Professional Documents
Culture Documents
Weekly Review
Weekly Review
Weekly Review
1. Change request for Labor 1. Labor and Productivity 1. Development and Unit
and productivity module Report automation defects testing for 2015 reporting
completed. fixed. changes.
2. Database changes to be
2. Discussion with Alan on 2. Labor and Productivity promoted for Labor and
2015 reporting changes. Report automation UAT Productivity module on
completed and signed off Production.
3. Labor and Productivity from Alan. 3. Request for Move to
module released to UAT. Production for Labor and
3. Requirements document Productivity report to
for Metrics -2015 reporting Romano.
changes completed and
shared with Alan.
Assignments
Modification Planned Planned Actual EXLEstimate Actual Effort
Phase Status
Start Completion Completion (Hrs) (Hrs)
Labor andProductivityReport
Analysis Completed 50 50
Automation. 10/17/2014 11/29/2014 12/15/2014
Testing Completed 80 80
1/11/2015 1/27/2015 2/23/2015
2015- ReportingModifications
Analysis InProgress 100 20
3/9/2015 3/25/2015
Vacation Planned
Resource Till Date Vacation
Abhishek Singh 3 3
Mar-15
3/10
3/11
3/13
3/14
3/15
3/16
3/18
3/19
3/20
3/21
3/22
3/23
3/24
3/25
3/26
3/27
3/28
3/29
3/30
3/31
3/12
3/17
3/3
3/5
3/6
3/8
3/9
3/1
3/2
3/4
3/7