstrative Cost Appendix C1
(Notional) Appendix C2
30.91 36.36
Appendix D
14 Depreciation 136.26 160.31 Appendix D1
  Total 1260.56 1336.81
ADD - ON SLIDES

Not in use after wards


ADD - ON SLIDES

Not in use after wards


ADD - ON SLIDES

Not in use after wards


ADD - ON SLIDES

Not in use after wards


ADD - ON SLIDES

Seams, thickness, parting thickness & Seam-wise Geological Reserve

Thickness(m)
Geological Reserves (Mt)
Strategraphic Sequence
Min. Max. (As on 01.04.2015)

Top partings 63.78 210.50  

Purewa Merged Seam 8.00 31.10 81.56

Parting between Purewa Merged


60.00 80.00  
& Turra seam

Turra Seam 12.16 26.23 88.30

Total 169.86
ADD - ON SLIDES

QUALITY
V I & II B &C
Coal Prodn. Total Total
Year

(Mtpa) Turra PM Total


Turra GCV Grade PM GCV Grade Turra GCV PM GCV
Grade Grade

1 5.47 3.06 G7 1.41 G10 0.5 G7 0.5 G10 3.56 1.91 5.47
2 7 2.55 G8 2.45 G10 1.51 G7 0.49 G10 4.06 2.94 7
3 8 2.37 G8 2.63 G10 2.07 G7 0.93 G9 4.44 3.56 8
4 8 2.16 G8 2.84 G11 1.55 G7 1.45 G8 3.71 4.29 8
5 8 2.16 G8 2.84 G11 1.54 G7 1.46 G8 3.7 4.3 8
6 8 2.16 G8 2.84 G11 1.36 G7 1.64 G10 3.52 4.48 8
7 8 2.02 G8 2.98 G13 1.36 G7 1.64 G10 3.38 4.62 8
8 8 1.6 G8 2.40 G13 1.81 G7 2.19 G10 3.41 4.59 8
9 8 1.46 G8 2.20 G13 1.91 G7 2.43 G10 3.37 4.63 8
10 8 1.21 G8 1.79 G13 2.07 G8 2.93 G11 3.28 4.72 8
11 8         3.32 G8 4.68 G11 3.32 4.68 8
12 8         3.33 G8 4.67 G11 3.33 4.67 8
13 8         3.34 G7 4.66 G10 3.34 4.66 8
14 8         3.34 G7 4.66 G10 3.34 4.66 8
15 8         3.93 G8 4.07 G10 3.93 4.07 8
16 8         4.08 G8 3.92 G10 4.08 3.92 8
17 7         3.57 G8 3.43 G10 3.57 3.43 7
18 6         3.06 G8 2.94 G10 3.06 2.94 6
19 6         2.98 G8 3.02 G10 2.98 3.02 6
20 5.3         2.72 G8 2.58 G10 2.72 2.58 5.3
Total

148.77 20.75   24.38   49.35   54.29   70.1 78.67 148.77


ADD - ON SLIDES

GEOLOGICAL PLAN
ADD - ON SLIDES

GOOGLE EARTH IMAGE OF PROJECT AREA AND ITS SURROUNDINGS


ADD - ON SLIDES

CROSS-SECTIONS
ADD - ON SLIDES

CROSS-SECTIONS
ADD - ON SLIDES

CROSS-SECTIONS
ADD - ON SLIDES

CROSS-SECTIONS
ADD - ON SLIDES

EQUIPMENT PHASING
Years
As per
HEMM Size/ Cap. sanctioned Existing as on
01.04.15 Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Yr-20 Total
3.5 Mtpa

OBR                                                  
Electric Rope Shovel 20m3
Diesel Hyd. Backhoe 10-12m3
Rear Dumper 190t Outsoursing

Outsoursing
Outsoursing

Rear Dumper 100t


RBH Electric Drill 250mm
Dozer 850 HP
Dozer 411 HP
Coal Winning
Diesel Hyd. Shovel 10-12m3 1 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Diesel Hyd. Backhoe 10-12m3 1 - - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Rear Dumper 100t 10 15 15 22 22 22 22 22 22 22 22 22 22 22 22 22 22 22 19 16 14 14 22
RBH Electric Drill 160mm 3 4 4 5 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 5 5 6
Dozer 410 HP 2 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
Common                                                  
FE Loader 5.74m3 1 -                                          
FE Loader 10-12m3 - - - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Motor Grader 280 HP 2 1 1 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
Hyd. Backhoe 2.8 m3 2 - - 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Mobile Crane 50/40/30t 2 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Mobile Crane 8/10/11t 2 2 2 4 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6
Wheel Dozer 410 HP 1 - - 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Diesel Hyd. Backhoe* 3.5 m3 - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Reclamation                                                  
Dozer 410 HP 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
Motor Grader 280 HP 1 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Water Sprinkler 28 KL 3 3 3 3 3 3 3 Existing 3 No. water sprinkler of 28 KL capacity would be upgraded into 01 no. water sprinkler of 70 KL capacity.

Water Sprinkler 70 KL - - - 1 1 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Road Sweeping Machine - - - - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
* It will work in coal extraction in 1st and 2nd year. Hereafter in miscellaneous jobs                                    
ADD - ON SLIDES

CALENDAR PROGRAM OF COAL AND OB


Years of Quarry Operation

TOTAL Actual Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Yr-20
Particulars (Including Prod. Total
2015-16) (2015-16)
2016-17 2017-18 2018-19 2019-20 2020-21 2021-22 2022-23 2023-24 2024-25 2025-26 2026-27 2027-28 2028-29 2029-30 2030-31 2031-32 2032-33 2033-34 2034-35 2035-36

Coal Production Seam wise (Mt)

152.87 4.1 5.47 7 8 8 8 8 8 8 8 8 8 8 8 8 8 8 7 6 6 5.3 148.77


Total Coal
79.52 0.85 1.91 2.94 3.56 4.29 4.3 4.48 4.62 4.59 4.63 4.72 4.68 4.67 4.66 4.66 4.07 3.92 3.43 2.94 3.02 2.58 78.67
PUREW MERGED
73.35 3.25 3.56 4.06 4.44 3.71 3.7 3.52 3.38 3.41 3.37 3.28 3.32 3.33 3.34 3.34 3.93 4.08 3.57 3.06 2.98 2.72 70.1
TURRA
Natural OBR (Mm3)

683.36 26.97 35.49 37.48 45.06 42.82 42.82 39.87 36.04 36.49 36.97 37.84 41.55 40.17 38.13 38.13 23.56 21.89 18.9 16.42 15.64 11.12 656.39
Total OB
480.41 20.29 25.38 28.07 34.01 30.33 30.33 28.98 26.69 27 27.52 28.51 31.25 30.01 28.16 28.16 13.76 11.13 9.36 8.1 8.54 4.83 460.12
Top OB

202.95 6.68 10.11 9.41 11.05 12.49 12.49 10.89 9.35 9.49 9.45 9.33 10.3 10.16 9.97 9.97 9.8 10.76 9.54 8.32 7.1 6.29 196.27

