Project Update Dashboard – Mobile App

• Project Objective: To develop a mobile application


for future and current customers of SoliD

Iteration 4 • Project Time: The app is iterating over many two


week iterations with releases delivered regularly
• Project Updates:
• Issues fixes from last release
• Positive feedback for beta testers
• With PO acceptance, next release may go out
tomorrow

Next Product • Project Risks:


• None at the moment
Release:
• Next Steps:
Tomorrow • Iteration 5 starts after next release
• Beta testers try out next release
• Extending the base product beyond initial user
base
Project Update Dashboard – Government Approvals

• Project Objective:To secure various government


approvals for SoliD

Day 48 of 60 • Project Time:60 business days starting April 1

• Project Updates:
• FFIC approvals are moving as scheduled
• Approved documents onto Verification Office for
sign off
• % of 8 major tasks were completed this week.

• Project Risks:
FFIC Approvals • Delays might be caused if alternate resources are not
made available

On time • Project Next Steps:


• Complete the next 7 tasks by Day 53