DAILY REPORT Nguyen Minh Hiep

Sep 04th(Mon), 2023


1. ORDER STATUS in SEP.
Amount Remarks

New PO s $0

Sales $0

Total Sales in 2023 $314,853.00

2023 Viettel Sales Status

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Total

Plan $0 $0 $172,000 $0 $130,000 $0 $349,500 $300,000 $300,000 $0 $0 $0 $1,251,500

New PO
$74,853 $240,000 $314,853
amount

Actual $0 $0 $0 $0 $0 $74,853 $0 $240,000 $314,853


DAILY REPORT
2. F/UP WORK
Items Progress Status Remarks

1. Viettel 32T32R 1 set salt spray test


Start date: 09/04 => 10/04
Viettel RRU 2. 300 set quotation: Submitted
32T32R old Total amount: $610.60
version Total tool cost: $499,200
Wait feedback of customer

Required docs may update for Gen 10 logic cage


- DFMA (Design for manufacturing and assembly)
- APQP (Aristocrat project quality planning)
Aristocrat - PPAP (Production part approval process) (Control plan)
- Process Flow Chart
- PFMEA (Product failure mode and effects analysis)
 Due date: 09/06

VIMA Study and make BOM of 6 part cable 250: Submitted


DAILY REPORT
2. F/UP WORK
Items Progress Status Remarks

Viettel RRU Quotation of 20 sets


64T64R - Price: $8,605/set

Viettel Antenna Quotation of 4 sets


32T32R - Price: $3,332

Quotation: Submitted
Full assy gear box: $111.60 (for 8000 units first)
Flange: $3.65 – 1st - Portable Winch may
Portable Winch $4.95 – 3000 pcs – 2nd visit on Oct.04
$4.75 – 8000 pcs
Tooling cost: $51,000
DAILY REPORT
2. F/UP WORK
Items Progress Status Remarks

Meeting with Michael Ballou:


1. PW will complete drawing and send SJ to review this week
2. Tool building spend 10 weeks: 8 weeks for design, 2 weeks for fabrication
3. PW possible to issue PO on Oct 1st , next process is tooling and sample
making
4. PW plan to visit SJ to audit on first week of Dec
5. PW will assess both of pre-assembly and assembly product at SJ facility
Portable Winch and a send sample
6. Mike will ask PW for qualification requirement docs
7. PW is developing electric winch and Mike will follow to get other RFQ of
PCB, drum, heatsink
8. EAU of gasoline winch will not affect by electric winch, electric winch will
more competitive than gasoline, every people will use
9. Mike will ask PW for WI reference and test required of winch
10. Mike’s goal to reach WARN Industries base on business with PW
DAILY REPORT
3. OTHERS (outstanding payment…..)
OUTSTANDING PAYMENT IN 2022

Shipment
PO Invoice Part name Total price Shipment date Due date
Q’ty
20230619
02-2023/HNE- 40 VND 5,640,000,000 20230704 20230915
SEOJIN 00000824 Viettel 32T32R ($240,000)
20230815