MENA Eagle Day Template - 11th Sep'18
MENA Eagle Day Template - 11th Sep'18
MENA Eagle Day Template - 11th Sep'18
<Date>
2
Project Details
Timeline for
Category Action point Responsibility next update Status
4
Crash Plan vs Actuals – Project Physical S-Curve
Crash Plan Total Till Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Balance
Foundation
Erection
Stringing
Act + Aug Eagle Day Plan
Foundation
Erection
Stringing
Act + Sep Eagle Day Plan
Foundation
Erection
Stringing
100.00% 98.81%
96.95% 97.94%
95.79%
93.23% 91.45% 95.00%
90.00% 89.50% 90.32%
81.40% 80.68%
80.00%
79.56%
50.00% 50.86%
43.26%
40.00% 4
Till Jun-18 18-Jul 18-Aug 18-Sep 18-Oct 18-Nov 18-Dec
5
Construction Plan Ahead & Resources Planning – Q2 & Q3 – FY19
No. Gangs in a
Month
Strength per
gang Foundation &
erection
productivity
No. Of TSE rise is
sets attributable to
Productivity
per gang
Plan for
Month
6
Plan Ahead – Revenue Details (Q2 & Q3)
Total
Total
Amount in INR Cr
7
Assistance from HO
Issues involving HO Issue Report Date / Responsible Team Support Required / Action Plan
Pending Since
8
Outstanding and Overdue + Collection Plan
Unbilled AR
Price Total
Description Variation Dependency Retention Outstanding
Total >30 days Total 0 – 45 days > 45 days
1.7
60
Past Incident Learning 39%
50 57.18
52.38
49.84 Lock Out / Tag Out 37%
Work Stoppage Violation Unsafe Observation Action Areas for MMR Improvement
Note (WSN) Memo (UA/UC) Focus on Near Miss and UA/UC reporting through
training
Issued Closed Issued Closed Identified Closed Focus on First aid cases reporting through training
0 0 0 0 1 1
MMR – Minimum Mandatory Requirement
10
EHS – Major Incident / Client Appreciation /Site Photographs
Major Incident
Client Appreciation
First aid Training
11
Human Resource - Mozambique
.
Would be filled by HR
.
12
An Group Company
THANK YOU