Professional Documents
Culture Documents
Works Procurement
Works Procurement
October 2018
By Frew Bekele
1
Contents
1. Procurement Methods
2. Procurement Types
3. Procurement Procedure
4. Basic Contract Types
5. Bidding Documents
6. Evaluation And Qualification Criteria Framework
2
WORKS CONTRACTS
3
Nature and Complexity of Works
Size and Duration of Contract
Degree of Definition/Risk/Uncertainty
Status of Design
Technical/Supervisory Resources of
Employer
Budgetary/Financing/Borrowing constraints
Previous experiences of employer
Standard Documents of Funding Agency
7
E. Types of Works Contract
Basic
Lump Sum (all-inclusive Price)
Unit Rate (paid against measured work)
Cost plus (paid against constituent
inputs)
Fixed fee
Percentage fee
Variable (incentive) fee
8
E. Types of Works Contract
Lump Sum
Uses
Small, well-defined works/ building of
short duration
Large industrial process plants (Turnkey)
9
E. Types of Works Contract
Lump-sum(cont)
ADVANTAGES
Fixed sum for budgeting
Easy to administer
Little/No measurement
Less documentation
DISADVANTAGES
Inflexible to changes/High Risk
10
E. Types of Works Contract (cont..)
11
E. Types of Works Contract (cont..)
12
E. Types of Works Contract (cont..)
13
E. Types of Works Contract (cont..)
Cost Reimbursable Plus fee (Cost
Plus) Cont…
Advantages
Early mobilization and rapid start
Contractor assumes little or no risk
Disadvantages
Inappropriate (in basic form) for competitive
bidding (see target cost)
With fixed fee, no incentive for quality or timely
work
Additional employer staff needed to monitor costs.
14
F. Other Types of Works Contract
15
F. Other Types of Works Contract (cont..)
16
F. Other Types of Works Contract (cont..)
Turnkey
For complex industrial process plants, etc.
Similar to design and Build. Contractor for the design,
as well as construction.
Contractor delivers working package for specified end
product
Normally LS with price adjustment for long duration
17
F. Other Types of Works Contract (cont..)
BOT/Concessionary
For revenue earning projects (toll roads, power, water,
etc.)
Essentially concessionary Turnkey contract
Useful when owner has limited budget or borrowing
capacity
Costs and risks borne by BOT investors
18
Some questions for preliminary
discussion
19
4. What are BDs and their
objectives;
• What are BD?
• How Bidding Documents are designed?
20
3. Bidding Documents
21
A. Objectives of BDs
22
A. Objectives of BDs Cont ..
23
B. Parts of SBD
24
B. Parts of SBD Cont…
25
B. Parts of SBD Cont…
Section 1 - ITB;
Section 2 - BDS;
Section 3 - EQC;
Section 4 - Bidding forms;
Section 5 – Eligible countries;
26
B. Parts of SBD Cont…
Part 3 – Contract;
Section 7 – GCC
Section 8 – SCC
Section 9 – Contract Forms;
27
C. Contents of Each Section of BD
Section 1 - ITB
Provides information to help bidders prepare their bids;
ITB contains provisions that are to be used without
modifications;
ITB will not be part of the final contract;
It is procedural & instructional information used during
bidding process.
Evaluation and comparison of Bids;
Award of contract
28
C. Contents of Each Section of BD
29
C. Contents of Each Section of BD
Section 3- EQC
This section contains all the criteria that the employer shall
use to evaluate bids & qualify bidders;
This is again to modify ITB and provide figures and details
for the qualification criteria to the particular contract.
Evaluation;
30
C. Contents of Each Section of BD
31
C. Contents of Each Section of BD
32
C. Contents of Each Section of BD
In ICB contracts:
33
C. Contents of Each Section of BD
Specifications;
Drawings;
Supplementary information;
BoQ;
34
C. Contents of Each Section of BD
Section 7: GCC
GCCs are standard, that have been evolved over years;
The rights and obligations of the parties to the contract is
defined GCCs;
FIDIC Conditions of Contract is use for major engineering
contracts (different models available for different contract
modes);
PPA has also its own GCC
FDIIC conditions of contract is suitable for admeasurements
contracts;
GCCs are not modified
35
C. Contents of Each Section of BD
36
C. Contents of Each Section of BD
Section 9: Contract Forms
This section contains forms which, once completed, will form
part of the contract.
This forms are:
Letter of Acceptance;
Contract agreement;
Performance Security;
Advance payment Security;
All these forms are not filled and submitted during bid
submission but used while drafting the contract
37
C. Contents of Each Section of BD
38
4. Evaluation and Qualification
Criteria Framework
39
A. Qualification Criteria
General Qualification
Legal Status
Eligibility
Technical Examination
Major Equipment
Key personnel
Proposal of work methods and programs
Historical Contract Non-Performance
History of Non-Performing Contracts
Pending Litigation
40
A. Qualification Criteria cont…
Financial Situation
Historical Financial Performance
Current Contract Commitments
Annual Construction Turnover
Experience
General Construction Experience
Specific Construction Experience
41
A. Qualification Criteria Cont…
General Qualification
Technical Examination
Historical Contract
• Major Equipment
Non-Performance
• Key personnel
• Proposal of work
Financial Situation methods and programs
Experience
42
B. Qualification criteria frameworks
PPA
First with 2006 standard bidding documents
(prepared as user guide)
Current January 2016
WB and other financers
B. Qualification criteria frameworks cont…
Required Evidences
Documents which confirm the
contractor is in the industry to
confirm the above
B. Qualification criteria frameworks cont…
Required Evidences
Confirmation from the Client and
others
Audited report prepared by independent
auditor not accountant
Summary Questions
1. Identify standard and particular parts
of the BD
2. Which sections of the BD will be part
of the resulting contract agreement?
3. Can technical specifications be
standardized?
48
Summary Questions
5. Do you agree?
EQC will be part of the resulting
contract.
BDS is can not be modified.
49
Summary Questions
6. An item not listed in the Price Schedule shall
be assumed to be not included in the bid,
and provided that the bid is substantially
responsive, the average price of the item
quoted by substantially responsive bidders
will be added to the bid price and the
equivalent total cost of the bid so
determined will be used for price
comparison. What risk would this provision
in the BD have?
50
Summary Questions
6. Discuss the advantages and disadvantages
of Prequalification
7. Discuss Common mistakes in BD
preparations
51