Deployment of Safety Officer Per Scope of Work

You might also like

Download as pptx, pdf, or txt
Download as pptx, pdf, or txt
You are on page 1of 10

Scope of Work - Deployment of Safety

Officer & PIC w/ COSH Training Matrix


Date: August 24, 2020
Scope of Work – Vertical Project (Site Clearing)
Risk
SCOPE OF WORK Category Deployment of Safety Officer REMARKS

VERTICAL PROJECT (Site Clearing)

c/o MDC, but SubCon to provide supervisor More than 1 month duration or
1 Clearing & grabbing Medium maximum of 30 manpower & 10
(PIC/FE/Foreman with COSH Training Heavy Equipment

2 Demolition      
  a. Blasting High SubCon to provide  
  b. Equipment High SubCon to provide  

  c. Manual Medium to c/o MDC, but SubCon to provide supervisor More than 1 month duration or
High (PIC/FE/Foreman with COSH Training maximum of 40 manpower

3 Board up installation medium c/o MDC, but SubCon to provide supervisor More than 1 month duration or
(PIC/FE/Foreman with COSH Training maximum of 40 manpower
c/o MDC, but SubCon to provide supervisor More than 1 month duration or
4 Ball-out/Relocation of trees Medium
(PIC/FE/Foreman with COSH Training maximum of 30 manpower
c/o MDC, but SubCon to provide supervisor More than 3 month duration or
5 Soil Testing /Drilling Medium
(PIC/FE/Foreman with COSH Training maximum of 30 manpower
c/o MDC, but SubCon to provide supervisor More than 1 month duration or
6 Bomb / UXO scanning High
(PIC/FE/Foreman with COSH Training maximum of 5 manpower
Less than a week duration with
7 Site internet connection set up low c/o MDC less than 5 manpower
Scope of Work – Structural Works
Risk
SCOPE OF WORK Deployment of Safety Officer REMARKS
Category
STRUCTURAL WORKS
Push Pile using diesel hammer &  
1 hydraulic pile driver High SubCon to provide
2 Bored Pile High SubCon to provide  
c/o MDC, but SubCon to provide supervisor  
 3 Excavation High
(PIC/FE/Foreman with COSH Training
 4 Soil Poisoning/Treatment Medium c/o MDC, but SubCon to provide supervisor Maximum of 30 manpower
(PIC/FE/Foreman with COSH Training
 5 Pile Hacking Medium SubCon to provide Maximum of 30 manpower
Structural (Rebar, Formworks &  
6 High SubCon to provide
Concreting)
Fabrication of Rebar & Precast -  
7 Installation High SubCon to provide

Slope Protection (Shotcrate, soil  


8 High SubCon to provide
nailing & Sheet Piles)
Cistern Tanks (Rebar, Formworks &  
9 High SubCon to provide
Concreting)
STP (Rebar, Formworks & c/o MDC, but SubCon to provide supervisor  
10 Concreting) High (PIC/FE/Foreman with COSH Training
11 Fuel Tank - Steel Medium SubCon to provide Maximum of 30 manpower
12 Perimeter Fence - CHB & Smart Block High SubCon to provide  
Construction of Overhead Street c/o MDC, but SubCon to provide supervisor  
13 High
Protection (PIC/FE/Foreman with COSH Training
c/o MDC, but SubCon to provide supervisor  
14 Mock-up / Stub-out Low
(PIC/FE/Foreman with COSH Training
Scope of Work - MEPFS
Risk
SCOPE OF WORK Category Deployment of Safety Officer REMARKS

MEPFS

1 Plumbing & Sanitary High SubCon to provide

2 Mechanical Ducting High SubCon to provide


3 Fire Pro Installation High SubCon to provide
4 Electrical Works High SubCon to provide

5 Elevator Installation High SubCon to provide

6 Escalator Installation High SubCon to provide

c/o MDC, but SubCon to provide supervisor


7 CCTV & FDAS cabling Medium (PIC/FE/Foreman with COSH Training Maximum of 40 manpower

Electrical Busduct Inst. & Testing


8 High SubCon to provide
Commisioning

9 Genset Installation - Testing & High SubCon to provide


Commissioning
Scope of Work – Architectural Works
Risk
SCOPE OF WORK Deployment of Safety Officer REMARKS
Category
ARCHITECTURAL WORKS
Roofing Installation (crown &  
1 High SubCon to provide
conference room)
2 Painting Works Exterior High SubCon to provide  
c/o MDC, but SubCon to provide supervisor
3 Painting Works Interior Medium Maximum of 50 manpower
(PIC/FE/Foreman with COSH Training
Water Proofing -Cistern Tank, STP,
4 High SubCon to provide Maximum of 50 manpower
T&B and Roofdeck
Light Weight Panel Interior Wall &  
5 Medium SubCon to provide
CHB Installation
6 Ceiling Works Medium SubCon to provide  
c/o MDC, but SubCon to provide supervisor
7 Kitchen Cabinet Installation Low Maximum of 50 manpower
(PIC/FE/Foreman with COSH Training
c/o MDC, but SubCon to provide supervisor  
8 Tiles Setting & Installation Medium (PIC/FE/Foreman with COSH Training
Railings Fabrication & Installation  
9 High SubCon to provide
(Stairs & Balcony)
Window / Glass /aluminum Framing  
10 (Hauling and installation) High SubCon to provide
11 Window Installation High SubCon to provide  
12 Steel Door Installation Medium c/o MDC, but SubCon to provide supervisor Maximum of 30 manpower
(PIC/FE/Foreman with COSH Training

