Professional Documents
Culture Documents
Recast Block-B - ESC - NCL Board 150119 Gorbi
Recast Block-B - ESC - NCL Board 150119 Gorbi
TO
THE PRESENTATION
ON
RECAST EPR FOR BLOCK-B OCP
(3.5 to 8.0 Mty)
Jhingurdah
Block-B
Extn.
Block-B
kri
Ka
Jayant
Nigahi Dudhichua
a
Bin
Amlohri
Khadia ra k
Mar
Gorb
i Mine
Pvt Industry
NH 75E
External
Village Dump Rail Line
Bijul
Block-
B Extn.
Proposed E xtn.
hi Dip
External Niga
Dump
c ks with SPL
Blo
Mineable Coal Reserve (Mt) OB (Mm3) & SR
(m3/t)
Date of Approval of EPR (Dec’15) by NCL Board for Option II: 18.12.2015
Date of recommendation of UCE (Aug’ 16) by NCL Board for Option II : 09.01.2017
ESC considered the proposal on 31.03.2017 and directed to include economic evaluation
based on avg. actual sale price also.
The above UCE was recommended by NCL Board on 26.05.2017 for Option II.
The UCE of Block-B OCP was considered in Empowered Sub-committee of CIL Board on 31.08.2017.
The Empowered Sub-committee deferred the Report for next ESC meeting.
As the earlier UCE was prepared with base date of July, 2016 and for inclusion of land rate as per
RFCLARR-2013, NCL desired to recast the EPR vide letter No. NCL/CP/Project Monitoring/671, dated
24.11.2017 and NCL/CP/Minutes/709, dated 08.12.2017.
In this connection, a meeting was held on 18.04.2018 at CMPDI (HQ), Ranchi with officials from
GM(OC) & other officials of CMPDI (HQ), officials from CMPDI, RI-VI and officials of NCL for
preparation of Recast EPR of Block-B OCP (8 Mtpa).
Accordingly, the Recast EPR for Block-B OCP (8 Mtpa) has been prepared in the following
options:
Option-I - Coal & OB both departmental with shovel dumper
Actual selling
PROJECT BACKGROUND
As on 01.04.2018
RECAST EXPANSION PROJECT REPORT (8.0 Mtpa)
Demand on NCL
BLOCK-B
LOCATION
Block-B
OCP
Recast EPR for Block-B OCP (8.0 Mtpa) has been prepared in the following
Options:
• Option-I : Coal & OBR Both, Departmental
• Option-II : Total Coal production with Departmental
& Total OBR with outsourced
• Option-III : Considering old Gorbi mine for part OB dumping
• Option III(a) : Coal departmental & total OB outsourcing with shovel dumper
(transportation of part OB by shovel dumper to old Gorbi mine)
• Option III(b) :Coal departmental & total OB outsourcing with shovel- dumper
(with implementation of crushing & conveying by conveyor of part OB to old Gorbi mine)
• TECHNOLOGY:
Option I, II & III(a&b)- Coal & OB Both with Shovel-Dumper combination
MINING
PDF
MINING
YEAR OF ACHIEVING TARGET : 4th Year
QUARRY SURFACE AREA (Ha) : 709 Ha, (on surface); 409.79 Ha (on
floor)
LIFE OF MINE : 19 years
DEPTH RANGE : Existing Depth: 175m
Calendar Program :
Option I Maximum Year-wise GCV-wise Coal Production
Option II
Depth : 285m
Option III (a) & (b)
Lithology of Representative Borehole
PDF
MINING
Based on the floor gradient pattern, the entire mine has been divided into two sub-
blocks i.e. Gorbi-B & C and Vindhya-I & II.
The same Opencast mining by shovel dumper combination has been proposed in expansion
project also.
CROSS-SECTION
Particulars
Incremental Integrated Incremental Integrated
(4.5 Mtpa) (8.0 Mtpa) (4.5 Mtpa) (8.0 Mtpa)
Appendix B1
Option I
Option II, III(a) & III(b)
MINING
LIST OF HEMM REQUIREMENT : Option-I
OBR
HEMM
Sanctioned as per Option-I
Sl. HEMM Size/ Provision Existing as on Integrated
No. Cap. 01.04.2018 Completion
(3.5 Mtpa) (8.00 Mtpa)
Report
Elect. Rope
1 20 m3 8
Shovel
Outsourcing
Outsourcing
3 Rear Dumper 190-210 T 64
6 Dozer 850 HP 8
7 Dozer 410 HP 2
MINING
LIST OF HEMM REQUIREMENT : Option-I
Coal
HEMM
Sanctioned Existing as as per Option-I
Sl. HEMM Size/ Provision on Integrated
No. Cap. Completion
(3.5 Mtpa) 01.04.2018 (8.00 Mtpa)
Report
6 Dozer 410 HP 2 2 2 3
Elect. Rope
1 20 m3
Shovel
Diesel Hyd.
2 10-12 m3
Outsourcing
Outsourcing
Outsourcing
Outsourcing
Outsourcing
Backhoe
3 Dumper 190 -210T
4 Dumper 100 T
5 RBH Drill 250 mm
6 Dozer 850 HP
7 Dozer 410 HP
MINING
LIST OF HEMM REQUIREMENT : Option-II, III(a) & III(b)
Coal
HEMM Option-II,
Option-II,
Sl. Size/ Sanctioned Existing as as per III(a) & III(b) III(a) & III(b)
HEMM Provision on Completion Increm-
No. Cap. (3.5 Mtpa) 01.04.2018 tal Integrated
Report (8.00 Mtpa)
(4.50 Mtpa)
6 Dozer 410 HP 2 2 2 1 3
COMMON
1 FE Loader 5.74m3 1 1 1 - 1 - 1
2 FE Loader 10-12 m3 - - - 1 1 1 1
3 Motor Grader 280 HP 2 2 2 2 4 2 4
4 Hyd.Backhoe 2.8/3.5m3 2 1 2## - 2 - 2
5 Mobile Crane 30/50t 2 2 2 - 2 - 2
6 Mobile Crane 8-10t 2 2 2 3 5 3 5
7 Wheel Dozer/Dozer 410 HP 1 1 1 - 1 - 1
RECLAMATION
1 Dozer 410 HP 2 4 4 1 5 1 5
2 Motor Grader 280 HP 1 2 - 1 3 1 3
3 Water Sprinkler 28 KL 3 3 4** - 2 - 2
4 Water Sprinkler 70 KL - - - 1 2(1+1**) 1 2(1+1**)
5 Road Sweeping Machine - - 1 - - 1 - 1
6## 1Mist Spray3 Gun
No. 2.8m Hyd. Shovel transferred- to other project -
- in Completion Report - 2 2 2 2
** 2 No. 28 KL Water Sprinkler to be upgraded to 1 No. 70 KL Water Sprinkler.
MINING
Balance cap. in
90.24 409.68
Existing Dump
Balance cap. in
Existing Dump 90.24 409.68
Proposed in
248.73 600.17
External Dump
External 90
2 Dump Proposed OB in 143.76 -
Old Gorbi Mine
Total 482.73
MINE INFRASTRUCTURE
Coal Handling Plant
Main CHP Existing (3.5 Mtpa)
One mumber receiving pit with 170t hopper
One number 1600 TPH Gyratory crusher to crush ROM coal from (-)1500 mm to(-)100 mm.
One number Self-flowing storage bunker of 20000t capacity.
Four number 1800TPH Plough feeders for reclamation of coal from the bunker.
Two number 1800 TPH Silo loading conveyors.
1 No. 3000 Te capacity Silo.
Railway Siding is under construction.
Proposed CHP (Incremental 4.5 Mtpa)
One number of semi- mobile crushing plant of 1600 TPH capacity comprising of receiving hopper-
apron feeder and twin shaft sizer to crush ROM coal from (-) 1500 mm to (-) 100 mm size. Receiving pit
with 170t hopper with secondary sizer.
This CHP is linked with main CHP for storage and dispatch.
LAND REQUIREMENT AND R & R
Total Land Details
Type of Land Area (Ha) Percentage(%)
NON-FOREST LAND 1186.92 52.58
FOREST LAND 1070.25 47.42
TOTAL 2257.17 100.00
Non-Forest
Land 1186.92 892 173.81 121.11 16.27
EMP Status : The project has EC for capacity of 5.47 Mtpa vide letter
No. J-11015/80/2013-IA.II (M) dated 06.08.2014.
(Amt. in ` Lakh)
Option -I Option -II Option III (a) Option III (b)
SL
PARTICULARS Integrated Incremental Integrated Incremental Integrated Incremental Integrated Incremental
NO
(8 Mtpa) (4.5 Mtpa) (8 Mtpa) (4.5 Mtpa) (8 Mtpa) (4.5 Mtpa) (8 Mtpa) (4.5 Mtpa)
1 Land 25522 19767 25522 19767 25522 19767 25522 19767
2 Buildings
a) Service 10069 9773 5846 5550 5846 5550 5846 5550
b) Residential 11534 9779 5158 3402 5158 3402 5158 3402
Sub Total 21603 19551 11004 8953 11004 8953 11004 8953
3 Plant & Machinery
a) H. E. M. M. 252808 244748 13826 5766 13826 5766 13826 5766
b) CHP 33584 10182 33584 10182 33584 10182 33584 10182
c) Pumping 781 621 781 621 781 621 781 621
d) Electrical 4909 4407 2996 2493 2996 2493 3015 2512
e) Workshop 3535 3291 1966 1722 1966 1722 1966 1722
f) Other P&M 127 62 127 62 127 62 127 62
Sub Total 295745 263311 53280 20846 53280 20846 53299 20865
4 Furniture & Fittings 293 74 277 58 277 58 277 58
5 Railway Siding 8516 0 8516 0 8516 0 8516 0
6 Vehicles 939 711 939 711 939 711 939 711
7 Prospecting & Boring 44 0 44 0 44 0 44 0
8 Development
Capital Outlay in 37839
8.1 40695 37839 40695 37839 40695 40695 37839
Mines
8.2 Roads & Culverts 4523 3956 3712 3146 11560 10994 3712 3146
Water Supply & 5586
8.3 6972 5942 6617 5586 6617 6617 5586
Sewerage
8.4 Scientific Research 80 80 80 80 80 80 80 80
8.5 P.R. Prep. Cost 1762 1762 1762 1762 1762 1762 1762 1762
Sub Total 54032 49579 52867 48414 60714 56261 52867 48414
Revenue Exp.
9.1 Capitalised 0 0 0 0 0 0 0 0
less Depreciation
10 Land Reclamation 2456 1123 2456 1123 2456 1123 2456 1123
TOTAL CAPITAL 409148 354116 154903 99871 162751 107719 154922 99890
MINE ECONOMICS
Capital Investment
Total
Capital ` Crores 535.1 3541.16 4091.48 998.71 1549.03 1077.19 1627.51 998.90 1549.22
Outlay
Specific
`/t 1528.86 7869.24 5114.35 2219.36 1936.29 2393.76 2034.39 2219.78 1936.53
Investment
Cost of Production
At 100%
`/t 689.8 2077.31 1449.05 1097.45 1073.56 1166.35 1111.4 1260.56 1162.3
Prodn. Level
At 85%
`/t 748.35 2348.68 1639.7 1169.11 1154.5 1240.44 1193.67 1336.81 1245.65
Prodn. Level
Weighted
Avg. Selling `/t 1099.84 1386.83 1386.83 1386.83 1386.83 1386.83 1386.83 1386.83 1386.83
Price
MINE ECONOMICS
Salient Features of all the Options
Option-I Option-II Option-III (a) Option-III (b)
Latest
Particulars Unit Sanctioned Incre-mental Integrated Incre-mental Integrated Incre-mental Integrated Incre-mental Integrated
(3.5Mtpa) (4.5 Mtpa) (8 Mtpa) (4.5 Mtpa) (8 Mtpa) (4.5 Mtpa) (8 Mtpa) (4.5 Mtpa) (8 Mtpa)
Profit
At 100%
`/t 410.04 -690.48 -62.23 289.38 313.26 220.48 275.43 126.27 224.53
Prodn.Level
At 85%
`/t 351.5 -961.86 -252.87 217.72 232.33 146.38 193.15 50.02 141.18
Prodn. Level
Financial IRR
At 100%
% 104.05% -ve -1.00% 29.15% 81.02% 18.40% 72.07% 11.15% 65.28%
Prodn. Level
At 85%
% 68.45% -ve -ve 16.72% 39.21% 10.79% 30.95% 5.20% 25.00%
Prodn. Level
At 100%
`/t 672.27 2532.72 1640.12 1241.44 1170.71 1315.56 1208.87 1396.89 1250.01
Prodn. Level
At 85%
`/t 731.92 2882.16 1862.96 1326.6 1259.39 1404.59 1299.54 1486.52 1340.89
Prodn. Level
NPV at 12%
At 100%
` Lakhs 93258.62 -307155.78 -111665.16 38969.55 132692.77 19102.54 112825.76 -2696.6 91413.8
Prodn.Level
At 85%
` Lakhs 53170.34 -340701.03 -193517.78 13721.12 73551.67 -4047.36 55783.19 -22714.14 37489.07
Prodn. Level
4 Misc. Expenses 86.42 94.79 121.22 132.10 36.07 40.34 29.54 32.96
5 Adminstrative Cost (Cash) 3.62 4.26 3.62 4.26 3.62 4.26 3.62 4.26
6 Mine Closure Cost 18.88 22.21 13.88 16.33 18.88 22.21 13.88 16.33
8 COAL Outsourcing 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
9 Interest on Working capital 51.89 58.04 73.94 82.60 42.33 44.80 42.89 44.84
10 Total Cash Cost 1125.39 1258.92 1603.78 1791.59 918.14 971.65 930.30 972.46
12 Adminstrative Cost (Notional) 30.91 36.36 30.91 36.36 30.91 36.36 30.91 36.36
13 Adminstrative Cost 30.91 36.36 30.91 36.36 30.91 36.36 30.91 36.36
(Notional)
14 Depreciation 130.20 153.17 146.59 172.46 124.52 146.50 136.26 160.31
Total 1111.40 1193.67 1166.35 1240.44 1162.30 1245.65 1260.56 1336.81
MINE ECONOMICS – SENSITIVITY ANALYSIS
Capacity Utilisation
Sl. Option – I (Integrated 8 Mtpa) Option – I (Incremental 4.5 Mtpa)
No Particulars
.
100% 90% 85% 80% 75% 100% 90% 85% 80% 75%
Capacity Utilisation
A
(Base Case)
-1.00% -10.53% -ve -ve -ve -ve -ve -ve -ve -ve
Increase in Capital
1)5% -1.80% -11.05% -ve -ve -ve -ve -ve -ve -ve -ve
B
2)10% -2.53% -11.51% -ve -ve -ve -ve -ve -ve -ve -ve
3)15% -3.21% -11.91% -ve -ve -ve -ve -ve -ve -ve -ve
Increase in Operating Cost
C 1)5% -5.70% -ve -ve -ve -ve -ve -ve -ve -ve -ve
2)10% -14.62% -ve -ve -ve -ve -ve -ve -ve -ve -ve
3)15% -ve -ve -ve -ve -ve -ve -ve -ve -ve -ve
Decrease in Sales
D 1)5% -6.78% -ve -ve -ve -ve -ve -ve -ve -ve -ve
2)10% -ve -ve -ve -ve -ve -ve -ve -ve -ve -ve
3)15% -ve -ve -ve -ve -ve -ve -ve -ve -ve -ve
Increase in Capital + Operating Cost
E 1)5% -6.40% -ve -ve -ve -ve
-ve -ve -ve -ve -ve
2)10% -15.27% -ve -ve -ve -ve -ve -ve -ve -ve -ve
3)15% -ve -ve -ve -ve -ve -ve -ve -ve -ve -ve
Option I (Integrated) Appendix C3 Appendix C4
Option I (Incremental) Appendix C3 Appendix C4
MINE ECONOMICS – SENSITIVITY ANALYSIS
Capacity Utilisation
Sl. Option – II (Integrated 8 Mtpa) Option – II (Incremental 4.5 Mtpa)
No Particulars
.
100% 90% 85% 80% 75% 100% 90% 85% 80% 75%
Capacity Utilisation
A 81.02% 51.63% 39.21% 29.44% 21.88% 29.15% 20.06% 16.72% 13.75% 11.00%
(Base Case)
Increase in Capital
1)5% 77.27% 47.86% 36.17% 27.20% 20.26% 25.77% 18.27% 15.30% 12.58% 10.02%
B
2)10% 73.35% 44.24% 33.39% 25.19% 18.80% 23.24% 16.77% 14.05% 11.53% 9.13%
3)15% 69.26% 40.84% 30.88% 23.38% 17.47% 21.22% 15.46% 12.96% 10.60% 8.32%
Increase in Operating Cost
C 1)5% 64.73% 38.07% 28.61% 21.38% 15.60% 21.45% 15.28% 12.65% 10.19% 7.82%
2)10% 47.67% 27.00% 20.27% 14.89% 10.31% 16.08% 11.33% 9.15% 7.03% 4.92%
3)15% 32.65% 18.62% 13.73% 9.53% 5.72% 11.82% 7.93% 6.04% 4.14% 2.22%
Decrease in Sales
D 1)5% 54.20% 32.23% 24.64% 18.62% 13.60% 19.13% 13.74% 11.35% 9.07% 6.85%
2)10% 31.64% 19.26% 14.67% 10.66% 7.01% 12.55% 8.66% 6.78% 4.91% 3.01%
3)15% 17.64% 10.37% 7.22% 4.22% 1.29% 7.30% 4.21% 2.64% 1.02% -0.68%
Increase in Capital + Operating Cost
E 1)5% 60.52% 34.99% 26.38% 19.77% 14.41% 19.50% 14.00% 11.58% 9.28% 7.03%
2)10% 39.95% 22.97% 17.36% 12.71% 8.63% 13.62% 9.52% 7.57% 5.64% 3.69%
3)15% 25.22% 14.79% 10.82% 7.25% 3.92% 9.25% 5.90% 4.22% 2.52% 0.76%
Option II (Integrated) Appendix C3 Appendix C4
Option II (Incremental) Appendix C3 Appendix C4
MINE ECONOMICS – SENSITIVITY ANALYSIS
Capacity Utilisation
Sl. Option – III (a) (Integrated 8 Mtpa) Option – III (a) (Incremental 4.5 Mtpa)
Particulars
No.
100% 90% 85% 80% 75% 100% 90% 85% 80% 75%
Capacity
A Utilisation (Base 72.07% 41.79% 30.95% 22.96% 16.79% 18.40% 13.13% 10.79% 8.55% 6.36%
Case)
Increase in Capital
1)5% 67.45% 38.07% 28.31% 21.10% 15.44% 16.77% 11.99% 9.81% 7.70% 5.62%
B
2)10% 62.63% 34.72% 25.99% 19.46% 14.23% 15.38% 10.98% 8.93% 6.93% 4.93%
3)15% 57.70% 31.76% 23.93% 17.99% 13.13% 14.17% 10.07% 8.13% 6.22% 4.31%
Increase in Operating Cost
C 1)5% 53.35% 29.15% 21.70% 15.95% 11.18% 13.56% 9.37% 7.39% 5.43% 3.47%
2)10% 35.76% 19.83% 14.62% 10.25% 6.35% 9.58% 6.06% 4.32% 2.55% 0.73%
3)15% 23.18% 12.87% 8.95% 5.40% 2.03% 6.13% 3.05% 1.47% -0.17% -1.89%
Decrease in Sales
D
1)5% 43.23% 24.72% 18.71% 13.81% 9.58% 12.15% 8.29% 6.43% 4.57% 2.69%
2)10% 23.65% 14.03% 10.25% 6.83% 3.59% 7.10% 4.01% 2.44% 0.82% -0.87%
3)15% 12.37% 6.34% 3.59% 0.89% -1.84% 2.64% 0.01% -1.39% -2.86% -4.44%
Increase in Capital + Operating Cost
E
1)5% 48.51% 26.61% 19.92% 14.65% 10.20% 12.42% 8.51% 6.63% 4.75% 2.86%
2)10% 29.26% 16.74% 12.33% 8.49% 4.98% 7.97% 4.76% 3.15% 1.49% -0.22%
3)15% 17.86% 9.93% 6.65% 3.57% 0.57% 4.34% 1.56% 0.10% -1.42% -3.03%
Option III (a) (Integrated) Appendix C3 Appendix C4
Option III (a) (Incremental) Appendix C3 Appendix C4
MINE ECONOMICS – SENSITIVITY ANALYSIS
Capacity Utilisation
Sl. Option – III (b) (Integrated 8 Mtpa) Option – III (b) (Incremental 4.5 Mtpa)
Particulars
No.
100% 90% 85% 80% 75% 100% 90% 85% 80% 75%
Capacity Utilisation
A 65.28% 34.71% 25.00% 17.96% 12.43% 11.15% 7.14% 5.20% 3.26% 1.28%
(Base Case)
Increase in Capital
1)5% 60.31% 31.43% 22.82% 16.46% 11.34% 10.17% 6.39% 4.54% 2.67% 0.76%
B
2)10% 55.20% 28.57% 20.91% 15.11% 10.35% 9.29% 5.71% 3.93% 2.13% 0.27%
3)15% 50.10% 26.09% 19.23% 13.91% 9.45% 8.50% 5.08% 3.36% 1.62% -0.19%
Increase in Operating Cost
C 1)5% 43.72% 22.28% 16.02% 11.02% 6.71% 6.79% 3.42% 1.71% -0.06% -1.91%
2)10% 26.11% 13.57% 9.18% 5.31% 1.69% 3.01% 0.02% -1.56% -3.23% -5.02%
3)15% 15.20% 7.01% 3.58% 0.32% -2.94% -0.41% -3.18% -4.69% -6.32% -8.12%
Decrease in Sales
D 1)5% 34.74% 18.87% 13.68% 9.32% 5.42% 12.15% 8.29% 6.43% 4.57% 2.69%
2)10% 17.19% 9.06% 5.68% 2.49% -0.63% 7.10% 4.01% 2.44% 0.82% -0.87%
3)15% 7.09% 1.68% -0.94% -3.60% -6.38% 2.64% 0.01% -1.39% -2.86% -4.44%
Increase in Capital + Operating Cost
E 1)5% 39.09% 20.31% 14.65% 10.02% 5.95% 6.10% 2.86% 1.20% -0.52% -2.32%
2)10% 21.40% 11.32% 7.49% 4.00% 0.68% 2.01% -0.81% -2.32% -3.92% -5.65%
3)15% 11.62% 4.94% 1.95% -0.96% -3.92% -1.51% -4.12% -5.56% -7.12% -8.84%
Coal & OB Both Departmental with Shovel-Dumper (Without considering old Gorbi Mine for Dumping)
Total OB 597.42 22.56 32.22 32.22 45.89 43.22 40.91 40.91 40.91 37.44 35.98 35.74 35.67 38.13 29.92 19.89 19.89 17.40 14.92 13.60 597.42
Top OB above PM 416.45 14.02 23.00 23.00 32.26 31.29 30.42 30.42 30.42 28.34 27.14 26.72 26.57 28.16 20.05 10.13 10.13 8.86 7.60 7.92 416.45
Parting bet. Turra & Purewa Merged 180.97 8.54 9.22 9.22 13.63 11.93 10.49 10.49 10.49 9.10 8.84 9.02 9.10 9.97 9.87 9.76 9.76 8.54 7.32 5.68 180.97
AV. STRIPPING RATIO(Natural) (m3/t) 4.33 4.12 5.89 5.89 5.74 5.40 5.11 5.11 5.11 4.68 4.50 4.47 4.46 4.77 3.74 2.49 2.49 2.49 2.49 2.92 4.33
Top OB above PM 416.45 14.02 23.58 23.58 26.37 28.07 29.51 29.51 29.51 30.90 31.16 30.98 30.82 28.16 20.05 10.13 10.13 8.86 7.60 3.51 416.45
Parting bet. Turra & Purewa Merged 180.97 8.54 9.22 9.22 13.63 11.93 10.49 10.49 10.49 9.10 8.84 9.02 9.10 9.97 9.87 9.76 9.76 8.54 7.32 5.68 180.97
Av. S.R (adjusted) (m3/t) 4.33 4.12 6.00 6.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 4.99 4.77 3.74 2.49 2.49 2.49 2.49 1.97 4.33
4 System-Wise OBR(Mm3)
Top OBR Adjusted 597.42 22.56 32.80 32.80 40.00 40.00 40.00 40.00 40.00 40.00 40.00 40.00 39.92 38.13 29.92 19.89 19.89 17.40 14.92 9.19 597.42
Sanctioned OB Outsouring 22.56 22.56 22.56
Additional OB Outsouring 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Av. S.R (adjusted) (m3/t) 4.33 4.12 6.00 6.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 4.99 4.77 3.74 2.49 2.49 2.49 2.49 1.97 4.33
ADD - ON SLIDES
Sl.