Parting bet. PUREW MERGED & TURRA


4.47 6.58 6.49 5.35 5.63 5.35 5.35 4.98 4.51 4.56 4.62 4.73 5.19 5.02 4.77 4.77 2.95 2.74 2.70 2.74 2.61 2.10 4.41
Av Natural S.R (m3/t)
Adjusted OBR (Mm3)

683.36 26.97 40 40 40 40 40 40 40 40 40 40 40 40 40 40 25 22.69 15.24 11.96 11.8 9.7 656.39


Total OB
480.41 20.29 29.89 30.58 28.95 27.5 27.5 29.12 30.65 30.5 30.58 30.66 29.7 29.84 30.04 30.03 15.2 11.93 6.2 4.29 4.7 2.26 460.12
Top OB

202.95 6.68 10.11 9.41 11.05 12.49 12.49 10.89 9.35 9.49 9.45 9.33 10.3 10.16 9.97 9.97 9.8 10.76 9.04 7.67 7.1 7.44 196.27
Parting bet. PUREW MERGED & TURRA
System-Wise OBR( Mm3)                                              

Top OBR Adjusted 683.36 26.97 40 40 40 40 40 40 40 40 40 40 40 40 40 40 25 22.69 15.24 11.96 11.8 9.7 656.39

Sanctioned Outsourcing 106.97 26.97 40 40                                     80

Additional O.B. Outsourcing 576.39       40 40 40 40 40 40 40 40 40 40 40 40 25 22.69 15.24 11.96 11.8 9.7 576.39

4.47 6.58 7.31 5.71 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 3.13 2.84 2.18 1.99 1.97 1.83 4.41
Av Adjusted S.R (m3/t)
ADD - ON

COAL FLOW DIAGRAM


ADD - ON SLIDES

EVACUATION ROUTE
ADD - ON SLIDES

Table showing land use, viz. quarry, dump, etc.

Total required
Sl. No. Particulars Area (Ha)

1 Total quarry area 705.00


2 Existing External dump 409.35
3 Proposed External Dump (North) 441.61
4 Proposed External Dump (South) 389.98
5 Infrastructure 210.23
6 Safety Zone 174.33
7 Colony Proposed 32.55
8 Existing Gorbi Colony 44.92
9 Green Belt and Others 322.59
  Total 2730.56
ADD - ON SLIDES

Table showing land rates, and the impact of enhanced land rates as per LARR Act)
Option-II (Amt. in Rs. Lakhs)

Sanctioned
Report Total Provision Existing as on 31.3.15 (3.5 Mtpa) Balance Provision ( Phasing of Balance Provision
(3.5 Mtpa) ( 8 Mtpa) 4.5 Mtpa)
Sl.
No. Particulars

Qty. Amt. Qty.(Ha) Amt. Qty. (Ha) Committed Amt. Qty. (Ha) Rate (Rs.in Amt. Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6
(Ha) Amt. Lakh/Ha)

  PHASE -I                                

Leased
Leased Leased land
land, Leased land, Amount
amount land on amount shown
1 Forest Land 447 shown in 840.62 Mine 447   shown 393.62   on            
Mine Dev. in Mine Mine
Dev. Fund Dev. Dev.
Fund Fund Fund

                             

2 Non -Forest Land (Total) 892 858.0 1889.94 858.0 892   858 997.94            

  a) Govt. Land             359.94              


  b) Tenancy Land       31900.0       638.00 50.0 31900   5317 10633 15950    
  Total 1339 858.0 2730.56 32758 1339   858 1391.56   31900   5317 10633 15950    
ADD - ON SLIDES

APPENDIX A (for approved variant)


Base Date: July, 2016
(Amt. in `
Option - II (Integrated - 8 Mtpa)   Lakhs)

PHASING OF CAPITAL
TOTAL EXISTING AS ON COMMITTED BALANCE
SANCTIONED TOTAL PROVN DEPN ANNUAL
SL NO PARTICULARS 31.03.2015 (3.5 EXPENSES FOR PROVISION (4.5
CAPITAL (8 Mtpa) Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 RATE DEPN
Mtpa) 3.5 Mtpa Mtpa)
(3.5 Mtpa)

1 Land 858 32758 858   31900 0 5317 10633 15950 0 0    


2 Buildings:                          

  Service 2279 6773 206 1729 4837 0 829 1612 2396 0 0 28 242
  Residential 1371 6451 596 1825 4030 0 695 1343 1992 0 0 58 111

3 Plant & Machinery                          


  a) H. E. M. M. 8298 16152 6954 0 9198 0 8715 484 0 0 0 0 1960

  c) Others than HEMM 23201 38006 19874 5156 12976 0 4452 5810 1550 0 1164 0 2589

4 Furniture & Fittings 98 242 97 89 57 0 29 28 0 0 0 20 12


5 Railway Siding 3600 8261 222 8039 0 0 0 0 0 0 0 18 459
6 Vehicles 308 901 102 69 730 0 364 298 68 0 0 7/12 101

7 Prospecting & Boring 115 44 44   0 0 0 0 0 0 0 20 2

8 Development.                          

8.1 Capital Outlay in Mines 7125 23405 6507   16898 0 2812 5384 7702 500 500 20 1170

8.2 Roads & Culverts 2417 3500 223 213 3064 0 517 941 1272 334 0 20 175

8.3 Water Supply & Sewerage 1842 5929 42 1118 4769 0 795 1590 2384 0 0 20 296
8.4 Scientific Research 50 80 0   80 0 80 0 0 0 0 20 4.00
8.5 P.R Prep.Cost 497 1992 0   1992   1992         20 100
9.1 Revenue Exp.capitalised 618 0 0   0             20 0

  during Devel. period                          


10 Land Reclamation 831 1760 1069   692 0 692 0 0 0 0 0 201

  INITIAL CAPITAL 53508 146255 36794 18238 91223 0 27288 28122 33314 834 1664   7422
ADD - ON SLIDES

APPENDIX A (for approved variants)


Base Date: July, 2016
Option - II (Incremental - 4.5 Mtpa) Amount in Rs. Lakhs

PHASING OF CAPITAL
TOTAL EXISTING AS
SANCTIONED TOTAL ON COMMITTED BALANCE DEPN ANNUAL
SL NO PARTICULARS CAPITAL PROVN 31.03.2015 EXPENSES PROVISION RATE DEPN
Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6
(3.5 Mtpa) (4.5 Mtpa) (3.5 Mtpa) FOR 3.5 Mtpa (4.5 Mtpa)

1 Land 858 31900     31900   5317 10633 15950        


2 Buildings:                          
  Service 2279 4837     4837   829 1612 2396     28 173
  Residential 1371 4030     4030   695 1343 1992     58 69
3 Plant & Machinery                          
  a) H. E. M. M. 8298 9198     9198   8715 484         1062
  c) Others than HEMM 23201 12976     12976   4452 5810 1550   1164   824
4 Furniture & Fittings 98 57     57   29 28       20 3
5 Railway Siding 3600                     18  
6 Vehicles 308 730     730   364 298 68     7/12 78
7 Prospecting & Boring 115                     20  
8 Development.                          
8.1 Capital Outlay in Mines 7125 16898     16898   2812 5384 7702 500 500 20 845
8.2 Roads & Culverts 2417 3064     3064   517 941 1272 334   20 153

