Professional Documents
Culture Documents
Contract Implementation Under RA 9184
Contract Implementation Under RA 9184
CHANGE ORDER
covers any increase/decrease in quantities of
original work items in the contract.
HOPE or
Review by authorized
Contractor
Project representative
files Notice
Engineer/PE’s investigates
of Variation
representative proposed
Variation Order
Approval of Variation
Order by HOPE or Submission
authorized of Findings
representative
TIME FRAME FOR THE PROCESSING OF
VARIATION ORDERS
GENERAL RULE:
Under no circumstances shall a contractor proceed
to commence work under any Change Order or
Extra Work Order unless it has been approved by
the Head of the Procuring Entity or his duly
authorized representative.
EXCEPTIONS:
The Head of the Procuring Entity or his duly authorized
representative may, subject to the availability of funds,
authorize the immediate start of work under any
Change or Extra Work Order under any or all of the
following conditions:
Note:
Minimum first progress billing for NIA is atleast 20%
MC 35 s. 2021 :
Maximum progress billing for NIA is 90% for 100M & below
PROGRESS PAYMENT
When imposed?
and
Liable Persons:
Contractor /Consultants /Procuring Entity’s
Representatives (Project manager; Construction
Manager; Supervisors)/ Third Parties/Users.
Warranty Period:
- Effective for 1 year from date of issuance of
Certificate of Final Acceptance, to be returned
after lapse of said period
Form of Warranty:
- Cash or LC (Universal or Commercial Bank)
…….5% of TCP
- Bank Guarantee (Universal or Commercial
Bank)……10% of TCP
- Surety Bond callable on demand, OIC-
certified….30% of TCP
Implementation Provision (Sec 62.2.4 of IRR)
- Structural Defects/Failure occur the
applicable warranty period
- PE to undertake restoration or reconstruction
- PE entitled to full reimbursement, upon
demand, of expenses incurred by parties found
liable for defects
- Forfeiture of warranty securities posted
- Without prejudice to the filing of appropriate
administrative, civil and/or criminal charges
against responsible persons
CONTRACT ADMINISTRATION
FINALACCEPTANCE
COMPLETION Semi-Permanent
Structures = 5 years
Other Structures = 2
years
CONTRACT TERMINATION BY
DEFAULT, UNLAWFUL ACTS OR
INSOLVENCY
CONTRACT TERMINATION FOR DEFAULT,
UNLAWFUL ACTS OR INSOLVENCY
Guidelines on Termination of Contract per GPPB
Resolution No. 018-2004 dated Dec. 22, 2004
By the PE through the HOPE
• while the project is ongoing, negative slippage of
15% or more due to contractor’s fault
Effect of rescission
• confiscation by the PE of the performance
security and possible recommendation for
blacklisting. Payment will be based on quantum
meruit
OTHER INSTANCES WHEN PE MAY TERMINATE THE
CONTRACT
• The PE, by prima facie evidence, determines that
the contractor has engaged BEFORE or DURING
contract implementation, in unlawful deeds and
behaviors relative to contract acquisition and
implementation such as: corrupt, fraudulent,
collusive or coercive practices; drawing up or
using forged documents; using adulterated
materials, means or methods, or engaging in
production contrary to rules of science or trade;
and, any other act analogous to the foregoing.
By the Contractor
• PE fails to deliver, within a reasonable period of
time, supplies, materials, ROW or other items PE is
obligated to furnish