Huntington Park Culvert Rehabilitation Options
Huntington Park Culvert Rehabilitation Options
Huntington Park Culvert Rehabilitation Options
1
Huntington Park Culvert and Pathway
2
Existing Culverts Condition
• Ex. culvert comprises of two corrugated steel
arch shaped pipes (CSP - Arch), built in 1967
– 3.5m wide x 2.1m high x 11.3 m long
• Ex. culverts have been damaged beyond
repairs – complete structural failure
o Severe deformation and shape is irregular
o Sheet piling at north & south sides of
structure have completely failed with
major deformation
o Culvert has lost its structural integrity with
no stable foundation
o Sever corrosion with full loss of section at
the outlet
o Loss of bedding behind apron wall at
outlet
3
Existing Culverts Condition
4
Existing Channel Condition
5
Proposed Channel Restoration
6
Typical Channel Restoration Works
7
Replacement/ Rehabilitation Options
Option Structure Est. Cost Comments
#1 Replace with 20m Total: $808k • New Pedestrian bridge can only be built after
span Pedestrian Ped. Bridge - $408k; removal of the existing culverts and creek is re-
bridge (prefabricated Channel work - $400k sloped and bank restored
steel truss) • TRCA will not allow to leave the ex. culvert as it is
#2 Replace with same Total: $1200k • New culvert can only be built after removal of the
size concrete culvert Culvert - $800k; existing culverts, creek is re-sloped and bank
(size depends on Channel work - $400k restored
hydraulic analysis) • TRCA will not allow to leave the ex. culvert as it is
#3 Rehabilitate with N/A Not suitable for lining as the existing culverts are:
Cured-In-Place-Pipe • Arch; and
(CIPP) Liner • Deformed
Note: Only circular pipes can be lined – see below
8
Pathway Looping Options
• The City leases Huntington Park from the Province, since 2012
– Current term of the Lease expires Sept 30, 2022
– City has a right to renew for a further 10 years
9
Pathway Looping Options
10