8.3 Water Supply & 1842 4769     4769   795 1590 2384     20 238
Sewerage
8.4 Scientific Research 50 80     80   80         20 4.00
8.5 P.R Prep.Cost 497 1992     1992   1992         20 100

9.1 Revenue Exp.capitalised 618                     20  

  during Devel. period                          


10 Land Reclamation 831 692     692   692           75
  INITIAL CAPITAL 53508 91223     91223   27288 28122 33314 834 1664   3625
ADD - ON SLIDES

APPENDIX A (for all variants)


Base Date: July, 2016

Option - I (Integrated - 8 Mtpa) (Amt. in Rs Lakhs)

PHASING OF BALANCE PROVISION


TOTAL TOTAL EXISTING AS COMMITTED BALANCE
SL PARTICULARS SANCTIONED PROVN ON EXPENSES FOR PROVISION DEPN ANNUAL
NO CAPITAL (8 Mtpa) 31.03.2015 3.5 Mtpa (4.5 Mtpa) Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 RATE DEPN
(3.5 Mtpa) (3.5 Mtpa)

1 Land 858 32758 858   31900   5317 10633 15950        


2 Buildings:                          
  Service 2279 10037 206 1729 8101   1350 2700 4051     28 358
  Residential 1371 12347 596 1825 9926   1713 3309 4904     58 213
3 Plant & Machinery                          
  a) H. E. M. M. 8298 310869 6954   303916   8433 295482         21298
  c) Others than HEMM 23201 40531 19874 5156 15501   6188 6485 1664   1164   2730
4 Furniture & Fittings 98 259 97 89 74   37 37       20 13
5 Railway Siding 3600 8261 222 8039               18 459
6 Vehicles 308 901 102 69 730   364 298 68     7/12 101
7 Prospecting & Boring 115 44 44                 20 2
8 Development.                          
8.1 Capital Outlay in Mines 7125 23405 6507   16898   2812 5384 7702 500 500 20 1170
8.2 Roads & Culverts 2417 4096 223 213 3660   610 1140 1570 340   20 205

8.3 Water Supply & Sewerage 1842 6523 42 1118 5363   894 1788 2681     20 326

8.4 Scientific Research 50 80     80   80         20 4.00


8.5 P.R Prep.Cost 497 1992     1992   1992         20 100

9.1 Revenue Exp.capitalised 618                     20  


  during Devel. period                          
10 Land Reclamation 831 3364 1069   2296   895 669 581 151     373
  INITIAL CAPITAL 53508 455468 36794 18238 400436   30685 327925 39171 991 1664   27351
ADD - ON SLIDES

APPENDIX A (for all variants)


Base Date: July, 2016

Option - I (Incremental - 4.5 Mtpa (Amt. in Rs. Lakhs )

PHASING OF BALANCE PROVISION


TOTAL TOTAL EXISTING AS BALANCE
SL SANCTIONED PROVN ON COMMITTED DEPN ANNUAL
PARTICULARS EXPENSES FOR PROVISION
NO CAPITAL (4.5 Mtpa) 31.03.2015 3.5 Mtpa (4.5 Mtpa) RATE DEPN
(3.5 Mtpa) (3.5 Mtpa) Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6

1 Land 858 31900     31900   5317 10633 15950        


2 Buildings:                          
  Service 2279 8101     8101   1350 2700 4051     28 289
  Residential 1371 9926     9926   1713 3309 4904     58 171
3 Plant & Machinery                          
  a) H. E. M. M. 8298 303916     303916   8433 295482         20401
  c) Others than HEMM 23201 15501     15501   6188 6485 1664   1164   964
4 Furniture & Fittings 98 74     74   37 37       20 4
5 Railway Siding 3600                     18  
6 Vehicles 308 730     730   364 298 68     7/12 78
7 Prospecting & Boring 115                     20  
8 Development.                          
8.1 Capital Outlay in Mines 7125 16898     16898   2812 5384 7702 500 500 20 845
8.2 Roads & Culverts 2417 3660     3660   610 1140 1570 340   20 183

8.3 Water Supply & Sewerage 1842 5363     5363   894 1788 2681     20 268

8.4 Scientific Research 50 80     80   80         20 4.00


8.5 P.R Prep.Cost 497 1992     1992   1992         20 100
9.1 Revenue Exp.capitalised 618                     20  
  during Devel. period                          
10 Land Reclamation 831 2296     2296   895 669 581 151     248
  INITIAL CAPITAL 53508 400436     400436   30685 327925 39171 991 1664   23554
ADD - ON SLIDES

APPENDIX A (for all variants)


Base Date: July, 2016

Option - I (Without Expansion - 3.5 Mtpa) (Amt. in Rs. Lakhs)

PHASING OF BALANCE PROVISION


TOTAL TOTAL EXISTING AS
SL SANCTIONED PROVN ON COMMITTED BALANCE DEPN ANNUAL
NO PARTICULARS CAPITAL
EXPENSES FOR PROVISION
(3.5 Mtpa) 31.03.2015 3.5 Mtpa Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 RATE DEPN
(3.5 Mtpa) (3.5 Mtpa)

1 Land 858 858 858                    


2 Buildings:                          
  Service 2279 1936 206 1729               28 69
  Residential 1371 2421 596 1825               58 42
3 Plant & Machinery                          
  a) H. E. M. M. 8298 6954 6954                   897
  c) Others than HEMM 23201 25030 19874 5156                 1765
4 Furniture & Fittings 98 185 97 89               20 9
5 Railway Siding 3600 8261 222 8039               18 459
6 Vehicles 308 171 102 69               7/12 23
7 Prospecting & Boring 115 44 44                 16 3
8 Development.                          
8.1 Capital Outlay in Mines 7125 6507 6507                 16 407
8.2 Roads & Culverts 2417 436 223 213               16 27
8.3 Water Supply & Sewerage 1842 1160 42 1118               16 73
8.4 Scientific Research 50                     16  
8.5 P.R Prep.Cost 497                     16  
9.1 Revenue Exp.capitalised 618                     16  
  during Devel. period                          
10 Land Reclamation 831 1069 1069                   125
  INITIAL CAPITAL 53508 55032 36794 18238                 3899
ADD - ON SLIDES

APPENDIX B.1 (for approved variant)


 APPENDIX - B.1

Option-II (Total Coal Departmental & Total OB Outsourcing)

