RS-2520SW-G-01585E Weekly Update - Sarku - 11082023

You might also like

Download as pptx, pdf, or txt
Download as pptx, pdf, or txt
You are on page 1of 33

RS-2520SW-G-01585E-SARKU - Weekly Update Report –

W84
EPCM Water Distribution Line & Storage System – TPBP
11th Aug 2023
HSE Update
Positive

Attention
Negative
HSE Activity
Positive

Attention
Negative

TOOLBOX MEETING

ELECTRICAL SIGN ASSEMBLY


Project Timeline (Baseline rev.F)
Positive

Attention
Negative
Main Water Tank Schedule
Positive

Attention
Negative

2023
Start Dur. Finish
WBS Activity July - August
Day # (Days) Day #
24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

1 Main Tank-1
1 1 Wall Panel Ring 9 24 1 24 n
1 2 Wall Panel Ring 10 25 1 25 n
1 3 Chemi Anchor 24 2 25 n n
1 4 N+8:24 26 1 26 n
1 5 Trush 26 1 26 n
1 6 Roof Sheet 26 2 27 n n
1 7 Geofabric 27 1 27 n
1 8 Liner 27 2 28 n n
1 9 Nozzle 28 3 30 n n n
1 10 Access Platform 30 2 31 n n
1 11 Piping Inlet 26 4 29 n n n n
1 12 Piping Outlet 27 3 29 n n n
1 13 Level Switch & Level Indicator 28 1 28 n
1 14 Nozzle Fabrication 24 4 27 n n n n
1 15 Pembongkaran Scaffolding Dalam
1 16 Pembongkaran Scaffolding Luar
1 17 Commissioning Tank 1
Main Water Tank Schedule
Positive

Attention
Negative

2023
Start Dur. Finish
WBS Activity July - August
Day # (Days) Day #
24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

2 Main Tank-2
2 1 Wall Panel Ring 6 1 1 1 n
2 2 Wall Panel Ring 7 2 1 2 n
2 3 Wall Panel Ring 8 3 1 3 n
2 4 Wall Panel Ring 9 4 1 4 n
2 5 Wall Panel Ring 10 5 1 5 n
2 6 Chemi Anchor 4 2 5 n n
2 7 Lis for Trush 6 1 6 n
2 8 Trush 6 1 6 n
2 9 Roof Sheet 6 2 7 n n
2 10 Geofabric 7 1 7 n
2 11 Liner 7 2 8 n n
2 12 Nozzle 8 3 10 n n n
2 13 Access Platform 10 2 11 n n
2 14 Piping Inlet 8 2 9 n n
2 15 Piping Outlet 8 2 9 n n
2 16 Level Switch & Level Indicator 9 1 9 n
2 17 Commissioning Tank 2
Progress of Project (Engineering– Phase I)
Positive

Attention
Negative
S-CURVE (Engineering – Phase I)
Positive

Attention
Negative
Progress of Project (Procurement)
Positive

Attention
Negative
S-CURVE (Procurement)
Positive

Attention
Negative
Progress of Project (Construction)
Positive

Attention
Negative
Progress of Project (Construction)
Positive

Attention
Negative

SUMMMARY UPDATE PER DICIPLINE:

1. CIVIL (progress is completed)


2. PIPING (progress is completed)
3. MECHANICAL
• Trusess, Roof Sheet, Access Platform, Geopabric progress has been completed for Main Tank 1
• Nozzle (Fabrication Model) and Liner target completion on 4 August 2023
• Breaker Tank 3 (progress is completed)
• Breaker Tank 4 (progress is completed)
• Breaker Tank Distribution (progress is completed)
4. ELECTRICAL (progress is completed)
5. INSTRUMENT
• On-going progress
Progress of Project (Construction)
Positive

Attention
Negative
Progress of Project (Construction)
Positive

Attention
Negative
Progress of Project (Construction)
Positive

Attention
Negative
Progress of Project (Construction)
Positive

Attention
Negative

• Main Water Tank (Tank 1)


