17-1 Project Management

Operations Management

William J. Stevenson

8th edition
17-2 Project Management

Project
Management

Operations Management, Eighth Edition, by William J. Stevenson


McGraw-Hill/Irwin Copyright © 2005 by The McGraw-Hill Companies, Inc. All rights reserved.
17-3 Project Management

Projects

JAN FEB MAR APR MAY JUN


Build A

A Done

Build B

B Done

Build C

C Done
On time!
Build D

Ship

Unique, one-time operations designed to accomplish


a specific set of objectives in a limited time frame.
17-4 Project Management

Project Management

 How is it different?
 Limited time frame
 Narrow focus, specific objectives

 Why is it used?
 Special needs
 Pressures for new or improves products or
services
17-5 Project Management

Project Management

 What are the Key Metrics


 Time
 Cost
 Performance objectives
 What are the Key Success Factors?
 Top-down commitment
 Having a capable project manager
 Having time to plan
 Careful tracking and control
 Good communications
17-6 Project Management

Project Management

 What are the Major Administrative Issues?


 Executive responsibilities
 Project selection
 Project manager selection
 Organizational structure
 Organizational alternatives
 Manage within functional unit
 Assign a coordinator
 Use a matrix organization with a project leader
17-7 Project Management

Project Management

 What are the tools?


 Work breakdown structure
 Network diagram

 Gantt charts

 Risk management
17-8 Project Management

Key Decisions

 Deciding which projects to implement


 Selecting a project manager
 Selecting a project team
 Planning and designing the project
 Managing and controlling project resources
 Deciding if and when a project should be
terminated
17-9 Project Management

Project Manager
Responsible for:

Work Quality
Human Resources Time
Communications Costs
17-10 Project Management

Ethical Issues

 Temptation to understate costs


 Withhold information
 Misleading status reports
 Falsifying records
 Comprising workers’ safety
 Approving substandard work
17-11 Project Management

Project Life Cycle

Definition

Management
Planning
Concept
Execution

Termination/
Delivery
17-12 Project Management

Work Breakdown Structure


Figure 17.2

Project
Project X
X

Level 1

Level 2

Level 3

Level 4
17-13 Project Management

Planning and Scheduling

Gantt Chart MAR APR MAY JUN JUL AUG SEP OCT NOV DEC

Locate new
facilities

Interview staff

Hire and train staff

Select and order


furniture

Remodel and install


phones

Move in/startup
17-14 Project Management

PERT and CPM


PERT: Program Evaluation and
Review Technique
CPM: Critical Path Method

 Graphically displays project activities


 Estimates how long the project will take
 Indicates most critical activities
 Show where delays will not affect project
17-15 Project Management

PERT and GANTT Chart


 PERT charts are network diagrams that use boxes to
represent tasks and arrows to present dependencies between tasks.
The boxes are laid out from left to right, but there is no fixed Y-axis
with dates. The first box, or root, is centered vertically on the left
side, and the subsequent tasks can be drawn anywhere along the Y-
axis. Arrows can point to the right, up or down, but never to the
left.
 Gantt charts are bar graphs. The X-axis contains dates and the
Y-axis lists separate tasks. On each line of the Y-axis, the chart
depicts a bar positioned to extend from the task’s start date to its
end date. Tasks are listed in the start-date order.
17-16 Project Management
PERT

GANTT
17-17 Project Management

The Network Diagram

 Network (precedence) diagram


 Activity-on-arrow (AOA)
 Activity-on-node (AON)
 Activities
 Events
17-18 Project Management

The Network Diagram (cont’d)

 Path
 Sequence of activities that leads from the starting
node to the finishing node
 Critical path
 The longest path; determines expected project
duration
 Critical activities
 Activities on the critical path
 Slack
 Allowable slippage for path; the difference the
length of path and the length of critical path
17-19 Project Management

Project Network – Activity on Arrow


Figure 17.4

Order
AOA furniture 4
Furniture
Locate 2 setup
facilities
Remodel
1 5 6
Move
in
Interview
Hire and
train
3
17-20 Project Management

Project Network – Activity on Node


Figure 17.4
Order
furniture
Locate Furniture
2 setup
facilities
AON
1 6
Move
Remodel
in

S 5 7

Hire and
Interview
train

3 4
17-21 Project Management

Example 1
Figure 17.5

6 weeks
Deterministic 4
time estimates rd er e
O i tu r

Fu r p
n 3 weeks
fu r

set
8 weeks 2

n i tu
u
Rem
ate s od e

re
c
L o i l i ti e 11 weeks
l Move
fac in
1 5 6
In 1 week
te ain
rv r
i dt
4 weeks ew an
re
Hi 9 weeks

3
17-22 Project Management

Project Crashing

 Crashing a project involves paying more


money to complete a project more quickly.
 Since the critical path determines the length of
a project, it makes sense to reduce the length
of activities on the critical path.
 CP activities should be reduced until the
project is reduced to the desired length or you
are paying more per day than you save.
 If you have multiple CPs, they should be
shortened simultaneously.
17-23 Project Management

Advantages of PERT

 Forces managers to organize


 Provides graphic display of activities
 Identifies
4
 Critical activities
2
 Slack activities
1 5 6

3
17-24 Project Management

Limitations of PERT

 Important activities may be omitted


 Precedence relationships may not be correct
 Estimates may include 4

a fudge factor 2

 May focus solely


on critical path 1 5 6

142 weeks

3
17-25 Project Management

Technology for Managing Projects

 Computer aided design (CAD)


 Groupware (Lotus Notes)

 Project management software


 CA Super Project
 Harvard Total Manager

 MS Project

 Sure Track Project Manager

 Time Line
17-26 Project Management

Advantages of PM Software
 Imposes a methodology
 Provides logical planning structure
 Enhances team communication
 Flag constraint violations
 Automatic report formats
 Multiple levels of reports
 Enables what-if scenarios
 Generates various chart types
17-27 Project Management

Project Risk Management

 Risk: occurrence of events that have


undesirable consequences
 Delays
 Increased costs
 Inability to meet specifications
 Project termination
17-28 Project Management

Risk Management

 Identify potential risks


 Analyze and assess risks
 Work to minimize occurrence of risk
 Establish contingency plans
17-29 Project Management

Summary

 Projects are a unique set of activities


 Projects go through life cycles
 PERT and CPM are two common techniques
 Network diagrams
 Project management software available