Years of Quarry Operation
No. Life/ Year YEAR TOTAL
Y-1 Y-2 Y-3 Y-4 Y-5 Y-6 Y-7 Y-8 Y-9 Y-10 Y-11 Y-12 Y-13 Y-14 Y-15 Y-16 Y-17 Y-18 Y-19
1 Coal Production Seam wise
Total Coal, Million tonnes 138.07 5.47 5.47 5.47 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 7.00 6.00 4.66 138.07
Purewa Merged Seam 74.27 2.92 2.61 2.61 3.75 4.17 4.60 4.61 4.60 4.73 4.75 4.73 4.71 4.66 4.33 3.92 3.92 3.43 2.94 2.23 74.22
Turra Seam 63.80 2.55 2.86 2.86 4.25 3.83 3.40 3.39 3.40 3.27 3.25 3.27 3.29 3.34 3.67 4.08 4.08 3.57 3.06 2.43 63.85
Total OB 597.42 22.56 32.22 32.22 45.89 43.22 40.91 40.91 40.91 37.44 35.98 35.74 35.67 38.13 29.92 19.89 19.89 17.40 14.92 13.60 597.42
Top OB above PM 416.45 14.02 23.00 23.00 32.26 31.29 30.42 30.42 30.42 28.34 27.14 26.72 26.57 28.16 20.05 10.13 10.13 8.86 7.60 7.92 416.45
Parting bet. Turra & Purewa Merged 180.97 8.54 9.22 9.22 13.63 11.93 10.49 10.49 10.49 9.10 8.84 9.02 9.10 9.97 9.87 9.76 9.76 8.54 7.32 5.68 180.97
AV. STRIPPING RATIO(Natural) (m 3/t) 4.33 4.12 5.89 5.89 5.74 5.40 5.11 5.11 5.11 4.68 4.50 4.47 4.46 4.77 3.74 2.49 2.49 2.49 2.49 2.92 4.33
Total OB 597.42 22.56 32.80 32.80 40.00 40.00 40.00 40.00 40.00 40.00 40.00 40.00 39.92 38.13 29.92 19.89 19.89 17.40 14.92 9.19 597.42
Top OB above PM 416.45 14.02 23.58 23.58 26.37 28.07 29.51 29.51 29.51 30.90 31.16 30.98 30.82 28.16 20.05 10.13 10.13 8.86 7.60 3.51 416.45
Parting bet. Turra & Purewa Merged 180.97 8.54 9.22 9.22 13.63 11.93 10.49 10.49 10.49 9.10 8.84 9.02 9.10 9.97 9.87 9.76 9.76 8.54 7.32 5.68 180.97
Av. S.R (adjusted) (m3/t) 4.33 4.12 6.00 6.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 4.99 4.77 3.74 2.49 2.49 2.49 2.49 1.97 4.33
4 System-Wise OBR(Mm3)
Top OBR Adjusted 597.42 22.56 32.80 32.80 40.00 40.00 40.00 40.00 40.00 40.00 40.00 40.00 39.92 38.13 29.92 19.89 19.89 17.40 14.92 9.19 597.42
Additional OB Outsouring 574.86 0.00 32.80 32.80 40.00 40.00 40.00 40.00 40.00 40.00 40.00 40.00 39.92 38.13 29.92 19.89 19.89 17.40 14.92 9.19 574.86
Av. S.R (adjusted) (m3/t) 4.33 4.12 6.00 6.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 4.99 4.77 3.74 2.49 2.49 2.49 2.49 1.97 4.33
ADD - ON SLIDES
Recast EPR of Block-B OCP (8 Mtpa)
Calender Programme of Excavation
Coal Departmental & Total OB Outsourcing with Shovel-Dumper (Considering old Gorbi Mine for Dumping)
Option III(a)&(b) (Coal Departmental & Total OB Outsourcing with Shovel-Dumper (Considering old Gorbi Mine for Dumping)
AV. STRIPPING RATIO(Natural) (m 3/t) 4.33 4.12 5.89 5.89 5.74 5.40 5.11 5.11 5.11 4.68 4.50 4.47 4.46 4.77 3.74 2.49 2.49 2.49 2.49 2.92 4.33
Av. S.R (adjusted) (m3/t) 4.33 4.12 6.00 6.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 4.99 4.77 3.74 2.49 2.49 2.49 2.49 1.97 4.33
ADD - ON SLIDES
APPENDIX - B.1
RECAST EPR FOR BLOCK- B OPENCAST PROJECT (8 Mtpa)
STATEMENT SHOWING THE CATEGROY/SCALEWISE MANPOWER
Option-I (Total Coal & OB Departmental)
SL. NO. CODE CATEGORY/GRADE/SCALE OB COAL COMMON RECLAMATION TOTAL
1 CAT-1 CAT-1 0 13 89 3 105
2 CAT-2 CAT-2 60 86 130 0 276
3 CAT-3 CAT-3 0 40 39 0 79
4 CAT-4 CAT-4 0 8 35 0 43
5 CAT-5 CAT-5 0 55 68 0 123
6 CAT-6 CAT-6 0 18 21 0 39
7 SPL. GR SPL. GR 211 0 0 0 211
8 GR-A GR-A 105 15 34 0 154
9 GR-B GR-B 64 68 74 54 260
10 GR-C GR-C 12 0 101 0 113
11 GR-D GR-D 0 0 13 0 13
12 GR-E GR-E 35 20 0 0 55
13 S1 MONTHLY RATED GRADE-H 0 1 44 0 45
14 S2 GRADE-G 0 0 0 0 0
15 S3 GRADE-F 0 0 27 0 27
16 S4 GRADE-E 0 0 56 0 56
17 S5 GRADE-D 10 8 79 0 97
18 S6 GRADE-C 0 5 72 0 77
19 S7 GRADE-B 0 18 117 0 135
20 S8 GRADE-A 0 6 65 2 73
21 E1 Rs 16400-40500 0 0 0 0 0
22 E2 Rs 20600-46500 0 0 9 0 9
23 E3 Rs 24900-50500 0 5 28 1 34
24 E4 Rs 29100-54500 0 3 23 0 26
25 E5 Rs 32900-58000 0 1 18 0 19
26 E6 Rs 36600-62000 0 1 16 1 18
27 E7 Rs 43200-66000 0 1 7 0 8
28 E8 Rs 51300-73000 0 0 2 0 2
TOTAL 497 372 1167 61 2097
ADD - ON SLIDES
APPENDIX - B.1
RECAST EPR FOR BLOCK-B OPENCAST PROJECT (8 Mtpa)
STATEMENT SHOWING THE CATEGROY/SCALEWISE MANPOWER
OPTION-II, III(a)& III(b)
SL. NO. CODE CATEGORY/GRADE/SCALE OB COAL COMMON RECLAMATION TOTAL
1 CAT-1 CAT-1 0 13 46 3 62
2 CAT-2 CAT-2 30 86 78 0 194
3 CAT-3 CAT-3 0 40 36 0 76
4 CAT-4 CAT-4 0 8 31 0 39
5 CAT-5 CAT-5 0 55 55 0 110
6 CAT-6 CAT-6 0 18 21 0 39
7 SPL. GR SPL. GR 0 0 0 0 0
8 GR-A GR-A 3 15 32 0 50
9 GR-B GR-B 0 68 79 54 201
10 GR-C GR-C 0 0 3 0 3
11 GR-D GR-D 0 0 0 0 0
12 GR-E GR-E 0 20 0 0 20
13 S1 MONTHLY RATED GRADE-H 0 1 38 0 39
14 S2 GRADE-G 0 0 0 0 0
15 S3 GRADE-F 0 0 23 0 23
16 S4 GRADE-E 0 0 23 0 23
17 S5 GRADE-D 0 8 91 0 99
18 S6 GRADE-C 8 5 57 0 70
19 S7 GRADE-B 4 18 48 0 70
20 S8 GRADE-A 0 6 33 2 41
21 E1 E1 0 0 0 0 0
22 E2 E2 0 0 7 0 7
23 E3 E3 4 5 29 1 39
24 E4 E4 0 3 13 0 16
25 E5 E5 0 1 10 0 11
26 E6 E6 1 1 21 1 24
27 E7 E7 0 1 9 0 10
28 E8 E8 0 0 2 0 2
TOTAL 50 372 785 61 1268
ADD - ON SLIDES
Appendix - A
TOTAL
BALANCE
SANCTION TOTAL EXISTING AS COMMITTED
SL. INCREMENTAL
PARTICULARS ED PROVN ON 31.03.18 EXPENSES Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7
NO. PROVISION
CAPITAL (8 Mtpa) (3.5 Mtpa) FOR 3.5 Mtpa
(4.5 Mtpa)
(3.5 Mtpa)
Appendix - C
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Option - I (Total Coal & OB Departmental) - 8 Mtpa
Appendix - C.1
Statement Showing Estimated Year wise Operating Cost at 100% capacity utilisation
Option - I (Total Coal & OB Departmental) - 8 Mtpa
Option - I (Integrated - 8 Mtpa) (Amt. in ` Lakhs)
% of
Sl. Avg Cost
Particulars Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total Cost Total
No. (`/t)
Cost
1 Salary & Wages 11308.53 11308.53 14585.45 18253.08 18253.08 18253.08 18253.08 18253.08 18253.08 18253.08 18253.08 18253.08 18253.08 18253.08 18253.08 18253.08 18253.08 18253.08 18253.08 329251.84 238.47 16.46
2 Stores 8103.21 36278.53 37085.86 49647.68 49647.68 49647.68 49647.68 49647.68 49647.68 49647.68 49647.68 49640.56 49481.21 48750.36 47857.49 47857.49 47596.83 47337.05 46774.70 863944.73 625.73 43.18
3 Power 2681.64 3719.81 5240.76 5622.57 6302.59 6982.62 7075.65 7082.20 7088.74 7095.29 7095.29 7095.29 7095.29 7095.29 7095.29 6762.95 6394.90 6062.57 113588.75 82.27 5.68
4 Misc. Expenses 1670.69 4453.33 4744.33 6344.97 6840.50 6840.50 6840.50 6840.50 6840.50 6840.50 6840.50 6840.50 6840.50 6840.50 6840.50 6840.50 6761.75 6683.00 6577.47 119321.50 86.42 5.96
5 Adminstrative Cost (Cash) 198.00 198.00 198.00 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 253.39 217.19 168.68 4997.84 3.62 0.25
6 Mine Closure Cost 853.47 896.14 940.95 987.99 1037.39 1089.26 1143.73 1200.91 1260.96 1324.01 1390.21 1459.72 1532.70 1609.34 1689.81 1774.30 1863.01 1956.16 2053.97 26064.03 18.88 1.30
8 Coal Outsourcing
Interest on Working
9 2278.87 2697.78 2961.60 3903.60 3948.39 3983.76 4019.26 4026.52 4029.74 4033.11 4036.62 4039.64 4035.46 4003.84 3964.58 3968.66 3938.73 3907.33 3861.37 71638.89 51.89 3.58
capital
1553822.7
10 Total Cash Cost 49427.93 58513.95 64235.99 84667.67 85639.19 86406.47 87176.46 87333.93 87403.74 87476.70 87552.96 87618.37 87527.83 86842.00 85990.33 86078.90 85429.74 84748.72 83751.85 1125.39 77.66
3
11 Interest
Adminstrative Cost
12 1690.68 1690.68 1690.68 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2163.57 1854.49 1440.32 42674.94 30.91 2.13
(Notional)
13 Depreciation 3600.24 13057.87 17010.92 23180.46 23183.59 23183.59 23184.01 23184.01 23197.46 23198.06 23198.66 23199.35 23199.35 23199.35 23199.35 23199.35 23199.35 23199.35 22635.33 404209.63 292.76 20.20
2000707.3
Total 54718.85 73262.49 82937.58 110320.79 111295.44 112062.72 112833.12 112990.60 113073.86 113147.42 113224.28 113290.37 113199.84 112514.00 111662.33 111750.91 110792.66109802.56107827.50 1449.05 100.00
1
Cost (`/t) 1000.34 1339.35 1516.23 1379.01 1391.19 1400.78 1410.41 1412.38 1413.42 1414.34 1415.30 1416.13 1415.00 1406.43 1395.78 1396.89 1582.75 1830.04 2313.89 1449.05
Fixed Cost (`/t) 422.02 970.77 1136.56 1032.60 1043.53 1050.89 1058.29 1059.96 1060.98 1061.87 1062.81 1063.73 1064.69 1065.69 1066.75 1067.86 1213.04 1406.24 1785.12 1080.32 74.55
Variable Cost (`/t) 578.32 368.58 379.67 346.41 347.66 349.89 352.12 352.43 352.45 352.47 352.49 352.40 350.31 340.73 329.03 329.03 369.71 423.80 528.78 368.73 25.45
1914790.8
Total Sales (` in Lakhs) 95384.32 87101.30 87101.30 111999.99 107816.29 105646.59 106774.26 106823.68102211.38103605.64106770.87108376.16117849.17120733.69106088.65106088.65 92827.57 79566.49 62024.82 1386.83
2
2000707.3
Total Cost (` in Lakhs) 54718.85 73262.49 82937.58 110320.79 111295.44 112062.72 112833.12 112990.60 113073.86 113147.42 113224.28 113290.37 113199.84 112514.00 111662.33 111750.91 110792.66109802.56107827.50 1449.05
1
Total Profits (` in Lakhs) 40665.47 13838.80 4163.72 1679.20 -3479.15 -6416.12 -6058.86 -6166.91 -10862.48 -9541.77 -6453.40 -4914.21 4649.33 8219.69 -5573.68 -5662.26 -17965.09 -30236.08 -45802.68 -85916.49 -62.23
ADD - ON SLIDES
Appendix - C.2
Sl. % of
Avg Cost
No Particulars Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total Cost Total
(`/t)
. Cost
1 Salary & Wages 11308.53 11308.53 14585.45 18253.08 18253.08 18253.08 18253.08 18253.08 18253.08 18253.08 18253.08 18253.08 18253.08 18253.08 18253.08 18253.08 18253.08 18253.08 18253.08 329251.84 280.55 17.11
2 Stores 7423.80 33826.56 34590.80 46340.53 46340.53 46340.53 46340.53 46340.53 46340.53 46340.53 46340.53 46334.48 46199.04 45577.81 44818.87 44818.87 44597.31 44376.50 43898.50 807186.82 687.79 41.95
3 Power 2581.08 3580.32 5044.23 5411.72 6066.25 6720.78 6810.32 6816.62 6822.92 6829.22 6829.22 6829.22 6829.22 6829.22 6829.22 6509.34 6155.10 5835.22 109329.17 93.16 5.68
4 Misc. Expenses 1576.03 4121.07 4407.33 5883.33 6378.86 6378.86 6378.86 6378.86 6378.86 6378.86 6378.86 6378.86 6378.86 6378.86 6378.86 6378.86 6311.92 6244.99 6155.29 111246.29 94.79 5.78
Adminstrative
5 198.00 198.00 198.00 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 253.39 217.19 168.68 4997.84 4.26 0.26
Cost (Cash)
Mine Closure
6 853.47 896.14 940.95 987.99 1037.39 1089.26 1143.73 1200.91 1260.96 1324.01 1390.21 1459.72 1532.70 1609.34 1689.81 1774.30 1863.01 1956.16 2053.97 26064.03 22.21 1.35
Cost
7 OB Outsourcing 21262.89 21262.89 18.12 1.10
8 Coal Outsourcing
Interest on
9 2060.10 2558.35 2817.97 3711.94 3756.04 3790.18 3824.45 3831.54 3834.75 3838.10 3841.61 3844.67 3841.65 3815.33 3782.54 3786.62 3759.76 3731.48 3690.96 68118.05 58.04 3.54
Working capital
10 Total Cash Cost 44682.81 55489.72 61120.81 80510.70 81467.22 82207.76 82951.02 83104.83 83174.39 83247.09 83323.09 83389.62 83324.14 82753.23 82041.96 82130.54 81547.81 80934.49 80055.71 1477456.93 1258.92 76.78
11 Interest
Adminstrative
12 1690.68 1690.68 1690.68 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2163.57 1854.49 1440.32 42674.94 36.36 2.22
Cost (Notional )
13 Depreciation 3600.24 13057.87 17010.92 23180.46 23183.59 23183.59 23184.01 23184.01 23197.46 23198.06 23198.66 23199.35 23199.35 23199.35 23199.35 23199.35 23199.35 23199.35 22635.33 404209.63 344.42 21.01
Total 49973.73 70238.27 79822.41 106163.82 107123.46 107864.01 108607.68 108761.49 108844.51 108917.80 108994.40 109061.62 108996.14 108425.23 107713.97 107802.54 106910.73 105988.34 104131.36 1924341.51 1639.70 100.00
Cost (`/t) 1074.82 1510.66 1716.80 1561.23 1575.35 1586.24 1597.17 1599.43 1600.65 1601.73 1602.86 1603.85 1602.88 1594.49 1584.03 1585.33 1796.82 2078.20 2628.92 1639.70
Fixed Cost (`/t) 496.50 1142.08 1337.13 1214.82 1227.68 1236.34 1245.05 1247.01 1248.21 1249.26 1250.37 1251.45 1252.58 1253.76 1255.00 1256.30 1427.11 1654.40 2100.14 1270.97 77.51
Variable Cost (`/t) 578.32 368.58 379.67 346.41 347.66 349.89 352.12 352.43 352.45 352.47 352.49 352.40 350.31 340.73 329.03 329.03 369.71 423.80 528.78 368.73 22.49
Total Sales (` in
81076.67 74036.10 74036.10 95199.99 91643.85 89799.60 90758.12 90800.13 86879.68 88064.80 90755.24 92119.74 100171.80 102623.63 90175.35 90175.35 78903.43 67631.51 52721.10 1627572.20 1386.83
Lakhs)
Total Cost (` in
49973.73 70238.27 79822.41 106163.82 107123.46 107864.01 108607.68 108761.49 108844.51 108917.80 108994.40 109061.62 108996.14 108425.23 107713.97 107802.54 106910.73 105988.34 104131.36 1924341.51 1639.70
Lakhs)
Total Profits (` in
31102.94 3797.84 -5786.30 -10963.83 -15479.62 -18064.40 -17849.55 -17961.36 -21964.83 -20853.01 -18239.16 -16941.88 -8824.35 -5801.60 -17538.62 -17627.19 -28007.30 -38356.82 -51410.26 -296769.31 -252.87
Lakhs)
ADD - ON SLIDES
Appendix - C.3
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Option - I (Total Coal & OB Departmental) - 8 Mtpa
Statement Showing Economics at Different Capacity Utilisation
Sl Capacity Utilisation
Particulars
No. 100% 90% 85% 80% 75%
Appendix - C.4
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Option - I (Total Coal & OB Departmental) - 8 Mtpa
Statement showing Sensitivity of IRR
Appendix - D
Sl.
Particulars Existing Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total
No.
1 Initial Capital 31326.68 182099.77 66374.19 105642.09 385442.73
-
2 Replacement Capital 507.10 6267.15 6344.53 1858.92 384.15 4733.49 361.90 303.12 2457.13 9923.85 14427.16 14251.99 8930.06 812.85 3058.39 1763.74
30009.08
46376.45
86947.4
5 Total Cash Outflow 31326.68 49427.93 236765.75 132522.26 191054.30 82107.30 81508.29 86571.23 82354.65 82596.30 87366.19 95970.23 99872.78 99655.50 94414.14 86680.50 88692.91
6
84748.72 53742.77 1934325.88
106823.6 102211.3 103605.6 106770.8 108376.1 117849.1 120733.6 106088.6 106088.6 92827.5
6 Inflow from Sales 95384.32 87101.30 87101.30 111999.99 107816.29 105646.59 106774.26
8 8 4 7 6 7 9 5 5 7
79566.49 62024.82 1914790.82
7 Net Cash Flow -31326.68 45956.39 -149664.45 -45420.96 -79054.32 25708.99 24138.31 20203.03 24469.04 19615.09 16239.45 10800.64 8503.38 18193.67 26319.54 19408.15 17395.74 5880.11 -5182.23 8282.05 -19535.06
Appendix - D.1
Sl.
Particulars Existing Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total
No.
