CCN2 Platform

5.1 CCN2 Status & Plan


IT Infrastructure and
Technology meeting, DG TAXUD, A5
21st January 2016,
Brussels
CCN2 R1
Roadmap

• Release 1: On-going
• Implementation of the CCN2 SOA (web service) functionality of
CCN2 platform (Pilot)
R1 – Core + non-functional requirements (R1)
CCN2 • Production: Q3 2017
platform + • Release 1.5: Starting
SOA • Additional transformations (e.g. EDIFACT <-> XML)
functionality
• Managed File Transfer (MFT)
• Oracle 11g  12c
• Ready for Conformance testing: Q4 2016

• Release 2: Starting
• CCN/CSI integration
• CCN/CSI migration (long migration expected)
R2 – CSI/MFT • CCN/CSI CCN2 message transformation
• Phase out of the CCN/CSI Gateway
(CSI protocol supported as long as needed)
• Production: Q1 2019

• Release 3: Provisional
R3+ MDM • Master Data Management (MDM)
2
• Additional extensions to CCN2 platform
• Production : TBD
CCN2 Status
Roadmap

2015 2016 2017 2018 2019

Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4

CD Systems
Planning Specifi-
cations Construction Phase
Deployment & Legend
Configuration
CCN2
=
Specifications Validation by
NA
CCN2 pSAT/ Depl
Release 1

Build & FAT SAT


oy-
CCN2-DEV
Test ment
CCN2

Activity
Test Plans &
Specifications
CCN MS connectivity ITSM2 Lot 1
MS CT and activity
CCN2 Platform Planning

preparation, configuration & Deployment


testing
X-DEV
Release 1.5

Specificati activity
ons
CCN2

CCN2 F S
Build & A A
test T T
Release 2

Specifications
CCN2

Build & test FAT pSAT/ SAT MS


Deployment

MS Migration
CCN2 R3

Specifi-
cations MS
Build & pSA Depl
test FAT T/ ???? oyme
SAT nt
3
CCN2
Major achievements

• CCN2 Pilot Playground is available for 4 NA participating in


the testing.
• Extension of the PGS Availability – June 2016
• CCN Pilot Testing is ongoing with NAs (AT, DE, IT, PL) and
with TAXUD Customs Decision Pilot
• REQ and SPM documents accepted by NAs
• Functional Specification finalized and sent for review –MS
review ongoing
• Number of design concerns were analysed, solved and
documented – only a few left
• Conformance Test Specification (TDS CT) and Conformance
Test Plan (ATP CT) finalized and send for review – MS
review ongoing
• CCN2 testing and operation teams are ready
• Development ongoing, preparing for FAT
4
CCN2 Release 1
Work in progress

• Drafting the final version of Release 1 Design Specification


• Drafting of the final version or Release 1 Technical
Specification
• "Last mile" implementation of CCN2 Release 1
• Unit and integration testing of Release 1
• Preparing the detailed planning for Releases 1.5 and 2.0 is
on-going
• Design of the CCN2 CSI adapter started (Release 2)
• Installation of the CCN2-related infrastructure in TAXUD DC
has started
• SE on-boarding (PGS)

5
CCN2
Status Summary

• CCN2 PGS availability extended until June 2016


• Implementation of the Release 1 to be finalised in coming
weeks.
• Number of document reviews, some already done some are
coming, review of a few deliverables postponed
• Installation of the CCN2 infrastructure in TAXUD DC is
ongoing.
• Design of the CCN2 Release2 which includes legacy CSI
interfaces is starting

6
Questions