SL. CODE CATEGORY/GRADE/SCALE OB COAL COMMON RECLAMATION TOTAL

1 CAT-1 CAT-1  0 0 44 2 46
2 CAT-2 CAT-2 30 47 78 0 155
3 CAT-3 CAT-3 0 10 36 0 46
4 CAT-4 CAT-4 0 3 31 0 34
5 CAT-5 CAT-5 0 13 55 0 68
6 CAT-6 CAT-6  0 6 21 0 27
7 SPL. GR SPL. GR 0 0 0 0 0
8 GR-A GR-A 3 15 32 0 50
9 GR-B GR-B 0 81 79 18 178
10 GR-C GR-C 0 0 3 0 3
11 GR-D GR-D 0 0 0 0 0
12 GR-E GR-E  0 20 0 0 20
13 S1 MONTHLY RATED GRADE-H 0 1 38 0 39
14 S2 GRADE-G 0 0 0 0 0
15 S3 GRADE-F 0 0 24 0 24
16 S4 GRADE-E 0 0 21 0 21
17 S5 GRADE-D 0 9 93 0 102
18 S6 GRADE-C 8 3 58 0 69
19 S7 GRADE-B 4 11 50 0 65
20 S8 GRADE-A 0 5 33 2 40
21 E1 Rs 16400-40500 0 0 0 0 0
22 E2 Rs 20600-46500 0 0 7 0 7
23 E3 Rs 24900-50500 4 3 29 1 37
24 E4 Rs 29100-54500 0 1 13 0 14
25 E5 Rs 32900-58000 0 0 10 0 10
26 E6 Rs 36600-62000 1 3 21 0 25
27 E7 Rs 43200-66000 0 1 9 0 10
28 E8 Rs 51300-73000 0 0 2 0 2
  TOTAL       50 232 787 23 1092
ADD - ON SLIDES

APPENDIX B.1 (for all variants)


  APPENDIX - B.1
OPTION-I (DEPARTMENTAL) 
SL. CODE CATEGORY/GRADE/SCALE OB COAL COMMON RECLAMATION TOTAL
1 CAT-1 CAT-1 0 13 89 3 105
2 CAT-2 CAT-2 71 95 130 0 296
3 CAT-3 CAT-3 0 40 39 0 79
4 CAT-4 CAT-4 0 8 35 0 43
5 CAT-5 CAT-5 0 55 68 0 123
6 CAT-6 CAT-6 0 18 21 0 39
7 SPL. GR SPL. GR 265 0 0 0 265
8 GR-A GR-A 116 15 34 0 165
9 GR-B GR-B 63 81 74 37 255
10 GR-C GR-C 12 0 101 0 113
11 GR-D GR-D 0 0 13 0 13
12 GR-E GR-E 35 20 0 0 55
13 S1 MONTHLY RATED GRADE-H 0 1 44 0 45
14 S2 GRADE-G 0 0 0 0 0
15 S3 GRADE-F 0 0 27 0 27
16 S4 GRADE-E 0 0 56 0 56
17 S5 GRADE-D 8 8 79 0 95
18 S6 GRADE-C 0 5 72 0 77
19 S7 GRADE-B 0 18 117 0 135
20 S8 GRADE-A 0 6 65 2 73
21 E1 Rs 16400-40500 0 0 0 0 0
22 E2 Rs 20600-46500 0 0 9 0 9
23 E3 Rs 24900-50500 0 5 28 1 34
24 E4 Rs 29100-54500 0 3 23 0 26
25 E5 Rs 32900-58000 0 1 18 0 19
26 E6 Rs 36600-62000 0 1 16 1 18
27 E7 Rs 43200-66000 0 1 7 0 8
28 E8 Rs 51300-73000 0 0 2 0 2
    TOTAL 570 394 1167 44 2175
ADD - ON SLIDES

APPENDIX C (for approved variant)


Appendix - C

Option - II (Integrated - 8 Mtpa)

Total Coal OB Common


Sl.No. Particulars
(Rs/t) (Rs/t) (Rs/m3) (Rs/t)
1 Salary & Wages 106.15 19.91 0.95 82.03

2 Stores 141.12 63.66 12.10 24.09

3 Power 62.15 14.15   48.00

4 Misc. Expenses 47.06 25.07 0.02 21.88

5 Adm. Expenses 28.28     28.28

6 Mine closure Cost 25.84     25.84

7 OB Outsourcing Cost 440.62   99.87  

8 COAL Outsourcing Cost        

9 Interest on Working capital 41.14 5.93 5.46 11.12

10 Total cash Cost 892.35 128.73 118.40 241.24

11 Interest        

12 Depreciation 92.30 49.65   42.65

  Total 984.66 178.38 118.40 283.89

13 Common cost apportioned to coal & OB   36.84 55.99  

  Total   215.22 174.39  

14 OB Cost Charged to coal   769.44    

  Total Cost   984.66    


ADD - ON SLIDES

APPENDIX C1 (for approved variant)

Option - II (Integrated - 08 Mtpa) (Amt. in Rs Lakhs)

Sl.No Particulars Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Yr-20 Total Cost
Avg Cost
. (Rs/t)

1 Salary & Wages 4121.94 6252.97 8196.55 8196.55 8196.55 8196.55 8196.55 8196.55 8196.55 8196.55 8196.55 8196.55 8196.55 8196.55 8196.55 8196.55 8196.55 8196.55 8196.55 8196.55 157912.78 106.15

2 Stores 8717.79 11152.74 11506.45 11534.05 11534.05 11557.33 11557.33 11557.33 11557.33 11557.33 11557.33 11557.33 11557.33 11557.33 9743.00 9463.59 8498.97 8038.74 8019.38 7720.93 209945.69 141.12

3 Power 3409.96 3766.41 4116.61 4359.95 4587.41 4814.88 4814.88 4814.88 4814.88 4814.88 4814.88 4814.88 4814.88 4814.88 4814.88 4814.88 4814.88 4814.88 4814.88 4814.88 92463.48 62.15

4 Misc. Expenses 2230.69 2833.78 3340.39 3510.11 3824.76 3732.08 3687.90 3725.47 3733.53 3614.65 3643.08 3644.01 3858.76 3858.76 3806.22 3816.30 3541.28 3266.26 3260.88 3074.88 70003.79 47.06

5 Adm. Expenses 1546.92 1979.60 2262.40 2262.40 2262.40 2262.40 2262.40 2262.40 2262.40 2262.40 2262.40 2262.40 2262.40 2262.40 2262.40 2262.40 1979.60 1696.80 1696.80 1498.84 42072.16 28.28

6 Mine Closure Cost 1162.38 1220.50 1281.53 1345.61 1412.89 1483.53 1557.71 1635.59 1717.37 1803.24 1893.40 1988.07 2087.48 2191.85 2301.44 2416.51 2537.34 2664.21 2797.42 2937.29 38435.34 25.84

7 OB Outsourcing 39946.74 39946.74 39946.74 39946.74 39946.74 39946.74 39946.74 39946.74 39946.74 39946.74 39946.74 39946.74 39946.74 39946.74 24966.71 22659.79 15219.71 11944.08 11784.29 9687.08 655516.02 440.62