-
2 Replacement Capital 507.10 6267.15 6344.53 1858.92 384.15 4733.49 361.90 303.12 2457.13 9923.85 14427.16 14251.99 8930.06 812.85 3058.39 1763.74 46376.45
30009.08
3 Less: GST credit on Capital Goods 4355.06 4355.06 5600.00 5390.81 5282.33 5338.71 5341.18 5110.57 2567.64 1506.59 2172.75 2124.33 1357.91 122.68 444.39 246.02 51316.04
81547.8
4 Cash Operating Expenses 44682.81 55489.72 61120.81 80510.70 81467.22 82207.76 82951.02 83104.83 83174.39 83247.09 83323.09 83389.62 83324.14 82753.23 82041.96 82130.54 80934.49 80055.71 1477456.93
1
83065.5
5 Total Cash Outflow 31326.68 44682.81 233741.52 129407.08 186897.33 77935.32 77309.58 82345.79 78125.55 78366.94 83136.58 91740.36 95644.03 95451.81 90325.37 82732.13 84744.54 80934.49 50046.64 1857960.08
3
- - -
7 Net Cash Flow 36393.86 -55370.98 -91697.35 13708.52 12490.03 8412.33 12674.58 8512.74 4928.22 -985.11 -3524.29 4719.99 12298.26 7443.22 5430.81 -4162.10 2674.46 -230387.88
31326.68 159705.42 13302.98
8 Coal Production (Lakh Tonnes) 46.50 46.50 46.50 68.00 68.00 68.00 68.00 68.00 68.00 68.00 68.00 68.00 68.00 68.00 68.00 68.00 59.50 51.00 39.61 1173.60
-
11 Net Present Value (` Lakhs)
193517.78
ADD - ON SLIDES
Appendix - A
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Appendix - C
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Option - I (Total Coal & OB Departmental) - Incremental 4.5 Mtpa
Appendix - C.1
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Statement Showing Estimated Year wise Operating Cost at 100% capacity utilisation
Option - I (Total Coal & OB Departmental) - Incremental 4.5 Mtpa
Option - I (Incremental- 4.5 Mtpa) (Amt. in ` Lakhs)
% of
Sl. Avg Cost
Particulars Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total Cost Total
No. (`/t)
Cost
1 Salary & Wages 6551.82 5760.27 9031.58 12708.07 12708.07 12708.07 12708.07 12708.07 12708.07 12708.07 12708.07 12708.07 12708.07 12708.07 12708.07 12708.07 12708.07 12708.07 12708.07 224672.73 296.32 14.26
2 Stores 799.68 28391.92 29199.25 42659.28 42659.28 42659.28 42659.28 42659.28 42659.28 42659.28 42659.28 42652.16 42492.81 41761.96 41064.05 41064.05 40933.27 40895.88 40738.45 731267.72 964.48 46.43
3 Power 2421.14 3152.40 4262.16 4527.98 5020.35 5512.71 5571.05 5574.27 5577.49 5580.71 5580.71 5580.71 5580.71 5580.71 5580.71 5252.43 4888.87 4560.58 89805.70 118.45 5.70
4 Misc. Expenses 421.13 3105.91 3319.53 4861.96 5357.49 5357.49 5357.49 5357.49 5357.49 5357.49 5357.49 5357.49 5357.49 5357.49 5357.49 5357.49 5318.11 5318.11 5271.65 91906.24 121.22 5.84
5 Adminstrative Cost (Cash) 71.31 71.31 71.31 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 144.79 144.79 123.43 2744.52 3.62 0.17
6 Mine Closure Cost 344.56 361.79 379.88 398.88 418.82 439.76 461.75 484.84 509.08 534.53 561.26 589.32 618.79 649.73 682.21 716.32 752.14 789.75 829.23 10522.62 13.88 0.67
8 Coal Outsourcing
Interest on Working
9 830.96 1938.76 2182.44 3144.24 3182.00 3206.81 3231.67 3235.61 3236.94 3238.32 3239.77 3240.78 3234.50 3200.67 3168.51 3170.16 3146.93 3129.36 3104.52 56062.96 73.94 3.56
capital
1215986.1
10 Total Cash Cost 18023.14 42051.11 47336.39 68197.48 69016.52 69554.64 70093.86 70179.22 70208.01 70238.07 70269.46 70291.42 70155.26 69421.52 68723.92 68759.68 68255.73 67874.83 67335.93 1603.78 77.20
8
11 Interest
Adminstrative Cost
12 608.89 608.89 608.89 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1236.33 1236.33 1053.97 23434.59 30.91 1.49
(Notional)
13 Depreciation 9452.56 13396.69 19565.83 19565.83 19565.83 19565.83 19565.83 19565.83 19565.83 19565.83 19565.83 19565.83 19565.83 19565.83 19565.83 19565.83 19514.42 19307.92 335593.14 442.62 21.31
1575013.9
Total 18632.03 52112.57 61341.97 89154.17 89973.22 90511.34 91050.55 91135.91 91164.70 91194.76 91226.16 91248.11 91111.95 90378.21 89680.62 89716.38 89057.88 88625.57 87697.81 2077.31 100.00
1
Cost (`/t) 945.79 2645.31 3113.81 1981.20 1999.40 2011.36 2023.35 2025.24 2025.88 2026.55 2027.25 2027.74 2024.71 2008.40 1992.90 1993.70 2226.45 2215.64 2571.78 2077.31
Fixed Cost (`/t) 415.85 1880.18 2321.98 1461.69 1478.34 1487.43 1496.55 1498.11 1498.73 1499.38 1500.06 1500.71 1501.40 1502.12 1502.87 1503.67 1681.77 1674.33 1945.61 1537.80 74.03
Variable Cost (Rs/t) 529.94 765.13 791.82 519.51 521.06 523.93 526.80 527.14 527.15 527.17 527.19 527.03 523.31 506.29 490.03 490.03 544.67 541.31 626.18 539.50 25.97
1051491.5
Total Sales (` in Lakhs) 27320.47 27320.47 27320.47 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 55473.04 55473.04 47290.77 1386.83
6
1575013.9
Total Cost (` in Lakhs) 18632.03 52112.57 61341.97 89154.17 89973.22 90511.34 91050.55 91135.91 91164.70 91194.76 91226.16 91248.11 91111.95 90378.21 89680.62 89716.38 89057.88 88625.57 87697.81 2077.31
1
Total Profits (` in Lakhs) 8688.44 -24792.09 -34021.49 -26746.99 -27566.04 -28104.16 -28643.38 -28728.74 -28757.53 -28787.59 -28818.98 -28840.93 -28704.78 -27971.03 -27273.44 -27309.20 -33584.84 -33152.52 -40407.04 -523522.34 -690.48
ADD - ON SLIDES
Appendix - C.2
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Statement Showing Estimated Year wise operating cost at 85% capacity utilisation
Option - I (Total Coal & OB Departmental) - Incremental 4.5 Mtpa
(Amount in Rs. Lakhs)
Option - I (Incremental- 4.5 Mtpa)
% of
Sl. Avg Cost
Particulars Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total Cost Total
No. (`/t)
Cost
1 Salary & Wages 6551.82 5760.27 9031.58 12708.07 12708.07 12708.07 12708.07 12708.07 12708.07 12708.07 12708.07 12708.07 12708.07 12708.07 12708.07 12708.07 12708.07 12708.07 12708.07 224672.73 348.62 14.84
2 Stores 679.73 26586.87 27351.11 39864.33 39864.33 39864.33 39864.33 39864.33 39864.33 39864.33 39864.33 39858.27 39722.83 39101.60 38508.38 38508.38 38397.21 38365.43 38231.62 684226.03 1061.69 45.20
3 Power 2330.35 3034.18 4102.33 4358.18 4832.08 5305.99 5362.14 5365.24 5368.34 5371.43 5371.43 5371.43 5371.43 5371.43 5371.43 5055.46 4705.53 4389.56 86437.98 134.12 5.71
4 Misc. Expenses 397.86 2845.04 3053.92 4471.71 4967.24 4967.24 4967.24 4967.24 4967.24 4967.24 4967.24 4967.24 4967.24 4967.24 4967.24 4967.24 4933.77 4933.77 4894.28 85137.24 132.10 5.62
5 Adminstrative Cost (Cash) 71.31 71.31 71.31 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 144.79 144.79 123.43 2744.52 4.26 0.18
6 Mine Closure Cost 344.56 361.79 379.88 398.88 418.82 439.76 461.75 484.84 509.08 534.53 561.26 589.32 618.79 649.73 682.21 716.32 752.14 789.75 829.23 10522.62 16.33 0.70
8 Coal Outsourcing
Interest on Working
9 758.76 1834.52 2074.56 2982.56 3019.84 3043.76 3067.73 3071.56 3072.88 3074.26 3075.70 3076.77 3071.64 3043.11 3016.01 3017.66 2996.25 2979.62 2956.85 53234.06 82.60 3.52
capital
10 Total Cash Cost 16457.17 39790.16 44996.55 64690.77 65499.36 66018.13 66537.98 66621.05 66649.72 66679.65 66710.92 66733.99 66622.89 66004.07 65416.23 65451.99 64987.69 64626.97 64133.04 1154628.32 1791.59 76.28
11 Interest
Adminstrative Cost
12 608.89 608.89 608.89 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1236.33 1236.33 1053.97 23434.59 36.36 1.55
(Notional)
13 Depreciation 9452.56 13396.69 19565.83 19565.83 19565.83 19565.83 19565.83 19565.83 19565.83 19565.83 19565.83 19565.83 19565.83 19565.83 19565.83 19565.83 19514.42 19307.92 335593.14 520.73 22.17
1513656.0
Total 17066.06 49851.61 59002.13 85647.46 86456.06 86974.82 87494.68 87577.75 87606.41 87636.34 87667.61 87690.68 87579.58 86960.77 86372.92 86408.68 85789.85 85377.71 84494.92 2348.68 100.00
5
Cost (`/t) 1019.17 2977.10 3523.57 2239.15 2260.29 2273.85 2287.44 2289.61 2290.36 2291.15 2291.96 2292.57 2289.66 2273.48 2258.12 2259.05 2523.23 2511.11 2915.13 2348.68
Fixed Cost (`/t) 489.23 2211.98 2731.74 1719.64 1739.23 1749.92 1760.65 1762.48 1763.21 1763.97 1764.77 1765.54 1766.35 1767.20 1768.09 1769.02 1978.56 1969.80 2288.95 1809.18 77.03
Variable Cost (Rs/t) 529.94 765.13 791.82 519.51 521.06 523.93 526.80 527.14 527.15 527.17 527.19 527.03 523.31 506.29 490.03 490.03 544.67 541.31 626.18 539.50 22.97
Total Sales (` in Lakhs) 23222.40 23222.40 23222.40 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 47152.09 47152.09 40197.16 893767.83 1386.83
1513656.0
Total Cost (` in Lakhs) 17066.06 49851.61 59002.13 85647.46 86456.06 86974.82 87494.68 87577.75 87606.41 87636.34 87667.61 87690.68 87579.58 86960.77 86372.92 86408.68 85789.85 85377.71 84494.92 2348.68
5
Total Profits (` in Lakhs) 6156.34 -26629.21 -35779.73 -32601.36 -33409.96 -33928.72 -34448.58 -34531.65 -34560.31 -34590.24 -34621.51 -34644.58 -34533.48 -33914.67 -33326.82 -33362.58 -38637.76 -38225.62 -44297.77 -619888.22 -961.86
ADD - ON SLIDES
Appendix - C.3
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Option - I (Total Coal & OB Departmental) - Incremental 4.5 Mtpa
Statement Showing Economics at Different Capacity Utilisation
Appendix - C.4
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Option - I (Total Coal & OB Departmental) - Incremental 4.5 Mtpa
Statement showing Sensitivity of IRR
Appendix - D
Sl.
Particulars Existing Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total
No.
2 Replacement Capital 182.00 731.00 182.00 731.00 9417.62 9084.36 8657.06 5611.47 182.00 876.20 145.60 -9125.69 26674.61
3 Less: GST credit on Capital Goods 1366.02 1366.02 3120.36 3120.36 3120.36 3120.36 3120.36 3120.36 3120.36 3120.36 3120.36 3120.36 3120.36 3120.36 3120.36 1900.81 45197.53
4 Cash Operating Expenses 18023.14 42051.11 47336.39 68197.48 69016.52 69554.64 70093.86 70179.22 70208.01 70238.07 70269.46 70291.42 70155.26 69421.52 68723.92 68759.68 68255.73 67874.83 67335.93 1215986.18
5 Total Cash Outflow 18023.14 222784.86 112344.55 170719.21 65896.16 66616.28 67704.50 67058.86 67269.65 67848.71 76566.72 76255.41 75691.96 71912.63 65785.57 66515.52 66500.51 67874.83 58210.24 1551579.31
6 Inflow from Sales 27320.47 27320.47 27320.47 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 55473.04 55473.04 47290.77 1051491.56
- -
7 Net Cash Flow 9297.33 -85024.07 -3488.99 -4209.11 -5297.32 -4651.69 -4862.47 -5441.53 -14159.54-13848.24-13284.79 -9505.45 -3378.39 -4108.35 -11027.47 -12401.78 -10919.47 -500087.75
195464.38 108312.04
8 Coal Production (Lakh Tonnes) 19.70 19.70 19.70 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 40.00 40.00 34.10 758.20
-
11 Net Present Value (` Lakhs)
307155.78
ADD - ON SLIDES
Appendix - D.1
Sl.
Particulars Existing Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total
No.
2 Replacement Capital 182.00 731.00 182.00 731.00 9417.62 9084.36 8657.06 5611.47 182.00 876.20 145.60 -9125.69 26674.61
3 Less: GST credit on Capital Goods 1366.02 1366.02 3120.36 3120.36 3120.36 3120.36 3120.36 3120.36 3120.36 3120.36 3120.36 3120.36 3120.36 3120.36 3120.36 1900.81 45197.53
4 Cash Operating Expenses 16457.17 39790.16 44996.55 64690.77 65499.36 66018.13 66537.98 66621.05 66649.72 66679.65 66710.92 66733.99 66622.89 66004.07 65416.23 65451.99 64987.69 64626.97 64133.04 1154628.32
5 Total Cash Outflow 16457.17 220523.90 110004.71 167212.50 62379.00 63079.77 64148.63 63500.70 63711.36 64290.29 73008.17 72697.99 72159.59 68495.18 62477.87 63207.83 63232.48 64626.97 55007.35 1490221.45
6 Inflow from Sales 23222.40 23222.40 23222.40 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 47152.09 47152.09 40197.16 893767.83
- -
7 Net Cash Flow 6765.24 -86782.31 -9332.91 -10033.67 -11102.53-10454.60-10665.26-11244.19-19962.07-19651.89-19113.49-15449.08 -9431.77 -10161.73 -16080.39 -17474.88 -14810.19 -596453.62
197301.50 114166.40
8 Coal Production (Lakh Tonnes) 16.75 16.75 16.75 38.25 38.25 38.25 38.25 38.25 38.25 38.25 38.25 38.25 38.25 38.25 38.25 38.25 34.00 34.00 28.99 644.47
-
11 Net Present Value (` Lakhs)
340701.03
ADD - ON SLIDES
Appendix - A
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Appendix - C
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Option - II (Total Coal Departmentaln & Total OB Outsourced) - 8 Mtpa
Appendix - C.1
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Statement Showing Estimated Year wise Operating Cost at 100% capacity utilisation
Option - II (Total Coal Departmentaln & Total OB Outsourced) - 8 Mtpa
Option - II (Integrated - 8 Mtpa) (Amt. in ` Lakhs)
Avg % of
Sl.
Particulars Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total Cost Cost Total
No.
(`/t) Cost
1 Salary & Wages 6872.42 6995.38 9153.36 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 202262.44 146.49 13.65
2 Stores 8103.21 9014.77 9418.19 12558.35 12558.35 12558.35 12558.35 12558.35 12558.35 12558.35 12558.35 12551.23 12391.89 11661.03 10768.16 10768.16 10507.50 10247.73 9685.38 215584.07 156.14 14.54
3 Power 333.85 946.06 1894.72 2147.96 2567.13 2986.29 3083.48 3090.32 3097.16 3104.00 3104.00 3104.00 3104.00 3104.00 3104.00 3104.00 3104.00 3104.00 48082.92 34.83 3.24
4 Misc. Expenses 1554.24 1700.09 1942.63 2540.12 2837.84 2837.84 2837.84 2837.84 2837.84 2837.84 2837.84 2837.84 2837.84 2837.84 2837.84 2837.84 2759.09 2680.34 2574.82 49805.45 36.07 3.36
Adminstrative Cost
5 198.00 198.00 198.00 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 253.39 217.19 168.68 4997.84 3.62 0.34
(Cash)
6 Mine Closure Cost 853.47 896.14 940.95 987.99 1037.39 1089.26 1143.73 1200.91 1260.96 1324.01 1390.21 1459.72 1532.70 1609.34 1689.81 1774.30 1863.01 1956.16 2053.97 26064.03 18.88 1.76
7 OB Outsourcing 25015.16 36369.56 36369.56 44353.12 44353.12 44353.12 44353.12 44353.12 44353.12 44353.12 44353.12 44264.42 42279.61 33176.14 22054.59 22054.59 19293.61 16543.71 10190.13 662436.05 479.78 44.69
8 Coal Outsourcing
Interest on Working
9 2058.83 2682.88 2850.16 3568.28 3597.30 3620.06 3642.96 3650.42 3653.65 3657.03 3660.56 3659.29 3559.18 3087.56 2510.75 2514.83 2367.52 2221.00 1884.01 58446.25 42.33 3.94
capital
10 Total Cash Cost 44655.33 58190.67 61818.90 77394.75 78024.13 78517.93 79014.46 79176.29 79246.41 79319.67 79396.24 79368.65 77197.38 66968.07 54457.31 54545.89 51350.69 48172.71 40863.56 1267679.06 918.14 85.52
11 Interest
Adminstrative Cost
12 1690.68 1690.68 1690.68 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2163.57 1854.49 1440.32 42674.94 30.91 2.88
(Notional)
13 Depreciation 3600.24 3853.96 7505.26 9831.40 9834.54 9834.54 9834.95 9834.95 9848.40 9849.00 9849.60 9850.29 9850.29 9850.29 9850.29 9850.29 9850.29 9850.29 9286.09 171914.95 124.51 11.60
Total 49946.25 63735.31 71014.84 89698.81 90331.32 90825.13 91322.06 91483.89 91567.47 91641.33 91718.49 91691.60 89520.33 79291.01 66780.26 66868.83 63364.56 59877.49 51589.97 1482268.95 1073.56 100.00
Cost (`/t) 913.09 1165.18 1298.26 1121.24 1129.14 1135.31 1141.53 1143.55 1144.59 1145.52 1146.48 1146.14 1119.00 991.14 834.75 835.86 905.21 997.96 1107.08 1073.56
Fixed Cost (`/t) 334.77 350.18 477.53 427.05 434.13 438.93 443.77 445.47 446.49 447.40 448.34 449.26 450.21 451.22 452.27 453.38 514.52 596.12 747.64 458.64 42.72
Variable Cost (`/t) 578.32 815.00 820.73 694.18 695.01 696.39 697.76 698.08 698.10 698.12 698.14 696.89 668.79 539.92 382.48 382.48 390.69 401.84 359.44 614.92 57.28
Total Cost (` in Lakhs) 49946.25 63735.31 71014.84 89698.81 90331.32 90825.13 91322.06 91483.89 91567.47 91641.33 91718.49 91691.60 89520.33 79291.01 66780.26 66868.83 63364.56 59877.49 51589.97 1482268.95 1073.56
Total Profits (` in Lakhs) 45438.07 23365.99 16086.46 22301.17 17484.97 14821.47 15452.20 15339.79 10643.92 11964.31 15052.38 16684.56 28328.84 41442.67 39308.39 39219.82 29463.01 19689.00 10434.85 432521.87 313.26
ADD - ON SLIDES
Appendix - C.2
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Statement Showing Estimated Year wise operating cost at 85% capacity utilisation
Option - II (Total Coal Departmentaln & Total OB Outsourced) - 8 Mtpa
(Amt. in ` Lakhs)
Option - II (Integrated - 8 Mtpa)
Avg % of
Sl.
Particulars Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total Cost Cost Total
No.
(`/t) Cost
1 Salary & Wages 6872.42 6995.38 9153.36 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 202262.44 172.34 14.93
2 Stores 7423.80 8198.63 8583.19 11476.57 11476.57 11476.57 11476.57 11476.57 11476.57 11476.57 11476.57 11470.51 11335.07 10713.85 9954.91 9954.91 9733.34 9512.53 9034.54 197727.81 168.48 14.59
3 Power 321.33 910.58 1823.67 2067.41 2470.86 2874.31 2967.85 2974.43 2981.01 2987.60 2987.60 2987.60 2987.60 2987.60 2987.60 2987.60 2987.60 2987.60 46279.81 39.43 3.42
4 Misc. Expenses 1459.58 1605.43 1844.95 2399.80 2697.52 2697.52 2697.52 2697.52 2697.52 2697.52 2697.52 2697.52 2697.52 2697.52 2697.52 2697.52 2630.59 2563.65 2473.95 47348.25 40.34 3.49
Adminstrative Cost
5 198.00 198.00 198.00 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 253.39 217.19 168.68 4997.84 4.26 0.37
(Cash)
6 Mine Closure Cost 853.47 896.14 940.95 987.99 1037.39 1089.26 1143.73 1200.91 1260.96 1324.01 1390.21 1459.72 1532.70 1609.34 1689.81 1774.30 1863.01 1956.16 2053.97 26064.03 22.21 1.92
7 OB Outsourcing 21262.89 30914.13 30914.13 37700.15 37700.15 37700.15 37700.15 37700.15 37700.15 37700.15 37700.15 37624.75 35937.67 28199.71 18746.40 18746.40 16399.57 14062.16 8661.61 563070.65 479.78 41.56
8 Coal Outsourcing
Interest on Working
9 1840.06 2374.57 2539.68 3184.22 3212.78 3234.78 3256.91 3264.20 3267.42 3270.79 3274.30 3273.73 3189.17 2788.84 2299.14 2303.22 2178.39 2054.26 1768.17 52574.62 44.80 3.88
capital
10 Total Cash Cost 39910.21 51503.60 55084.84 69064.57 69683.99 70161.31 70641.36 70799.37 70869.22 70942.22 71018.52 71006.00 69171.89 60489.03 49867.54 49956.11 47248.46 44556.12 38351.10 1140325.45 971.65 84.16
11 Interest
Adminstrative Cost
12 1690.68 1690.68 1690.68 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2163.57 1854.49 1440.32 42674.94 36.36 3.15
(Notional )
13 Depreciation 3600.24 3853.96 7505.26 9831.40 9834.54 9834.54 9834.95 9834.95 9848.40 9849.00 9849.60 9850.29 9850.29 9850.29 9850.29 9850.29 9850.29 9850.29 9286.09 171914.95 146.49 12.69
Total 45201.13 57048.24 64280.78 81368.62 81991.18 82468.50 82948.96 83106.97 83190.28 83263.87 83340.77 83328.94 81494.84 72811.97 62190.48 62279.06 59262.32 56260.91 49077.51 1354915.34 1154.50 100.00
Cost (`/t) 972.17 1226.98 1382.53 1196.60 1205.75 1212.77 1219.84 1222.16 1223.39 1224.47 1225.60 1225.43 1198.45 1070.76 914.57 915.87 996.01 1103.16 1239.02 1154.50
Fixed Cost (`/t) 393.85 411.98 561.80 502.42 510.74 516.39 522.08 524.08 525.29 526.35 527.46 528.54 529.66 530.84 532.08 533.39 605.32 701.31 879.58 539.58 46.74
Variable Cost (`/t) 578.32 815.00 820.73 694.18 695.01 696.39 697.76 698.08 698.10 698.12 698.14 696.89 668.79 539.92 382.48 382.48 390.69 401.84 359.44 614.92 53.26
100171.8 102623.6
Total Sales (` in Lakhs) 81076.67 74036.10 74036.10 95199.99 91643.85 89799.60 90758.12 90800.13 86879.68 88064.80 90755.24 92119.74
0 3
90175.35 90175.35 78903.43 67631.51 52721.10 1627572.20 1386.83
Total Cost (` in Lakhs) 45201.13 57048.24 64280.78 81368.62 81991.18 82468.50 82948.96 83106.97 83190.28 83263.87 83340.77 83328.94 81494.84 72811.97 62190.48 62279.06 59262.32 56260.91 49077.51 1354915.34 1154.50
Total Profits (` in Lakhs) 35875.54 16987.86 9755.33 13831.36 9652.67 7331.10 7809.16 7693.16 3689.40 4800.92 7414.47 8790.80 18676.96 29811.66 27984.87 27896.29 19641.11 11370.61 3643.58 272656.86 232.33
ADD - ON SLIDES
Appendix - C.3
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Option - II (Total Coal Departmentaln & Total OB Outsourced) - 8 Mtpa
Statement Showing Economics at Different Capacity Utilisation
Capacity Utilisation
Sl No. Particulars
100% 90% 85% 80% 75%
Appendix - C.4
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Option - II (Total Coal Departmentaln & Total OB Outsourced) - 8 Mtpa
Statement showing Sensitivity of IRR
Option - II (Integrated - 8 Mtpa)
Capacity Utilisation
Sl No. Particulars
100% 90% 85% 80% 75%
A Base Case 81.02% 51.63% 39.21% 29.44% 21.88%
B Increase in Capital
1)5% 77.27% 47.86% 36.17% 27.20% 20.26%
2)10% 73.35% 44.24% 33.39% 25.19% 18.80%
3)15% 69.26% 40.84% 30.88% 23.38% 17.47%
C Increase in Op.Cost
1)5% 64.73% 38.07% 28.61% 21.38% 15.60%
2)10% 47.67% 27.00% 20.27% 14.89% 10.31%
3)15% 32.65% 18.62% 13.73% 9.53% 5.72%
D Decrease in Sales
1)5% 54.20% 32.23% 24.64% 18.62% 13.60%
2)10% 31.64% 19.26% 14.67% 10.66% 7.01%
3)15% 17.64% 10.37% 7.22% 4.22% 1.29%
E Increase in Cap.+Op.Cost
1)5% 60.52% 34.99% 26.38% 19.77% 14.41%
2)10% 39.95% 22.97% 17.36% 12.71% 8.63%
3)15% 25.22% 14.79% 10.82% 7.25% 3.92%
ADD - ON SLIDES
Appendix - D
Sl.
Particulars Existing Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total
No.
-
2 Replacement Capital 507.10 6267.15 6344.53 1858.92 384.15 4733.49 361.90 303.12 2457.13 506.24 6162.03 11133.69 5198.35 812.85 3058.39 1763.74 24254.5 27598.17
9
Cash Operating 78024.1 78517.9 79014.4 79176.2 79246.4 79319.6 79396.2 79368.6 66968.0 54457.3 54545.8 48172.7 40863.5 1267679.0
4 44655.33 58190.67 61818.90 77394.75 77197.38 51350.69
Expenses 3 3 6 9 1 7 4 5 7 1 9 1 6 6
79603.7 78843.4 83026.7 79482.9 79521.7 81403.1 79832.4 84618.7 71377.7 55147.4 57159.8 48172.7 16608.9 1415887.5
5 Total Cash Outflow 31326.68 44655.33 63103.56 127829.09 114622.15 86682.42 52868.42
9 9 0 8 7 7 8 2 5 8 9 1 7 2
107816. 105646. 106774. 106823. 102211. 103605. 106770. 108376. 120733. 106088. 106088. 79566.4 62024.8 1914790.8
6 Inflow from Sales 95384.32 87101.30 87101.30 111999.99 117849.17 92827.57
29 59 26 68 38 64 87 16 69 65 65 9 2 2
28212.5 26803.1 23747.5 27340.7 22689.6 22202.4 26938.4 23757.4 49355.9 50941.1 48928.7 31393.7 45415.8
7 Net Cash Flow -31326.68 50728.99 23997.74 -40727.79 -2622.16 31166.75 39959.15 498903.30
0 1 6 0 2 8 0 4 4 7 5 8 5
Appendix - D.1
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Option - II (Total Coal Departmentaln & Total OB Outsourced) - 8 Mtpa
Statement Showing Estimated Cash Flow Analysis
(Pre-Tax IRR on Total Capital)
At 85% capacity utilisation
Option - II (Integrated - 8 Mtpa) (Amt. in ` Lakhs)
Sl.
