Professional Documents
Culture Documents
RS-2520SW-G-01585E Weekly Update - Sarku - 11082023
RS-2520SW-G-01585E Weekly Update - Sarku - 11082023
RS-2520SW-G-01585E Weekly Update - Sarku - 11082023
W84
EPCM Water Distribution Line & Storage System – TPBP
11th Aug 2023
HSE Update
Positive
Attention
Negative
HSE Activity
Positive
Attention
Negative
TOOLBOX MEETING
Attention
Negative
Main Water Tank Schedule
Positive
Attention
Negative
2023
Start Dur. Finish
WBS Activity July - August
Day # (Days) Day #
24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
1 Main Tank-1
1 1 Wall Panel Ring 9 24 1 24 n
1 2 Wall Panel Ring 10 25 1 25 n
1 3 Chemi Anchor 24 2 25 n n
1 4 N+8:24 26 1 26 n
1 5 Trush 26 1 26 n
1 6 Roof Sheet 26 2 27 n n
1 7 Geofabric 27 1 27 n
1 8 Liner 27 2 28 n n
1 9 Nozzle 28 3 30 n n n
1 10 Access Platform 30 2 31 n n
1 11 Piping Inlet 26 4 29 n n n n
1 12 Piping Outlet 27 3 29 n n n
1 13 Level Switch & Level Indicator 28 1 28 n
1 14 Nozzle Fabrication 24 4 27 n n n n
1 15 Pembongkaran Scaffolding Dalam
1 16 Pembongkaran Scaffolding Luar
1 17 Commissioning Tank 1
Main Water Tank Schedule
Positive
Attention
Negative
2023
Start Dur. Finish
WBS Activity July - August
Day # (Days) Day #
24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
2 Main Tank-2
2 1 Wall Panel Ring 6 1 1 1 n
2 2 Wall Panel Ring 7 2 1 2 n
2 3 Wall Panel Ring 8 3 1 3 n
2 4 Wall Panel Ring 9 4 1 4 n
2 5 Wall Panel Ring 10 5 1 5 n
2 6 Chemi Anchor 4 2 5 n n
2 7 Lis for Trush 6 1 6 n
2 8 Trush 6 1 6 n
2 9 Roof Sheet 6 2 7 n n
2 10 Geofabric 7 1 7 n
2 11 Liner 7 2 8 n n
2 12 Nozzle 8 3 10 n n n
2 13 Access Platform 10 2 11 n n
2 14 Piping Inlet 8 2 9 n n
2 15 Piping Outlet 8 2 9 n n
2 16 Level Switch & Level Indicator 9 1 9 n
2 17 Commissioning Tank 2
Progress of Project (Engineering– Phase I)
Positive
Attention
Negative
S-CURVE (Engineering – Phase I)
Positive
Attention
Negative
Progress of Project (Procurement)
Positive
Attention
Negative
S-CURVE (Procurement)
Positive
Attention
Negative
Progress of Project (Construction)
Positive
Attention
Negative
Progress of Project (Construction)
Positive
Attention
Negative
Attention
Negative
Progress of Project (Construction)
Positive
Attention
Negative
Progress of Project (Construction)
Positive
Attention
Negative
Progress of Project (Construction)
Positive
Attention
Negative
Attention
Negative
ENGINEERING (DED Phase I)
Positive
Attention
Negative
PROCUREMENT
ACTIVITY in THIS PERIOD
• Waiting confirmation of 5th delivery of remaining material Main Tank (nozzle) from TWS
Attention
Negative
Attention
Negative
Attention
Negative
Current Activity
Work Area Map & Construction Progress :
1. Install Main Water Tank
2. Tie In Pump BA 002 Breaker Tank Distribution
Plan Activity
Work Area Map & Construction Progress :
Install Main Water Tank
Legend :
No Progress Yet
On Progress
Plan Activity
Done
CONSTRUCTION
Positive
Attention
Negative
Attention
Negative
Legend :
No Progress Yet
On Progress
Plan Progress
Done
LONG SECTION PIPELINE PROGRESS
Positive
Attention
Negative
Legend :
No Progress Yet
On Progress
Plan Progress
Done
LONG SECTION PIPELINE PROGRESS
Positive
Attention
Negative
Legend :
No Progress Yet
On Progress
Plan Progress
Done
LONG SECTION PIPELINE PROGRESS
Positive
Attention
Negative
Legend :
No Progress Yet
On Progress
Plan Progress
Done
LONG SECTION PIPELINE PROGRESS
Positive
Attention
Negative
Legend :
No Progress Yet
On Progress
Plan Progress
Done
LONG SECTION PIPELINE PROGRESS
Positive
Attention
Negative
Legend :
No Progress Yet
On Progress
Plan Progress
Done
LONG SECTION PIPELINE PROGRESS
Positive
Attention
Negative
Legend :
No Progress Yet
On Progress
Plan Progress
Done
LONG SECTION PIPELINE PROGRESS
Positive
Attention
Negative
Legend :
No Progress Yet
On Progress
Plan Progress
Done
LONG SECTION PIPELINE PROGRESS
Positive
Attention
Negative
Legend :
No Progress Yet
On Progress
Plan Progress
Done
AREA OF CONCERN/ISSUE
Positive
Attention
Negative
• Installation of Main Water Tank (target commissioning Main Tank 1 at 5 Aug 2023)
• 5th delivery of remaining material nozzle Main Water Tank
ATTACHMENT
Positive
Attention
Negative