EXCAVATION , DRILLING AND GROUTING SCHEDULE

Rockfall Mitigation
Stage 1 to Stage 3

CH320 to CH484
CH-9.28 to CH80 Excavation to EL124m : 2023.7.20 to 2023.8.25
Excavation to Foundation 2024.5.11
Drilling & Grouting 2024.4.30
Foundation Treatment & Clean Up 2024.5.30

CH200 to CH399
Excavation to Foundation: 2024.04.30

Drilling & Grouting 2024.10.1


RCC Footprint 2024.5.30
CH80 to CH200 Earthfill Dam Footprint: 2024.11.10
Excavation to Foundation 2023.8.10 Foundation Treatment & Clean Up 2024.8.30
Drilling & Grouting 2024.4.6 Surface Excavation after Grouting 2 024.11.10
Foundation Treatment & Clean Up 2023.9.1
GROUTING PLAN

CH80 to CH320
Drilling and Grouting 3 台钻机

CH0 to CH80
Drilling and Grouting 1 台钻机
Earthfill Dam Footprint
From EL124m to EL89m 2025.10.10

CH80 to CH320
Drilling and Grouting 4 台钻机

CH80 to CH320
Drilling and Grouting 3 台钻机

CH80 to CH320
Drilling and Grouting 3 台钻机
RCC AND EARTHFILL PLAN

Foundation Treatment
RCC Placing to EL137.40m Earthfill to EL138.00m 2025.10.11

EL120m

EL100.2m

Foundation Cleaning 2023.9.30


RCC Placing to EL120.00m 2024.9.30
Foundation Cleaning 2024.5.30
RCC Placing to EL 100.2m 2025.2.6

RCC Trial embankment


Earthfill Trial Embankment 2024.5.1
RCC Placing to EL 120.00m 2025.5.15
DAM IMPOUNDMENT

As of 29th November 2025


RCC Embankment As of 16th October 2025
EL136.75 – EL139.15 Earth Fill
@EL###m Rip Rap (U/S)
Earth Fill @EL###m
@EL###m Rip Rap (U/S)
MOL : EL 115m @EL###m

Main Dam Impoundment


16th October 2025

Estimated duration to reach MOL : 44 days


Estimated date: 29th November 2025
ACCESS TUNNEL

Setup and installation of equipment for excavation for


Access Tunnel
Rockfall Mitigation for Access Tunnel :
Access Tunnel to Exploratory Adit - D&B tunnel 2023.8.10~2023.8.30
excavation

Temporary Platform:
16-Jul-22 to 16-Dec-22
EXPLORATORY ADIT

Rockfall Mitigation
Stage 1 to Stage 3 :

CH250 to CH200 to
CH550 CH50 to CH550 CH0 to CH250 CH0 to CH200 CH0 to CH50
CH550 Invert Concrete:
Portal Structure of Exploratory Adit:

CH50 to CH0
CH50 to CH550 Drilling & Blasting , Tunnel Excavation Works:
Drilling & Blasting , Tunnel Excavation Works:

CH0 to CH200
CH200 to CH450 Drilling of Exploratory Hole:
Drilling of Exploratory Hole:

CH250 to CH550 CH0 to CH250 Main Dam Impoundment


Drilling and Grouting In Adit: Drilling and Grouting In Adit: 16th October 2025