D7264

NFXP PROJECT
SUB-CONTRACTOR
DELIVERABLES
VDCS & IDOCS PROCESS

VDCS iDocs Link


VDCS & iDOCS ACCESS
REQUESTING FORM
iDOCS NOTIFICATION EMAIL
iDOCS IT TEAM EMAIL TO ACCESS
iDOCS INSTRUCTION FILE TO
ACCESS THE iDOCS LINK
iDOCS APPLICATION SCREEN
&
RETURNING THE REVIEWED DOCUMENTS
iDOCS APPLICATION SCREEN
&
RETURNING THE REVIEWED DOCUMENTS
ENGINEERING DOCUMENT
TECHNICAL COVER PAGE

This will be singed by Sub-contractor. This section will be


singed by McDermott
ENGINEERING DOCUMENT
REVISION HISTORY MAINTENANCE
ENGINEERING DOCUMENT
DRAWING COVER PAGE
SUB-CONTRACTOR DELIVERABLES
RULES

1. Make sure the document titles reflect same as per SDRL file

2. Fill appropriate Revision and Revision Descriptions on the Cover page

3. Make sure the Footer’s on all pages except the cover page

4. Make sure the Date & Signature’s are updated with no mark-ups and not digitally protected

5. Kindly address all emails to D7264.DDM@mcdermott.com “D7264 Document Control”


QATAR GAS COMMENTS
REVIEW SUMMARY
CRS FORMATS

McDermott Comments to be added in a


separate tab with the same header row
SUB-CONTRACTOR DELIVERABLES
CLASSES
CLASSES

IFR IFA AFC AS-BUILT


CLASS 1
Issued For Review Issued for Approval Approved for AS-BUILT/Final
Construction Issue

CLASSES
IFR IFA AFC AS-BUILT
CLASS 2
Issued For Review Issued for Approval Approved for AS-BUILT/Final
Construction Issue

IFR IFA AFC AS-BUILT


CLASS 3
Approved for AS-BUILT/Final
Construction/Issued for Issue
Information
SUB-CONTRACTOR DELIVERABLES
REVISION’S
Issued for Review
REV. B, C, D, etc. Approved for Constructi
on (AFC) or Issued for
d for Purchase (IFP)
Rev. 00, 01, 02 etc. Information (IFI) or Issue

Next Alphabet Issued for


(Based on the previous Approval
Revision Review Code )
Rev. 50, 51 As-Built / Final Issue

Rev. Cancelled
Rev. 00 or Next Numeric
EDMS)
Rev. X VOID (to be updated in

Please note : There is no Rev. A in these projects


SUB-CONTRACTOR DELIVERABLES
REVIEW CODES

Company Codes
Accepted / Reviewed
There are no comments
A
Accepted / Reviewed with minor comments

Reviewed with comments


B Document contains minor errors that require
correction but would have no negative impact on
the work based on its content.

C
Document contains errors
of a technical nature that,
although not significant,
could negatively impact
Rejected
work based on its content.

No Review
D Significant deficiencies and errors to the
extent that a complete re-work is
required
Document does not require
APPROVAL or has been
returned without Review I
SUB-CONTRACTOR DELIVERABLES
REVISION CONTROL
SUB-CONTRACTOR DELIVERABLES
REVISION CONTROL
SUB-CONTRACTOR DELIVERABLES
REVISION CONTROL
SUB-CONTRACTOR DELIVERABLES
REVISION CONTROL
SUB-CONTRACTOR DELIVERABLES
REVISION CONTROL
SUB-CONTRACTOR DELIVERABLES
PROJECT INFORMATION HANDOVER (PIH)
REQUIREMENTS: VENDOR DOCUMENTATION

 COMPANY Project Information Handover Procedure: PRJ-PJL-PRC-006


 Vendor shall deliver native files for all Vendor Integrity Critical deliverables as defined in Appendix 09 of PRJ-PJL-PRC-006
 Installation, Operation and Maintenance (IOM) Manuals form part of the Vendor Engineering Documentation. Template QG-PIH-IM-05-T001
shows the structure that shall be utilized for Vendor IOM Manuals.
 A standard workshop manual shall be provided for each modified equipment. Template QG-PIH-IM-05-T002 shows the structure that shall be
utilized for the Workshop Repair Manuals.
 Each Vendor shall prepare a MRB for the purchased equipment or materials in accordance with the Purchase Order requirements. Vendor
shall be responsible for maintenance of the complete MRB prior to handover (including all third parties).Template QG-PIH-IM-05-T003 shows
the structure that shall be utilized for the MRB contents. MRB index shall not be altered, sections which are not applicable shall be marked as
NA in MRB Index.
 The Export control documents contains documentation related to shipments of the purchased equipment. Template QG-PIH-IM-05-T005
shows the structure that shall be utilized for Export Control document deliverables.
 Fabrication Record Book (FRB) needs to be compiled inlines with Qatargas Template QG-PIH-IM-06-T002 - Rev01 - Fabrication Records Book.
SUB-CONTRACTOR DELIVERABLES
APPENDIX 04
SUB-CONTRACTOR DELIVERABLES