8 COAL Outsourcing                                            

9 Interest
on Working 2954.93 3245.72 3414.78 3439.18 3468.63 3479.69 3481.14 3486.72 3491.06 3489.46 3495.20 3499.82 3515.00 3520.04 2711.07 2592.12 2164.77 1963.37 1960.89 1833.30 61206.88 41.14
capital
10 Total Cash Cost 64091.35 70398.46 74065.45 74594.58 75233.42 75473.20 75504.64 75625.68 75719.85 75685.25 75809.58 75909.80 76239.13 76348.55 58802.27 56222.13 46953.09 42584.87 42531.09 39763.75 1327556.13 892.35

11 Interest                                            

12 Depreciation 3570.49 5303.58 6278.13 7067.85 7109.55 7199.23 7199.23 7199.23 7199.23 7199.23 7199.23 7199.23 7199.23 7199.23 7199.23 7199.23 7199.23 7199.23 7199.23 7199.23 137318.08 92.30

  Total 67661.84 75702.05 80343.58 81662.44 82342.98 82672.43 82703.87 82824.91 82919.08 82884.48 83008.81 83109.03 83438.36 83547.78 66001.50 63421.36 54152.32 49784.10 49730.32 46962.98 1464874.21 984.66

  Cost/t (`) 1236.96 1081.46 1004.29 1020.78 1029.29 1033.41 1033.80 1035.31 1036.49 1036.06 1037.61 1038.86 1042.98 1044.35 825.02 792.77 773.60 829.74 828.84 886.09 984.66  

  Fixed Cost (`/t) 362.56 376.83 380.76 394.97 400.26 404.24 404.98 406.20 407.31 407.81 409.14 410.39 412.82 414.19 401.08 400.45 444.91 509.59 511.68 573.10 417.67  

  Variable Cost (`/t) 874.41 704.63 623.53 625.81 629.03 629.17 628.82 629.11 629.18 628.24 628.47 628.47 630.16 630.16 423.94 392.32 328.69 320.14 317.16 313.00 566.98  
ADD - ON SLIDES

APPENDIX C (for approved variant)

Option - II (Incremental - 4.5 Mtpa)


Total Coal OB Common
Sl.No. Particulars
(Rs/t) (Rs/t) (Rs/m3 ) (Rs/t)
1 Salary & Wages 96.74 13.94 0.99 77.80
2 Stores 121.27 38.48 12.10 21.46
3 Power 69.60 4.85   64.76
4 Misc. Expenses 46.91 22.99 0.02 23.79
5 Adm. Expenses 28.28     28.28
6 Mine closure Cost 20.73     20.73
7 OB Outsourcing Cost 506.42   99.87  
8 COAL Outsourcing Cost        
9 Interest on Working capital 43.01 3.88 5.46 11.45
10 Total cash Cost 932.98 84.15 118.43 248.26
11 Interest        
12 Depreciation 69.67 24.43   45.23
  Total 1002.65 108.58 118.43 293.49
13 Common cost apportioned to coal & OB   33.70 51.23  
  Total   142.28 169.66  
14 OB Cost Charged to coal   860.36    
  Total Cost   1002.65    
ADD - ON SLIDES

APPENDIX C1 (for approved variant)


Option - II (Incremental - 4.5 Mtpa) (Amt. in Rs Lakhs)

Sl. No. Particulars Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Yr-20 Total Avg Cost
Cost Rs/t

1 Salary & Wages 808.87 2964.60 3870.55 3870.55 3870.55 3870.55 3870.55 3870.55 3870.55 3870.55 3870.55 3870.55 3870.55 3870.55 3870.55 3870.55 8367.85 8367.85 8367.85 8367.85 91432.64 96.74

2 Stores 1877.36 4989.66 6515.44 6543.04 6543.04 6566.32 6566.32 6566.32 6566.32 6566.32 6566.32 6566.32 6566.32 6566.32 5194.68 5670.45 4976.04 4515.81 4496.46 4198.00 114616.86 121.27

3 Power 2316.09 2569.00 2815.55 3038.84 3246.00 3453.17 3453.17 3453.17 3453.17 3453.17 3453.17 3453.17 3453.17 3453.17 3453.17 3453.17 3453.17 3453.17 3453.17 3453.17 65782.98 69.60

4 Misc. Expenses 567.01 1241.53 1695.46 1922.29 2237.21 2259.71 2269.71 2269.71 2269.71 2269.71 2269.71 2269.71 2269.71 2269.71 2269.71 2743.01 3062.17 2790.16 2790.16 2599.75 44335.85 46.91

5 Adm. Expenses 557.12 989.80 1272.60 1272.60 1272.60 1272.60 1272.60 1272.60 1272.60 1272.60 1272.60 1272.60 1272.60 1272.60 1272.60 1764.67 1979.60 1696.80 1696.80 1498.84 26727.43 28.28

6 Mine Closure Cost 592.38 622.00 653.10 685.75 720.04 756.04 793.84 833.54 875.21 918.97 964.92 1013.17 1063.83 1117.02 1172.87 1231.51 1293.09 1357.74 1425.63 1496.91 19587.59 20.73

7 OB Outsourcing 14390.81 19983.36 29660.45 29660.45 29660.45 29660.45 29660.45 29660.45 29660.45 29660.45 29660.45 29660.45 29660.45 29660.45 18335.55 21351.53 15219.71 11944.08 11784.29 9687.08 478621.87 506.42

8 COAL Outsourcing 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Interest on Working
9 1020.30 1612.40 2246.69 2271.35 2298.25 2312.21 2314.52 2316.44 2318.45 2320.57 2322.79 2325.12 2327.57 2330.14 1719.17 1937.44 1853.66 1649.40 1644.03 1512.91 40653.42 43.01
capital

10 Total Cash Cost 22129.95 34972.35 48729.83 49264.88 49848.14 50151.06 50201.17 50242.78 50286.47 50332.35 50380.52 50431.10 50484.20 50539.97 37288.31 42022.34 40205.30 35775.01 35658.38 32814.52 881758.64 932.98

11 Interest                                         0.00 0.00

12 Depreciation 0.00 1731.31 2704.40 3493.79 3535.49 3625.16 3625.16 3625.16 3625.16 3625.16 3625.16 3625.16 3625.16 3625.16 3625.16 3625.16 3625.16 3625.16 3625.16 3625.16 65842.44 69.67

  Total 22129.95 36703.66 51434.23 52758.67 53383.63 53776.22 53826.34 53867.95 53911.64 53957.51 54005.68 54056.26 54109.37 54165.13 40913.47 45647.51 43830.46 39400.18 39283.55 36439.68 947601.08 1002.65

  Cost/t (Rs) 1123.35 1048.68 1142.98 1172.41 1186.30 1195.03 1196.14 1197.07 1198.04 1199.06 1200.13 1201.25 1202.43 1203.67 909.19 731.53 626.15 656.67 654.73 687.54 1002.65  

  Fixed Cost (Rs/t) 268.66 348.80 351.19 375.90 384.18 391.16 392.14 393.06 394.03 395.05 396.12 397.25 398.43 399.67 381.79 292.56 327.96 372.09 373.07 414.79 373.14  

  Variable Cost (`Rst) 854.68 699.88 791.79 796.52 802.13 803.86 804.00 804.00 804.00 804.00 804.00 804.00 804.00 804.00 527.39 438.97 298.19 284.58 281.66 272.75 629.51  
ADD - ON SLIDES

