Memon Health and Education

Foundation (MHEF)
Hospital Expansion Project
Meeting of Board of Governors, June 24, 2023
EXPANSION PROJECT - MMIH

MAIN HIGHLIGHTS:
Area: 200,000 SQFT
Start Date Of Project: August 15, 2020 BLOCK - 05
BLOCK - 04 BLOCK - 06
CONSULTANTS AND CONTRACTORS

CONSULTANTS:

Architect: Habib Fida Ali


Mechanical Consultant: Y. H. Associates
Electrical Consultant: Ayub Associates
Structural Consultant: Alliance Consultants

CONTRACTORS:

Civil / Electrical / Plumbing (1st Floor) Principal Builders


Electrical (2 to 3 Floor)
nd rd
Jammy Tech.
HVAC Contractors: (1 to 3 Floor)
st rd
Mega Engineering
CURRENT PROGRESS:
• Coring Work for Drainage System in Progress at 1st & 2nd Floors.
• Laying of Drainage & Water-supply Lines at 1st Floor in Progress.
• MEP Work in progress at 1st Floor 60% complete.
• MEP Work in progress at 2nd Floor 20% complete.
• Block masonry of 4th floor in progress.
• External & Internal Plaster in Progress.

Design & Planning Status (MEP):


• Consultants (Y. H. Asso & Ayub Asso) have again been asked to Submit
INFRA-STRUCTURE DESIGN for Expansion Project.
• M/s Habib Fida Ali being followed-up for submission of Dumb Elevator
Design from Surgical Suite (4th Floor) to CSSD (5th Floor). Architect visit
of CSSD and related queries answered.
• Workshop on Comprehensive MEP Design from 1st to 5th Floor to
begin from coming Week at Habib Fida Ali’s Office.
• Storm water Drainage’s revised scheme being prepared by Y. H. Asso.
• Working on Gen Set being done by Ayub Associates

PICTORIAL PROGRESS:

4th Floor

3rd Floor

2nd Floor

1st Floor
PROGRESS GRAPH
GENERAL WARD INTERIOR MOCK-UP
ROOM:
3D VIEW OF GENERAL WARD
PRIVATE WARD INTERIOR MOCK-UP
ROOM:
3D VIEW OF GENERAL WARD
BASEMENT OFFICES BLOCK

Pictorial Progress
Work progress is as under;
• Civil Works 95% Complete.
• False Ceiling Works 95% Complete.
• ID Works 95% Complete.
• Electrical Works 95% complete.
• HVAC System 95% complete
• Fire-fighting & Sprinkler 95% complete.
• I.T. Works 90% Complete.
• Furniture 80% Installed.

Target Dates
• Finance, HR, Marketing & MHEF Furniture
have been Placed.
• Work in Progress at Executive Areas &
Finance Marketing rework.