Particulars Existing Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total
No.
-
2 Replacement Capital 507.10 6267.15 6344.53 1858.92 384.15 4733.49 361.90 303.12 2457.13 506.24 6162.03 11133.69 5198.35 812.85 3058.39 1763.74
24254.59
27598.17
48766.1
5 Total Cash Outflow 31326.68 39910.21 56416.49 121095.03 106291.96 71263.65 70486.86 74653.60 71106.06 71144.58 73025.71 71454.75 76256.06 78656.93 64898.70 50557.70 52570.12
8
44556.12 14096.51 1288533.91
30137.2
7 Net Cash Flow -31326.68 41166.46 17619.61 -47058.92 -11091.97 20380.20 19312.74 16104.52 19694.07 15735.10 15039.09 19300.49 15863.68 21514.87 37724.93 39617.65 37605.23
5
23075.39 38624.59 339038.28
Coal Production
8 46.50 46.50 46.50 68.00 68.00 68.00 68.00 68.00 68.00 68.00 68.00 68.00 68.00 68.00 68.00 68.00 59.50 51.00 39.61 1173.60
(Lakh Tonnes)
9 Pre Tax Internal rate of return 39.21%
Appendix - A
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
8.3 Water Supply & Sewerage 1842 5586 5586 1117 4469
Appendix - C
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Option - II (Total Coal Departmental & Total OB Outsourced) - Incremental 4.5 Mtpa
Appendix - C.1
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Statement Showing Estimated Year wise Operating Cost at 100% capacity utilisation
Option - II (Total Coal Departmental & Total OB Outsourced) - Incremental 4.5 Mtpa
Option - II (Incremental - 4.5 Mtpa) (Amt. in ` Lakhs)
% of
Sl. Avg Cost
Particulars Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total Cost Total
No. (`/t)
Cost
1 Salary & Wages 2214.27 1478.46 3615.04 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 97874.91 129.09 11.76
2 Stores 799.68 1128.16 1531.58 5569.95 5569.95 5569.95 5569.95 5569.95 5569.95 5569.95 5569.95 5562.83 5403.49 4672.63 3974.72 3974.72 3843.94 3806.55 3649.12 82907.07 109.35 9.96
3 Power 92.81 393.25 929.00 1063.20 1292.93 1522.65 1583.17 1586.00 1588.84 1591.68 1591.68 1591.68 1591.68 1591.68 1591.68 1591.68 1591.68 1591.68 24376.97 32.15 2.93
4 Misc. Expenses 307.27 353.50 518.24 1057.18 1354.91 1354.91 1354.91 1354.91 1354.91 1354.91 1354.91 1354.91 1354.91 1354.91 1354.91 1354.91 1315.53 1315.53 1269.07 22395.22 29.54 2.69
5 Adminstrative Cost (Cash) 71.31 71.31 71.31 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 144.79 144.79 123.43 2744.52 3.62 0.33
6 Mine Closure Cost 344.56 361.79 379.88 398.88 418.82 439.76 461.75 484.84 509.08 534.53 561.26 589.32 618.79 649.73 682.21 716.32 752.14 789.75 829.23 10522.62 13.88 1.26
7 OB Outsourcing 9003.68 13095.26 13095.26 32266.90 32266.90 32266.90 32266.90 32266.90 32266.90 32266.90 32266.90 32178.19 30193.39 21089.91 12396.70 12396.70 11010.66 10544.95 8870.62 432010.50 569.78 51.92
8 Coal Outsourcing
Interest on Working
9 615.80 801.43 947.55 2225.52 2247.36 2259.48 2271.64 2275.68 2276.99 2278.36 2279.79 2276.51 2174.30 1700.47 1248.14 1249.79 1175.43 1152.93 1063.02 32520.20 42.89 3.91
capital
10 Total Cash Cost 13356.58 17382.72 20552.11 48270.77 48744.48 49007.26 49271.14 49358.78 49387.17 49416.83 49447.82 49376.78 47159.89 36882.67 27071.69 27107.45 25494.62 25006.63 23056.63 705352.01 930.30 84.77
11 Interest
Adminstrative Cost
12 608.89 608.89 608.89 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1236.33 1236.33 1053.97 23434.59 30.91 2.82
(Notional)
13 Depreciation 248.66 3891.03 6216.77 6216.77 6216.77 6216.77 6216.77 6216.77 6216.77 6216.77 6216.77 6216.77 6216.77 6216.77 6216.77 6216.77 6165.36 5958.86 103298.63 136.24 12.41
Total 13965.47 18240.27 25052.04 55878.40 56352.11 56614.89 56878.77 56966.41 56994.80 57024.46 57055.46 56984.42 54767.53 44490.30 34679.33 34715.09 32947.72 32408.32 30069.46 832085.24 1097.45 100.00
Cost (`/t.) 708.91 925.90 1271.68 1241.74 1252.27 1258.11 1263.97 1265.92 1266.55 1267.21 1267.90 1266.32 1217.06 988.67 770.65 771.45 823.69 810.21 881.80 1097.45
Fixed Cost (`/t) 178.97 159.51 493.53 385.46 395.21 399.71 404.24 405.83 406.45 407.09 407.76 408.42 409.10 409.82 410.58 411.37 459.40 459.10 527.68 406.06 37.00
Variable Cost (`/t) 529.94 766.39 778.14 856.28 857.06 858.40 859.74 860.09 860.10 860.12 860.14 857.91 807.95 578.85 360.07 360.07 364.30 351.11 354.12 691.39 63.00
1051491.5
Total Sales (` in Lakhs) 27320.47 27320.47 27320.47 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 55473.04 55473.04 47290.77 1386.83
6
Total Cost (` in Lakhs) 13965.47 18240.27 25052.04 55878.40 56352.11 56614.89 56878.77 56966.41 56994.80 57024.46 57055.46 56984.42 54767.53 44490.30 34679.33 34715.09 32947.72 32408.32 30069.46 832085.24 1097.45
Total Profits (` in Lakhs) 13355.00 9080.21 2268.44 6528.77 6055.06 5792.28 5528.40 5440.76 5412.37 5382.71 5351.72 5422.76 7639.65 17916.87 27727.85 27692.09 22525.33 23064.73 17221.31 219406.32 289.38
ADD - ON SLIDES
Appendix - C.2
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Statement Showing Estimated Year wise operating cost at 85% capacity utilisation
Option - II (Total Coal Departmental & Total OB Outsourced) - Incremental 4.5 Mtpa
(Amount in Rs. Lakhs)
Option - II (Incremental - 4.5 Mtpa)
% of
Sl. Avg Cost
Particulars Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total Cost Total
No. (`/t)
Cost
1 Salary & Wages 2214.27 1478.46 3615.04 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 97874.91 151.87 12.99
2 Stores 679.73 958.94 1343.50 5000.36 5000.36 5000.36 5000.36 5000.36 5000.36 5000.36 5000.36 4994.30 4858.86 4237.64 3644.41 3644.41 3533.25 3501.47 3367.65 74767.01 116.01 9.92
3 Power 89.33 378.50 894.16 1023.33 1244.44 1465.55 1523.80 1526.53 1529.26 1531.99 1531.99 1531.99 1531.99 1531.99 1531.99 1531.99 1531.99 1531.99 23462.84 36.41 3.11
4 Misc. Expenses 284.00 330.23 491.95 988.26 1285.98 1285.98 1285.98 1285.98 1285.98 1285.98 1285.98 1285.98 1285.98 1285.98 1285.98 1285.98 1252.51 1252.51 1213.02 21244.23 32.96 2.82
5 Adminstrative Cost (Cash) 71.31 71.31 71.31 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 144.79 144.79 123.43 2744.52 4.26 0.36
6 Mine Closure Cost 344.56 361.79 379.88 398.88 418.82 439.76 461.75 484.84 509.08 534.53 561.26 589.32 618.79 649.73 682.21 716.32 752.14 789.75 829.23 10522.62 16.33 1.40
7 OB Outsourcing 7653.13 11130.97 11130.97 27426.86 27426.86 27426.86 27426.86 27426.86 27426.86 27426.86 27426.86 27351.46 25664.38 17926.42 10537.19 10537.19 9359.06 8963.21 7540.03 367208.92 569.78 48.74
8 Coal Outsourcing
Interest on Working
9 543.61 697.02 841.54 1959.04 1980.64 1992.34 2004.09 2008.02 2009.32 2010.68 2012.11 2009.53 1922.86 1520.33 1136.08 1137.73 1074.65 1055.80 979.51 28894.88 44.84 3.83
capital
10 Total Cash Cost 11790.61 15118.04 18252.69 42490.89 42959.32 43213.07 43467.92 43553.18 43581.46 43611.01 43641.89 43585.92 41706.20 32975.42 24641.20 24676.96 23308.84 22899.97 21245.32 626719.93 972.46 83.18
11 Interest
Adminstrative Cost
12 608.89 608.89 608.89 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1236.33 1236.33 1053.97 23434.59 36.36 3.11
(Notional )
13 Depreciation 248.66 3891.03 6216.77 6216.77 6216.77 6216.77 6216.77 6216.77 6216.77 6216.77 6216.77 6216.77 6216.77 6216.77 6216.77 6216.77 6165.36 5958.86 103298.63 160.28 13.71
Total 12399.50 15975.59 22752.62 50098.52 50566.96 50820.71 51075.56 51160.82 51189.10 51218.65 51249.53 51193.56 49313.83 40583.06 32248.84 32284.60 30761.94 30301.65 28258.14 753453.16 1169.11 100.00
Cost (`/t.) 740.49 954.05 1358.77 1309.77 1322.01 1328.65 1335.31 1337.54 1338.28 1339.05 1339.86 1338.39 1289.25 1060.99 843.11 844.04 904.76 891.23 974.92 1169.11
Fixed Cost (`/t) 210.55 187.66 580.63 453.49 464.95 470.25 475.57 477.45 478.17 478.93 479.72 480.49 481.30 482.14 483.03 483.97 540.47 540.11 620.80 477.71 40.86
Variable Cost (`/t) 529.94 766.39 778.14 856.28 857.06 858.40 859.74 860.09 860.10 860.12 860.14 857.91 807.95 578.85 360.07 360.07 364.30 351.11 354.12 691.39 59.14
Total Sales (` in Lakhs) 23222.40 23222.40 23222.40 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 47152.09 47152.09 40197.16 893767.83 1386.83
Total Cost (` in Lakhs) 12399.50 15975.59 22752.62 50098.52 50566.96 50820.71 51075.56 51160.82 51189.10 51218.65 51249.53 51193.56 49313.83 40583.06 32248.84 32284.60 30761.94 30301.65 28258.14 753453.16 1169.11
Total Profits (` in Lakhs) 10822.90 7246.81 469.78 2947.57 2479.14 2225.39 1970.54 1885.28 1857.00 1827.45 1796.57 1852.54 3732.27 12463.04 20797.26 20761.50 16390.15 16850.44 11939.01 140314.67 217.72
ADD - ON SLIDES
Appendix - C.3
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Option - II (Total Coal Departmental & Total OB Outsourced) - Incremental 4.5 Mtpa
Appendix - C.4
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Option - II (Total Coal Departmental & Total OB Outsourced) - Incremental 4.5 Mtpa
Statement showing Sensitivity of IRR
Appendix - D
Sl.
Particulars Existing Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total
No.
2 Replacement Capital 182.00 731.00 182.00 731.00 819.23 5538.75 1879.76 182.00 876.20 145.60 -3371.03 7896.51
3 Less: GST credit on Capital Goods 706.76 2151.99 27.76 111.51 27.76 111.51 110.58 795.19 286.74 27.76 111.51 4469.07
4 Cash Operating Expenses 13356.58 17382.72 20552.11 48270.77 48744.48 49007.26 49271.14 49358.78 49387.17 49416.83 49447.82 49376.78 47159.89 36882.67 27071.69 27107.45 25494.62 25006.63 23056.63 705352.01
5 Total Cash Outflow 13356.58 21858.51 81238.91 80120.62 48744.48 49161.49 49890.63 49358.78 49541.40 50036.32 49447.82 50085.43 51903.46 38475.68 27225.93 27872.14 25640.22 25006.63 19685.61 808650.65
6 Inflow from Sales 27320.47 27320.47 27320.47 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 55473.04 55473.04 47290.77 1051491.56
7 Net Cash Flow 13963.89 5461.96 -53918.44 -17713.44 13662.70 13245.68 12516.55 13048.40 12865.77 12370.86 12959.35 12321.75 10503.72 23931.49 35181.25 34535.03 29832.82 30466.41 27605.16 242840.92
8 Coal Production (Lakh Tonnes) 19.70 19.70 19.70 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 40.00 40.00 34.10 758.20
Appendix - D.1
Option - II (Total Coal Departmental & Total OB Outsourced) - Incremental 4.5 Mtpa
Sl.
Particulars Existing Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total
No.
2 Replacement Capital 182.00 731.00 182.00 731.00 819.23 5538.75 1879.76 182.00 876.20 145.60 -3371.03 7896.51
3 Less: GST credit on Capital Goods 706.76 2151.99 27.76 111.51 27.76 111.51 110.58 795.19 286.74 27.76 111.51 4469.07
4 Cash Operating Expenses 11790.61 15118.04 18252.69 42490.89 42959.32 43213.07 43467.92 43553.18 43581.46 43611.01 43641.89 43585.92 41706.20 32975.42 24641.20 24676.96 23308.84 22899.97 21245.32 626719.93
5 Total Cash Outflow 11790.61 19593.84 78939.50 74340.74 42959.32 43367.31 44087.41 43553.18 43735.70 44230.50 43641.89 44294.57 46449.76 34568.44 24795.44 25441.65 23454.44 22899.97 17874.29 730018.56
6 Inflow from Sales 23222.40 23222.40 23222.40 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 47152.09 47152.09 40197.16 893767.83
7 Net Cash Flow 11431.80 3628.57 -55717.09 -21294.64 10086.78 9678.79 8958.69 9492.92 9310.40 8815.60 9404.21 8751.53 6596.34 18477.66 28250.66 27604.45 23697.64 24252.12 22322.87 163749.27
8 Coal Production (Lakh Tonnes) 16.75 16.75 16.75 38.25 38.25 38.25 38.25 38.25 38.25 38.25 38.25 38.25 38.25 38.25 38.25 38.25 34.00 34.00 28.99 644.47
Appendix - A
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Appendix - C
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Option - III (a) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines
for Dumping) - 8 Mtpa
Appendix - C.1
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Statement Showing Estimated Year wise Operating Cost at 100% capacity utilisation
Option - III (a) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines for Dumping) - 8 Mtpa
Option - III (a) (Integrated - 8 Mtpa) (Amt. in ` Lakhs)
1 Salary & Wages 6872.42 6995.38 9153.36 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 202262.44 146.49 13.18
2 Stores 8103.21 9014.77 9418.19 12558.35 12558.35 12558.35 12558.35 12558.35 12558.35 12558.35 12558.35 12551.23 12391.89 11661.03 10768.16 10768.16 10507.50 10247.73 9685.38 215584.07 156.14 14.05
3 Power 333.85 946.06 1894.72 2147.96 2567.13 2986.29 3083.48 3090.32 3097.16 3104.00 3104.00 3104.00 3104.00 3104.00 3104.00 3104.00 3104.00 3104.00 48082.92 34.83 3.13
4 Misc. Expenses 1554.24 1700.09 1942.63 2573.08 3002.64 3002.64 3002.64 3002.64 3002.64 3002.64 3002.64 3002.64 3002.64 3002.64 3002.64 3002.64 2923.89 2845.14 2739.62 52310.41 37.89 3.41
5 Adminstrative Cost (Cash) 198.00 198.00 198.00 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 253.39 217.19 168.68 4997.84 3.62 0.33
6 Mine Closure Cost 853.47 896.14 940.95 987.99 1037.39 1089.26 1143.73 1200.91 1260.96 1324.01 1390.21 1459.72 1532.70 1609.34 1689.81 1774.30 1863.01 1956.16 2053.97 26064.03 18.88 1.70
7 OB Outsourcing 25015.16 36369.56 38725.20 46708.76 46708.76 46708.76 46708.76 46708.76 46708.76 46708.76 46708.76 46620.05 44635.25 35531.77 24410.23 24410.23 21649.25 18832.84 12407.20 702276.81 508.64 45.77
8 Coal Outsourcing
Interest on Working
9 2058.83 2682.88 2964.01 3683.73 3719.12 3741.88 3764.78 3772.24 3775.47 3778.85 3782.38 3781.11 3681.00 3209.38 2632.57 2636.66 2489.34 2339.61 1999.14 60492.96 43.81 3.94
capital
1312071.4
10 Total Cash Cost 44655.33 58190.67 64288.39 79898.80 80666.39 81160.19 81656.72 81818.55 81888.67 81961.93 82038.50 82010.91 79839.64 69610.33 57099.57 57188.15 53992.95 50745.24 43360.56 950.29 85.50
9
11 Interest
Adminstrative Cost
12 1690.68 1690.68 1690.68 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2163.57 1854.49 1440.32 42674.94 30.91 2.78
(Notional)
13 Depreciation 3600.24 3853.96 7597.58 10316.11 10319.24 10319.24 10319.65 10319.65 10333.11 10333.71 10334.30 10335.00 10335.00 10335.00 10335.00 10335.00 10335.00 10335.00 9770.79 179762.59 130.20 11.71
1534509.0
Total 49946.25 63735.31 73576.66 92687.56 93458.29 93952.09 94449.02 94610.86 94694.44 94768.30 94845.46 94818.56 92647.30 82417.98 69907.22 69995.80 66491.52 62934.73 54571.67 1111.40 100.00
3
Cost (`/t) 913.09 1165.18 1345.09 1158.59 1168.23 1174.40 1180.61 1182.64 1183.68 1184.60 1185.57 1185.23 1158.09 1030.22 873.84 874.95 949.88 1048.91 1171.07 1111.40
Fixed Cost (`/t) 334.77 350.18 479.22 433.54 442.35 447.15 451.99 453.69 454.71 455.61 456.56 457.48 458.43 459.44 460.49 461.60 523.91 607.07 761.75 466.23 41.95
Variable Cost (`/t) 578.32 815.00 865.87 725.05 725.88 727.25 728.63 728.95 728.97 728.99 729.01 727.76 699.66 570.79 413.35 413.35 425.97 441.84 409.31 645.17 58.05
1914790.8
Total Sales (` in Lakhs) 95384.32 87101.30 87101.30 111999.99 107816.29 105646.59 106774.26106823.68102211.38103605.64106770.87108376.16117849.17120733.69106088.65106088.65 92827.57 79566.49 62024.82 1386.83
2
1534509.0
Total Cost (` in Lakhs) 49946.25 63735.31 73576.66 92687.56 93458.29 93952.09 94449.02 94610.86 94694.44 94768.30 94845.46 94818.56 92647.30 82417.98 69907.22 69995.80 66491.52 62934.73 54571.67 1111.40
3
Total Profits (` in Lakhs) 45438.07 23365.99 13524.64 19312.42 14358.00 11694.50 12325.24 12212.82 7516.95 8837.35 11925.41 13557.60 25201.88 38315.71 36181.42 36092.85 26336.04 16631.76 7453.15 380281.80 275.43
ADD - ON SLIDES
Appendix - C.2
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Statement Showing Estimated Year wise operating cost at 85% capacity utilisation
Option - III (a) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines for Dumping) - 8 Mtpa
(Amt. in ` Lakhs)
Option - III (a) (Integrated - 8 Mtpa)
1 Salary & Wages 6872.42 6995.38 9153.36 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 202262.44 172.34 14.44
2 Stores 7423.80 8198.63 8583.19 11476.57 11476.57 11476.57 11476.57 11476.57 11476.57 11476.57 11476.57 11470.51 11335.07 10713.85 9954.91 9954.91 9733.34 9512.53 9034.54 197727.81 168.48 14.11
3 Power 321.33 910.58 1823.67 2067.41 2470.86 2874.31 2967.85 2974.43 2981.01 2987.60 2987.60 2987.60 2987.60 2987.60 2987.60 2987.60 2987.60 2987.60 46279.81 39.43 3.30
4 Misc. Expenses 1459.58 1605.43 1844.95 2432.76 2862.33 2862.33 2862.33 2862.33 2862.33 2862.33 2862.33 2862.33 2862.33 2862.33 2862.33 2862.33 2795.39 2728.45 2638.75 49853.21 42.48 3.56
5 Adminstrative Cost (Cash) 198.00 198.00 198.00 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 253.39 217.19 168.68 4997.84 4.26 0.36
6 Mine Closure Cost 853.47 896.14 940.95 987.99 1037.39 1089.26 1143.73 1200.91 1260.96 1324.01 1390.21 1459.72 1532.70 1609.34 1689.81 1774.30 1863.01 1956.16 2053.97 26064.03 22.21 1.86
7 OB Outsourcing 21262.89 30914.13 32916.42 39702.45 39702.45 39702.45 39702.45 39702.45 39702.45 39702.45 39702.45 39627.05 37939.96 30202.01 20748.69 20748.69 18401.86 16007.91 10546.12 596935.29 508.64 42.61
8 Coal Outsourcing
Interest on Working
9 1840.06 2374.57 2636.46 3282.59 3317.52 3339.53 3361.66 3368.94 3372.16 3375.53 3379.05 3378.47 3293.91 2893.58 2403.88 2407.97 2283.13 2156.27 1867.22 54332.49 46.30 3.88
capital
1178452.9
10 Total Cash Cost 39910.21 51503.60 57183.91 71198.19 71955.82 72433.15 72913.19 73071.21 73141.06 73214.05 73290.35 73277.83 71443.73 62760.86 52139.37 52227.95 49520.29 46768.69 40499.46 1004.14 84.12
2
11 Interest
Adminstrative Cost
12 1690.68 1690.68 1690.68 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2163.57 1854.49 1440.32 42674.94 36.36 3.05
(Notional )
13 Depreciation 3600.24 3853.96 7597.58 10316.11 10319.24 10319.24 10319.65 10319.65 10333.11 10333.71 10334.30 10335.00 10335.00 10335.00 10335.00 10335.00 10335.00 10335.00 9770.79 179762.59 153.17 12.83
1400890.4
Total 45201.13 57048.24 66472.17 83986.95 84747.72 85225.05 85705.50 85863.52 85946.82 86020.41 86097.31 86085.48 84251.38 75568.51 64947.02 65035.60 62018.86 58958.18 51710.58 1193.67 100.00
6
Cost (`/t) 972.17 1226.98 1429.66 1235.10 1246.29 1253.31 1260.38 1262.70 1263.92 1265.01 1266.14 1265.96 1238.99 1111.30 955.10 956.41 1042.33 1156.04 1305.49 1193.67
Fixed Cost (`/t) 393.85 411.98 563.79 510.05 520.41 526.06 531.75 533.75 534.96 536.02 537.12 538.21 539.33 540.51 541.75 543.06 616.37 714.20 896.18 548.50 45.95
Variable Cost (`/t) 578.32 815.00 865.87 725.05 725.88 727.25 728.63 728.95 728.97 728.99 729.01 727.76 699.66 570.79 413.35 413.35 425.97 441.84 409.31 645.17 54.05
1627572.2
Total Sales (` in Lakhs) 81076.67 74036.10 74036.10 95199.99 91643.85 89799.60 90758.12 90800.13 86879.68 88064.80 90755.24 92119.74 100171.80102623.63 90175.35 90175.35 78903.43 67631.51 52721.10 1386.83
0
1400890.4
Total Cost (` in Lakhs) 45201.13 57048.24 66472.17 83986.95 84747.72 85225.05 85705.50 85863.52 85946.82 86020.41 86097.31 86085.48 84251.38 75568.51 64947.02 65035.60 62018.86 58958.18 51710.58 1193.67
6
Total Profits (` in Lakhs) 35875.54 16987.86 7563.93 11213.03 6896.12 4574.56 5052.62 4936.61 932.85 2044.38 4657.93 6034.26 15920.41 27055.12 25228.33 25139.75 16884.57 8673.33 1010.52 226681.74 193.15
ADD - ON SLIDES
Appendix - C.3
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Option - III (a) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines for Dumping) - 8 Mtpa
Sl Capacity Utilisation
Particulars
No. 100% 90% 85% 80% 75%
1 Output (Mtpa) 8.00 7.20 6.80 6.40 6.00
Appendix - C.4
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Option - III (a) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines for Dumping) - 8 Mtpa
Appendix - D
Option - III (a) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines for Dumping) - 8 Mtpa
Sl.
