Professional Documents
Culture Documents
#400 - 230 Volt in VAULTRms
#400 - 230 Volt in VAULTRms
1. Brief Intro
2. Applications
3. Meralco Supplied Transformers
4. Vault Requirements for Deadfront DT
5. Vault Requirements for Padmounted DT
13.8/7.96 kV
• 1-phase unit
• 2 deadfront primary
bushings
• Spade-type secondary
terminals
• Standard DT accessories
Transformers for the New Service Voltage
APPROVED LOCATIONS
Ground floor
Second floor
CONSTRUCTION
Reinforced concrete walls (‘buhos’), 150-mm
thick
Reinforced concrete floor (‘buhos’), 100-mm thick
when in contact with earth, 150 mm when above
another storey
No openings such as doors or vents to any part of
the building interior
Provided with 150-mm high door sill for liquid
confinement
No hoisting facility required
Presentation to private contractors 2006
APS/RRM/2006
Vault Requirement for Deadfront DTs
ACCESS
Doorway directly accessible from the outside of
the building
Hatchway may be used for basement and 2nd
floor installations
Dedicated personnel access doorway for
basement and 2nd floor
Clear and permanent access road leading to the
vault (at least 3.5 m if no crane is necessary; 6.5
m for installations requiring crane)
Where crane will be used, no overhang or canopy
in the immediate vicinity
Presentation to private contractors 2006
APS/RRM/2006
Vault Requirement for Deadfront DTs
VENTILATION
Louvered vents with a combined net area of
opening not less than 20 sqcm. Per kVA
For natural air ventilation, opening shall be on
different sides of the vault (one near the floor and
the other near the ceiling)
Where only one side is exposed to outside air,
exhaust fan and duct are required (one exhaust
per bank)
Fan shall be temperature controlled (ON at 40°C,
OFF at 36ºC) with by-pass switch for testing
Exhaust and intake fan for basement installations
Presentation to private contractors 2006
APS/RRM/2006
Vault Requirement for Deadfront DTs
HOISTING FACILITY
Ground Floor
(W) 5 m X (D) 4 m (W) 6 m X (D) 6 m
2 nd
Floor
X (H) 3 m X (H) 3 m
1st Basement
NOTE: W = Width
D = Depth
H = Height (Headroom)
ELECTRONIC
4500
POLYPHASE
METER
PRIMARY CABLE EQUIPMENT
CABINET
TRENCH EXHAUST ACCESS
FAN DOORWAY
2000
4000
MAIN
BREAKER
2000
EXHAUST
FAN
EXHAUST
DUCT
MAIN
BREAKER
3000
DEADFRONT
DT
LOW-VOLTAGE
Presentation to private contractors 2006 SERVICE CABLES
APS/RRM/2006
GROUND FLOOR 4000
TRANSFORMER VAULT 2000 2000
(SIDE ELEVATION)
EXHAUST
EXHAUST FAN
DUCT
DEADFRONT
1000
800
TO
DT
2000
LOUVERED
STEEL
1000
DOOR
SETBACK
ACCESS ROAD
(VARIES)
600
900
SERVICE
CABLES
STAIRCASE
2500
MAIN
4000
BREAKER
1500
ENTRANCE
EXHAUST
FAN
EXHAUST
DUCT
1000
800
TO
DEADFRONT
DT TRANSFORMER
ACCESS DOOR
1000
PRIMARY CABLE
300
900
REINFORCED
CONCRETE
600
LEDGE
400
1300
SECONDARY
700 700
CABLES SETBACK ACCESS ROAD
25 25 (VARIES)
GROUND
Presentation
ROD to private contractors 2006
APS/RRM/2006
2ND FLOOR
5000
TRANSFORMER VAULT
(FRONT ELEVATION) 1100 1400 1400 1100
EXHAUST
DUCT
MAIN
BREAKER
3000
DEADFRONT
DT
LOW-VOLTAGE
SERVICE CABLES
GROUND FLOOR
BUILDING WALL ELECTRONIC
POLYPHASE
METER
CABINET
STAIRCASE
PERSONNEL
ACCESS DOOR
1ST BASEMENT TRANSFORMER VAULT
(PLAN)
4500
HATCHWAY OPENING
2500
PRIMARY
CABLE
TRENCH
4000
MAIN
CIRCUIT
BREAKER
1500
STAIRCASE SECONDARY
CABLE