APPENDIX C (for all variants)

Option - I (Integrated - 8 Mtpa)


Total Coal OB Common
Sl.No. Particulars
(Rs/t) (Rs/t) (Rs/m3) (Rs/t)
1 Salary & Wages 188.08 31.46 10.79 109.02
2 Stores 554.73 63.66 104.32 30.80
3 Power 113.72 13.61 9.29 59.11
4 Misc. Expenses 114.53 25.36 14.46 25.37
5 Adm. Expenses 28.28     28.28
6 Mine closure Cost 25.84     25.84
7 OB Outsourcing Cost 53.70   12.17  
8 COAL Outsourcing Cost        
9 Interest on Working capital 52.15 6.48 7.30 13.46
10 Total cash Cost 1131.02 140.58 158.33 291.89
11 Interest        
12 Depreciation 333.35 49.65 53.04 49.67
  Total 1464.37 190.23 211.37 341.56
13 Common cost apportioned to coal & OB   44.32 67.37  
  Total   234.55 278.74  
14 OB Cost Charged to coal   1229.82    
  Total Cost   1464.37    
ADD - ON SLIDES

APPENDIX C1 (for all variants)


Option - I (Integrated - 8 Mtpa) (Amt. in Rs Lakhs)

Sl. Total Avg


No. Particulars YR-1 YR-2 YR-3 YR-4 YR-5 YR-6 YR-7 YR-8 YR-9 YR-10 YR-11 YR-12 YR-13 YR-14 YR-15 YR-16 YR-17 YR-18 YR-19 YR-20 Cost Cost
(Rs/t)

1 Salary & Wages 3724.85 6007.16 14938.84 15007.63 15007.63 15007.63 15007.63 15007.63 15007.63 15007.63 15007.63 15007.63 15007.63 15007.63 15007.63 15007.63 15007.63 15007.63 15007.63 15007.63 279800.56 188.08

2 Stores 8717.79 11228.57 45465.18 45687.85 45730.06 45753.34 45753.34 45753.34 45753.34 45753.34 45753.34 45753.34 45753.34 45753.34 43939.01 43659.60 42694.98 42234.74 42215.39 41916.94 825270.20 554.73

3 Power 4236.00 4580.55 9005.73 9241.43 9461.85 9682.27 9682.27 9682.27 9682.27 9682.27 9682.27 9682.27 9682.27 9682.27 9241.91 8361.18 7418.76 6978.40 6978.40 6538.03 169182.71 113.72

4 Misc. Expenses 2220.76 2834.82 8745.56 8997.26 9418.03 9325.47 9281.29 9318.86 9326.92 9208.04 9236.47 9237.41 9452.15 9452.15 9399.61 9409.69 9134.67 8859.65 8854.27 8668.28 170381.36 114.53

5 Adm. Expenses 1546.92 1979.60 2262.40 2262.40 2262.40 2262.40 2262.40 2262.40 2262.40 2262.40 2262.40 2262.40 2262.40 2262.40 2262.40 2262.40 1979.60 1696.80 1696.80 1498.84 42072.16 28.28

6 Mine Closure Cost 1162.38 1220.50 1281.53 1345.61 1412.89 1483.53 1557.71 1635.59 1717.37 1803.24 1893.40 1988.07 2087.48 2191.85 2301.44 2416.51 2537.34 2664.21 2797.42 2937.29 38435.34 25.84

7 OB Outsourcing 39946.74 39946.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 79893.48 53.70

8 COAL Outsourcing 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

9 Interest on Working 2975.18 3276.90 3948.80 3989.54 4025.82 4036.54 4037.99 4043.57 4047.91 4046.32 4052.05 4056.67 4071.85 4076.90 3970.68 3920.66 3807.36 3743.00 3748.25 3700.74 77576.73 52.15
capital

10 Total Cash Cost 64530.63 71074.84 85648.03 86531.71 87318.68 87551.19 87582.63 87703.68 87797.85 87763.24 87887.57 87987.80 88317.13 88426.55 86122.68 85037.67 82580.34 81184.43 81298.15 80267.74 1682612.54 1131.02

11 Interest                                         0.00 0.00

12 Depreciation 3570.49 5437.45 25983.12 26979.67 27038.49 27128.17 27128.17 27128.17 27128.17 27128.17 27128.17 27128.17 27128.17 27128.17 27128.17 27128.17 27128.17 27128.17 27128.17 27128.17 495931.72 333.35

  Total 68101.11 76512.29 111631.16 113511.39 114357.17 114679.36 114710.80 114831.84 114926.02 114891.41 115015.74 115115.96 115445.29 115554.71 113250.85 112165.84 109708.51 108312.60 108426.32 107395.91 2178544.26 1464.37

  Cost/t (Rs) 1244.99 1093.03 1395.39 1418.89 1429.46 1433.49 1433.88 1435.40 1436.58 1436.14 1437.70 1438.95 1443.07 1444.43 1415.64 1402.07 1567.26 1805.21 1807.11 2026.34 1464.37  

  Fixed Cost (Rs/t) 366.74 384.90 1058.81 1078.40 1084.72 1088.63 1089.37 1090.59 1091.70 1092.20 1093.53 1094.78 1097.21 1098.57 1081.14 1071.85 1201.64 1386.68 1388.76 1559.49 1073.61  

  Variable Cost (Rs/t) 878.25 708.14 336.58 340.50 344.75 344.86 344.52 344.81 344.88 343.94 344.17 344.17 345.86 345.86 334.49 330.22 365.62 418.53 418.34 466.85 390.76  
ADD - ON SLIDES

APPENDIX C (for all variants)

Option - I (Incremental - 4.5 Mtpa)


Sl.No. Particulars Total Coal OB Common
(Rs/t) (Rs/t) (Rs/m3) (Rs/t)
1 Salary & Wages 223.72 30.27 14.46 120.11
2 Stores 772.34 38.48 138.40 32.02
3 Power 154.06 4.58 12.78 84.65
4 Misc. Expenses 153.07 23.40 19.80 29.28
5 Adm. Expenses 28.28     28.28
6 Mine closure Cost 20.73     20.73
7 OB Outsourcing Cost 36.37   7.17  
8 COAL Outsourcing Cost        
9 Interest on Working capital 67.11 4.68 9.31 15.23
10 Total cash Cost 1455.68 101.42 201.92 330.30
11 Interest        
12 Depreciation 449.11 24.43 72.65 56.29
  Total 1904.79 125.85 274.57 386.59
13 Common cost apportioned to coal & OB   44.40 67.48  
  Total   170.25 342.05  
14 OB Cost Charged to coal   1734.54    
  Total Cost   1904.79    
ADD - ON SLIDES

APPENDIX C (for all variants)

Option - I (Incremental - 4.5 Mtpa) (Amt. in Rs Lakhs)


Avg Cost
Sl.No. Particulars Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Yr-20 Total Cost
(`Rst)