Particulars Existing Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total
No.
2 Replacement Capital 507.10 6267.15 6344.53 1858.92 384.15 4733.49 361.90 303.12 2457.13 506.24 6162.03 11133.69 5198.35 812.85 3058.39 1763.74 -24254.59 27598.17
3 Less: GST credit on Capital Goods 70.00 1650.52 3118.98 279.26 58.60 721.24 55.20 27.76 373.63 70.00 911.97 1648.65 788.67 122.68 444.39 246.02 10587.58
53992.9
4 Cash Operating Expenses 44655.33 58190.67 64288.39 79898.80 80666.39 81160.19 81656.72 81818.55 81888.67 81961.93 82038.50 82010.91 79839.64 69610.33 57099.57 57188.15 50745.24 43360.56 1312071.49
5
55510.6
5 Total Cash Outflow 31326.68 44655.33 63103.56 131868.11 123404.30 82246.05 81485.74 85668.96 82125.24 82164.03 84045.43 82474.73 87260.98 89324.68 74020.01 57789.74 59802.15 50745.24 19105.96 1468127.60
8
106774.2 106823.6 102211.3 103605.6 106770.8 108376.1 117849.1 120733.6 106088.6 106088.6 92827.5
6 Inflow from Sales 95384.32 87101.30 87101.30 111999.99 107816.29 105646.59 79566.49 62024.82 1914790.82
6 8 8 4 7 6 7 9 5 5 7
37316.8
7 Net Cash Flow -31326.68 50728.99 23997.74 -44766.81 -11404.32 25570.24 24160.85 21105.30 24698.44 20047.36 19560.22 24296.14 21115.18 28524.49 46713.68 48298.91 46286.50 28821.25 42918.86 446663.22
9
8 Coal Production (Lakh Tonnes) 54.70 54.70 54.70 80.00 80.00 80.00 80.00 80.00 80.00 80.00 80.00 80.00 80.00 80.00 80.00 80.00 70.00 60.00 46.60 1380.70
Appendix - D.1
Option - III (a) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines for Dumping) - 8 Mtpa
Sl.
Particulars Existing Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total
No.
2 Replacement Capital 507.10 6267.15 6344.53 1858.92 384.15 4733.49 361.90 303.12 2457.13 506.24 6162.03 11133.69 5198.35 812.85 3058.39 1763.74 -24254.59 27598.17
3 Less: GST credit on Capital Goods 70.00 1650.52 3118.98 279.26 58.60 721.24 55.20 27.76 373.63 70.00 911.97 1648.65 788.67 122.68 444.39 246.02 10587.58
49520.2
4 Cash Operating Expenses 39910.21 51503.60 57183.91 71198.19 71955.82 72433.15 72913.19 73071.21 73141.06 73214.05 73290.35 73277.83 71443.73 62760.86 52139.37 52227.95 46768.69 40499.46 1178452.92
9
51038.0
5 Total Cash Outflow 31326.68 39910.21 56416.49 124763.63 114703.69 73535.48 72758.70 76925.44 73377.90 73416.41 75297.54 73726.58 78527.90 80928.76 67170.54 52829.54 54841.95 46768.69 16244.87 1334509.03
1
27865.4
7 Net Cash Flow -31326.68 41166.46 17619.61 -50727.52 -19503.71 18108.36 17040.91 13832.69 17422.23 13463.26 12767.25 17028.66 13591.84 19243.03 35453.09 37345.81 35333.40 20862.82 36476.23 293063.17
2
8 Coal Production (Lakh Tonnes) 46.50 46.50 46.50 68.00 68.00 68.00 68.00 68.00 68.00 68.00 68.00 68.00 68.00 68.00 68.00 68.00 59.50 51.00 39.61 1173.60
Appendix - A
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
STATEMENT OF ESTIMATED CAPITAL INVESTMENT AND YEARWISE PHASING
Option - III (a) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines for Dumping) - Incremental 4.5 Mtpa
Base Date: October, 2018
Option - III (a) (Incremental - 4.5 Mtpa) (Amt. in ` Lakhs)
PHASING OF CAPITAL
TOTAL
EXISTING BALANCE
SANCTIONE TOTAL COMMITTED
SL AS ON INCREMENTA
PARTICULARS D CAPITAL PROVN EXPENSES
NO 31.03.18 L PROVISION Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7
(3.5 (4.5 Mtpa) FOR 3.5 Mtpa
(3.5 Mtpa) (4.5 Mtpa)
Mtpa)
1 Land 858 19767 19767 988 18779
2 Buildings
Service 2279 5550 5550 1110 4440
Residential 1371 3402 3402 680 2722
3 Plant & Machinery
a) HEMM 8298 5766 5766 257 5509
b) Others than HEMM 23201 15080 15080 4428 10652
4 Furniture & Fittings 98 58 58 29 29
5 Railway Siding 3600
6 Vehicles 308 711 711 240 471
7 Prospecting & Boring 115
8 Development.
8.1 Capital Outlay in Mines 7125 37839 37839 1725 33450 2664
8.2 Roads & Culverts 2417 10994 10994 2199 8795
8.3 Water Supply & Sewerage 1842 5586 5586 1117 4469
8.4 Scientific Research 50 80 80 80
8.5 P.R. Prep. Cost 497 1762 1762 1762
9.1 Revenue Exp. Capitalised
618
less Depreciation
10 Land Reclamation 831 1123 1123 595 527
Appendix - C
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Option - III (a) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines for Dumping) -
Incremental 4.5 Mtpa
Appendix - C.1
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Statement Showing Estimated Year wise Operating Cost at 100% capacity utilisation
Option - III (a) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines for Dumping) - Incremental 4.5 Mtpa
Option - III (a) (Incremental - 4.5 Mtpa) (Amt in ` Lakhs
1 Salary & Wages 2214.27 1478.46 3615.04 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 97874.91 129.09 11.07
2 Stores 799.68 1128.16 1531.58 5569.95 5569.95 5569.95 5569.95 5569.95 5569.95 5569.95 5569.95 5562.83 5403.49 4672.63 3974.72 3974.72 3843.94 3806.55 3649.12 82907.07 109.35 9.38
3 Power 92.81 393.25 929.00 1063.20 1292.93 1522.65 1583.17 1586.00 1588.84 1591.68 1591.68 1591.68 1591.68 1591.68 1591.68 1591.68 1591.68 1591.68 24376.97 32.15 2.76
4 Misc. Expenses 307.27 353.50 518.24 1090.14 1519.71 1519.71 1519.71 1519.71 1519.71 1519.71 1519.71 1519.71 1519.71 1519.71 1519.71 1519.71 1480.33 1480.33 1433.87 24900.19 32.84 2.82
5 Adminstrative Cost (Cash) 71.31 71.31 71.31 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 144.79 144.79 123.43 2744.52 3.62 0.31
6 Mine Closure Cost 344.56 361.79 379.88 398.88 418.82 439.76 461.75 484.84 509.08 534.53 561.26 589.32 618.79 649.73 682.21 716.32 752.14 789.75 829.23 10522.62 13.88 1.19
7 OB Outsourcing 9003.68 13095.26 15450.90 34622.53 34622.53 34622.53 34622.53 34622.53 34622.53 34622.53 34622.53 34533.83 32549.03 23445.55 14752.33 14752.33 13366.30 12834.08 11087.69 471851.25 622.33 53.36
8 Coal Outsourcing
Interest on Working
9 615.80 801.43 1061.41 2340.97 2369.18 2381.30 2393.46 2397.50 2398.81 2400.18 2401.61 2398.33 2296.12 1822.29 1369.96 1371.61 1297.25 1271.54 1178.15 34566.91 45.59 3.91
capital
10 Total Cash Cost 13356.58 17382.72 23021.60 50774.81 51386.73 51649.52 51913.39 52001.04 52029.43 52059.09 52090.08 52019.04 49802.15 39524.93 29713.95 29749.71 28136.88 27579.17 25553.63 749744.44 988.85 84.78
11 Interest
Adminstrative Cost
12 608.89 608.89 608.89 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1236.33 1236.33 1053.97 23434.59 30.91 2.65
(Notional)
13 Depreciation 248.66 3983.36 6701.47 6701.47 6701.47 6701.47 6701.47 6701.47 6701.47 6701.47 6701.47 6701.47 6701.47 6701.47 6701.47 6701.47 6650.06 6443.56 111146.27 146.59 12.57
Total 13965.47 18240.27 27613.85 58867.16 59479.08 59741.86 60005.74 60093.38 60121.77 60151.43 60182.42 60111.38 57894.49 47617.27 37806.29 37842.05 36074.68 35465.56 33051.16 884325.31 1166.35 100.00
Cost/t (`) 708.91 925.90 1401.72 1308.16 1321.76 1327.60 1333.46 1335.41 1336.04 1336.70 1337.39 1335.81 1286.54 1058.16 840.14 840.93 901.87 886.64 969.24 1166.35
Fixed Cost (`/t) 178.97 159.51 498.22 397.00 409.82 414.32 418.85 420.44 421.06 421.70 422.37 423.03 423.71 424.43 425.19 425.98 475.83 475.53 546.96 419.87 36.00
Variable Cost (`/t) 529.94 766.39 903.50 911.16 911.94 913.28 914.61 914.97 914.98 915.00 915.02 912.78 862.83 633.73 414.95 414.95 426.03 411.11 422.28 746.48 64.00
1051491.5
Total Sales (` in Lakhs) 27320.47 27320.47 27320.47 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 55473.04 55473.04 47290.77 1386.83
6
Total Cost (` in Lakhs) 13965.47 18240.27 27613.85 58867.16 59479.08 59741.86 60005.74 60093.38 60121.77 60151.43 60182.42 60111.38 57894.49 47617.27 37806.29 37842.05 36074.68 35465.56 33051.16 884325.31 1166.35
Total Profits (` in Lakhs) 13355.00 9080.21 -293.38 3540.02 2928.10 2665.32 2401.44 2313.80 2285.41 2255.75 2224.75 2295.79 4512.68 14789.91 24600.88 24565.12 19398.36 20007.49 14239.61 167166.25 220.48
ADD - ON SLIDES
Appendix - C.2
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Statement Showing Estimated Year wise operating cost at 85% capacity utilisation
Option - III (a) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines for Dumping) - Incremental 4.5 Mtpa
(Amount in Rs. Lakhs)
Option - III (a) (Incremental - 4.5 Mtpa)
1 Salary & Wages 2214.27 1478.46 3615.04 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 97874.91 151.87 12.24
2 Stores 679.73 958.94 1343.50 5000.36 5000.36 5000.36 5000.36 5000.36 5000.36 5000.36 5000.36 4994.30 4858.86 4237.64 3644.41 3644.41 3533.25 3501.47 3367.65 74767.01 116.01 9.35
3 Power 89.33 378.50 894.16 1023.33 1244.44 1465.55 1523.80 1526.53 1529.26 1531.99 1531.99 1531.99 1531.99 1531.99 1531.99 1531.99 1531.99 1531.99 23462.84 36.41 2.93
4 Misc. Expenses 284.00 330.23 491.95 1021.22 1450.78 1450.78 1450.78 1450.78 1450.78 1450.78 1450.78 1450.78 1450.78 1450.78 1450.78 1450.78 1417.31 1417.31 1377.82 23749.20 36.85 2.97
5 Adminstrative Cost (Cash) 71.31 71.31 71.31 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 144.79 144.79 123.43 2744.52 4.26 0.34
6 Mine Closure Cost 344.56 361.79 379.88 398.88 418.82 439.76 461.75 484.84 509.08 534.53 561.26 589.32 618.79 649.73 682.21 716.32 752.14 789.75 829.23 10522.62 16.33 1.32
7 OB Outsourcing 7653.13 11130.97 13133.26 29429.15 29429.15 29429.15 29429.15 29429.15 29429.15 29429.15 29429.15 29353.75 27666.67 19928.71 12539.48 12539.48 11361.35 10908.97 9424.54 401073.56 622.33 50.17
8 COAL Outsourcing
Interest on Working
9 543.61 697.02 938.32 2057.41 2085.38 2097.08 2108.83 2112.76 2114.06 2115.43 2116.85 2114.27 2027.60 1625.07 1240.82 1242.47 1179.40 1157.81 1078.56 30652.74 47.56 3.83
capital
10 Total Cash Cost 11790.61 15118.04 20351.76 44624.51 45231.16 45484.91 45739.76 45825.02 45853.30 45882.84 45913.73 45857.76 43978.03 35247.26 26913.04 26948.80 25580.68 25112.53 23393.68 664847.40 1031.62 83.17
11 Interest
Adminstrative Cost
12 608.89 608.89 608.89 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1236.33 1236.33 1053.97 23434.59 36.36 2.93
(Notional )
13 Depreciation 248.66 3983.36 6701.47 6701.47 6701.47 6701.47 6701.47 6701.47 6701.47 6701.47 6701.47 6701.47 6701.47 6701.47 6701.47 6701.47 6650.06 6443.56 111146.27 172.46 13.90
Total 12399.50 15975.59 24944.01 52716.85 53323.50 53577.25 53832.10 53917.36 53945.64 53975.19 54006.07 53950.10 52070.37 43339.60 35005.38 35041.14 33518.48 32998.93 30891.21 799428.27 1240.44 100.00
Cost/t (`) 740.49 954.05 1489.64 1378.22 1394.08 1400.71 1407.38 1409.60 1410.34 1411.12 1411.92 1410.46 1361.32 1133.06 915.17 916.11 985.84 970.56 1065.77 1240.44
Fixed Cost (`/t) 210.55 187.66 586.14 467.06 482.14 487.44 492.76 494.64 495.36 496.12 496.91 497.68 498.48 499.33 500.22 501.16 559.80 559.45 643.49 493.96 39.82
Variable Cost (`/t) 529.94 766.39 903.50 911.16 911.94 913.28 914.61 914.97 914.98 915.00 915.02 912.78 862.83 633.73 414.95 414.95 426.03 411.11 422.28 746.48 60.18
Total Sales (` in Lakhs) 23222.40 23222.40 23222.40 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 47152.09 47152.09 40197.16 893767.83 1386.83
Total Cost (` in Lakhs) 12399.50 15975.59 24944.01 52716.85 53323.50 53577.25 53832.10 53917.36 53945.64 53975.19 54006.07 53950.10 52070.37 43339.60 35005.38 35041.14 33518.48 32998.93 30891.21 799428.27 1240.44
Total Profits (` in Lakhs) 10822.90 7246.81 -1721.61 329.25 -277.40 -531.15 -786.00 -871.26 -899.54 -929.09 -959.97 -904.00 975.72 9706.50 18040.72 18004.96 13633.61 14153.16 9305.94 94339.56 146.38
ADD - ON SLIDES
Appendix - C.3
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Option - III (a) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines for Dumping) - Incremental 4.5 Mtpa
Appendix - C.4
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Option - III (a) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines for Dumping) - Incremental 4.5
Mtpa
Statement showing Sensitivity of IRR
E Increase in Cap.+Op.Cost
Appendix - D
Option - III (a) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines for Dumping) - Incremental 4.5 Mtpa
Sl.
Particulars Existing Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total
No.
2 Replacement Capital 182.00 731.00 182.00 731.00 819.23 5538.75 1879.76 182.00 876.20 145.60 -3371.03 7896.51
3 Less: GST credit on Capital Goods 706.76 2151.99 27.76 111.51 27.76 111.51 110.58 795.19 286.74 27.76 111.51 4469.07
4 Cash Operating Expenses 13356.58 17382.72 23021.60 50774.81 51386.73 51649.52 51913.39 52001.04 52029.43 52059.09 52090.08 52019.04 49802.15 39524.93 29713.95 29749.71 28136.88 27579.17 25553.63 749744.44
5 Total Cash Outflow 13356.58 21858.51 85277.93 88902.78 51386.73 51803.75 52532.89 52001.04 52183.66 52678.58 52090.08 52727.69 54545.72 41117.94 29868.19 30514.40 28282.48 27579.17 22182.60 860890.72
6 Inflow from Sales 27320.47 27320.47 27320.47 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 55473.04 55473.04 47290.77 1051491.56
7 Net Cash Flow 13963.89 5461.96 -57957.46 -26495.60 11020.44 10603.42 9874.29 10406.14 10223.51 9728.60 10317.09 9679.49 7861.46 21289.23 32538.99 31892.77 27190.56 27893.88 25108.17 190600.84
8 Coal Production (Lakh Tonnes) 19.70 19.70 19.70 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 40.00 40.00 34.10 758.20
Appendix - D.1
Option - III (a) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines for Dumping) - Incremental 4.5 Mtpa
Sl.
Particulars Existing Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total
No.
2 Replacement Capital 182.00 731.00 182.00 731.00 819.23 5538.75 1879.76 182.00 876.20 145.60 -3371.03 7896.51
3 Less: GST credit on Capital Goods 706.76 2151.99 27.76 111.51 27.76 111.51 110.58 795.19 286.74 27.76 111.51 4469.07
4 Cash Operating Expenses 11790.61 15118.04 20351.76 44624.51 45231.16 45484.91 45739.76 45825.02 45853.30 45882.84 45913.73 45857.76 43978.03 35247.26 26913.04 26948.80 25580.68 25112.53 23393.68 664847.40
5 Total Cash Outflow 11790.61 19593.84 82608.09 82752.48 45231.16 45639.14 46359.25 45825.02 46007.53 46502.34 45913.73 46566.40 48721.60 36840.27 27067.27 27713.49 25726.28 25112.53 20022.65 775993.68
6 Inflow from Sales 23222.40 23222.40 23222.40 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 47152.09 47152.09 40197.16 893767.83
7 Net Cash Flow 11431.80 3628.57 -59385.69 -29706.38 7814.94 7406.95 6686.85 7221.08 7038.57 6543.76 7132.37 6479.70 4324.50 16205.83 25978.82 25332.61 21425.81 22039.55 20174.51 117774.15
8 Coal Production (Lakh Tonnes) 16.75 16.75 16.75 38.25 38.25 38.25 38.25 38.25 38.25 38.25 38.25 38.25 38.25 38.25 38.25 38.25 34.00 34.00 28.99 644.47
Appendix - A
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Appendix - C
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Option - III (b) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines for Dumping) - 8 Mtpa
Statement Showing Average Cost of Production
Option - III (b) (Integrated - 8 Mtpa)
Total Coal OB Common
Sl. No. Particulars
(`/t) (`/t) (`/m3) (`/t)
1 Salary & Wages 146.49 39.48 1.31 101.32
2 Stores 156.15 84.12 8.90 33.50
3 Power 52.19 7.05 3.93 28.13
4 Misc. Expenses 36.07 5.96 0.03 29.96
5 Adminstrative Cost (Cash) 3.62 3.62
6 Mine closure Cost 18.88 18.88
7 OB Outsourcing Cost 364.33 84.20
8 OB Crushing & Conveying Cost 182.71 42.23
9 COAL Outsourcing Cost
10 Interest on Working capital 46.42 6.60 6.80 10.41
11 Total cash Cost 1006.87 143.22 147.41 225.82
12 Interest
13 Adminstrative Cost (Notional) 30.91 30.91
14 Depreciation 124.52 43.34 81.19
Total 1162.30 186.56 147.41 337.92
15 Common cost apportioned to coal & OB 44.60 67.79
Total 231.16 215.20
16 OB Cost Charged to coal 931.14
Total Cost 1162.30
ADD - ON SLIDES
Appendix - C.1
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Statement Showing Estimated Year wise Operating Cost at 100% capacity utilisation
Option - III (b) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines for Dumping) - 8 Mtpa
Option - III (b) (Integrated - 8 Mtpa) (Amt. in ` Lakhs)
% of
Sl. Avg Cost
Particulars Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total Cost Total
No. (`/t)
Cost
1 Salary & Wages 6872.42 6995.38 9153.36 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 202262.44 146.49 12.60
2 Stores 8103.21 9014.77 9418.21 12558.69 12558.69 12558.69 12558.69 12558.69 12558.69 12558.69 12558.69 12551.57 12392.23 11661.37 10768.50 10768.50 10507.84 10248.07 9685.72 215589.54 156.15 13.43
3 Power 1145.80 2031.25 3257.98 3516.54 3940.24 4363.94 4463.90 4471.90 4479.91 4487.91 4487.91 4487.91 4487.91 4487.91 4487.91 4487.91 4487.91 4487.91 72062.66 52.19 4.49
4 Misc. Expenses 1554.24 1700.09 1942.63 2540.20 2837.93 2837.93 2837.93 2837.93 2837.93 2837.93 2837.93 2837.93 2837.93 2837.93 2837.93 2837.93 2759.18 2680.43 2574.90 49806.81 36.07 3.10
5 Adminstrative Cost (Cash) 198.00 198.00 198.00 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 253.39 217.19 168.68 4997.84 3.62 0.31
6 Mine Closure Cost 853.47 896.14 940.95 987.99 1037.39 1089.26 1143.73 1200.91 1260.96 1324.01 1390.21 1459.72 1532.70 1609.34 1689.81 1774.30 1863.01 1956.16 2053.97 26064.03 18.88 1.62
7 OB Outsourcing 25015.16 36369.56 26944.52 34928.08 34928.08 34928.08 34928.08 34928.08 34928.08 34928.08 34928.08 34839.38 32854.58 23751.10 12629.55 12629.55 9868.57 7384.79 1319.51 503030.93 364.33 31.35
9 Coal Outsourcing
10 Interest on Working capital 2058.83 2722.12 3168.00 3899.59 3928.86 3951.85 3974.96 3982.55 3985.84 3989.28 3992.86 3991.59 3891.48 3419.86 2843.06 2847.14 2699.82 2545.81 2200.71 64094.21 46.42 3.99
1390181.3
11 Total Cash Cost 44655.33 59041.86 68712.90 84580.67 85215.63 85714.19 86215.46 86380.20 86451.54 86526.03 86603.82 86576.23 84404.96 74175.64 61664.89 61753.46 58558.27 55217.75 47732.53 1006.87 86.63
8
12 Interest
Adminstrative Cost
13 1690.68 1690.68 1690.68 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2163.57 1854.49 1440.32 42674.94 30.91 2.66
(Notional)
14 Depreciation 3600.24 3853.96 7505.31 9832.30 9835.44 9835.44 9835.85 9835.85 9849.31 9849.90 9850.50 9851.19 9851.19 9851.19 9851.19 9851.19 9851.19 9851.19 9286.99 171929.41 124.52 10.71
1604785.7
Total 49946.25 64586.50 77908.89 96885.63 97523.72 98022.28 98523.97 98688.70 98773.50 98848.58 98926.97 98900.08 96728.81 86499.49 73988.74 74077.31 70573.03 66923.44 58459.84 1162.30 100.00
4
Cost (`/t) 913.09 1180.74 1424.29 1211.07 1219.05 1225.28 1231.55 1233.61 1234.67 1235.61 1236.59 1236.25 1209.11 1081.24 924.86 925.97 1008.19 1115.39 1254.50 1162.30
Fixed Cost (`/t) 334.77 361.85 493.13 440.47 447.59 452.44 457.32 459.05 460.09 461.00 461.95 462.87 463.83 464.83 465.89 466.99 530.08 614.27 771.02 472.31 40.64
Variable Cost (`/t) 578.32 818.89 931.16 770.60 771.45 772.84 774.23 774.56 774.58 774.61 774.63 773.38 745.28 616.41 458.97 458.97 478.11 501.12 483.48 689.99 59.36
Total Profits (` in Lakhs) 45438.07 22514.80 9192.41 15114.35 10292.57 7624.31 8250.30 8134.98 3437.88 4757.06 7843.90 9476.09 21120.36 34234.20 32099.91 32011.34 22254.53 12643.05 3564.98 310005.09 224.53
ADD - ON SLIDES
Appendix - C.2
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Statement Showing Estimated Year wise operating cost at 85% capacity utilisation
Option - III (b) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines for Dumping) - 8 Mtpa
(Amount in Rs. Lakhs)
Option - III (b) (Integrated - 8 Mtpa)
% of
Sl. Avg Cost
Particulars Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total Cost Total
No. (`/t)
Cost
1 Salary & Wages 6872.42 6995.38 9153.36 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 11202.58 202262.44 172.34 13.84
2 Stores 7423.80 8198.63 8583.21 11476.89 11476.89 11476.89 11476.89 11476.89 11476.89 11476.89 11476.89 11470.83 11335.39 10714.17 9955.23 9955.23 9733.66 9512.85 9034.86 197732.95 168.48 13.53
3 Power 1102.83 1955.08 3135.81 3384.67 3792.48 4200.29 4296.50 4304.20 4311.91 4319.62 4319.62 4319.62 4319.62 4319.62 4319.62 4319.62 4319.62 4319.62 69360.31 59.10 4.74
4 Misc. Expenses 1459.58 1605.43 1844.95 2399.88 2697.60 2697.60 2697.60 2697.60 2697.60 2697.60 2697.60 2697.60 2697.60 2697.60 2697.60 2697.60 2630.66 2563.73 2474.03 47349.49 40.35 3.24
5 Adminstrative Cost (Cash) 198.00 198.00 198.00 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 289.58 253.39 217.19 168.68 4997.84 4.26 0.34
6 Mine Closure Cost 853.47 896.14 940.95 987.99 1037.39 1089.26 1143.73 1200.91 1260.96 1324.01 1390.21 1459.72 1532.70 1609.34 1689.81 1774.30 1863.01 1956.16 2053.97 26064.03 22.21 1.78
7 OB Outsourcing 21262.89 30914.13 22902.84 29688.87 29688.87 29688.87 29688.87 29688.87 29688.87 29688.87 29688.87 29613.47 27926.39 20188.43 10735.12 10735.12 8388.28 6277.08 1121.58 427576.29 364.33 29.25
10 Interest on Working capital 1840.06 2412.34 2815.75 3473.24 3502.05 3524.27 3546.61 3554.02 3557.30 3560.72 3564.29 3563.71 3479.15 3078.83 2589.13 2593.21 2468.37 2337.87 2044.89 57505.81 49.00 3.93
1247281.1
11 Total Cash Cost 39910.21 52322.87 61072.73 75333.42 75958.21 76440.11 76924.73 77085.53 77156.56 77230.73 77308.21 77295.69 75461.59 66778.72 56157.23 56245.81 53538.15 50707.67 44352.98 1062.79 85.32
3
12 Interest
Adminstrative Cost (Notional
13 1690.68 1690.68 1690.68 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2472.66 2163.57 1854.49 1440.32 42674.94 36.36 2.92
)
14 Depreciation 3600.24 3853.96 7505.31 9832.30 9835.44 9835.44 9835.85 9835.85 9849.31 9849.90 9850.50 9851.19 9851.19 9851.19 9851.19 9851.19 9851.19 9851.19 9286.99 171929.41 146.50 11.76
1461885.4
Total 45201.13 57867.51 70268.72 87638.37 88266.30 88748.20 89233.23 89394.04 89478.52 89553.29 89631.36 89619.54 87785.43 79102.57 68481.08 68569.65 65552.91 62413.35 55080.29 1245.65 100.00
9
Cost (`/t) 972.17 1244.60 1511.32 1288.80 1298.03 1305.12 1312.25 1314.62 1315.86 1316.96 1318.11 1317.93 1290.96 1163.27 1007.07 1008.38 1101.73 1223.79 1390.57 1245.65
Fixed Cost (`/t) 393.85 425.71 580.16 518.19 526.58 532.28 538.03 540.06 541.28 542.35 543.47 544.56 545.68 546.86 548.10 549.41 623.62 722.67 907.08 555.66 44.61
Variable Cost (`/t) 578.32 818.89 931.16 770.60 771.45 772.84 774.23 774.56 774.58 774.61 774.63 773.38 745.28 616.41 458.97 458.97 478.11 501.12 483.48 689.99 55.39
100171.8 102623.6 1627572.2
Total Sales (` in Lakhs) 81076.67 74036.10 74036.10 95199.99 91643.85 89799.60 90758.12 90800.13 86879.68 88064.80 90755.24 92119.74 90175.35 90175.35 78903.43 67631.51 52721.10 1386.83
0 3 0
1461885.4
Total Cost (` in Lakhs) 45201.13 57867.51 70268.72 87638.37 88266.30 88748.20 89233.23 89394.04 89478.52 89553.29 89631.36 89619.54 87785.43 79102.57 68481.08 68569.65 65552.91 62413.35 55080.29 1245.65
9
Total Profits (` in Lakhs) 35875.54 16168.59 3767.39 7561.61 3377.54 1051.40 1524.89 1406.09 -2598.84 -1488.49 1123.88 2500.20 12386.36 23521.07 21694.27 21605.70 13350.52 5218.17 -2359.19 165686.71 141.18
ADD - ON SLIDES
Appendix - C.3
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Option - III (b) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines for Dumping) - 8 Mtpa
Sl Capacity Utilisation
Particulars
No. 100% 90% 85% 80% 75%
1 Output (Mtpa) 8.00 7.20 6.80 6.40 6.00
Appendix - C.4
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Option - III (b) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines for Dumping) - 8 Mtpa
Statement showing Sensitivity of IRR
Appendix - D
Option - III (b) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines for Dumping) - 8 Mtpa
Sl.