PERSONNEL TRENCH
ACCESS DOOR
Presentation to private contractors 2006
APS/RRM/2006
5000
1ST BASEMENT
TRANSFORMER VAULT
(SIDE ELEVATION)
ELECTRONIC
POLYPHASE ELEVATED
METER HATCHWAY WITH
CABINET STEEL COVER
SETBACK
(VARIES) ACCESS ROAD
EXHAUST
VENT
500
740
1000
400
600
700 700
25
MAIN
CIRCUIT
BREAKER
3000
SECONDARY
CABLES
LOWEST BASEMENT
GROUND
Presentation to private contractors 2006
ROD
APS/RRM/2006
Dead-front Padmounted
Distribution Transformer
APPROVED LOCATIONS
Ground floor
Second floor
CONSTRUCTION
Reinforced concrete walls (‘buhos’), 150-mm
thick
Reinforced concrete floor (‘buhos’), 100-mm thick
when in contact with earth, 150 mm when above
another storey
No openings such as doors or vents to any part of
the building interior
Provided with 150-mm high door sill for liquid
confinement
No hoisting facility required (for ground floor
installations)
Presentation to private contractors 2006
APS/RRM/2006
Vault Requirement for Deadfront DTs
ACCESS
Doorway directly accessible from the outside of
the building
Hatchway for basement installations
GROUND GRID
METER
CUSTOMER’S
MAIN TRANSFORMER
SECONDARY ACCESS DOOR
TRANSFORMER
CIRCUIT
BREAKER
PRIMARY
CABLE DUCTS
EXHAUST FAN
AND DUCT
TRANSFORMER TRANSFORMER
BANK #1 BANK #2
EXHAUST FANS
AND DUCTS
PRIMARY TRANSFORMER
CABLE DUCTS ACCESS DOORS
PLAN
Presentation to private contractors 2006
APS/RRM/2006
G/F Transformer Vault
EXHAUST FAN
AND DUCT
CUSTOMER’S
MAIN
SECONDARY
CIRCUIT
BREAKER
TRANSFORMER
ACCESS DOOR
TRANSFORMER
SIDE VIEW
PRIMARY SECONDARY
CABLE
Presentation
CABLEto private contractors 2006
DUCTS
APS/RRM/2006 DUCTS
2/F Transformer Vault
(Single Bank)
TRANSFORMER
ACCESS DOOR
TRANSFORMER HOISTING
I-BEAM
CUSTOMER’S
MAIN
SECONDARY
CIRCUIT
BREAKER
PERSONNEL
PLAN PRIMARY
Presentation to private contractors 2006 ACCESS STAIRCASE
APS/RRM/2006 CABLE DUCTS DOOR
2/F
Transformer CUSTOMER’S MAIN
Vault SECONDARY CIRCUIT
BREAKERS METER #1 METER #2
(Double Bank)
PERSONNEL
ACCESS DOOR
STAIRCASE
TRANSFORMER
ACCESS DOORS
PLAN
Presentation to private contractors 2006
APS/RRM/2006
2/F Transformer Vault
HOISTING I-BEAM
EXHAUST FAN
AND DUCT
TRANSFORMER
ACCESS DOOR
HOISTING
FACILITY
PERSONNEL
ACCESS
TRANSFORMER
DOOR
CUSTOMER’S
MAIN
SECONDARY
CIRCUIT
BREAKER
GROUND GRID
GROUND GRID
METER
AIR
INTAKE
VENT
TRANSFORMER
PERSONNEL
PLAN PRIMARY
Presentation to private contractors 2006 ACCESS STAIRCASE
APS/RRM/2006 CABLE DUCTS DOOR
2/F Transformer
Vault with CUSTOMER’S MAIN
SECONDARY CIRCUIT
METER #1 METER #2
Hatchway BREAKERS
(Double Bank)
PERSONNEL
ACCESS DOOR
STAIRCASE
HOISTING I-BEAM
HOISTING I-BEAM
HATCHWAYS
PLAN
Presentation to private contractors 2006
APS/RRM/2006
2/F Transformer
Vault with Hatchway
HOISTING I-BEAM
EXHAUST FAN
AND DUCT
CUSTOMER’S
MAIN HOISTING
SECONDARY FACILITY
CIRCUIT PERSONNEL
BREAKER
TRANSFORMER
ACCESS
DOOR
HATCHWAY
GROUND GRID
PERSONNEL
ACCESS GROUND GRID PRIMARY
DOOR CABLE DUCTS
HATCHWAY
OPENING
TRANSFORMER
STAIRCASE
SECONDARY
CABLE DUCTS
PLAN
Presentation to private contractors 2006 CUSTOMER’S MAIN
APS/RRM/2006 SECONDARY CIRCUIT
BREAKER
1/B Transformer
Vault with Hatchway
PERSONNEL
ACCESS
DOOR
AIR INTAKE
FAN & VENT
HATCHWAY
STAIRCASE
PERSONNEL
ACCESS ELEVATED
DOOR HATCHWAY
WITH STEEL
COVER
AIR AIR
INTAKE EXHAUST
FAN FAN
STAIRCASE
TRANSFORMER