1 Salary & Wages 465.23 2709.12 10617.59 10682.35 10682.35 10682.35 10682.35 10682.35 10682.35 10682.35 10682.35 10682.35 10682.35 10682.35 10682.35 10682.35 14693.34 14693.34 14693.34 14693.34 211435.86 223.72

2 Stores 1877.36 5065.50 40474.17 40696.83 40739.05 40762.33 40762.33 40762.33 40762.33 40762.33 40762.33 40762.33 40762.33 40762.33 39390.69 39866.46 39172.05 38711.82 38692.47 38394.01 729941.38 772.34

3 Power 3289.95 3530.69 7845.40 8058.14 8255.62 8453.10 8453.10 8453.10 8453.10 8453.10 8453.10 8453.10 8453.10 8453.10 8013.45 7134.16 6193.29 6131.70 5753.64 5314.00 145597.93 154.06

4 Misc. Expenses 558.42 1242.33 7100.74 7409.45 7830.50 7853.12 7863.12 7863.12 7863.12 7863.12 7863.12 7863.12 7863.12 7863.12 7863.12 8336.42 8643.43 8371.41 8371.41 8181.00 144666.31 153.07

5 Adm. Expenses 557.12 989.80 1272.60 1272.60 1272.60 1272.60 1272.60 1272.60 1272.60 1272.60 1272.60 1272.60 1272.60 1272.60 1272.60 1764.67 1979.60 1696.80 1696.80 1498.84 26727.43 28.28

6 Mine Closure Cost 592.38 622.00 653.10 685.75 720.04 756.04 793.84 833.54 875.21 918.97 964.92 1013.17 1063.83 1117.02 1172.87 1231.51 1293.09 1357.74 1425.63 1496.91 19587.59 20.73

7 OB Outsourcing 14390.81 19983.36                                     34374.17 36.37

8 COAL Outsourcing                                            

Interest on Working
9 capital
1050.34 1650.24 3284.91 3325.58 3359.17 3372.68 3374.99 3376.91 3378.92 3381.04 3383.26 3385.59 3388.04 3390.61 3305.76 3335.75 3478.78 3429.87 3413.94 3362.94 63429.32 67.11

10 Total Cash Cost 22781.61 35793.03 71248.51 72130.71 72859.33 73152.22 73202.33 73243.94 73287.63 73333.51 73381.68 73432.26 73485.36 73541.13 71700.85 72351.34 75453.57 74392.68 74047.23 72941.04 1375759.98 1455.68

11 Interest                                            

12 Depreciation   1865.18 22409.39 23405.61 23464.42 23554.10 23554.10 23554.10 23554.10 23554.10 23554.10 23554.10 23554.10 23554.10 23554.10 23554.10 23554.10 23554.10 23554.10 23554.10 424456.08 449.11

  Total 22781.61 37658.21 93657.90 95536.32 96323.75 96706.32 96756.43 96798.04 96841.73 96887.61 96935.78 96986.36 97039.46 97095.23 95254.95 95905.44 99007.67 97946.78 97601.33 96495.14 1800216.05 1904.79

  Cost/t (Rs) 1156.43 1075.95 2081.29 2123.03 2140.53 2149.03 2150.14 2151.07 2152.04 2153.06 2154.13 2155.25 2156.43 2157.67 2116.78 1536.95 1414.40 1632.45 1626.69 1820.66 1904.79  

  Fixed Cost (Rs/t) 289.06 367.95 1559.18 1593.30 1603.37 1610.18 1611.16 1612.08 1613.05 1614.07 1615.14 1616.27 1617.45 1618.69 1593.13 1155.04 1078.88 1247.35 1243.38 1393.52 1406.13  

  Variable Cost (Rs/t) 867.37 708.00 522.10 529.73 537.16 538.85 538.98 538.98 538.98 538.98 538.98 538.98 538.98 538.98 523.64 381.90 335.51 385.10 383.31 427.14 498.65  
SALIENT FEATURES

Mine Parameters

Vindhya-I & II quarry


- Strike on surface (Max.) Km. 3.40

- Strike on floor (Max.) Km. 3.11


- Gradient of the seam Deg. 4o-12o

(Gorbi-B & Gorbi-C


Quarry)
Km. 2.31
- Strike on surface (Max.)
Km. 1.98
- Strike on floor (Max.)
Deg. 12o-22o
- Gradient of the seam
MAIN INFRASTRUCTURE

Coal Handling Plant

• Existing :
• 10 Mty for (-)200 mm product size
• 2 numbers Silo (2400 T & 3000 T) with RLS

• Proposed :
• Secondary crushing for existing CHP for (-)100 mm product size
• Additional 15 Mty Semi-mobile in-pit crushing for (-)100 mm product
size
• 1 number Silo (4000 T) with RLS

(Incremental Provision of Rs 680.20 Crs has been made


in EPR)
PROJECT BACKGROUND

Production in last five years

Year Coal (Mt) OBR (Mm3) S.R (m3/t)


2011-12 4.01 16.53 4.12
2012-13 4.38 17.31 3.95
2013-14 4.38 13.07 2.98
2014-15 4.48 1.75 0.39
2015-16 4.10 26.97 6.58

Total 21.35 75.63 3.6


PROJECT BACKGROUND
CHOICE OF TECHNOLOGY
In view of following facts:
i) Presence of faults creating sub-blocks;
ii) Strike length of sub-blocks;
iii) Surface topography i.e. hilly area in dip side;
iv) Sharp variation in dip in different sub-blocks
v) Steeply dipping seam in Gorbi-B & C block
 
It is proposed to continue with existing shovel-dumper combination of mining.
Further, based on the floor gradient pattern, the entire mine has been divided into two sub-
blocks i.e. Gorbi-B & C and Vindhya-I & II.
Gorbi-B & C is limited by the fault F-20 and F-19 having floor gradient varying from 12 o to
22o. In this block, horizontal slicing method has been proposed.  
Vindhya-I & II block is limited by the fault F-19 and boundary of Moher and Moher-Amlohri
Block having floor gradient varying from 4o to 12o. In this block inclined seam method has
been proposed.
MINING

OB Dumping
As on 01.04.2016
Internal Dump External Dump
Total OB
OB from Quarry
(Mm3)
V-I V-II OLD Ext. Dump South Ext. Dump North Ext. Dump

V-I 32.50 8.29 26.16 99.83 0.00 166.78

V-II 0.00 15.02 0.00 26.69 0.00 41.71

Total Vindhya-I & 32.50 23.31 26.16 126.52 0.00 208.49


II

B &C 0.00 23.88 76.41 82.16 265.45 447.90

Total OB(Mm3) 32.50 47.19 102.57 208.68 265.45 656.39

Percentage 12.14 87.86 100.00


UCE OF EPR FOR BLOCK-B OCP (8.0 Mtpa) (3.50 Mtpa to 8.00 Mtpa)
SALIENT FEATURES OF BOTH THE OPTIONS
Option-I Option-II
Without Integra-
SL. Latest Sanctioned Incre- Integra-ted Incre-
Particulars Unit Expn. ted
No.  (3.5Mtpa) mental mental
(3.5Mtpa)
(4.5Mtpa) (8 Mtpa) (4.5Mtpa)
(8 Mtpa)
1 Coal Production Mtpa 3.5 3.5 4.50 8.00 4.50 8.00
2 OB Removal - Peak Mm3 13.30 10.30 29.70 40.00 29.70 40.00
3 Total Capital Outlay `Crs. 535.08 550.32 4004.36 4554.68 912.23 1462.55
4 Specific Investment `/t 1528.80 1572.34 8898.58 5693.35 2027.18 1828.19
Cost of Production (`/t)          
5 100% Prodn. Level   689.80   626.85 1904.79 1464.37 1002.65 984.66
85% Prodn. Level   748.35   704.37 2152.93 1653.83 1068.49 1058.36