Particulars Existing Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total
No.
2 Replacement Capital 507.10 6267.15 6344.53 1858.92 384.15 4733.49 361.90 303.12 2457.13 506.24 6162.03 11133.69 5198.35 812.85 3058.39 1763.74 -24256.34 27596.42
3 Less: GST credit on Capital Goods 70.00 1650.69 3121.73 279.26 58.60 721.24 55.20 27.76 373.63 70.00 911.97 1648.65 788.67 122.68 444.39 246.02 10590.49
4 Cash Operating Expenses 44655.33 59041.86 68712.90 84580.67 85215.63 85714.19 86215.46 86380.20 86451.54 86526.03 86603.82 86576.23 84404.96 74175.64 61664.89 61753.46 58558.27 55217.75 47732.53 1390181.38
5 Total Cash Outflow 31326.68 44655.33 63954.75 134724.04 121823.33 86795.29 86039.74 90227.71 86686.89 86726.90 88609.52 87040.05 91826.30 93890.00 78585.32 62355.06 64367.47 60076.00 55217.75 23476.19 1538404.31
106774.2 106823.6 102211.3 103605.6 106770.8 108376.1 117849.1 120733.6 106088.6 106088.6
6 Inflow from Sales 95384.32 87101.30 87101.30 111999.99 107816.29 105646.59 92827.57 79566.49 62024.82 1914790.82
6 8 8 4 7 6 7 9 5 5
-
7 Net Cash Flow 50728.99 23146.55 -47622.74 -9823.34 21021.00 19606.86 16546.56 20136.79 15484.49 14996.12 19730.82 16549.86 23959.18 42148.36 43733.59 41721.18 32751.57 24348.73 38548.63 376386.51
31326.68
8 Coal Production (Lakh Tonnes) 54.70 54.70 54.70 80.00 80.00 80.00 80.00 80.00 80.00 80.00 80.00 80.00 80.00 80.00 80.00 80.00 70.00 60.00 46.60 1380.70
Appendix - D.1
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Option - III (b) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines for Dumping) - 8 Mtpa
Sl.
Particulars Existing Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total
No.
2 Replacement Capital 507.10 6267.15 6344.53 1858.92 384.15 4733.49 361.90 303.12 2457.13 506.24 6162.03 11133.69 5198.35 812.85 3058.39 1763.74 -24256.34 27596.42
3 Less: GST credit on Capital Goods 70.00 1650.69 3121.73 279.26 58.60 721.24 55.20 27.76 373.63 70.00 911.97 1648.65 788.67 122.68 444.39 246.02 10590.49
4 Cash Operating Expenses 39910.21 52322.87 61072.73 75333.42 75958.21 76440.11 76924.73 77085.53 77156.56 77230.73 77308.21 77295.69 75461.59 66778.72 56157.23 56245.81 53538.15 50707.67 44352.98 1247281.13
5 Total Cash Outflow 31326.68 39910.21 57235.76 127083.87 112576.07 77537.87 76765.66 80936.97 77392.23 77431.92 79314.23 77744.44 82545.76 84946.62 71188.40 56847.40 58859.81 55055.87 50707.67 20096.64 1395504.06
100171.8 102623.6
6 Inflow from Sales 81076.67 74036.10 74036.10 95199.99 91643.85 89799.60 90758.12 90800.13 86879.68 88064.80 90755.24 92119.74 90175.35 90175.35 78903.43 67631.51 52721.10 1627572.20
0 3
-
7 Net Cash Flow 41166.46 16800.34 -53047.76 -17376.08 14105.98 13033.95 9821.15 13407.90 9447.76 8750.57 13010.80 9573.98 15225.17 31435.23 33327.95 31315.54 23847.56 16923.85 32624.46 232068.13
31326.68
8 Coal Production (Lakh Tonnes) 46.50 46.50 46.50 68.00 68.00 68.00 68.00 68.00 68.00 68.00 68.00 68.00 68.00 68.00 68.00 68.00 59.50 51.00 39.61 1173.60
Appendix - A
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Appendix - C
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Option - III (b) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines for Dumping) - Incremental 4.5 Mtpa
Appendix - C.1
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Statement Showing Estimated Year wise Operating Cost at 100% capacity utilisation
Option - III (b) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines for Dumping) - Incremental 4.5 Mtpa
Option - III (b) (Incremental - 4.5 Mtpa) (Amt. in ` Lakhs)
% of
Sl. Avg Cost
Particulars Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total Cost Total
No. (`/t)
Cost
1 Salary & Wages 2214.27 1478.46 3615.04 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 97874.91 129.09 10.24
2 Stores 799.68 1128.16 1531.60 5570.29 5570.29 5570.29 5570.29 5570.29 5570.29 5570.29 5570.29 5563.17 5403.83 4672.97 3975.06 3975.06 3844.28 3806.89 3649.46 82912.53 109.35 8.68
3 Power 930.44 1519.90 2353.22 2492.30 2730.38 2968.45 3031.17 3034.11 3037.05 3040.00 3040.00 3040.00 3040.00 3040.00 3040.00 3040.00 3040.00 3040.00 49456.98 65.23 5.17
4 Misc. Expenses 307.27 353.50 518.24 1057.27 1354.99 1354.99 1354.99 1354.99 1354.99 1354.99 1354.99 1354.99 1354.99 1354.99 1354.99 1354.99 1315.62 1315.62 1269.16 22396.59 29.54 2.34
5 Adminstrative Cost (Cash) 71.31 71.31 71.31 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 144.79 144.79 123.43 2744.52 3.62 0.29
6 Mine Closure Cost 344.56 361.79 379.88 398.88 418.82 439.76 461.75 484.84 509.08 534.53 561.26 589.32 618.79 649.73 682.21 716.32 752.14 789.75 829.23 10522.62 13.88 1.10
7 OB Outsourcing 9003.68 13095.26 3670.22 22841.86 22841.86 22841.86 22841.86 22841.86 22841.86 22841.86 22841.86 22753.15 20768.35 11664.87 2971.66 2971.66 1585.62 1386.04 272605.38 359.54 28.52
9 Coal Outsourcing
10 Interest on Working capital 615.80 841.91 1267.40 2559.77 2581.85 2594.37 2606.94 2611.09 2612.40 2613.77 2615.21 2611.93 2509.72 2035.89 1583.56 1585.20 1510.85 1480.85 1382.83 38221.34 50.41 4.00
11 Total Cash Cost 13356.58 18260.84 27489.56 55520.59 55999.42 56270.96 56543.59 56633.54 56662.04 56691.81 56722.91 56651.87 54434.98 44157.76 34346.78 34382.54 32769.71 32119.19 29993.11 829007.77 1093.39 86.74
12 Interest
13 Adminstrative Cost (Notional) 608.89 608.89 608.89 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1236.33 1236.33 1053.97 23434.59 30.91 2.45
14 Depreciation 248.66 3891.09 6217.67 6217.67 6217.67 6217.67 6217.67 6217.67 6217.67 6217.67 6217.67 6217.67 6217.67 6217.67 6217.67 6217.67 6166.26 5959.76 103313.10 136.26 10.81
Total 13965.47 19118.39 31989.54 63129.13 63607.95 63879.49 64152.13 64242.08 64270.57 64300.34 64331.44 64260.40 62043.51 51766.29 41955.32 41991.08 40223.70 39521.78 37006.84 955755.46 1260.56 100.00
Cost (`/t) 708.91 970.48 1623.83 1402.87 1413.51 1419.54 1425.60 1427.60 1428.23 1428.90 1429.59 1428.01 1378.74 1150.36 932.34 933.14 1005.59 988.04 1085.24 1260.56
Fixed Cost (`/t) 178.97 192.94 538.50 410.37 420.20 424.85 429.52 431.16 431.77 432.42 433.09 433.75 434.43 435.15 435.91 436.70 487.89 487.59 561.11 432.09 34.28
Variable Cost (`/t) 529.94 777.53 1085.33 992.50 993.31 994.69 996.08 996.44 996.46 996.48 996.50 994.26 944.31 715.21 496.43 496.43 517.70 500.45 524.13 828.47 65.72
1051491.5
Total Sales (` in Lakhs) 27320.47 27320.47 27320.47 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 55473.04 55473.04 47290.77 1386.83
6
Total Cost (` in Lakhs) 13965.47 19118.39 31989.54 63129.13 63607.95 63879.49 64152.13 64242.08 64270.57 64300.34 64331.44 64260.40 62043.51 51766.29 41955.32 41991.08 40223.70 39521.78 37006.84 955755.46 1260.56
Total Profits (` in Lakhs) 13355.00 8202.09 -4669.07 -721.95 -1200.78 -1472.32 -1744.95 -1834.90 -1863.40 -1893.17 -1924.27 -1853.23 363.66 10640.88 20451.86 20416.10 15249.34 15951.27 10283.93 95736.10 126.27
ADD - ON SLIDES
Appendix - C.2
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Statement Showing Estimated Year wise operating cost at 85% capacity utilisation
Option - III (b) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines for Dumping) - Incremental 4.5 Mtpa
(Amount in Rs. Lakhs)
Option - III (b) (Incremental - 4.5 Mtpa)
Sl. Avg Cost
Particulars Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total Cost
No. (`/t)
1 Salary & Wages 2214.27 1478.46 3615.04 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 5660.45 97874.91 151.87
2 Stores 679.73 958.94 1343.52 5000.68 5000.68 5000.68 5000.68 5000.68 5000.68 5000.68 5000.68 4994.62 4859.18 4237.96 3644.73 3644.73 3533.57 3501.79 3367.97 74772.15 116.02
3 Power 895.55 1462.90 2264.97 2398.84 2627.99 2857.14 2917.50 2920.33 2923.16 2926.00 2926.00 2926.00 2926.00 2926.00 2926.00 2926.00 2926.00 2926.00 47602.34 73.86
4 Misc. Expenses 284.00 330.23 491.95 988.33 1286.06 1286.06 1286.06 1286.06 1286.06 1286.06 1286.06 1286.06 1286.06 1286.06 1286.06 1286.06 1252.59 1252.59 1213.10 21245.47 32.97
5 Adminstrative Cost (Cash) 71.31 71.31 71.31 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 162.89 144.79 144.79 123.43 2744.52 4.26
6 Mine Closure Cost 344.56 361.79 379.88 398.88 418.82 439.76 461.75 484.84 509.08 534.53 561.26 589.32 618.79 649.73 682.21 716.32 752.14 789.75 829.23 10522.62 16.33
7 OB Outsourcing 7653.13 11130.97 3119.69 19415.58 19415.58 19415.58 19415.58 19415.58 19415.58 19415.58 19415.58 19340.18 17653.10 9915.14 2525.91 2525.91 1347.78 1178.13 231714.57 359.54
9 Coal Outsourcing
10 Interest on Working capital 543.61 735.98 1119.54 2250.90 2272.72 2284.81 2296.95 2300.98 2302.29 2303.66 2305.09 2302.51 2215.84 1813.31 1429.06 1430.71 1367.63 1342.41 1259.23 33877.25 52.57
11 Total Cash Cost 11790.61 15963.23 24282.41 48821.25 49294.60 49556.78 49820.06 49907.54 49935.93 49965.58 49996.56 49940.59 48060.87 39330.10 30995.88 31031.63 29663.52 29116.49 27312.17 734785.80 1140.14
12 Interest
13 Adminstrative Cost (Notional ) 608.89 608.89 608.89 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1390.87 1236.33 1236.33 1053.97 23434.59 36.36
14 Depreciation 248.66 3891.09 6217.67 6217.67 6217.67 6217.67 6217.67 6217.67 6217.67 6217.67 6217.67 6217.67 6217.67 6217.67 6217.67 6217.67 6166.26 5959.76 103313.10 160.31
Total 12399.50 16820.78 28782.39 56429.78 56903.14 57165.32 57428.60 57516.08 57544.46 57574.11 57605.10 57549.13 55669.41 46938.63 38604.41 38640.17 37117.51 36519.07 34325.90 861533.49 1336.81
Cost (`/t) 740.49 1004.53 1718.86 1475.29 1487.66 1494.52 1501.40 1503.69 1504.43 1505.21 1506.02 1504.55 1455.41 1227.15 1009.27 1010.20 1091.69 1074.09 1184.26 1336.81
Fixed Cost (`/t) 210.55 226.99 633.53 482.79 494.36 499.83 505.32 507.24 507.97 508.73 509.52 510.29 511.10 511.94 512.84 513.77 573.99 573.64 660.13 508.34
Variable Cost (`/t) 529.94 777.53 1085.33 992.50 993.31 994.69 996.08 996.44 996.46 996.48 996.50 994.26 944.31 715.21 496.43 496.43 517.70 500.45 524.13 828.47
Total Sales (` in Lakhs) 23222.40 23222.40 23222.40 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 47152.09 47152.09 40197.16 893767.83 1386.83
Total Cost (` in Lakhs) 12399.50 16820.78 28782.39 56429.78 56903.14 57165.32 57428.60 57516.08 57544.46 57574.11 57605.10 57549.13 55669.41 46938.63 38604.41 38640.17 37117.51 36519.07 34325.90 861533.49 1336.81
Total Profits (` in Lakhs) 10822.90 6401.62 -5559.98 -3383.68 -3857.04 -4119.22 -4382.50 -4469.98 -4498.36 -4528.02 -4559.00 -4503.03 -2623.31 6107.47 14441.69 14405.93 10034.58 10633.01 5871.25 32234.34 50.02
ADD - ON SLIDES
Appendix - C.3
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Option - III (b) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines for Dumping) -
Incremental 4.5 Mtpa
Statement Showing Economics at Different Capacity Utilisation
Appendix - C.4
RECAST EPR OF BLOCK-B OPENCAST PROJECT (8 Mtpa)
Option - III (b) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines for Dumping) - Incremental 4.5 Mtpa
Statement showing Sensitivity of IRR
Appendix - D
Option - III (b) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines for Dumping) - Incremental 4.5 Mtpa
Sl.
Particulars Existing Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total
No.
2 Replacement Capital 182.00 731.00 182.00 731.00 819.23 5538.75 1879.76 182.00 876.20 145.60 -3372.78 7894.76
3 Less: GST credit on Capital Goods 706.93 2154.73 27.76 111.51 27.76 111.51 110.58 795.19 286.74 27.76 111.51 4471.98
4 Cash Operating Expenses 13356.58 18260.84 27489.56 55520.59 55999.42 56270.96 56543.59 56633.54 56662.04 56691.81 56722.91 56651.87 54434.98 44157.76 34346.78 34382.54 32769.71 32119.19 29993.11 829007.77
5 Total Cash Outflow 13356.58 22736.63 88177.32 87385.70 55999.42 56425.19 57163.08 56633.54 56816.28 57311.30 56722.91 57360.52 59178.54 45750.77 34501.02 35147.23 32915.31 32119.19 26620.34 932320.87
6 Inflow from Sales 27320.47 27320.47 27320.47 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 62407.18 55473.04 55473.04 47290.77 1051491.56
7 Net Cash Flow 13963.89 4583.84 -60856.84 -24978.53 6407.76 5981.98 5244.09 5773.63 5590.90 5095.88 5684.27 5046.66 3228.63 16656.41 27906.16 27259.94 22557.74 23353.85 20670.43 119170.69
8 Coal Production (Lakh Tonnes) 19.70 19.70 19.70 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 40.00 40.00 34.10 758.20
Appendix - D.1
Option - III (b) (Total Coal Departmental & Total OB Outsourced - Considering Old Gorbi Mines for Dumping) - Incremental 4.5 Mtpa
Sl.
Particulars Existing Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total
No.
2 Replacement Capital 182.00 731.00 182.00 731.00 819.23 5538.75 1879.76 182.00 876.20 145.60 -3372.78 7894.76
3 Less: GST credit on Capital Goods 706.93 2154.73 27.76 111.51 27.76 111.51 110.58 795.19 286.74 27.76 111.51 4471.98
4 Cash Operating Expenses 11790.61 15963.23 24282.41 48821.25 49294.60 49556.78 49820.06 49907.54 49935.93 49965.58 49996.56 49940.59 48060.87 39330.10 30995.88 31031.63 29663.52 29116.49 27312.17 734785.80
5 Total Cash Outflow 11790.61 20439.03 84970.16 80686.36 49294.60 49711.02 50439.55 49907.54 50090.16 50585.07 49996.56 50649.24 52804.44 40923.11 31150.11 31796.33 29809.12 29116.49 23939.40 838098.90
6 Inflow from Sales 23222.40 23222.40 23222.40 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 53046.10 47152.09 47152.09 40197.16 893767.83
7 Net Cash Flow 11431.80 2783.38 -61747.76 -27640.26 3751.50 3335.08 2606.55 3138.56 2955.94 2461.03 3049.53 2396.86 241.66 12122.99 21895.99 21249.77 17342.97 18035.60 16257.76 55668.93
8 Coal Production (Lakh Tonnes) 16.75 16.75 16.75 38.25 38.25 38.25 38.25 38.25 38.25 38.25 38.25 38.25 38.25 38.25 38.25 38.25 34.00 34.00 28.99 644.47
A. OBR
1 Electric Rope Shovel 20m3 8 6 6 8 8 8 8 8 8 8 8 8 8 8 8 8 7 6 5 8
OUTSOURCING
OUTSOURCING
OUTSOURCING
OUTSOURCING
2 Diesel Hyd. Backhoe 10-12m3 2 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1 2
3 Rear Dumper 190-210T 64 48 48 64 64 64 64 64 64 64 64 64 64 64 64 64 56 48 40 64
4 Rear Dumper 100T 20 14 16 20 20 20 20 20 20 20 20 20 20 20 20 20 20 10 10 20
5 RBH Drill (Electric) 250mm 10 7 7 10 10 10 10 10 10 10 10 10 10 10 10 10 9 7 6 10
6 Dozer 850 HP 8 6 6 8 8 8 8 8 8 8 8 8 8 8 8 8 7 6 5 8
7 Dozer 410 HP 2 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1 2
B. Coal Winning
1 Diesel Hyd. Shovel 10-12m3 1 - 1* 1 1 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1 2
2 Diesel Hyd. Backhoe 10-12m 3
1 1 1 - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
3 Rear Dumper 85T - 1 - 1
4 Rear Dumper 100T 10 14 15 5 14 15 15 20 20 20 20 20 20 20 20 20 20 20 20 20 20 16 16 20
5 RBH Drill (Diesel) 160mm 3 4 5 1 5 5 5 6 6 6 6 6 6 6 6 6 6 6 6 6 6 5 4 6
6 Dozer 410 HP 2 2 2 1 2 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 2 2 3
C. Common
1 FE Loader* 5.74/6.4m3 1 1 1 - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
2 FE Loader* 10-12m3 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
3 Motor Grader 280 HP 2 2 2 2 2 2 3 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
4 Hyd. Backhoe 2.8/3.5 m3 2 1 2## - 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
5 Mobile Crane 30-50T 2 2 2 - 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
6 Mobile Crane 8-10T 2 2 2 3 2 2 4 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
7 Wheel Dozer/Dozer 410 HP 1 1 1 - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
D Reclamation
1 Dozer 410 HP 2 4 4 1 4 4 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
2 Motor Grader 280 HP 1 2 - 1 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
3 Water Sprinkler 28 KL 3 3 4** - 4 4 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
2(1+
4 Water Sprinkler 70KL - - - 2 - 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
1**)
Road Sweeping
5
Machine
- - 1 - - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
6 Mist SprayGun - - - 2 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
* 1 No. 10-12m3 Hyd. Shovel transferred to other project in Completion Report.
