Using Fragnet in Delay Analysis Techniques

• Determine Design activities impacted by change

• Determine Construction activities impacted by change

• Create a fragnet

• Insert Fragnet and link it logically with the schedule

• Calculate the impact of change

• Document all information, calculations and Impact results


Practical Example
Primavera P6