13 Wall validation - Grinding & Skim low c/o MDC, but SubCon to provide supervisor Maximum of 50 manpower
Coating (PIC/FE/Foreman with COSH Training
Scope of Work – Architectural Works
Risk
SCOPE OF WORK Deployment of Safety Officer REMARKS
Category
ARCHITECTURAL WORKS (cont….)
c/o MDC, but SubCon to provide supervisor  
14 Floor leveling & Vinyl Installation low (PIC/FE/Foreman with COSH Training
c/o MDC, but SubCon to provide supervisor  
15 Louver Installation Medium
(PIC/FE/Foreman with COSH Training
c/o MDC, but SubCon to provide supervisor  
16 Dust Proofing Low (PIC/FE/Foreman with COSH Training

17 Hard Scape Medium c/o MDC, but SubCon to provide supervisor More than 1 month duration or
(PIC/FE/Foreman with COSH Training maximum 0f 30 manpower
c/o MDC, but SubCon to provide supervisor More than 1 month duration or
18 Soft Scape Medium (PIC/FE/Foreman with COSH Training maximum 0f 40 manpower

19 Toilet Partition Low c/o MDC, but SubCon to provide supervisor More than 1 month duration or
(PIC/FE/Foreman with COSH Training maximum 0f 50 manpower
Working edge/Perimeter of
20 Building exerior works using High SubCon to provide Building
rapelling
c/o MDC, but SubCon to provide supervisor Usually QRT manpower is
21 Punchlist works low
(PIC/FE/Foreman with COSH Training deployed less than 5
Scope of Work – Land Dev’t Project
Risk
SCOPE OF WORK Deployment of Safety Officer REMARKS
Category
LAND DEV'T PROJECT
More than 1 month duration or
c/o MDC, but SubCon to provide supervisor maximum 40 manpower and 10
1 Clearing & Grabbing Medium (PIC/FE/Foreman with COSH Training Heavy Equipment
2 Excavation & Road Works High SubCon to provide  
3 Blasting Activity High SubCon to provide  
4 Concreting (road, gutter & side walk High SubCon to provide  
5 Pipe laying -RCP High SubCon to provide  
6 Pipe laying -Sewer High SubCon to provide  
7 Pipe laying - Water line High SubCon to provide  
8 Cable laying - Electrical High SubCon to provide  
9 Perimeter Fence High SubCon to provide  
c/o MDC, but SubCon to provide supervisor More than 1 month duration or
10 Hard Scape Medium (PIC/FE/Foreman with COSH Training maximum of 30 manpower
c/o MDC, but SubCon to provide supervisor More than 1 month duration or
11 Soft Scape Medium
(PIC/FE/Foreman with COSH Training maximum of 40 manpower
c/o MDC, but SubCon to provide supervisor More than 1 month duration or
12 Stone Masonry Medium
(PIC/FE/Foreman with COSH Training maximum of 30 manpower
c/o MDC, but SubCon to provide supervisor  
13 Soil Poisoning/Treatment Medium (PIC/FE/Foreman with COSH Training

14 CCTV /Street Lighting Medium c/o MDC, but SubCon to provide supervisor Maximum 40 manpower
(PIC/FE/Foreman with COSH Training
c/o MDC, but SubCon to provide supervisor
15 Amenities/Clubhouse Low (PIC/FE/Foreman with COSH Training Maximum 40 manpower

c/o MDC, but SubCon to provide supervisor  


16 Guard house/Mock Up Housing Low
(PIC/FE/Foreman with COSH Training
Scope of Work – Infrastructural Works

SCOPE OF WORK Risk Deployment of Safety Officer REMARKS


Category
INFRASTRUCTURAL WORKS
 
1 Road Works High SubCon to provide
 
2 Bridge Works High SubCon to provide

3 Railway Works High SubCon to provide

4 Girder Installation & Fitting High SubCon to provide

5 Post and Foundation Works High SubCon to provide


Risk and Opportunity Assessment

Risk Opportunity
Develop Operation personnel (PIC/FE/
1 Issued Safety Observation or EHS issues and 1 Foreman) to changed their culture and act as a
concern may not be prioritize
Safety

Develop Operation personnel (PIC/FE/


Recognition/ identifying work hazards may
2 not be same with EHS Personnel 2 Foreman) to recognized and identify work
hazards

Poor performance of (PIC/FE/Foreman) MDC EHS personnel has opportunity to learn


3 designated as Safety Officer, result to 3 more the process & minimize subcon safety
overload on the part of MDC EHS personnel deployment as savings

Operation personnel (PIC/FE/ Foreman) can be


Operation personnel (PIC/FE/ Foreman) not
4 4 a cross multifier as Safety Personnel and can be
interested to learn and develop a part of EHS Department
THANK YOU.

You might also like