## 1 No. 2.8 m3 Hyd. Shovel transferred to other project in Completion Report.
ADD - ON SLIDES
Option-II
As per As per
Existing as on Balance
HEMM SIZE/ CAP. sanctioned completion
31.03.2018 Provision
3.5 Mtpa report Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total
A. OBR
OUTSOURCING
OUTSOURCING
OUTSOURCING
OUTSOURCING
3 Rear Dumper 190-210T
6 Dozer 850 HP
7 Dozer 410 HP
B. Coal Winning
1 Diesel Hyd. Shovel 10-12m 3
1 - 1* 1 1 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1 2
2 Diesel Hyd. Backhoe 10-12m3 1 1 1 - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
3 Rear Dumper 85T - 1 - 1
4 Rear Dumper 100T 10 14 15 5 14 15 15 20 20 20 20 20 20 20 20 20 20 20 20 20 20 16 16 20
5 RBH Drill (Diesel) 160mm 3 4 5 1 5 5 5 6 6 6 6 6 6 6 6 6 6 6 6 6 6 5 4 6
6 Dozer 410 HP 2 2 2 1 2 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 2 2 3
C. Common
1 FE Loader* 5.74/6.4m3 1 1 1 - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
2 FE Loader* 10-12m 3
- - - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
3 Motor Grader 280 HP 2 2 2 2 2 2 3 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
4 Hyd. Backhoe 2.8/3.5 m 3
2 1 2##
- 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
5 Mobile Crane 30-50T 2 2 2 - 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
6 Mobile Crane 8-10T 2 2 2 3 2 2 4 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
7 Wheel Dozer/Dozer 410 HP 1 1 1 - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
D Reclamation
1 Dozer 410 HP 2 4 4 1 4 4 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
2 Motor Grader 280 HP 1 2 - 1 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
3 Water Sprinkler 28 KL 3 3 4** - 4 4 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
2(1+1
4 Water Sprinkler 70KL - - - 2 - 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
**)
5 Road Sweeping Machine - - 1 - - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
6 Mist SprayGun - - - 2 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
* 1 No. 10-12m3 Hyd. Shovel transferred to other project in Completion Report.
** 2 No. 28 KL Water Sprinkler to be upgraded to 1 No. 70 KL Water Sprinkler.
ADD - ON SLIDES
Option III(a) & III(b)
As per As per
Existing as on Balance
HEMM SIZE/ CAP. sanctioned completion
31.03.2018 Provision
3.5 Mtpa report Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Total
A. OBR
OUTSOURCING
OUTSOURCING
OUTSOURCING
OUTSOURCING
3 Rear Dumper 190-210T
6 Dozer 850 HP
7 Dozer 410 HP
B. Coal Winning
1 Diesel Hyd. Shovel 10-12m 3
1 - 1* 1 1 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1 2
2 Diesel Hyd. Backhoe 10-12m3 1 1 1 - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
3 Rear Dumper 85T - 1 - 1
4 Rear Dumper 100T 10 14 15 5 14 15 15 20 20 20 20 20 20 20 20 20 20 20 20 20 20 16 16 20
5 RBH Drill (Diesel) 160mm 3 4 5 1 5 5 5 6 6 6 6 6 6 6 6 6 6 6 6 6 6 5 4 6
6 Dozer 410 HP 2 2 2 1 2 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 2 2 3
C. Common
1 FE Loader* 5.74/6.4m3 1 1 1 - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
2 FE Loader* 10-12m3 - - - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
3 Motor Grader 280 HP 2 2 2 2 2 2 3 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
4 Hyd. Backhoe 2.8/3.5 m3 2 1 2## - 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
5 Mobile Crane 30-50T 2 2 2 - 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
6 Mobile Crane 8-10T 2 2 2 3 2 2 4 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
7 Wheel Dozer/Dozer 410 HP 1 1 1 - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
D Reclamation
1 Dozer 410 HP 2 4 4 1 4 4 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
2 Motor Grader 280 HP 1 2 - 1 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
3 Water Sprinkler 28 KL 3 3 4** - 4 4 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
2(1+
4 Water Sprinkler 70KL - - - 2 - 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
1**)
5 Road Sweeping Machine - - 1 - - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
6 Mist SprayGun - - - 2 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
* 1 No. 10-12m3 Hyd. Shovel transferred to other project in Completion Report.
ADD - ON SLIDES
Appendix-F
Appendix-F
Appendix-F
Appendix-A.1
Recast EPR for Block-B Opencast Project (8 Mtpa)
Statement of Estimated Capital Investment on Land
Base Date: October, 2018
Option-II (Coal Departmental & OB Outsourcing) (Amt. in ` Lakhs)
Sanctioned Report Total Provision Existing as on Balance Provision Phasing of Balance
(3.5 Mtpa) (8 Mtpa) 31.3.18 (3.5 Mtpa) ( 4.5 Mtpa) Provision
Sl.
Particulars Rate
No. Qty. Existing Qty.
Qty.(Ha) Amt. Qty.(Ha) Amt. Amt. (`Lakh Amt. Yr-1 Yr-2 Yr-3 Yr-4
(Ha) Amt. (Ha)
/Ha)
PHASE -I
Leased Leased
Leased
land, land
land, Leased
amount Amount
amount land on
1 Forest Land 447 1070.25 447 shown 623.25 shown
shown Mine Dev.
in Mine on Mine
in Mine Fund
Dev. Dev.
Dev. Fund
Fund Fund
Non -Forest
2 Land (Total) 892 858.0 1186.92 858.0 1065.81 858 121.11
a) Govt. Land 429 51.78
b) Tenancy
Land 463 19767.0 69.33 285.11 19766.95
Total 1339.00 858.0 2257.17 25522 1512.81 5755 858 744.36 19766.95 988.35 18778.60
ADD - ON SLIDES
Appendix-A.8.1
Recast EPR of Block-B Opencast Project (8 Mtpa)
Statement showing the Capital Expenditure on Capital Outlay
(SUMMARY)
Base Date: October, 2018
Option-II (Coal Departmental & OB Outsourcing) (Amt. in ` '00000)
Total Provision (8 Yearwise Phasing of Balance
Sl. Existing as on 31.3.18 (3.5 Mtpa) Balance Provision (4.5 Mtpa)
Mtpa) Provision
Item Description Unit
Committed Existing Rate in Rs.
No. Qty. Amt. Qty. Qty. Amt. Yr-1 Yr-2 Yr-3 Yr-4
Amt. Amt. Lakh
1 Earth work in filling and banking
a)Colony/ Aproach Road 282.75 282.75
b) Workshop 259.81 259.81
Total (a+b) including 18% GST 640.22 640.22 128.0 512.18
2 Open Lungs 16.04 16.04 3.2 12.83
3 a) Development of land for residential 131.28 131.28 26.3 105.02
and other buildings
b) Renovation of existing buildings 209.51 209.51 41.9 167.61
in the colony
4 Community Development 196.15 196.15 9.8 186.34
5 Arboriculture 122.29 122.29 6.1 116.18
Rehabilitation work and house compensation of PAP 15192.0
6 nos. 207 15991.58 207 15991.58 799.6
( 207 Nos.) 0
7 One time cash grant compensation against R&R 0.00
2140.5 1246.5 11841.7
8 Compensatory Afforestation (Balance Land 2x623.25 Ha) Ha 12465.00 894.00 10.000 12465.00 623.3
0 0 5
1070.2
9 Net Present Value of Forest Land ha 5733.90 447 623.25 9.2 5733.90 286.7 5447.21
5
10 Retaining wall/ Garland drain 160.85 160.85 32.2 128.68
11 Diversion of Nalla/ rain water etc. 210.34 210.34 42.1 168.27
12 Chain linked fencing around colony and quarry 278.06 278.06 55.6 222.45
13 Water Recharge & Harvesting Arrangement 250.00 250.00 50.0 200.00
14 Green belt Development of mine 60.00 60.00 12.0 48.00
Diversion of rail line or Provision of OB haul road bridge
15 1000.00 LS 1000.00 200.0 800.00
over rail line
16 Development - Others/spent 0.00
17 Tree feeling cost for Block-B 623.25 600.3212 374.15 74.8 299.32
The Financial analysis summary based on actual average sales price of last three years
has been done and findings are given below
COMPARISON
RS. CRS
Particulars diff.
Land Cost recast EPR Nov-18 Land Cost UCE May-17
Tenancy Land 197.67 319 -121.33
NPV 124.65 9.3238 115.3262
CA 57.339 24.6406 32.6984
Total 379.66 352.96 26.6946
Purewa 20.97
Merged 28.51 57.70 78.67
656.39
290.14 177.13 479.26
Turra 59.16 33.29 36.81 70.10
Total 87.67 290.14 54.26 177.13 94.51 479.26 148.77 656.39
Stripping
3.31 3.26 5.07 4.41
Ratio
LAND REQUIREMENT PLAN
PDF Plan
Option –III (b)
(Crushing and conveying of part OB to Old Gorbi Mine with spreader system)
Tentative estimation for Crushing and conveying of part OB to Old Gorbi Mine with
following considerations:
• Semi mobile crushing plant with double roll sizers; each capacity 3000 Tph ,
ROM OB from -1500 mm to -250/-300 mm size.
• 2 nos. rock breaker for breaking the above ROM -1500 mm OB
• Spreader with tipper car 6000 Tph.
• Transport Crawler, 400t.
• Associated conveyors.
Operating Cost
Sl. No. Particulars Amt (` Lakhs) Sl. No. Particulars Amt.(Rs. Lakhs)
1 Depreciation on P&M 2838.61
2 Depreciation on Belting 376.56
1 Conveyor 5566
3 Salary Wages 102.26
2 Equipment 18746
4 Power 4144.73
3 Electrical Equipment 4155
4 Civil Structure 9640 5 Stores 1144.164
5 Errection & commissioning 3186 6 Misc. Exp. 288.73
6 Design & Engg. 1752 7 Interest on working capital 274.53
7 Over head construction cost 5519 Total Cost 9169.58
8 Insurance 335
9 Contigency 1559
10 Misc. Electrical &Mechanical items 637 OB Quantity per year : 8.5 Mm3
11 Belting (steel) 3389
Total Capital 54484
Operating Cost : 107.88 Rs./Bm3
OB Crushing & Conveying System
PDF
POWER SUPPLY ARRANGEMENT
Proposed Sub-station
40 Madhauli S/S 16784 96.14
Option-I
Proposed Sub-station
Option-II & III (a) 30 Madhauli S/S 8841 40.26
Option-I (Integrated)
At 85% Capacity
At 100% At 85%
Sl. No. Particulars Capacity Capacity
Salary & Wages
10%
1 Salary & Wages 238.47 280.55 Adminstrative
Cost (Notional)
1% Depreciation
2 Stores 625.73 687.79 12%
Option-I (Incremental)
Sl. At 100% At 85% At 85% Capacity
Particulars Capacity Capacity
No.
1 Salary & Wages 296.32 348.62
2 Stores 964.48 1061.69
Salary & Wages
3 Power 118.45 134.12 Adminstrative Depreciation 15%
Cost (No- 22%
4 Misc. Expenses 121.22 132.10
tional)
2%
Interest on
5 Adminstrative Cost (Cash) 3.62 4.26
Working capi-
tal
4%
6 Mine Closure Cost 13.88 16.33 OB Outsourc-
ing
1%
7 OB Outsourcing 11.88 11.88 Mine Closure
Cost
1%
8 COAL Outsourcing 0.00 0.00 Adminstrative
Cost (Cash) Power Stores
9 Interest on Working capital 73.94 82.60 0% 6% 45%
Misc.
10 Total Cash Cost 1603.78 1791.59
Ex-
penses
6%
11 Interest 0.00 0.00
12 Adminstrative Cost
(Notional) 30.91 36.36
Appendix C Appendix D
13 Depreciation 442.62 520.73
Appendix C1
Appendix D1
Total 2077.31 2348.68 Appendix C2
CAPITAL INVESTMENT OPTION- I (INTEGRATED 8 MTPA)
Option -I
Integrated (8 Mtpa)
SL. NO. PARTICULARS Total Provn.
%age of Total
(8 Mtpa) Capital
(Rs. Lakhs) Land Reclamation Buil
Rail ding
1 Land 25522 6.24 way 0.60%
s
Sid- 5.28
Buildings ing Land %
2 a) Service 10069 2.46 2.08 6.24%
%
b) Residential 11534 2.82 Development.
Sub Total 21603 5.28 13.21%
Plant & Machinery
Oth
a) H. E. M. M. 252808 61.79 ers
3 b) CHP 33584 8.21 0.31
%
c) Pumping 781 0.19
d) Electrical 4909 1.20
e) Workshop 3535 0.86
f) Other P&M 127 0.03
Sub Total 295745 72.28
Furniture & Fittings 293 0.07
4 Railway Siding 8516 2.08
5 Vehicles 939 0.23
6 Prospecting & Boring 44 0.01
7 Development.
8 Capital Outlay in Mines 40695 9.95
8.1 Roads & Culverts 4523 1
Water Supply &
8.2 6972 1.70
Sewerage Plant & Machinery
72.28%
8.3 Scientific Research 80 0.02
8.4 P.R. Prep. Cost 1762 0.43
8.5 Sub Total 54032 13.21
Revenue Exp. Appendix A: Option-I (Integrated)
Capitalised less
9.1
Depreciation
10 Land Reclamation 2456 0.60
INITIAL CAPITAL 409148 100.00
CAPITAL INVESTMENT OPTION- I (INCREMENTAL 4.5 MTPA)
Option -I
Incremental (4.5 Mtpa) Land Reclamation
SL. NO. PARTICULARS Total Provn. 0.32% Build-
%age of Total ings
(8 Mtpa) Capital
(Rs. Lakhs) Land 5.52%
5.58%
1 Land 19767 5.58
Buildings Development.
14.00%
2 a) Service 9773 2.76
b) Residential 9779 2.76
Sub Total 19551 5.52
Plant & Machinery
3 a) H. E. M. M. 244748 69.12
b) CHP 10182 2.88
c) Pumping 621 0.18
d) Electrical 4407 1.24
e) Workshop 3291 0.93
f) Other P&M 62 0.02
Sub Total 263311 74.36
Furniture & Fittings 74 0.02
4 Railway Siding 0 0.00
5 Vehicles 711 0.20
Others
6 Prospecting & Boring 0 0.00 0.22%
7 Development.
8 Capital Outlay in Mines 37839 10.69
8.1 Roads & Culverts 3956 1.12
Water Supply & Plant & Machinery
8.2 5942 1.68 74.36%
Sewerage
8.3 Scientific Research 80 0.02
8.4 P.R. Prep. Cost 1762 0.50
8.5 Sub Total 49579 14.00 Appendix A: Option-I (Incremental)
Revenue Exp.
Capitalised less
9.1
Depreciation
10 Land Reclamation 1123 0.32
INITIAL CAPITAL 354116 100.00
CAPITAL INVESTMENT OPTION- II (INTEGRATED 8 MTPA)
Option -II
Integrated (8 Mtpa)
SL. Land Reclamation
NO. PARTICULARS Total Provn. 1.59%
%age of Total
(8 Mtpa)
Capital
(Rs. Lakhs)
1 Land 25522 16.48
Land
2 Buildings 16.48%
a) Service 5846 3.77
b) Residential 5158 3.33
Sub Total 11004 7.10
3 Plant & Machinery
Development. Buildings
a) H. E. M. M. 13826 8.93 34.13% 7.10%
b) CHP 33584 21.68
c) Pumping 781 0.50
d) Electrical 2996 1.93
e) Workshop 1966 1.27
f) Other P&M 127 0.08
Sub Total 53280 34.40
4 Furniture & Fittings 277 0.18
5.50 Plant & Machinery
5 Railway Siding 8516 34.40%
6 Vehicles 939 0.61
7 Prospecting & Boring 44 0.03 Railway Sid-
8 Development. ing
5.50%
8.1 Capital Outlay in Mines 40695 26.27 Others
2.40 0.81%
8.2 Roads & Culverts 3712
8.3 Water Supply & Sewerage 6617 4.27
8.4 Scientific Research 80 0.05
8.5 P.R. Prep. Cost 1762 1.14
Sub Total 52867 34.13
Appendix A: Option-II (Integrated)
Revenue Exp. Capitalised less
9.1
Depreciation
10 Land Reclamation 2456 1.59
INITIAL CAPITAL 154903 100.00
CAPITAL INVESTMENT OPTION- II (INCREMENTAL 4.5 MTPA)
Option -II
Incremental (4.5 Mtpa)
SL. Land Reclamation
PARTICULARS Total Provn. 1.12%
NO. %age of Total
(8 Mtpa) Capital
(Rs. Lakhs)
1 Land 19767 19.79
2 Buildings Land
5.56 19.79%
a) Service 5550
b) Residential 3402 3.41
Sub Total 8953 8.96
3 Plant & Machinery
a) H. E. M. M. 5766 5.77
b) CHP 10182 10.20
c) Pumping 621 0.62 Buildings
Development. 8.96%
d) Electrical 2493 2.50 48.48%
e) Workshop 1722 1.72
f) Other P&M 62 0.06
Sub Total 20846 20.87
4 Furniture & Fittings 58 0.06
5 Railway Siding 0 0.00 Plant & Machinery
20.87%
6 Vehicles 711 0.71
7 Prospecting & Boring 0 0.00
8 Development.
8.1 Capital Outlay in Mines 37839 37.89
8.2 Roads & Culverts 3146 3.15 Others
8.3 Water Supply & Sewerage 5586 5.59 0.77%
1 Main Pump , 1100 m3/hr (305 lps), 250-300m head, 1500kw 2 Nos
2 Main Pump , 650 m3/hr (180 lps), 200-250m head, 450kw 4 Nos
3 Face pump 40m3/hr (11 lps), 30m head, 10 kW 2 N0s
4 Slurry pump 101m3/hr (28 lps), 28m head, 37kW 2 Nos
Diesel pump 289m3/hr (80 lps), 150m head complete with diesel
5 2 No.
engine and other accessories.
6 ERW Pipes LS
7 Pipe fittings, bends, armoured suction, delivery hoses etc. LS
8 Phantoons, moving trolleys etc. 2
COST OF PRODUCTION (`\t) Option – II (Integrated)
Option-II (Integrated)
At 85% Capacity
Sl. At 100% At 85%
Particulars Capacity Capacity
No.
1 Salary & Wages 146.49 172.34 Depreciation Salary & Wages
13% 15%
2 Stores 156.14 168.48 Adminstrative Cost
(Notional)
3%
3 Power 34.83 39.43 Interest on Working
capital
4%
4 Misc. Expenses 36.07 40.34
Stores
5 Adminstrative Cost (Cash) 3.62 4.26 15%
12 Adminstrative Cost
Appendix C
30.91 36.36
(Notional) Appendix C1
Appendix C2
13 Depreciation 136.24 160.28 Appendix D
Total 1097.45 1169.11 Appendix D1
COST OF PRODUCTION (`\t) Option – III(a) (Integrated)
capital
10 Total Cash Cost 988.85 1031.62
11 Interest 0.00 0.00 Appendix C
12 Adminstrative Cost
Appendix C1
30.91 36.36 Appendix C2
(Notional) Appendix D
13 Depreciation 146.59 172.46 Appendix D1
Total 1166.35 1240.44
COST OF PRODUCTION (`\t) Option – III(b) (Integrated)
Option-III(b) (Integrated) Admin- At 85% Capacity
strative
At 100% At 85% Cost (No-
Sl. No. Particulars Capacity Capacity tional)
3%
Depreciation
Interest on 12% Salary & Wages
1 Salary & Wages 146.49 172.34 Working cap- 14%
ital
2 Stores 156.15 168.48
4%
Option-III(b) (Incremental)
Sl. At 100% At 85%
Particulars Capacity Capacity
No.
1 Salary & Wages At 85% Capacity
129.09 151.87
2 Stores 109.35 116.02
3 Power 65.23 73.86 Depreciation Salary & Wages
Adminstrative Cost 11%
4 Misc. Expenses 29.54 32.97 (Notional)
12%
3%
5 Adminstrative Cost (Cash) 3.62 4.26 Interest on Work-
ing capital
6 Mine Closure Cost 13.88 16.33 4% Stores
9%
Thickness(m)
Geological Reserves (Mt)
Strategraphic Sequence
Min. Max. (As on 01.04.2015)
Total 169.86
ADD - ON SLIDES
QUALITY
V I & II B &C
Coal Prodn. Total Total
Year
1 5.47 3.06 G7 1.41 G10 0.5 G7 0.5 G10 3.56 1.91 5.47
2 7 2.55 G8 2.45 G10 1.51 G7 0.49 G10 4.06 2.94 7
3 8 2.37 G8 2.63 G10 2.07 G7 0.93 G9 4.44 3.56 8
4 8 2.16 G8 2.84 G11 1.55 G7 1.45 G8 3.71 4.29 8
5 8 2.16 G8 2.84 G11 1.54 G7 1.46 G8 3.7 4.3 8
6 8 2.16 G8 2.84 G11 1.36 G7 1.64 G10 3.52 4.48 8
7 8 2.02 G8 2.98 G13 1.36 G7 1.64 G10 3.38 4.62 8
8 8 1.6 G8 2.40 G13 1.81 G7 2.19 G10 3.41 4.59 8
9 8 1.46 G8 2.20 G13 1.91 G7 2.43 G10 3.37 4.63 8
10 8 1.21 G8 1.79 G13 2.07 G8 2.93 G11 3.28 4.72 8
11 8 3.32 G8 4.68 G11 3.32 4.68 8
12 8 3.33 G8 4.67 G11 3.33 4.67 8
13 8 3.34 G7 4.66 G10 3.34 4.66 8
14 8 3.34 G7 4.66 G10 3.34 4.66 8
15 8 3.93 G8 4.07 G10 3.93 4.07 8
16 8 4.08 G8 3.92 G10 4.08 3.92 8
17 7 3.57 G8 3.43 G10 3.57 3.43 7
18 6 3.06 G8 2.94 G10 3.06 2.94 6
19 6 2.98 G8 3.02 G10 2.98 3.02 6
20 5.3 2.72 G8 2.58 G10 2.72 2.58 5.3
Total
GEOLOGICAL PLAN
ADD - ON SLIDES
CROSS-SECTIONS
ADD - ON SLIDES
CROSS-SECTIONS
ADD - ON SLIDES
CROSS-SECTIONS
ADD - ON SLIDES
CROSS-SECTIONS
ADD - ON SLIDES
EQUIPMENT PHASING
Years
As per
HEMM Size/ Cap. sanctioned Existing as on
01.04.15 Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Yr-20 Total
3.5 Mtpa
OBR
Electric Rope Shovel 20m3
Diesel Hyd. Backhoe 10-12m3
Rear Dumper 190t Outsoursing
Outsoursing
Outsoursing
Water Sprinkler 70 KL - - - 1 1 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Road Sweeping Machine - - - - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
* It will work in coal extraction in 1st and 2nd year. Hereafter in miscellaneous jobs
ADD - ON SLIDES
TOTAL Actual Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Yr-20
Particulars (Including Prod. Total
2015-16) (2015-16)
2016-17 2017-18 2018-19 2019-20 2020-21 2021-22 2022-23 2023-24 2024-25 2025-26 2026-27 2027-28 2028-29 2029-30 2030-31 2031-32 2032-33 2033-34 2034-35 2035-36
683.36 26.97 35.49 37.48 45.06 42.82 42.82 39.87 36.04 36.49 36.97 37.84 41.55 40.17 38.13 38.13 23.56 21.89 18.9 16.42 15.64 11.12 656.39
Total OB
480.41 20.29 25.38 28.07 34.01 30.33 30.33 28.98 26.69 27 27.52 28.51 31.25 30.01 28.16 28.16 13.76 11.13 9.36 8.1 8.54 4.83 460.12
Top OB
202.95 6.68 10.11 9.41 11.05 12.49 12.49 10.89 9.35 9.49 9.45 9.33 10.3 10.16 9.97 9.97 9.8 10.76 9.54 8.32 7.1 6.29 196.27
202.95 6.68 10.11 9.41 11.05 12.49 12.49 10.89 9.35 9.49 9.45 9.33 10.3 10.16 9.97 9.97 9.8 10.76 9.04 7.67 7.1 7.44 196.27
Parting bet. PUREW MERGED & TURRA
System-Wise OBR( Mm3)
Top OBR Adjusted 683.36 26.97 40 40 40 40 40 40 40 40 40 40 40 40 40 40 25 22.69 15.24 11.96 11.8 9.7 656.39
Additional O.B. Outsourcing 576.39 40 40 40 40 40 40 40 40 40 40 40 40 25 22.69 15.24 11.96 11.8 9.7 576.39
4.47 6.58 7.31 5.71 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 3.13 2.84 2.18 1.99 1.97 1.83 4.41
Av Adjusted S.R (m3/t)
ADD - ON
EVACUATION ROUTE
ADD - ON SLIDES
Total required
Sl. No. Particulars Area (Ha)
Table showing land rates, and the impact of enhanced land rates as per LARR Act)
Option-II (Amt. in Rs. Lakhs)
Sanctioned
Report Total Provision Existing as on 31.3.15 (3.5 Mtpa) Balance Provision ( Phasing of Balance Provision
(3.5 Mtpa) ( 8 Mtpa) 4.5 Mtpa)
Sl.
