Saddle Dam - Sequencing (For CREC Discussion)
Saddle Dam - Sequencing (For CREC Discussion)
Rockfall Mitigation
Stage 1 to Stage 3
CH320 to CH484
CH-9.28 to CH80 Excavation to EL124m : 2023.7.20 to 2023.8.25
Excavation to Foundation 2024.5.11
Drilling & Grouting 2024.4.30
Foundation Treatment & Clean Up 2024.5.30
CH200 to CH399
Excavation to Foundation: 2024.04.30
CH80 to CH320
Drilling and Grouting 3 台钻机
CH0 to CH80
Drilling and Grouting 1 台钻机
Earthfill Dam Footprint
From EL124m to EL89m 2025.10.10
CH80 to CH320
Drilling and Grouting 4 台钻机
CH80 to CH320
Drilling and Grouting 3 台钻机
CH80 to CH320
Drilling and Grouting 3 台钻机
RCC AND EARTHFILL PLAN
Foundation Treatment
RCC Placing to EL137.40m Earthfill to EL138.00m 2025.10.11
EL120m
EL100.2m
Temporary Platform:
16-Jul-22 to 16-Dec-22
EXPLORATORY ADIT
Rockfall Mitigation
Stage 1 to Stage 3 :
CH250 to CH200 to
CH550 CH50 to CH550 CH0 to CH250 CH0 to CH200 CH0 to CH50
CH550 Invert Concrete:
Portal Structure of Exploratory Adit:
CH50 to CH0
CH50 to CH550 Drilling & Blasting , Tunnel Excavation Works:
Drilling & Blasting , Tunnel Excavation Works:
CH0 to CH200
CH200 to CH450 Drilling of Exploratory Hole:
Drilling of Exploratory Hole: