SINGUR BR

1
CONTENTS
Ser Content Page
1 Site Layout 3
2 Overall Progress 4
3 Work Progm 5
4 Substructure Progress 6
5 Substructure Bal Works 7
6 Superstructure Unloading/Stacking, Plan and Exec 8-11
7 Superstructure Launch activities and Status 12-14
8 Mil Manpower state 15
9 Distr of Manpower 16
10 Conduct Modalities for Launching 17
11 Singur Br Substructure plan 18
12 Substructure Important Lvls 19
13 AB-1 Progress 20
14 AB-2 Progress 21
15 Pier Progress 22
16 RW Sec Types 23
17 RWs Progress (1,2,3&4) 24-27
18 Culvert Progress 28
19 Apch Rds Progress 29
20 Misc Pts 30

21 Superstructure Launch Scheme 31 2


SITE LAYOUT

L
RA
IT
CH
)
uj
t

ER
as
M

V
RI
ds
ar
ow
(T
54

Delta Panels
N-

AB-1
Assy Site

Briefing Loc

Pier
AB-2

Gabion

D ir
Wall

nch
Lau
Monument
Loc
a
sm
a
Ch
am
ar
G
ds
ar
w
To
3
OVERALL PROGRESS
In Activity Overall CA Status In prog
Description A/U Qty Complete Bal
Prog Prog % Prog %
Contr Mob 19 Aug 2020 (M/S Faisal)

Pile Load Test No 1 1 - - 100


Work Started 10 Aug 2020

 1 x Batching Plt (25CM/hr)


Rigging of  1 x Excavator
Nos 38 38 - - 100
Working Piles
 2 x 25 Ton Cranes
Plt /
Fixing, Lowering &  1 x FE Loader
Concreting of Nos 38 38 - - 100 Machinery  1 x Flat Bed
Steel Cages  2 x 85 KVA Gen Set
 1 x Transit Mixer (7CM)
Pile Cap Nos 3 3 - - 100
 45 x Mil
 1 x Loya Cslt
Abutment Walls Nos 2 2 - - 100 Manpower  1 x Engr FWO
84%  1 x Mabey Adviser
 17 x Contr*
Pier Shafts Nos 3 3 - - 100
*Contr Manpower Detail
Transoms Nos 3 3 - - 100 Batching Machinery
PM F/Man
plt op

Retaining Walls & 1 2 2 3


Nos 4 4 - - 95
1 x Culvert
Ck Lab Svy TOTAL
Launching of Br Mtr 99 - - - 11
2 5 2 17
Apch Rds Mtr 120 - - - -
4
WORK PROGM

5
SUB STRUCUTE PROGRESS
Transom (AB-1) Access bund Transom (AB-1)

RIVER CHITRAL
 Transom for crane  Transom
concreted complete concreted

1 2 3 1 2 1 2 3

Bkfill till transom complete


3
Bkfill till transom complete

4 5 6 4 5 6
3 4
7 8 9 27 m 2 72 m 7 8 9

1 5 6 Transom (Pier) 1
0 11 12  Transom 0
11 12
1 concreted
1 1
3
14 15 7 8 3
14 15

Gabion
Works
Complete
N 45

 RW-1 (98%)  RW-3 (98 %)


 Sec-1 straight portion 10M: Wall complete  Sec-2 8M: Wall complete
 Sec-4 straight portion 15M: Wall complete  Sec-3 13M: Wall complete
 Sec-4 curve portion 15M: Wall complete  Sec-5 9M: Wall complete
 RW-2 (98 %)  RW-4 (98%)
 Sec-1 straight portion 10M: Wall complete  Sec-2 8M: Wall complete
 Sec-4 straight portion 15M: Wall complete  Sec-3 13M: Wall complete
 Sec-4 curve portion 17M: Wall complete  Sec-5 9M: Wall complete
6
SUB STRUCTURE BAL WORKS
Ser Description Scope of work Days Req Remarks
1 Monument • 1812CM Earthwork
10
• 18CM Concrete platform Current Progress 60%
• Rip rap/ Stone pitching

2 Culvert • 0.5Ton Steel fixing


4 Current Progress 50%
• 18 CM A3 Concrete
Post launch activity

3 Apch rds • 50 + 69 M Length


• 1196 CM WBM
14 N-45 work in hand
• 1196 CM Sub Base
• 360 CM Stone Dust Post launch activity
• 213 CM ACWC

4 Barriers & • Barriers 60CM A1


3
Backwalls Concrete Post launch activity
• Backwalls 18CM A3
Concrete

5 Solar Street lts Post Inauguration activity


• 12 x Solar Lts 3
6 Fencing
• 250 M total length 4 “

7 Ancillary Works
• TP paint, Cat Eyes, Bds 3 Post launch activity
7
PLAN FOR STACKING SUPER STRUCTURE
Apch tr for crane
P
As ane
sy l s
Ar
ea
Delta s
Water Channel
Fitting &
Pane so
m
ls an Launching

De nels
Tr

Pa
Area

l ta
Delta
Nose
Panels
Dir
Eqpt
Launch

Delta P
anels Top &
Bottom
Chords Deck Units Deck Units &
Tool Boxes

Delta Panels
g Rollers
Unloading Launchin
Area

AB-2 Transom

8
LAND AVAL FOR STACKING

25
M M 35 M
25
25 M Tow
ard
sG
ar a
mC
has
ma

15 M
45 M
20 M

 Area Req - 7 Kanals


 Area Aval - 10.6 Kanals

Singur Br

j)
ards Mastu
N-45 (Tow

9
UNLOADING/STACKING

10
STACKING LAYOUT – 8 JUL 21

Delta Panels

Briefing Loc Nose Eqpt

Transoms

Deck Units

AB-2

11
SUPERSTRUCTURE ACTIVITIES & STATUS
Ser Activity Days Req Period Status
Chk all eqpt: Panels,
1
Transoms, Braces,
Completed
Nuts, Bolts etc 2 9-10 Jul

Assemble Delta
2 Completed
Panels off site
7 10-17 Jul 22/22 panels assembled
Install & Test Hauling
3 Completed
Rams and Jacks 2 x adapters for jacks being
2 14-15 Jul rectified till 30 Jul
Place launching and
4 In Progress
const rollers, chk Plinths for Rear Rollers will
heights 2 28-29 Jul be const as per revised
scheme on 26 Jul
Place rollers on Pier,
5 Activities till Ser 5 will be
chk height, packing
and stability 1 30 Jul completed before arrival of
Mabey Rep
12
SUPERSTRUCTURE ACTIVITIES & STATUS
Ser Activity Days Req Period* Status

Assemble Nose Under Mabey Rep


6 2 1-2 Aug supervision

Assembling and
7 8 3-10 Aug “
launching of 22 x
Bays

Use Dismantled
8 1 11 Aug “
Launch Nose for Tail
Bays at rear

Boom Br into final


9 1 12 Aug “
posn, dismantle Nose

Jack Down Span 2


10 3 15 Aug “

13
SUPERSTRUCTURE ACTIVITIES & STATUS
Ser Activity Days Req Period* Status

Const Ramp on Under Mabey Rep


11 2 16-17 Aug supervision
Launching Bank &
Decking

Const Barriers
12 1 18 Aug “

Jack Down Span 1


13 2 19-20 Aug “

Deck Down Span 1, Fit


14 1 21 Aug “
Barriers

Total Days 35
14
MIL MANPOWER STATE FOR LAUNCHING

S Unit Offrs JCOs NCOs Sldrs Total Remarks


/
N
Master
1 104 EB - 1 1 6 8
Trainers

2 35 LBBE - 1 2 22 25

3 177 BBE 1 1 3 3 8

4 479 BBE - 1 1 - 2

2 - 2
5 10 EME - -

Total 1 4 10 32 45
15
DISTR OF MANPOWER (45)

S Party/Gp Offrs JCOs NCOs Sldrs Total Remarks


/
N

1 Launch Party 1 1 2 10 14
No 1

2 Launch Party - 1 2 10 13
No 2

3 Launch Party 1 2 8 11
(Res)
Deficiency will
4 Security/ - 1 4 2 7 be adjusted from
Ser 3
Adm/Misc

Total 1 4 10 32 45

16
CONDUCT MODALITIES FOR LAUNCHING
 Engr Imran from FWO & 10 x Master Trainers from 104 EB of Delta Br
Launching, reached Chitral on 15 Jul 21
 From 15 Jul to 25 Jul, Tps from 35 LBBE, 177 BBE, 479 BBE & 10 EME
were trained by a/m Trainers. Training incl lectures, dry practices and
actual assy of Delta panels
 This period from 15 Jul to 25 Jul also include Off site assembling of
complete 22 x Delta Panels and ready for launch. Launching eqpt/tools
were also completed from 104 EB and Rwp during this period
 From 25 Jul to 30 Jul, all activities before arrival of Mr Morgan ex Mabey
Br (Site Advisor) be completed. These incl const of rear rollers plinths as
per revised scheme and detailed chk & layout of Nose Eqpt
 Mil Str present at site for launching were further segregated as per req
parties (3 x parties of 1 + 2 + 10 each) and were trained accordingly
 Mr Morgan ex Mabey Br to arrive at Chitral on 30 Jul 21 along with Mr
Asrar ex Jaffar Bros , further proceeding with launching procedures will be
carried out under his supervision and guidance from 1 Aug 21 to 21 Aug
17
SINGUR BR – PLAN

18
SINGUR BR – IMP LVLS
Ga
ra
-4 5 mc
has
N hm
a

Transoms Top lvl


1508.507

AB-2 Pile Cap Top lvl


AB-1 Pile Cap Top lvl 1502.169
1499.861 Pier Pile Cap Top lvl
1498.00
NSL BM
RD

19
ABUTMENT-1 (99%)
 Pile Cap (100%)
 Dim : 11 x 7.3 x 1.5 M
 Fixed Steel: 15.31 Tons
• (H25,H20,H12)
 Poured Concrete : 120.45 CM

 Abutment Wall (99%)


 Height : 4.5 + 2.8 M
 Fixed Steel : 21.094 Tons
 Poured Concrete : 143.7 CM

 Transom (100%)
 Dim : 11 x 2.2 x 1.2 M
 Fixed Steel : 3 Tons
 Poured Concrete : 24.2 CM

20
ABUTMENT-2 (99%)
 Pile Cap (100%)
 Dim : 11 x 7.3 x 1.5 M
 Fixed Steel : 15.31 Tons
• (H25,H20,H12)
 Poured Concrete : 120.45 CM

 Abutment Wall (99%)


 Height : 5.007 M
 Fixed Steel : 12.31 Tons
• (H20,H16,H12)
 Total Concrete : 146.39 CM
 Poured Concrete : 135 CM

 Transom (100%)
 Dim : 11 x 2.2 x 1.2 M
 Fixed Steel : 3 Tons
• (H16,H12)
 Poured Concrete : 24.2 CM

21
PIER (100 %)
 Pile Cap (100 %)
 Dim : 11 x 4.26 x 1.5 M
 Fixed Steel : 8.729 Tons
• (H20,H25)
 Poured Concrete : 70.29 CM

 3 x Pier Colms (100 %)


 Height / Dia : 9.176 / 1.2 M
 Fixed Steel : 7.786 Tons
• (H32,H16)
 Poured Concrete : 31.13 CM

 Transom (100 %)
 Dim : 11 x 2.5 x 1.31 M
 Fixed Steel : 3.812 Tons
• (H20,H16,H12)
 Poured Concrete : 33.11 CM

22
RW SECS TYPES

23
RW-1 (99 %)

4.9M
5.5M 5.6M

9.5M

 Sections incl : Sec 1 & Sec 4

 Length of Straight portion : 25 M


RW-1
 Length of Curved portion : 15 M
 Steel Progress : 38.33 / 38.33 Tons (100%)
• (H20,H16,H12)

 Concrete progress : 3355 / 375 CM (98%)


24
RW-2 (99 %)

4.3M
5.5M

9.7M

 Sections incl : Sec 1 & Sec 4

 Length of Straight portion : 25 M

 Length of Curved portion : 23.5 M


 Steel Progress : 35.9 / 35.9 Tons (100%)
RW-2
• (H20,H16,H12)

 Concrete progress : 355 / 378 CM (98%)


25
RW-3 (99 %)

2.8M

6.7M
7.8M

 Sections incl : Sec 2, Sec 3 & Sec 5


 Length of Straight portion : 30.8 M
 Length of Curved portion : 0 M
 Excavation : 200.8 / 251 CM (80 %)
RW-3  Steel Progress : 23.5 / 23.5 Tons (100%)
• (H20,H16,H12)

 Concrete progress : 201 / 211 CM (98%)


26
RW-4 (99%)

2.8M

6.5M
7.8M

 Sections incl : Sec 2, Sec 3 & Sec 5


 Length of Straight portion : 30.8 M
 Length of Curved portion : 0 M
 Excavation : 251 / 251 CM (100%)
RW-4  Steel Progress : 21.9 / 21.9 Tons (100%)
• (H20,H16,H12)

 Concrete progress : 201 / 211 CM (98%)


27
CULVERT ON WATER CHANNEL ( 50%)

Abutment-2

 Steel Progress : 0.25 / 0.5 Ton


• (H12,H10)

 Concrete Progress : 9 / 18 CM

28
APCH RDS (35%)

 Length of Apch Rds : 50 + 69 M


 Backfill Progress: 80%
 797+577 = 1012/1373 CM
 Layers in 30cm compacted
 Subbase Progress: 0%
 1196 CM (30cm thickness)
 WBM Progress: 0%
 : 1196 CM (30cm thickness)
 Stonedust Progress:
 360 CM
 ACWC Progress: 0%
 213 CM (5cm thickness)
29
Misc pts

 PC-1 Approved, Rs 30Mn out of Rs 705Mn allotted to


XEN C&W Chitral in phase 1 Fin Yr 21/22 for payment
to 45 Engrs Div

 Payment has been made to the land owners, land aqn


process complete, original Docus handed over to 35
LBBE by DC Chitral office

30
SUPERSTRUCTURE LAUNCH
SCHEME

31
Plan

32
Stage 1-2

33
Stage 3-6

34
Stage 7-10

35
Stage 11-13

36
Mabey Proposed Progm

37