S-CURVE (Construction & Installation)
Positive

Attention
Negative
ENGINEERING (DED Phase I)
Positive

Attention
Negative

ACTIVITY in THIS PERIOD


• Progress is Completed

ACTIVITY in the NEXT PERIOD


• Progress is Completed

PROCUREMENT
ACTIVITY in THIS PERIOD
• Waiting confirmation of 5th delivery of remaining material Main Tank (nozzle) from TWS

ACTIVITY in the NEXT PERIOD


• 5th delivery of remaining material Main Tank (nozzle)
CONSTRUCTION
Positive

Attention
Negative

HDPE Contract vs Actual:


CONSTRUCTION
Positive

Attention
Negative

HDPE Contract vs Actual:


WORK AREA MAP & CONSTRUCTION PROGRESS
Positive

Attention
Negative

Road Access Dorofanda, Road Access Wadubura


Previous Activity
Work Area Map & Construction Progress :
1. Tie In Pump BA 005 Soridoro River
2. Land Clearing Area near Ncangga River
3. install Pump BA 007 (Breaker Tank 3)
4. install Pump BA 008 (Breaker Tank 4)
5. Install Additional Breaker Tank for Support BA 005
6. Installation Temporary Distribution Panel and PLC Panel for BA 006
7. Install Grounding Route
8. Breaker Tank Distribution Has Been Arrived in Nangadoro Laydown
9. Installation Check Valve in Pump Nangadoro River (BA 005)
10. Install Grounding System (Camp Soridoro, Ngangga River, Wadubura River, Breaker Tank 3)
11. Pulling and installation Cable Low Voltage Cable (4C x 4 + E mm2)
12. Tie In Pump BA 006 Breaker Tank Solidoro
13. Tie In Pump BA 003 Ncangga River
14. Pulling cable Low Voltage Cable (4C x 16 + E mm2)
15. Fabrication Panel Support LCP

Current Activity
Work Area Map & Construction Progress :
1. Install Main Water Tank
2. Tie In Pump BA 002 Breaker Tank Distribution

Plan Activity
Work Area Map & Construction Progress :
Install Main Water Tank

Legend :
No Progress Yet
On Progress
Plan Activity
Done
CONSTRUCTION
Positive

Attention
Negative

ACTIVITY in THIS PERIOD


• Contruction Main Water Tank 1 (Install Roof sheet, Nozzle, Geopabric, Liner and Access Platform)
• Continue Pulling Cable Low Voltage Cable (3C x 2.5 mm2)
• Closing Punch List
• Commissioning Main Water Tank 1

ACTIVITY in the NEXT PERIOD


• Continue Construction Main Water Tank 2
• Continue install scaffolding at Main Water Tank for Support Working at Height
• Continue Punch List
LONG SECTION PIPELINE PROGRESS
Positive

Attention
Negative

LONG SECTION PIPELINE PROGRESS


(NANGADORO RIVER - BREAKER TANK 4 AT ROAD ACCESS SORIDORO)

NANGADORO RIVER - BREAKER TANK 4 AT ROAD ACCESS SORIDORO :


- HDPE Pipe 2" From Nangadoro River to Breaker Tank S01 (512 M base on gravity pipeline) Has Been Installed
- HDPE Pipe 3" From Breaker Tank S01 to Breaker Tank 4 (1474 M base on gravity pipeline) Has Been Installed

Legend :
No Progress Yet
On Progress
Plan Progress
Done
LONG SECTION PIPELINE PROGRESS
Positive

Attention
Negative

LONG SECTION PIPELINE PROGRESS


(NCANGGA RIVER - BREAKER TANK 4 AT ROAD ACCESS GEOTHERMAL)

NCANGGA RIVER - BREAKER TANK 4 AT ROAD ACCESS GEOTHERMAL :


- HDPE Pipe 2" From Ncangga River to Breaker Tank 3 (953 M base on gravity pipeline) Has Been Installed
- HDPE Pipe 3" From Breaker Tank 3 to Breaker Tank 4 (1474 M base on gravity pipeline) Has Been Installed

Legend :
No Progress Yet
On Progress
Plan Progress
Done
LONG SECTION PIPELINE PROGRESS
Positive

