ISSUES AND ACTION PLAN

FOR
BELT CONVEYORS- CCS SECTION
Issues common to belt
• Old starter- All belt operated by A67 Model starter of wallancetown make .
Spare is originally not available. Safety system of starter don’t have requisite
reliability.
• Anti Roll Back Device – Presently using only one anti roll back fitted in one
gearbox for belt in gradient. Require double anti-rollback device for reliable
operation.
• Loop takeup tensioning arrangement- No spare gearbox of LTU available.
During breakdown LTU gearbox of running BELT is used.
• 1200mm belt structure - The bottom and top idler of Vishwa 1200 belt
running are old and required to be changed alongwith stool post and
brackets.
FLUID COUPLING
SNO TYPES AND NUMBER IN SPARE STATUS REQUIREMENT/ ACTION NEEDED
MAKE OPERATION
1 Afc 80 premium 06 03 Oil seal and bearing
2 AFC 71 07 02 oil seal, bearing impeller runner
3 WF7 03 01 All parts
FLUIDOMANT
4 WFHFD-7 02 01 All parts
fluidomant
5. Oil seals some of fluid coupling fitted with oil seals of Viton material oil seal
viton material and bush bearing replaced with And good quality bearings
ball bearing . Which is decreased fluid coupling
leakage problem and improved performance.
Safety Issues
• Fine dust get accumulated at belt structure and gallery. Which require
water spraying for dust suppression.
• Presently water spraying is done using RAW WATER in TC1, TC2 and
TC3 while for belt no TC4, TC5, TC6 AND TC7 , dauwty water supplied
to development section is used.
• The use of raw water sometimes hinder skip pocket operation while
that of dauwty water affect development section.
• So CCS require independent water supply system for spraying purpose
throughout belt circuit.
BELT SPECIFIC ISSUES
AND
ACTION NEEDED
Belt no TC1
• BTL 150kw double drive . Requirement
• 4 no A67 switches. 2 of them are • Spare driving drum.
retrofitted units with protection • Spare for gearbox BTL
system working properly. model like input shaft, all
• Installed in 2021 and stages holdback device,
bearing specific to
performance is satisfactory. gearbox- 1set.
• Less hour of mechanical • Spare of retrofitted
breakdown. starter
Belt no TC2
• Vishwa 2x110KW Requirement
• 3 NOS of A67 switch • One extra switch transportation
• Single feeder to GEB • Required grouting work
• Tail end drum changing with tail
Issues structures.
• No spare switch • Cleaners
• Drive gearbox movement • Extra feeder required in case of
• Tail drum of shell 1300mm causes belt electrical breakdown. Cable
adjustment more frequently. length of 500mtr
• Less clearance b/w bottom roller and
ground. So belt cleaning required frequently
Belt no TC3

• Vishwa 2x110kw Requirement


• 2 nos of A67 switches and 1 • One 110 kw motor to make it
nos P70 switch for tensioning. double drive.
• Drive head performance good. • Spare trunking cable from
transformer to GEB.
• Presently running in single
drive operation.
Belt no TC4 and TC5
• Vishwa 2x150kw
• 2 nos of mineline switch in operation Requirement
for drives. • Daily basis drain cleaning at drive
• Also 3 nos of A67 switches as spare. and jib post.
• Procurement of spare of Mineline
Issues
starter.
• The drive head is installed at soft stone not on
hard stone. Accumulation of water from drain • Need more holdback device as
affect the grouting of base. spare for both driving gearbox.
• No spare of Mineline starter. • Need spare discharge pulley for
• At present only one holdback is installed. TC5
Failure of it cause belt reversal and jib post
arm bending.
• No spare discharge pulley- pulley shaft broken
Belt no TC6
• Vishwa 1200mm, 2x110KW Requirement /action needed
• 3 nos of A67 starter for drive and LTU • Blasting at jib post
winch
• Regrouting of gearbox base frame
Issues • Periodic water spraying throughout
• Roof and discharge drum clearance is 2feet gallery.
approx. so changing jib post drum is difficult.
• A drain need from TC6 belt tail end
• One gearbox has movement.
to 3a rise gallery to prevent water
• There is incidence of fire in between belt
gallery due to dust particle accumulation and
accumulation
belt structure friction.
• Frequent water accumulation at it tail end
affect belt operation.
Belt no TC7 & 6 rise bunker chute
• Vishwa 1200mm, 2x150KW Requirement /Action needed
• 4 nos of A67 starter for drive and LTU winch • Periodic water spraying
• 2 nos of mineline starter under installation throughout gallery.
Issues • Belt transported at tail end
• There is incidence of fire in between belt gallery for change. Manpower
due to dust particle accumulation and belt
structure friction. required
• All Belting is due for change. Last changed in 2020. • Required spring resilient
• Discharge above 6 rise bunker is directly at chute coupling for 150kw gearbox
causing problem especially during stone cutting
from face.
• No spare spring resilient coupling presently
running with gear coupling.
Belt no D17 B/G-1 & B/G-2
• Vishwa 1200mm, 2x110KW
• 4 nos of A67 starter for drive and LTU Requirement
winch • Fencing material required for 1 km
belt length.
Issues
• Water management from face to be
• No fencing throughout belt
continued and drive installation can
• Accumulation of water at B/G-2 drive be done before water influx in
disturbed foundation of drive and bearing development gallery for next panel.
of pulleys. Vibration arrested through extra
clamping and welding and anchoring. • Transformer should be provided as
• Significant voltage drop during starting of near possible to drivehead with
drive when it was singely feeded at 550V. It double feeder arrangement.
improved after drive was double feeded by
2 separate transformer.
Based on above analysis there is urgent requirement of
following materials
Sno Materials Remarks
1 Mineline starter spares For TC4, TC5 and TC7
2 A67 Retrofitted starter spares For TC1
3 Belt fencing material- 1km For longwall level belts
New starter switch For replacement of old starter
Spring resilient coupling For BTL- 150KW and Vishwa- 150kw
Holdback device For BTL- 150KW and Vishwa- 150kw
1200mm belt structures For all belt structure changing
Discharge pulley as spare For TC4 and TC7
Gearbox spares all stages For BTL- 150KW
Driving drum as spare For BTL- 150kw
2 inch pipe for water spraying Throughout belt circuit
THANK YOU