6 Weighted Average Selling Price `/t 1099.84 1313.42 1313.42 1313.42 1313.42 1313.42
Profitability(`/t) 
100% Prodn. Level   410.04 686.57 (-)591.37 (-)150.95 310.77 328.76
7
85% Prodn. Level   351.50 609.05 (-)839.51 (-)340.41 244.93 255.06
Financial IRR (%) 
8 100% Prodn. Level   104.05% 40.09% (-)ve (-)6.59% 20.82% 32.92%
85% Prodn. Level   68.45% 32.63% (-)ve (-)ve 13.51% 21.09%
Desired selling price to yield 12% FIRR (`/t)
9 100% Prodn. Level   672.27 790.28 2384.41 1704.55 1204.35 1134.53
85% Prodn. Level   731.92 882.27 2708.44 1929.55 1288.61 1223.65
NPV at 12% (` Lakhs)
100% Prodn. Level   93258.62 126208.03 (-)339037.73 (-)206469.24 34528.47 111495.20
10
85% Prodn. Level   53170.34 88412.26 (-)282184.41 6674.88 52513.12
(-)375370.91
Outsourcing Rate (`/B.m3)
11
OB Insitu (Excluding blasting)     99.87
12 Manpower No. 610 610 1565 2175 482 1092
13 OMS t 22.90 22.90 26.90 15.27 107.61 32.41
14 EMS ` 1837.58 2576.38 2531.66 2544.20 2624.97 2597.83
MINE ECONOMICS
VARIANT APPROVED BY SUBSIDIARY COMPANY BOARD:

DETAILS OF APPROVED VARIANT: (give hyperlink to add-on slide showing all variants)
TOTAL CAPITAL INVESTMENT : 1462.55 Crs.
EXISTING CAPITAL INVESTMENT : 367.94 Crs.
COMMITED CAPITAL : 182.38 Crs.
CAPITAL UPTO TARGET YEAR : 554.10 Crs.
CAPITAL BEYOND TARGET YEAR : 358.12 Crs.
COST OF PRODUCTION AT 100 % : 984.66
COST OF PRODUCTION AT 85 % : 1058.36

SELLING PRICE (Rs/t) : 1313.42

IRR AT 100 % : 32.92


IRR AT 85 % : 21.09

NPV AT 100 % (Rs Lakhs) : 111495.20


NPV AT 85 % (Rs Lakhs) : 52513.12

PROFIT/LOSS AT 100% (Rs./T) : 328.76


PROFIT/LOSS AT 85% (Rs./T) : 255.06
GEOLOGY
Geological Plan
Option-I Option-II Option-III (a) Option-III (b)
Without
Latest
Expansion
Particulars Unit Sanctioned Incre- Incre- Incre- Incre-
Existing Integrated Integrated Integrated Integrated
(3.5Mtpa) mental mental mental mental
(3.5 Mtpa) (8 Mtpa) (8 Mtpa) (8 Mtpa) (8 Mtpa
(4.5 Mtpa) (4.5 Mtpa) (4.5 Mtpa) (4.5 Mtpa)

Capital Investment (Rs. Crs)


Total
Capital Rs. Crores 535.08 550.32 3539.54 4089.86 1015.73 1566.05 1089.72 1640.04 1017.42 1567.74
Outlay

Upto
Rs. Crores     3534.12  3534.12  1010.31   1010.31 1084.30   1084.30 1012.00 1012.00
Target year

Specific
Rs./t 1528.80 1572.34 7865.64 5112.33 2257.18 1957.56 2421.6 2050.05 2260.93 1959.68
Investment

Cost of Production
At 100%
Prodn. Rs./t 689.80 941.03 2071.91 1406.75 1127.33 1041.03 1193.23 1076.51 1298.38 1132.30
Level
At 85%
Prodn. Rs./t 748.35 1026.52 2341.51 1591.36 1198.21 1118.59 1266.47 1155.35 1373.98 1212.30
Level
Weighted
Avg. Selling Rs./t 1099.84 1384.81 1384.81 1384.81 1384.81 1384.81 1384.81 1384.81 1384.81 1384.81
Price
MINE ECONOMICS – COMPARATIVE STATUS

COMPARISON OF INDICATIVE PARAMETERS


For Proposed
For Similar PRs of the Project
Subsidiary
Parameter Amlohri Option-II,
OCP(10Mtpa) Integrated
(8.00Mtpa)

Average Stripping Ratio (t/m3) 4.28 5.07


OMS 19.08 32.41
No. of PAPs per Mty 25 187.50
Capital for Land as % of Total 0.66 22.40
Capital
Capital for P&M as % of Total 81.6 37.02
Capital
Advantage of Option-III(b)
[Coal departmental & total OB outsourcing with shovel- dumper (with
implementation of crushing & conveying by conveyor of partial OB to old
Gorbi mine)]

-The total Volume of OB to be accommodated in old Gorbi is 143


Mm3 .This will reduce the forest land requirement for external OB Dump to
the tune of 152 Ha.
-The capital reduction in Land for 152 Ha forest land is 45 Cr. and there is
increase of IRR in this option (at 85% for incremental ) from 5.20% to 5.86%
-Crushing-conveying system (of part OB to old Gorbi) is eco-friendly and
energy efficient with use of electrical system.
-This will first require the treatment of acidic water in the voids of old Gorbi
mine & thereafter filling it with OB & subsequent OB benches of 90m in 3
tiers
-This will also address the condition of EC of 5.47 Mtpa w.e.f 06.08.2014
for treatment of acidic water of old Gorbi.
 The requirement of external OB dump will reduce about 152 Ha. Thus,
the total capital will be reduced by 45 Crs..
The IRR for Option-III (a) and Option-III (b) after reduction in capital is
given in table below:

Option-III (a) Option-III (b)

Sl. No. Financial IRR Incre- Incre- Inte-


Inte-grated
mental mental grated
(8 Mtpa)
(4.5 Mtpa) (4.5 Mtpa) (8 Mtpa)

A BASE CASE
At 100% production level 18.40 72.07 11.15 65.28
At 85% production level 10.79 30.95 5.20 25.00
AFTER REDUCTION
B
OF LAND

1 At 100% production level 20.16 76.09 12.18 69.80

2 At 85% production level 11.74 33.39 5.86 27.13

You might also like