No. Particulars
Qty. Amt. Qty.(Ha) Amt. Qty. (Ha) Committed Amt. Qty. (Ha) Rate (Rs.in Amt. Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6
(Ha) Amt. Lakh/Ha)
PHASE -I
Leased
Leased Leased land
land, Leased land, Amount
amount land on amount shown
1 Forest Land 447 shown in 840.62 Mine 447 shown 393.62 on
Mine Dev. in Mine Mine
Dev. Fund Dev. Dev.
Fund Fund Fund
2 Non -Forest Land (Total) 892 858.0 1889.94 858.0 892 858 997.94
PHASING OF CAPITAL
TOTAL EXISTING AS ON COMMITTED BALANCE
SANCTIONED TOTAL PROVN DEPN ANNUAL
SL NO PARTICULARS 31.03.2015 (3.5 EXPENSES FOR PROVISION (4.5
CAPITAL (8 Mtpa) Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 RATE DEPN
Mtpa) 3.5 Mtpa Mtpa)
(3.5 Mtpa)
Service 2279 6773 206 1729 4837 0 829 1612 2396 0 0 28 242
Residential 1371 6451 596 1825 4030 0 695 1343 1992 0 0 58 111
c) Others than HEMM 23201 38006 19874 5156 12976 0 4452 5810 1550 0 1164 0 2589
8 Development.
8.1 Capital Outlay in Mines 7125 23405 6507 16898 0 2812 5384 7702 500 500 20 1170
8.2 Roads & Culverts 2417 3500 223 213 3064 0 517 941 1272 334 0 20 175
8.3 Water Supply & Sewerage 1842 5929 42 1118 4769 0 795 1590 2384 0 0 20 296
8.4 Scientific Research 50 80 0 80 0 80 0 0 0 0 20 4.00
8.5 P.R Prep.Cost 497 1992 0 1992 1992 20 100
9.1 Revenue Exp.capitalised 618 0 0 0 20 0
INITIAL CAPITAL 53508 146255 36794 18238 91223 0 27288 28122 33314 834 1664 7422
ADD - ON SLIDES
PHASING OF CAPITAL
TOTAL EXISTING AS
SANCTIONED TOTAL ON COMMITTED BALANCE DEPN ANNUAL
SL NO PARTICULARS CAPITAL PROVN 31.03.2015 EXPENSES PROVISION RATE DEPN
Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6
(3.5 Mtpa) (4.5 Mtpa) (3.5 Mtpa) FOR 3.5 Mtpa (4.5 Mtpa)
8.3 Water Supply & 1842 4769 4769 795 1590 2384 20 238
Sewerage
8.4 Scientific Research 50 80 80 80 20 4.00
8.5 P.R Prep.Cost 497 1992 1992 1992 20 100
8.3 Water Supply & Sewerage 1842 6523 42 1118 5363 894 1788 2681 20 326
8.3 Water Supply & Sewerage 1842 5363 5363 894 1788 2681 20 268
1 CAT-1 CAT-1 0 0 44 2 46
2 CAT-2 CAT-2 30 47 78 0 155
3 CAT-3 CAT-3 0 10 36 0 46
4 CAT-4 CAT-4 0 3 31 0 34
5 CAT-5 CAT-5 0 13 55 0 68
6 CAT-6 CAT-6 0 6 21 0 27
7 SPL. GR SPL. GR 0 0 0 0 0
8 GR-A GR-A 3 15 32 0 50
9 GR-B GR-B 0 81 79 18 178
10 GR-C GR-C 0 0 3 0 3
11 GR-D GR-D 0 0 0 0 0
12 GR-E GR-E 0 20 0 0 20
13 S1 MONTHLY RATED GRADE-H 0 1 38 0 39
14 S2 GRADE-G 0 0 0 0 0
15 S3 GRADE-F 0 0 24 0 24
16 S4 GRADE-E 0 0 21 0 21
17 S5 GRADE-D 0 9 93 0 102
18 S6 GRADE-C 8 3 58 0 69
19 S7 GRADE-B 4 11 50 0 65
20 S8 GRADE-A 0 5 33 2 40
21 E1 Rs 16400-40500 0 0 0 0 0
22 E2 Rs 20600-46500 0 0 7 0 7
23 E3 Rs 24900-50500 4 3 29 1 37
24 E4 Rs 29100-54500 0 1 13 0 14
25 E5 Rs 32900-58000 0 0 10 0 10
26 E6 Rs 36600-62000 1 3 21 0 25
27 E7 Rs 43200-66000 0 1 9 0 10
28 E8 Rs 51300-73000 0 0 2 0 2
TOTAL 50 232 787 23 1092
ADD - ON SLIDES
11 Interest
Sl.No Particulars Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Yr-20 Total Cost
Avg Cost
. (Rs/t)
1 Salary & Wages 4121.94 6252.97 8196.55 8196.55 8196.55 8196.55 8196.55 8196.55 8196.55 8196.55 8196.55 8196.55 8196.55 8196.55 8196.55 8196.55 8196.55 8196.55 8196.55 8196.55 157912.78 106.15
2 Stores 8717.79 11152.74 11506.45 11534.05 11534.05 11557.33 11557.33 11557.33 11557.33 11557.33 11557.33 11557.33 11557.33 11557.33 9743.00 9463.59 8498.97 8038.74 8019.38 7720.93 209945.69 141.12
3 Power 3409.96 3766.41 4116.61 4359.95 4587.41 4814.88 4814.88 4814.88 4814.88 4814.88 4814.88 4814.88 4814.88 4814.88 4814.88 4814.88 4814.88 4814.88 4814.88 4814.88 92463.48 62.15
4 Misc. Expenses 2230.69 2833.78 3340.39 3510.11 3824.76 3732.08 3687.90 3725.47 3733.53 3614.65 3643.08 3644.01 3858.76 3858.76 3806.22 3816.30 3541.28 3266.26 3260.88 3074.88 70003.79 47.06
5 Adm. Expenses 1546.92 1979.60 2262.40 2262.40 2262.40 2262.40 2262.40 2262.40 2262.40 2262.40 2262.40 2262.40 2262.40 2262.40 2262.40 2262.40 1979.60 1696.80 1696.80 1498.84 42072.16 28.28
6 Mine Closure Cost 1162.38 1220.50 1281.53 1345.61 1412.89 1483.53 1557.71 1635.59 1717.37 1803.24 1893.40 1988.07 2087.48 2191.85 2301.44 2416.51 2537.34 2664.21 2797.42 2937.29 38435.34 25.84
7 OB Outsourcing 39946.74 39946.74 39946.74 39946.74 39946.74 39946.74 39946.74 39946.74 39946.74 39946.74 39946.74 39946.74 39946.74 39946.74 24966.71 22659.79 15219.71 11944.08 11784.29 9687.08 655516.02 440.62
8 COAL Outsourcing
9 Interest
on Working 2954.93 3245.72 3414.78 3439.18 3468.63 3479.69 3481.14 3486.72 3491.06 3489.46 3495.20 3499.82 3515.00 3520.04 2711.07 2592.12 2164.77 1963.37 1960.89 1833.30 61206.88 41.14
capital
10 Total Cash Cost 64091.35 70398.46 74065.45 74594.58 75233.42 75473.20 75504.64 75625.68 75719.85 75685.25 75809.58 75909.80 76239.13 76348.55 58802.27 56222.13 46953.09 42584.87 42531.09 39763.75 1327556.13 892.35
11 Interest
12 Depreciation 3570.49 5303.58 6278.13 7067.85 7109.55 7199.23 7199.23 7199.23 7199.23 7199.23 7199.23 7199.23 7199.23 7199.23 7199.23 7199.23 7199.23 7199.23 7199.23 7199.23 137318.08 92.30
Total 67661.84 75702.05 80343.58 81662.44 82342.98 82672.43 82703.87 82824.91 82919.08 82884.48 83008.81 83109.03 83438.36 83547.78 66001.50 63421.36 54152.32 49784.10 49730.32 46962.98 1464874.21 984.66
Cost/t (`) 1236.96 1081.46 1004.29 1020.78 1029.29 1033.41 1033.80 1035.31 1036.49 1036.06 1037.61 1038.86 1042.98 1044.35 825.02 792.77 773.60 829.74 828.84 886.09 984.66
Fixed Cost (`/t) 362.56 376.83 380.76 394.97 400.26 404.24 404.98 406.20 407.31 407.81 409.14 410.39 412.82 414.19 401.08 400.45 444.91 509.59 511.68 573.10 417.67
Variable Cost (`/t) 874.41 704.63 623.53 625.81 629.03 629.17 628.82 629.11 629.18 628.24 628.47 628.47 630.16 630.16 423.94 392.32 328.69 320.14 317.16 313.00 566.98
ADD - ON SLIDES
Sl. No. Particulars Yr-1 Yr-2 Yr-3 Yr-4 Yr-5 Yr-6 Yr-7 Yr-8 Yr-9 Yr-10 Yr-11 Yr-12 Yr-13 Yr-14 Yr-15 Yr-16 Yr-17 Yr-18 Yr-19 Yr-20 Total Avg Cost
Cost Rs/t
1 Salary & Wages 808.87 2964.60 3870.55 3870.55 3870.55 3870.55 3870.55 3870.55 3870.55 3870.55 3870.55 3870.55 3870.55 3870.55 3870.55 3870.55 8367.85 8367.85 8367.85 8367.85 91432.64 96.74
2 Stores 1877.36 4989.66 6515.44 6543.04 6543.04 6566.32 6566.32 6566.32 6566.32 6566.32 6566.32 6566.32 6566.32 6566.32 5194.68 5670.45 4976.04 4515.81 4496.46 4198.00 114616.86 121.27
3 Power 2316.09 2569.00 2815.55 3038.84 3246.00 3453.17 3453.17 3453.17 3453.17 3453.17 3453.17 3453.17 3453.17 3453.17 3453.17 3453.17 3453.17 3453.17 3453.17 3453.17 65782.98 69.60
4 Misc. Expenses 567.01 1241.53 1695.46 1922.29 2237.21 2259.71 2269.71 2269.71 2269.71 2269.71 2269.71 2269.71 2269.71 2269.71 2269.71 2743.01 3062.17 2790.16 2790.16 2599.75 44335.85 46.91
5 Adm. Expenses 557.12 989.80 1272.60 1272.60 1272.60 1272.60 1272.60 1272.60 1272.60 1272.60 1272.60 1272.60 1272.60 1272.60 1272.60 1764.67 1979.60 1696.80 1696.80 1498.84 26727.43 28.28
6 Mine Closure Cost 592.38 622.00 653.10 685.75 720.04 756.04 793.84 833.54 875.21 918.97 964.92 1013.17 1063.83 1117.02 1172.87 1231.51 1293.09 1357.74 1425.63 1496.91 19587.59 20.73
7 OB Outsourcing 14390.81 19983.36 29660.45 29660.45 29660.45 29660.45 29660.45 29660.45 29660.45 29660.45 29660.45 29660.45 29660.45 29660.45 18335.55 21351.53 15219.71 11944.08 11784.29 9687.08 478621.87 506.42
8 COAL Outsourcing 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Interest on Working
9 1020.30 1612.40 2246.69 2271.35 2298.25 2312.21 2314.52 2316.44 2318.45 2320.57 2322.79 2325.12 2327.57 2330.14 1719.17 1937.44 1853.66 1649.40 1644.03 1512.91 40653.42 43.01
capital
10 Total Cash Cost 22129.95 34972.35 48729.83 49264.88 49848.14 50151.06 50201.17 50242.78 50286.47 50332.35 50380.52 50431.10 50484.20 50539.97 37288.31 42022.34 40205.30 35775.01 35658.38 32814.52 881758.64 932.98
12 Depreciation 0.00 1731.31 2704.40 3493.79 3535.49 3625.16 3625.16 3625.16 3625.16 3625.16 3625.16 3625.16 3625.16 3625.16 3625.16 3625.16 3625.16 3625.16 3625.16 3625.16 65842.44 69.67
Total 22129.95 36703.66 51434.23 52758.67 53383.63 53776.22 53826.34 53867.95 53911.64 53957.51 54005.68 54056.26 54109.37 54165.13 40913.47 45647.51 43830.46 39400.18 39283.55 36439.68 947601.08 1002.65
Cost/t (Rs) 1123.35 1048.68 1142.98 1172.41 1186.30 1195.03 1196.14 1197.07 1198.04 1199.06 1200.13 1201.25 1202.43 1203.67 909.19 731.53 626.15 656.67 654.73 687.54 1002.65
Fixed Cost (Rs/t) 268.66 348.80 351.19 375.90 384.18 391.16 392.14 393.06 394.03 395.05 396.12 397.25 398.43 399.67 381.79 292.56 327.96 372.09 373.07 414.79 373.14
Variable Cost (`Rst) 854.68 699.88 791.79 796.52 802.13 803.86 804.00 804.00 804.00 804.00 804.00 804.00 804.00 804.00 527.39 438.97 298.19 284.58 281.66 272.75 629.51
ADD - ON SLIDES
1 Salary & Wages 3724.85 6007.16 14938.84 15007.63 15007.63 15007.63 15007.63 15007.63 15007.63 15007.63 15007.63 15007.63 15007.63 15007.63 15007.63 15007.63 15007.63 15007.63 15007.63 15007.63 279800.56 188.08
2 Stores 8717.79 11228.57 45465.18 45687.85 45730.06 45753.34 45753.34 45753.34 45753.34 45753.34 45753.34 45753.34 45753.34 45753.34 43939.01 43659.60 42694.98 42234.74 42215.39 41916.94 825270.20 554.73
3 Power 4236.00 4580.55 9005.73 9241.43 9461.85 9682.27 9682.27 9682.27 9682.27 9682.27 9682.27 9682.27 9682.27 9682.27 9241.91 8361.18 7418.76 6978.40 6978.40 6538.03 169182.71 113.72
4 Misc. Expenses 2220.76 2834.82 8745.56 8997.26 9418.03 9325.47 9281.29 9318.86 9326.92 9208.04 9236.47 9237.41 9452.15 9452.15 9399.61 9409.69 9134.67 8859.65 8854.27 8668.28 170381.36 114.53
5 Adm. Expenses 1546.92 1979.60 2262.40 2262.40 2262.40 2262.40 2262.40 2262.40 2262.40 2262.40 2262.40 2262.40 2262.40 2262.40 2262.40 2262.40 1979.60 1696.80 1696.80 1498.84 42072.16 28.28
6 Mine Closure Cost 1162.38 1220.50 1281.53 1345.61 1412.89 1483.53 1557.71 1635.59 1717.37 1803.24 1893.40 1988.07 2087.48 2191.85 2301.44 2416.51 2537.34 2664.21 2797.42 2937.29 38435.34 25.84
7 OB Outsourcing 39946.74 39946.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 79893.48 53.70
8 COAL Outsourcing 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
9 Interest on Working 2975.18 3276.90 3948.80 3989.54 4025.82 4036.54 4037.99 4043.57 4047.91 4046.32 4052.05 4056.67 4071.85 4076.90 3970.68 3920.66 3807.36 3743.00 3748.25 3700.74 77576.73 52.15
capital
10 Total Cash Cost 64530.63 71074.84 85648.03 86531.71 87318.68 87551.19 87582.63 87703.68 87797.85 87763.24 87887.57 87987.80 88317.13 88426.55 86122.68 85037.67 82580.34 81184.43 81298.15 80267.74 1682612.54 1131.02
12 Depreciation 3570.49 5437.45 25983.12 26979.67 27038.49 27128.17 27128.17 27128.17 27128.17 27128.17 27128.17 27128.17 27128.17 27128.17 27128.17 27128.17 27128.17 27128.17 27128.17 27128.17 495931.72 333.35
Total 68101.11 76512.29 111631.16 113511.39 114357.17 114679.36 114710.80 114831.84 114926.02 114891.41 115015.74 115115.96 115445.29 115554.71 113250.85 112165.84 109708.51 108312.60 108426.32 107395.91 2178544.26 1464.37
Cost/t (Rs) 1244.99 1093.03 1395.39 1418.89 1429.46 1433.49 1433.88 1435.40 1436.58 1436.14 1437.70 1438.95 1443.07 1444.43 1415.64 1402.07 1567.26 1805.21 1807.11 2026.34 1464.37
Fixed Cost (Rs/t) 366.74 384.90 1058.81 1078.40 1084.72 1088.63 1089.37 1090.59 1091.70 1092.20 1093.53 1094.78 1097.21 1098.57 1081.14 1071.85 1201.64 1386.68 1388.76 1559.49 1073.61
Variable Cost (Rs/t) 878.25 708.14 336.58 340.50 344.75 344.86 344.52 344.81 344.88 343.94 344.17 344.17 345.86 345.86 334.49 330.22 365.62 418.53 418.34 466.85 390.76
ADD - ON SLIDES
1 Salary & Wages 465.23 2709.12 10617.59 10682.35 10682.35 10682.35 10682.35 10682.35 10682.35 10682.35 10682.35 10682.35 10682.35 10682.35 10682.35 10682.35 14693.34 14693.34 14693.34 14693.34 211435.86 223.72
2 Stores 1877.36 5065.50 40474.17 40696.83 40739.05 40762.33 40762.33 40762.33 40762.33 40762.33 40762.33 40762.33 40762.33 40762.33 39390.69 39866.46 39172.05 38711.82 38692.47 38394.01 729941.38 772.34
3 Power 3289.95 3530.69 7845.40 8058.14 8255.62 8453.10 8453.10 8453.10 8453.10 8453.10 8453.10 8453.10 8453.10 8453.10 8013.45 7134.16 6193.29 6131.70 5753.64 5314.00 145597.93 154.06
4 Misc. Expenses 558.42 1242.33 7100.74 7409.45 7830.50 7853.12 7863.12 7863.12 7863.12 7863.12 7863.12 7863.12 7863.12 7863.12 7863.12 8336.42 8643.43 8371.41 8371.41 8181.00 144666.31 153.07
5 Adm. Expenses 557.12 989.80 1272.60 1272.60 1272.60 1272.60 1272.60 1272.60 1272.60 1272.60 1272.60 1272.60 1272.60 1272.60 1272.60 1764.67 1979.60 1696.80 1696.80 1498.84 26727.43 28.28
6 Mine Closure Cost 592.38 622.00 653.10 685.75 720.04 756.04 793.84 833.54 875.21 918.97 964.92 1013.17 1063.83 1117.02 1172.87 1231.51 1293.09 1357.74 1425.63 1496.91 19587.59 20.73
8 COAL Outsourcing
Interest on Working
9 capital
1050.34 1650.24 3284.91 3325.58 3359.17 3372.68 3374.99 3376.91 3378.92 3381.04 3383.26 3385.59 3388.04 3390.61 3305.76 3335.75 3478.78 3429.87 3413.94 3362.94 63429.32 67.11
10 Total Cash Cost 22781.61 35793.03 71248.51 72130.71 72859.33 73152.22 73202.33 73243.94 73287.63 73333.51 73381.68 73432.26 73485.36 73541.13 71700.85 72351.34 75453.57 74392.68 74047.23 72941.04 1375759.98 1455.68
11 Interest
12 Depreciation 1865.18 22409.39 23405.61 23464.42 23554.10 23554.10 23554.10 23554.10 23554.10 23554.10 23554.10 23554.10 23554.10 23554.10 23554.10 23554.10 23554.10 23554.10 23554.10 424456.08 449.11
Total 22781.61 37658.21 93657.90 95536.32 96323.75 96706.32 96756.43 96798.04 96841.73 96887.61 96935.78 96986.36 97039.46 97095.23 95254.95 95905.44 99007.67 97946.78 97601.33 96495.14 1800216.05 1904.79
Cost/t (Rs) 1156.43 1075.95 2081.29 2123.03 2140.53 2149.03 2150.14 2151.07 2152.04 2153.06 2154.13 2155.25 2156.43 2157.67 2116.78 1536.95 1414.40 1632.45 1626.69 1820.66 1904.79
Fixed Cost (Rs/t) 289.06 367.95 1559.18 1593.30 1603.37 1610.18 1611.16 1612.08 1613.05 1614.07 1615.14 1616.27 1617.45 1618.69 1593.13 1155.04 1078.88 1247.35 1243.38 1393.52 1406.13
Variable Cost (Rs/t) 867.37 708.00 522.10 529.73 537.16 538.85 538.98 538.98 538.98 538.98 538.98 538.98 538.98 538.98 523.64 381.90 335.51 385.10 383.31 427.14 498.65
SALIENT FEATURES
Mine Parameters
• Existing :
• 10 Mty for (-)200 mm product size
• 2 numbers Silo (2400 T & 3000 T) with RLS
• Proposed :
• Secondary crushing for existing CHP for (-)100 mm product size
• Additional 15 Mty Semi-mobile in-pit crushing for (-)100 mm product
size
• 1 number Silo (4000 T) with RLS
OB Dumping
As on 01.04.2016
Internal Dump External Dump
Total OB
OB from Quarry
(Mm3)
V-I V-II OLD Ext. Dump South Ext. Dump North Ext. Dump
6 Weighted Average Selling Price `/t 1099.84 1313.42 1313.42 1313.42 1313.42 1313.42
Profitability(`/t)
100% Prodn. Level 410.04 686.57 (-)591.37 (-)150.95 310.77 328.76
7
85% Prodn. Level 351.50 609.05 (-)839.51 (-)340.41 244.93 255.06
Financial IRR (%)
8 100% Prodn. Level 104.05% 40.09% (-)ve (-)6.59% 20.82% 32.92%
85% Prodn. Level 68.45% 32.63% (-)ve (-)ve 13.51% 21.09%
Desired selling price to yield 12% FIRR (`/t)
9 100% Prodn. Level 672.27 790.28 2384.41 1704.55 1204.35 1134.53
85% Prodn. Level 731.92 882.27 2708.44 1929.55 1288.61 1223.65
NPV at 12% (` Lakhs)
100% Prodn. Level 93258.62 126208.03 (-)339037.73 (-)206469.24 34528.47 111495.20
10
85% Prodn. Level 53170.34 88412.26 (-)282184.41 6674.88 52513.12
(-)375370.91
Outsourcing Rate (`/B.m3)
11
OB Insitu (Excluding blasting) 99.87
12 Manpower No. 610 610 1565 2175 482 1092
13 OMS t 22.90 22.90 26.90 15.27 107.61 32.41
14 EMS ` 1837.58 2576.38 2531.66 2544.20 2624.97 2597.83
MINE ECONOMICS
VARIANT APPROVED BY SUBSIDIARY COMPANY BOARD:
DETAILS OF APPROVED VARIANT: (give hyperlink to add-on slide showing all variants)
TOTAL CAPITAL INVESTMENT : 1462.55 Crs.
EXISTING CAPITAL INVESTMENT : 367.94 Crs.
COMMITED CAPITAL : 182.38 Crs.
CAPITAL UPTO TARGET YEAR : 554.10 Crs.
CAPITAL BEYOND TARGET YEAR : 358.12 Crs.
COST OF PRODUCTION AT 100 % : 984.66
COST OF PRODUCTION AT 85 % : 1058.36
Upto
Rs. Crores 3534.12 3534.12 1010.31 1010.31 1084.30 1084.30 1012.00 1012.00
Target year
Specific
Rs./t 1528.80 1572.34 7865.64 5112.33 2257.18 1957.56 2421.6 2050.05 2260.93 1959.68
Investment
Cost of Production
At 100%
Prodn. Rs./t 689.80 941.03 2071.91 1406.75 1127.33 1041.03 1193.23 1076.51 1298.38 1132.30
Level
At 85%
Prodn. Rs./t 748.35 1026.52 2341.51 1591.36 1198.21 1118.59 1266.47 1155.35 1373.98 1212.30
Level
Weighted
Avg. Selling Rs./t 1099.84 1384.81 1384.81 1384.81 1384.81 1384.81 1384.81 1384.81 1384.81 1384.81
Price
MINE ECONOMICS – COMPARATIVE STATUS
A BASE CASE
At 100% production level 18.40 72.07 11.15 65.28
At 85% production level 10.79 30.95 5.20 25.00
AFTER REDUCTION
B
OF LAND