Attention
Negative

LONG SECTION PIPELINE PROGRESS


(WADUBURA RIVER - BREAKER TANK 3 AT ROAD ACCESS GEOTHERMAL)

WADUBURA RIVER - BREAKER TANK 3 AT ROAD ACCESS GEOTHERMAL :


- HDPE Pipe 1,5" From Wadubura River to Breaker Tank 3 (403 M base on gravity pipeline) Has Been Installed

Legend :
No Progress Yet
On Progress
Plan Progress
Done
LONG SECTION PIPELINE PROGRESS
Positive

Attention
Negative

LONG SECTION PIPELINE PROGRESS


(MAIN WATER TANK - CENTRAL AT ROAD ACCESS WADUBURA)

MAIN WATER TANK - CENTRAL AT ROAD ACCESS WADUBURA :


- HDPE Pipe 8" From Main Water Tank to Central (2055 M base on gravity pipeline) Has Been Installed

Legend :
No Progress Yet
On Progress
Plan Progress
Done
LONG SECTION PIPELINE PROGRESS
Positive

Attention
Negative

LONG SECTION PIPELINE PROGRESS


(JUNCTION POINT - HOTSPOT AT ROAD ACCESS WADUBURA)

JUNCTION POINT - HOTSPOT AT ROAD ACCESS WADUBURA :


- HDPE Pipe 8" From Junction Point to Hotspot (127 M base on gravity pipeline) Has Been Installed

Legend :
No Progress Yet
On Progress
Plan Progress
Done
LONG SECTION PIPELINE PROGRESS
Positive

Attention
Negative

LONG SECTION PIPELINE PROGRESS


(MAIN WATER TANK - BREAKER TANK DISTRIBUTION AT ROAD ACCESS DOROFANDA)

WADUBURA RIVER - BREAKER TANK 3 AT ROAD ACCESS GEOTHERMAL :


- HDPE Pipe 8" From Main Water Tank to Breaker Tank Distribution (947 M base on gravity pipeline) Has Been

Legend :
No Progress Yet
On Progress
Plan Progress
Done
LONG SECTION PIPELINE PROGRESS
Positive

Attention
Negative

LONG SECTION PIPELINE PROGRESS


(BREAKER TANK DISTRIBUTION - WEX02 AT ROAD ACCESS DOROFANDA)

BREAKER TANK DISTRIBUTION - WEX 02 AT ROAD ACCESS DOROFANDA :


- HDPE Pipe 8" From Breaker Tank Distribution to WEX02 (2039 M base on gravity pipeline) Has Been Installed

Legend :
No Progress Yet
On Progress
Plan Progress
Done
LONG SECTION PIPELINE PROGRESS
Positive

Attention
Negative

LONG SECTION PIPELINE PROGRESS


(MAIN WATER TANK - IP#03 (HOTSPOT 2) AT ROAD ACCESS DOROFANDA)

MAIN WATER TANK - IP#03 (HOTSPOT 2) AT ROAD ACCESS DOROFANDA :


- HDPE Pipe 8" From Main Water Tank to IP#03 (Hotspot 2) (300 M base on gravity pipeline) Has Been Installed

Legend :
No Progress Yet
On Progress
Plan Progress
Done
LONG SECTION PIPELINE PROGRESS
Positive

Attention
Negative

LONG SECTION PIPELINE PROGRESS


(JUNCTION POINT - IP#02 AT ROAD ACCESS WADUBURA)

JUNCTION POINT - IP#02 AT ROAD ACCESS WADUBURA :


- HDPE Pipe 8" From Junction Point to IP#02 (300 M base on gravity pipeline) Has Been Installed

Legend :
No Progress Yet
On Progress
Plan Progress
Done
AREA OF CONCERN/ISSUE
Positive

Attention
Negative

• Installation of Main Water Tank (target commissioning Main Tank 1 at 5 Aug 2023)
• 5th delivery of remaining material nozzle Main Water Tank
ATTACHMENT
Positive

Attention
Negative

Photos Activities Onsite