X’Trapolis 2.

0 Planning
Report
Week - 50
X’Trapolis 2.0

Project
Project Status Engineering Org Overview

© ALSTOM SA 2021. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is
provided without liability and is subject to change without notice. Reproduction, use, alter or disclosure to third parties, without express written authorisation, is strictly prohibited. 2
X’Trapolis 3rd Nov – NO GO
22nd Nov - GO 20th Jan 3rd Jun 10th Oct

SGR IGR PGR CGR

Key Deliverable Total Plan Till Done Trend Remarks Ref


Date
RSL2 Allocation 23 23 23 Allocation Completion-98%
Train lab validation TRS
TRS Allocation 16 16 15 Pending – To close on
Dec’21

TPS-(SPL) 33 33 33
Coupler & HVAC -90% CC
CBC-(SPL) 33 33 0 PACIS ,Brakes, Battery are
<50 % CC
Coupler BA closed
BA-(SPL) 33 20 1 Delay in CBC’s impacts BA
Key Concerns
DR OK- 14 & NOK -17
SDR 31 31 31 26 –ESLI High Critical
Points • Supplier on boarding on time
TD Installation • Bogie Design Change as per AS 7509 , AS 7519
250 250 205 M3 Maturity by End-Dec’21 Impacts the maturity of installations.
M3
• Delay in D&S Inputs impacts M3 Maturity.
RIT Installation
86 86 0 M3 Maturity by Jan’22
M3
EIS 110 110 35 Delay in EIS from Supplier
© ALSTOM SA 2021. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is
provided without liability and is subject to change without notice. Reproduction, use, alter or disclosure to third parties, without express written authorisation, is strictly prohibited. 3